Has all Bench Marks such as GL,FFL, etc taken on some permanent
Structures? 2
Comments:
Sl. Yes / No / NA
Description Remarks
No. JMC's Rep. PMC's Rep.
Prior Work
Check for earth used for filling as per specification /
1
approved.
During Work
Check for earth free from all roots, grass, rubbish, lumps &
5
clods not exceeding 200mm.
After Work
Check for degree of compaction has achieved minimum 90-
10
95% of MDD for each layer.
Comments:
Name : Name :
After Work
10 Check for top levels of PCC.
11 Check for curing done for 7 days.
Sl. Yes / No / NA
Description Remarks
No. JMC 's Rep. PMC's Rep.
Reinforcement
1 Check for reinforcement diameter as per drawing.
2 Check for spacing in both directions / number of bars as per drawing.
3 Check for sufficient cover provided
4 Check for additional rings/stirrups provided above the pedestal top
5 Check for reinforcement tied properly.
6 Check for plumb of the verticals.
7 Check for proper supports are provided for the reinforcement.
8 Check for BBS and lapping zone
Formwork
1 Check for proper access provided.
2 Check the quality of formwork
3 Check for level/height
4 Check for center lines.
5 Check for dimensions as per drawing.
6 Check for alignment, verticality and diagonal
7 Check for supports are adequately provided.
8 Check for extra supports required, specify location.
9 Check for insert plates and embedment
Concrete Pour Card
1 Check for grade of concrete.
3 Check for availability of vibrator
4 Check for level of casting
5 Check for cubes are taken as per the requirement.
Comments:
Sl. Yes / No / NA
Description Remarks
No. JMc's Rep. PMC's Rep.
Reinforcement
1 Check for the grade of the steel. &diameter as per drawing.
2 Check for spacing as per drawing.
3 Check for laps provided as per drawing.
4 Check for cover blocks provided till required level.
5 Check for reinforcement tied properly.
6 Check for additional rings/stirrups provided above the slab top.
7 Check for column reinforcement reduction / extension.
8 Check for BBS
Formwork
1 Check for proper access provided.
2 Check for quality of form work.
3 Check for level/height.
4 Check for center lines.
5 Check for dimensions, alignment,verticality and diagonal
6 Check for supports & tie rods are adequately provided.
7 Check for extra supports required, specify location.
8 Check for insert plates and embedment.& MEP services
Concrete Pour Card
1 Check for grade of concrete.
2 Check for availability of vibrator.
3 Check for cubes are taken as per the requirement.
4 Check for level/height of casting
Comments:
Signature : Signature :
Name : Name :
Post Concrete
1 Check for dimensions of column at top, middle and bottom.
2 Check for surface honeycombs, buldging ,joints
3 Check for shear keys provided.
4 Check for line, level and plumb of column.
5 Check for proper cleaning of reinforcement.
6 Check for de-shuttering done as per specified time.
7 Check for arrangement of curing and marking of the date.
8 Check for curing upto 7 days with hessain cloths (Double layer)
9 Check for 7 days cube strength satisfied.
10 Check for 28 days cube strength satisfied.
Comments:
Signature : Signature :
Name : Name :
Doc. No : ATP/ SYN / QA / 004
Client : Aparna Constructions & Estates Private Limited, Hyderabad.
PMC : Synergy Property Development Services Pvt., Ltd
Contractor : JMC Projects (India ) Ltd.
Project : Aparna Technopolis
Quality Check List for Reinforcement, Formwork & Concrete - R.C.C Walls
Lenth of wall Date:
Signature : Signature :
Name : Name :
Post Concrete
1 Check for dimensions of the wall.
2 Check for line, level and plumb of the wall.
3 Check for shear key provided.
4 Check for proper cleaning of the reinforcement.
5 Check for de-shuttering done as per specified time.
6 Check for curing upto 7 days with hessain cloths (Double layer)
7 Check for 28 days cube strength satisfied.
Comments:
Signature : Signature :
Name : Name :
Doc. No : ATP/ SYN / QA / 005
Client : Aparna Constructions & Estates Private Limited, Hyderabad.
