Professional Documents
Culture Documents
Alasan Penghakiman Shah Alaam
Alasan Penghakiman Shah Alaam
25
23/11/2023 09:00:17
BETWEEN
AND
BETWEEN
AND
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
(HEARD TOGETHER WITH)
BETWEEN
AND
JUDGMENT
(3 Originating Summonses (OSs))
A. INTRODUCTION
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
[2] As a result of the AD, the followings were filed by the parties:
[3] Since there are 3 OSs filed in relation to this AD, the parties
agreed to having all the 3 OSs heard together and for the decision to be
delivered together. Since this is a cross suit between the parties, for
ease of reference the parties will be referred to henceforth with the
acronym of Juang and BMG wherever applicable.
B. BRIEF BACKGROUND
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
[5] Due to a non-payment of claims made by Juang from BMG, Juang
issued a payment claim to BMG requesting for a sum of
RM2,822,066.26, comprising as follows:
[6] BMG on the other hand had not responded to the payment claim
by any Payment Response to Juang.
C. ADJUDICATION PROCEEDINGS
cross claims:
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
ii. RM398,745.03 being the differential sum as a result of
remeasurement; and
iii. Costs.
[10] The parties agreed for this court to hear and decide the 3 OS
together.
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
& Chew Sdn Bhd and another appeal [2019] 8 CLJ 433; [2019] 5
AMR 516 FC; Bertam Development Sdn Bhd v. R&C Cergas Teguh
Sdn Bhd [2017] 1 LNS 2228)
E. ISSUES
[13] BMG
2012 is premised on :
and/or
ii. The Adjudicator had not acted impartially and had breached
natural justice in failing to consider all documents presented
to him which led to him acting in excess of his jurisdiction in
arriving at a disproportionate outcome to the detriment of
BMG.
ii. That there is a clear and unequivocal error in the AD; and
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
iii. That
be able to repay the Adjudication Sum should BMG is
successful at the Arbitration.
[15] Juang
2012 is premised as follows;
[16] The issues which BMG had raised against the AD are particularly
pursuant to s.15(b), (c) and (d) of CIPAA 2012. As such, I will consider
whether BMG had discharged its burden on a balance of probabilities to
prove to this court that there has been a denial of Natural Justice by the
Adjudicator, that the Adjudicator had failed to act impartially and that the
Adjudicator had acted in excess of his jurisdiction respectively in arriving
to his conclusion of the Adjudication Proceedings. It is also the
contention of BMG that there are clear and unequivocal errors in the AD.
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
had acted in breach of Natural Justice and in excess of his jurisdiction.
In particular, the Adjudicator had on LAD as
stated in paragraph 28 of the AD on the ground that :-
ii.
extension of time, Juang merely needs to complete the
works within a reasonable time.
[18] It
defence raised by BMG with regards to the LAD issue as stated in its
Adjudication Response. According to BMG, the Adjudicator in his
decision at paragraph 28 had failed to consider that there is a total delay
of 743 days (from the Completion Date of 18.11.2019 until the date of
practical completion on 30.11.2021) which exceeds the total number of
days of extension of time that Juang is entitled to.
[20] The principle of Natural Justice that is said to have been denied
here is the right to being heard, audi alteram partem. In an Adjudication
Proceedings, the Adjudicator has the duty to accord procedural fairness
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
to the parties during the course of the proceedings whereby the issues
raised by both parties are to be considered and a decision is to be
derived therefrom. In the case of ACFM Engineering & Construction
Sdn. Bhd. v. Esstar Vision Sdn Bhd & another appeal [2016] 1 LNS
1522; [2016] MLJU 1776, the Court of Appeal held:
[19] When one speaks of natural justice, it is nothing more than what we call
the concept of "procedural fairness" which needs to be accorded to the parties
[21] In perusing through the AD, unlike what is claimed by BMG, the
Adjudicator had deliberated on the issue of LAD at paragraph 17
onwards till he reached a conclusion on this issue at paragraph 28 of the
AD.
[22] Even BMG had conceded to the fact that the Adjudicator had
considered the LAD issue before concluding at paragraph 28 i.e that
time is at large and that Juang only has to complete the works within a
reasonable time.
[23] With regards to the issue of set off of RM398,745.03 being the
differential sum as a result of remeasurement, the Adjudicator
deliberated at length on this issue at paragraph 36(b) to 38 of his AD
before coming to his decision whereby he had decided against
claim for a set off.
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
[25] On whether the Adjudicator had considered issues which were
raised by Juang in the Adjudication Reply, it cannot be denied that the
[26]
but had also made his findings in accordance to all the documents in
relation to these issues which had been submitted for the purpose of this
proceedings.
[27] I refer to the case of Bina Puri Construction Sdn Bhd v Hing
Nyit Enterprise Sdn. Bhd. [2015] 8 CLJ 728 where it was stated as
follows:
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
Adjudicator lacked independence or impartiality in conducting the
Adjudication Proceedings and in delivering the AD.
