You are on page 1of 1

S/S-235 (235-SG-301)

Type Test Qty Completed Status % Progress


Mechanical Checks & Visual Inspection 1 1 100%
Contact resistance test for busbar 1 1 100%
continuity test for busbar 1 1 100%
Busbar
Insulation resistance for busbar 1 1 100%
AC Hipot test for busbar 1 1 100%
Current transformer test 151 151 100%
CT/ PT
Voltage transformer test 15 15 100%
Protection relay test 30 30 100%
Relay & Scheme Checks
Meter 24 24 100%
Insulation resistance for breaker 21 21 100%
contact resistance for breaker 21 21 100%
Breaker operation checks/Timing 21 21 100%
Breaker & Contactor
Insulation resistance for contactor - - -
contact resistance for contactor - - -
Contactor Operation Check - - -
Primary injection of CT 21 21 100%
Primary injection
Primary injection of VT 24 24 100%
Secondary injection of CT 21 21 100%
Secondary injection
Secondary injection of VT 24 24 100%
Auto transfer scheme checks 1 1 100%
Interpanel wiring 24 24 100%
Transformer differential stability 2 2 100%
Announciation signal checking 21 21 100%
PMS signal checking (end to end test) 21 21 100%
DCS signal checking (end to end test) 10 4 40%
Intertrip upstream 2 2 100%
Intertrip downstream 2 2 100%
Point to point test 24 24 100%
Final Function Check 24 24 100%
Total % 98%

You might also like