FUNCTIONAL TEST SHEET FOR LV FEEDER CUBICLES / ISOLATOR PANELS

LOCATION: SYSTEM:
EQUIPMENT/CUBICLE TAG NO:
TEST RESULT
1. Ensure that site inspection of feeder cubicles has been completed and relevant
construction test sheets completed.
2. Ensure that all the current transformers have been tested and relevant
functional test sheets completed.
3. MCCB - Thermal protection:
Test Type Test Setting Trip time
Trip Cold 200% x FLC I= Curve
Stability 20 min @ 100% x FLC I= Stable
Trip Hot 125% x FLC I= Curve
Single Phase 200% x FLC
4. MCCB - Magnetic protection
Test Type Test Setting Trip time
Trip Cold 10 x FLC I= Instant
5. Test and record pick-up voltage of contactor coil (V)
6. Test and record drop-off voltage of contactor coil (V).
7. Overload Relay - setting:
Test Type Test Setting Trip time
Trip Cold 200% x FLC I= Curve
Stability 20 min @ 100% x FLC I= Stable
Trip Hot 125% x FLC I= Curve
Single Phase 200% x FLC
8. Test reset mechanism of overload relay.
9. Earth Fault Relay:
Sensitivity (mA) Injected Current (A) Operated Current (A)

10. Check and record voltage across phases (V).


11. Check phase rotation.
12. Test operation of selector switches.
13. Test operation of push buttons.
14. Test operation of timers.
15. Measure and record voltage across secondary terminals of control
transformer.
16. Test operation of lamps and indicators.
17. Check all interlocks to starter by operating contacts of other control
devices like limit switches, pressure switches, level switches, etc.