PMC : Synergy Property Development Services Pvt., Ltd
Contractor : JMC Projects (India ) Ltd.
Project : Aparna Technopolis
Concrete checklist for slab and beams
DATE: Grade of concrete in slab:
Location/Pouring details
CHECK LIST FOR REINFORCEMENT
Contractor 's Rep/PMC's Rep.
Sr.No. DESCRIPTION Yes/No/NA Remarcks
Signature : Signature :
Name : Name :
Prepour concrete
Contractor 's Rep/PMC's Rep.
Sr.No. Description Yes/No/NA
Signature : Signature :
Name : Name :
Name :
Name :
De-Shuttering Check
De-Shuttering Date as per structural Consultant/PMC
Beam :
Slab :
Slab :
Back Proping
Beam :
Slab :
Comments:
Name :
Name :
Doc. No : ATP/ SYN / QA / 007
Client : Aparna Constructions & Estates Private Limited, Hyderabad.
PMC : Synergy Property Development Services Pvt., Ltd
Contractor : JMC Projects (India ) Ltd.
Project : Aparna Technopolis
QUALITY CHECKLIST FOR RETAINING WALL RAFT
Location: Date:
Signature : Signature :
Name : Name :
Post concrete
Signature : Signature :
Name : Name :
Signature : Signature :
Name : Name :
Post Pour Check
1 Check for curing arrangement.
2 Check for measurements as per drawing.
3 Check for pour top level, alignment, honeycomb, bulges and surface finishes.
4 Check for curing for 14 days.
7 Check for 28 days cube strength satisfied.
Comments:
Signature : Signature :
Name : Name :
Doc. No : ATP/ SYN / QA / 009
Client : Aparna Constructions & Estates Private Limited, Hyderabad.
Area
Grid No
Date
Drawing reference
Yes No
2 Are all the safety norms being covered as per HSEM process?
Yes No
3 Check All boreholes packing to be done as per approved methodology?
Yes No
4 Check the all works of plumbing /sanitation/Drain any MEP before taking up application
Yes No
Check structurally unsound and friable concrete must be removed and repaired with a suitable concrete
5
repair mortar.
Yes No
Check surface cleaned thoroughly of all contaminants like dust, traces of curing compound, oil and
6
grease.
Yes No
7 Check surface Free from All surface imperfections, protrusions, and sharpedges.
During Check
Yes No
Apply Dr. Fixit Torchshield Primer @ 4-6 sq.mtrs./litre to a clean, smooth and dry surface by brush or
8
roller
Peel off the release film from the self adhesive side and start unrolling the membrane and press it to the
9
surface
10 Check Side overlaps shall be a minimum of 50 mm on the selvedge and end overlaps 100 mm.
Yes No
11 Check availability of material and manpower for waterproofing as per planned scope for the day.
Post Check
Yes No
12 check voids or any gaps from primer surface after dry.
Yes No
13 Check any membrane sticked with with the base surface.
Yes No
14 Check any entrapped air.
Yes No
15 The membrane shall be protected with Geotextile Immediately after application from damage.
Signature :
Signature :
Name : Name :
Area
Grid No
Date
Prior Check
Yes No
1 Is the Method statement approved by client and available during execution?
Yes No
2 Are all the safety norms being covered as per HSEM process?
Yes No
Check for RCC surface shall be cleaned to remove all dust, foreign matter, loose materials or any deposits of
3
contamination by removing with wire brush or not?
Yes No
4 Check availability of material and manpower for waterproofing as per planned scope for the day.
Yes No
5 Check for material as per specifications / expiry date
During Check
Yes No
Check for cutting of PVC pipes from Tie rod holes and Sealing of tie rod holes using nonshrink high strength
1
cementitious Grout Conbextra GP2
Yes No
Along the construction joint & cracks make a V - groove of approx.20mmx20mm and pack it with using Polymer
2
modified Cement mortar of 1:4 admixed with Dr. Fixit Pidicrete URP/ NI-O-POL.
