Professional Documents
Culture Documents
for
Testing &
Commissioning of
DG Set
Purpose:
The purpose of this method statement is to define the testing & commissioning
procedure of the Diesel Generator within the project.
This includes Pre-Commissioning checks, commissioning tests & system interface
tests.
Scope:
The scope of this method statement is to define the system checks, type &
duration of testing that will be required to test standby generator sets to bring it into
a faulty working & approved mode of operations.
System Description:
DG set provides power to the emergency & life safety systems in the event of a
mains failure.
Interface:
Abbreviation:
Pre-Commissioning Phase
All installation checks must be carried out & approved by the relevant parties.
Further more the generator room must also be sufficiently completed to
facilitate successful & accurate testing & commissioning to be achieved I.e.
completion of construction work etc.
a) All connection are tight & leak Physically checked & tighten
proof, including cabling to auxiliary
terminal box
b) All protective covering used in Physically checked
packing are removed
c) Check the fuel, lubricating oil & Coolant & Oil will be filled at site. Fuel
coolant levels are adequate, top up will be supplied by contractor/Client.
if necessary
d) Change battery & connect to unit Batteries are dry changed, they will be
filled with electrolyte at site.
e) Check alternator connections Physically checked.
f) Check the fuses are in holds Physically checked
g) Isolate circuit breaker from load Switch off circuit breaker
h) Make sure the generator operating Physically checked
switch in the off position
Warning tapes will be placed around generator room & warning sign board will be
kept to indicate unauthorized personals not to enter in the area.
During start up & testing Generator, sound level of about 120dB will be observed so
ear protection head set will be worn by each one.
Commissioning Procedure
a) Check the exhaust flow is not obstructed or Visual check
damaged in order to avoid harmful fumes
b) Check that the Ventilation system is not Visual check
obstructed
c) Check the battery cable to generator set Connect battery cable to
starter Motor & batteries
d) Check if the generator is in running Test Run
Run Generator for 5 mins without load & record the following
Oil Temperature : Deg C
Engine Temperature : Deg C
Oil Pressure : Deg C
Engine Speed : RPM
Output Voltage : Vac
Output Frequency : Hz
Phase Rotation :
Function of all Instrument :
Standard performance testing is a test to ensure that a generator set will give
the required 100% output at specified voltage & frequency.
1) Start the DG set & adjust voltage & speed to required value
2) Check all the control equipment meets the functional requirement of the system.
3) Apply 50% of rated load & record all parameters.
4) Add 25% rated load & record all parameters.
5) Add 25% load to achieve 100% of rated load & record all parameters in the
format.
6) At 100% load, run the DG set for 7 hrs & check every 30 mins to see that the
engine normal operating temperature range, oil pressure drop are not exceeded.
7) Add 10% over load & run DG set for 1 hour. Record all parameter every 15 mins.
8) Remove rated load & allow the DG set to stabilize for 5 mins
9) Check the set for oil leak, coolant leak & any loose items.
10) Shutdown the DG set
11) Disconnect temporary load cables;es.
With 100% rated load, Operate DC, set for 7 hours continuously & without
interruption at 50 deg C ambient, taking readings at every 30 mins & record
following.
1) Time of Reading
2) Running Time
3) Ambient Temp in Deg C
4) Lube Oil pressure in k Pa
5) Lube Oil temperature in Deg C
6) Engine coolant temperature in Deg C
7) Exhaust stack temperature in Deg C
8) Alternator voltage, phase 1, 2 & 3
9) Alternator current phase 1, 2 & 3
10) Power in kW
11) Frequency in Hz
12) Power Factor
13) Battery charger current in A
14) Battery voltage
15) Alternator starter temperature in Deg C
At the end of 7 hours run increase the load to 110% of the rated value & take
readings every 15 mins during 1 hour of operation.
Before commissioning 8 hours run, decrease following shut down device & alarm.
Next install continuous strip chart recorders to record frequency & voltage variation
during load switching procedures with strip chart 1.3mm/s