S/S-235(235-SG-201)

Type Test Qty Completed Status % Progress


Mechanical Checks & Visual Inspection 1 1 100%
Contact resistance test for busbar 1 1 100%
continuity test for busbar 1 1 100%
Busbar
Insulation resistance for busbar 1 1 100%
AC Hipot test for busbar 1 1 100%
Current transformer test 54 54 100%
CT/ PT
Voltage transformer test 22 22 100%
Protection relay test 20 20 100%
Relay & Scheme Checks
Meter 14 14 100%
Insulation resistance for breaker 9 9 100%
contact resistance for breaker 9 9 100%
Breaker operation checks/Timing 9 9 100%
Breaker & Contactor
Insulation resistance for contactor 5 5 -
contact resistance for contactor 5 5 -
Contactor Operation Check 5 5 -
Primary injection of CT 14 14 100%
Primary injection
Primary injection of VT 16 16 100%
Secondary injection of CT 14 14 100%
Secondary injection
Secondary injection of VT 16 16 100%
Auto transfer scheme checks 1 1 100%
Transformer differential stability 2 2 100%
Interpanel wiring 16 16 100%
Announciation signal checking 16 16 100%
DCS signal checking (end to end test) 5 5 100%
LCS signel checking (end to end test) 3 3 100%
PMS signal checking (end to end test) 14 14 100%
DCS signal checking (end to end test) 5 5 100%
Intertrip upstream 2 2 100%
Intertrip downstream 4 2 50%
Point to point test 16 16 100%
Final Function Check 16 16 100%
Total % 98%