Yes No
During Grouting:- Fixing of PVC nipples at 500mm c/c at Construction joints & starter joints and Injection grouting
3 using cement slurry mixed with non-shrink admixture Dr. Fixit Pidicrete AM/Cebex 100 @ 225 gms per bag of cement
(Pressure grouting to be done at porous/Honeycomb areas as per site conditions).
Yes No
Check for post grouting :- Removal of PVC nipples and pack the openings using polymer modified cement mortar of 1:4
4
admixed with Dr. Fixit Pidicrete URP/ NI-O-POL.
Yes No
Check for Coving of Size of (100mm x 100mm) at the junction of slab & vertical walls with cement sand mortar 1:4 and
5
10 mm aggregate admixed with Proofsol LWP @ 100 ml per bag of cement
Yes No
6 Check the surface for removing the existing dust or loose particles by brush and bring the substrate to SSD Condition
Yes No
7 Check the application of Hydrocem coating in 2 coats with an intercoat period of 6-8 hrs @1.5kg/sqm.
Yes No
8 Check the application of 2nd coat in perpendicularly to the 1st coat.
Post Check
Yes No
1 Check for Curing for atleast 3 days.
Yes No
2 Check for Providing and fixing Protective 3mm PPE board by using suitable adhesive
Signature :
Signature :
Name : Name :
Area
Grid No
Date
Perior to Concrete
Yes No
1 Is the Method statement approved by client and available during execution?
Yes No
2 Are all the safety norms being covered as per HSEM process?
Yes No
3 Check for water proofing is completed
Yes No
4 Check for MEP services clearance
Yes No
5 Check for all reinforcement works are completed as per drawing
Yes No
6 Check the fixing of chamber. Is it in proper line and level
Yes No
7 Check for top level marking of grade slab as per approved drawings?
Yes No
8 Check for MS channels provided as per requirement
Yes No
9 Check hard barrication to restrict entry & protection.
Yes No
10 Check the availability of equipment like vibrator and accessories ?
Yes No
11 Check for cleanliness of area of work to be done
During Concrete
Yes No
1 Check for grade of the concrete and slump
Yes No
2 Check for the slopes are maintained as per drawing
Yes No
3 Check for proper vibration of concrete
Yes No
4 Check for proper trowelling for good finish is being achieved
After Concrete
Yes No
1 Check for proper removal of MS channels without damaging edges of concrete.
Yes No
2 Check for proper broom finish. Is it even & Uniform
No
3 Check for slope as per drawing
Yes
Yes No
4 Check for removal of excess concrete, wooden supports, dead mortar cleaning and fixing of channels.
Yes No
5 Check for adequate curing for minimum 10 days
Yes No
6 Check for deep cleaning along the periphery of panel extent.
Signature :
Signature :
Name : Name :
Area
Grid No
Date
Name of the
Vendor
S.No Details
Prior Check
Yes No
1 Are the safety norms being covered as per HSEM process?
Yes No
2 Is the method statement approved by client and available during execution?
Yes No
3 Check, for the avaibility of materials uPVC FOAMCORE pipe (IS 16098),SN4 -200mm dia and M sand.
Yes No
4 Check, for the availability of levels marked on near by columns? As per drawing.
Yes No
5 Excavation free from stones/pebbles?
Yes No
6 Ensure the trench is compacted?
Post Check
Yes No
1 Check for the gradient of pipes as per drawing to enable smooth flow?
Yes No
2 Check the RCC chamber is completed as per drawing?
Yes No
3 Check the chamber finishing is done ?
Yes No
4 Check for slope as per drawing inlet and out let of chamber pipes lines?
Yes No
5 Check the pipe joints verified for tightened and leakage.?
Yes No
6 Check for the suitable PVC fittings in all junctions?
Yes No
7 Check soil backfilled to required level below PCC of grade slab?
Signature :
Signature :
Name : Name :
Date
Drawing
reference
S.No Description Details
PRE-EXECUTION CHECKS YES NA
2 Are the latest "Good for Construction" drawings available at site are used.
Check the Safety norms being covered as per HSEM Process and Suitability &
3
Safety of Scaffolding acceptable?