There is also no basis for the Respondent to allege that the Adjudicator
had failed to act independently and impartially. The fact that the Adjudicator
did not agree with the Respondent's position on the law is no proof that he
had failed to act independently and impartially. Such an allegation should not
be launched without some evidence pointing inexorably to a lack of
independence or impartiality in the hearing and the delivery of the
Adjudi
[31] Apart from the allegations made against the Adjudicator, BMG had
not adduced any evidence to show that the Adjudicator lacked
independence or impartiality in making his decision in favour of Juang.
As shown in the above paragraphs when dealing with s.15(b) of CIPAA,
the Adjudicator had reasoned out every conclusion that he had reached
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
when deliberating the issues brought before him. As such, I am not
convinced that BMG has discharged the burden of proving the allegation
made against the Adjudicator under this limb.
there must be further compliance with the requirements of the Act as in that
the dispute must be one falling within the matters raised in the Payment Claim
and the Payment Response as provided for under section 27(1) CIPAA. In
that example the word "jurisdiction" is used in the sense of the scope of the
dispute that is before the Adjudicator for decision. So, for example an
Adjudicator may not be able to decide on the defence of set-off arising out of
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
costs of rectifying defective works if this has not been raised in the Payment
Response. If he so decides, then this Court may set it aside as been made in
[36] In fact, BMG had in its Affidavit in Support stated that the
Adjudicator had failed to consider Clause 17 of the Letter of Award date
19.9.2017 and PILING WORKS AND
STRUCTURES 8.1 PILING WORKS (ALL PROVISIONAL) Note: All
[37] However, BMG failed to show that this issue was in fact raised
during the Adjudication Proceedings. As submitted by Juang, BMG had
never raised the issue pertaining to clause 17 of the LOA and the terms
in Tender Bill No. 8 in the adjudication proceeding.
[38] Therefore, BMG cannot now allege that the Adjudicator has
exceeded his jurisdiction because he failed to consider clause 17 of the
LOA and terms in Tender Bill No. 8 because these points were never
raised by BMG in the Adjudication Proceedings in the first place.
[39] Therefore, having failed to establish s.15(b), (c) and (d) of CIPAA
2012 against the Adjudicator, BMG has failed to discharge its burden on
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
balance of probabilities to set aside the AD. As such, this application to
set aside the AD is hereby dismissed with costs of RM5,000.00 to be
paid to Juang by BMG subject to allocatur fees.
[40] BMG via its affidavit in support deposed by its director had stated
this application is in reliance to s.16(1)(b) CIPAA and that the execution
of the AD should be stayed on the basis that there is a pending civil suit.
[41] The Federal Court case of View Esteem Sdn Bhd v. Bina Puri
Holdings Bhd [2019] 5 CLJ 479 His Lordship Zulkefli Ahmad
Makinuddin PCA had in delivering the judgement stated the following:
[43] On the grounds that stay should be granted pending the final
determination of a pending civil suit, to prevent an abuse of s16 CIPAA, I
fall back on what was said by Justice Lee Swee Seng (as his Lordship
then was) in the case of Pasukhas Sdn Bhd v. Empire Multiple Sdn
Bhd and Another Case [2019] 1 LNS 757; [2019] MLJU 1393. His
Lordship in his judgment had succinctly reasoned that in spite of s.
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
16(1)(b), allowing a stay merely on the fact that the arbitration had
commenced with the service of a notice to arbitrate would render the
entire purpose of the CIPAA futile and statutory adjudication wholly
ineffective to ensure cashflow in the construction industry.
[44] The final reason given for this stay application is that the financial
standing of Juang is weak and as such, should BMG is successful in the
civil suit, Juang will not be able to pay back the Adjudication Sum to
BMG.
[45]
reveals that Juang has suffered a loss after tax of RM88,524.99. As
such, Juang may not be able to repay BMG should it be successful at
the civil suit.
[46] Be that as sit may, in the same report, it also shows that Juang
has a revenue of RM56,874,555.56. A revenue of such an amount
certainly does not reflect Juang as a weak concern. BMG has failed to
[48] As guided by Her Ladyship Mary Lim Thiam Suan JCA (as she
then was) in the Court of Appeal case of Inai Kiara Sdn Bhd v. Puteri
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
Nusantara Sdn Bhd [2019] 2 CLJ 229, the court may exercise its
discretion to grant leave under s. 28(1) and (2) CIPAA to enforce an
adjudication decision if the following three conditions (3 Conditions) are
met:
(2) the party against whom an adjudication decision is made, has failed to
pay the adjudicated amount on the date specified in the adjudication
decision; and
(3)
[49] In this case, in the absence of any evidences to say otherwise, all
3 conditions have been satisfied and since the setting aside and the
application for stay of execution of the AD have been dismissed, Juang
application to enforce the AD is allowed with no order as to costs.
G. CONCLUSION
(i) both the Setting Aside and Stay of Execution OSs are
dismissed;
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal
S/N 7OuMMXOk50SHzCdCr2t4pg
**Note : Serial number will be used to verify the originality of this document via eFILING portal