Installation Check List for Main LT Panel (LT)

Job Number
Job Name
Drawing Number
Panel Rating
Panel Reference

S.No Description Yes / No Remarks

1 Marking location of Panel as per drawing

2 Positioning of the Panels are as per the approved shop drawings

3 Positioning base frame level and alignment of Panel

4 Tightness of joints of coupling unit,if shipped in sections

5 All feeders to be checked as per approved SLD / GA

6 Earthing of Panel

7 Access (front / rear ) clearance as per drawing

8 Check the ACB connection

9 Check the tightness inside the Panel

10 Panel thoroughly checked and cleaned

11 All cables are provided with Cable Gland

12 Cable Terminations inside Panel are tightened

13 All control wires in the panel are tightened physically

LT Panel Commisioning Status Insulation Report


Pole to Earth R- Y- B-
Pole to Pole RY- YB- BR-

Performed By Approved By
Name Name
Signature Signature
Date Date