Check for all tie rod/wall tie holes in the columns/RC walls & beams closed
7
with non-shrink grout.
Check for all the tapes, nails, strucked ply & foam sheets have been
8
removed.
9 Check for all the protruded steel rods have been cut to the level.
10 Check for hacking (50 to 60 nos per SFT) done over RCC surface.
12 Check for sill and lintel levels marked on the column and shear wall.
Check for all joints of uniform thickness of 10mm & joints were raked
8
properly on both sides
11 Cutout and openeings required for MEP services left as per drawing
16 Check for cleaning area for dead mortar and block bat to location of disposal
2 Check for curing arrangements and curing to be ensured for one week
Check that all work area has been cleaned and is scraped free of mortar
5
splatters.
6 Check all waste block and mortar has been piled in designated trash area.
Contractor's Rep/ QC Checked By - PMC's Rep. :-Checked By - MEP's Rep. :- Checked By - Client's Rep. :-
Area
Grid No
Date
Drawing No
2 Check for all the electrical conduit drops cleared and take structure/plastering clearance from MEP?
3 Are the latest "Good for Construction" drawings available at site are used?
6 Check for all tie rod/wall tie holes in the columns/RC walls & beams closed with non-shrink grout.
7 Check the all size of openings( door, window etc..) as per GFC Drawing
9 Check for all the tapes, nails, strucked ply & foam sheets have been removed.
10 Check for all the protruded steel rods have been cut to the level.
11 Check for hacking (50 to 60 nos per SFT) done over RCC surface.
Check the all RCC junction either side Galvinished iron metal mesh 400mm wide is fixed with ziz zag
13
portion nails to be done.
Check all plumbing / electrical pipe line if more then two nos GI mesh to be fixed mortar mixing ratio
14
1:3
15 Check for suitability & safety of scaffolding. Is it acceptable?
5 Check for mortar mix proportion ( 1 Cement: 6 Sand) with measurement box used?
3 Check for straightness/Thickness of edges,Groove, Band, drip mould etc. as per design?
4 Check for dead mortar been removed and plumb checked subsequently
6 Check for proper termination for plastering bond in between old and new plaster
7 Check if the scaffolding has been completely removed and all openings have been sealed.
Signature : Signature :
Name : Name :
Area
Grid No
Date
Drawing No
2 Check for all the electrical conduit drops cleared and take structure/plastering clearance from MEP?
3 Are the latest "Good for Construction" drawings available at site are used?
6 Check for all tie rod/wall tie holes in the columns/RC walls & beams closed with non-shrink grout.
7 Check the all size of openings( door, window etc..) as per GFC Drawing
9 Check for all the tapes, nails, strucked ply & foam sheets have been removed.
10 Check for all the protruded steel rods have been cut to the level.
11 Check for hacking (50 to 60 nos per SFT) done over RCC surface.
1 Check whether the quality of materials like cement,lime,sand & mesh and inspection is as per specification.
5 Check for mortar mix proportion ( 1 Cement: 6 Sand) with measurement box used?
12 Check if architectural features such as Groove, Band etc. are being provided as specified while plastering.
13 Check the final finished surface shall have lime retarding finished smooth & plane as approved.
2 Check for trueness of plastered surface and record the variance if any
3 Check for straightness/Thickness of edges,Groove, Band, drip mould etc. as per design?
4 Check for dead mortar been removed and plumb checked subsequently
6 Check for proper termination for plastering bond in between old and new plaster
7 Check if the scaffolding has been completely removed and all openings have been sealed.
If any Observations:
Signature : Signature :
Name : Name :
Area
Grid No
Date
Drawing reference
PRIOR TO CONCRETING
Yes No
1 Is the Method statement approved?
Yes No
2 Are the Safety norms being covered as per HSEM Process?
Yes No
3 Check for availability of skilled manpower?
Yes No
4 Check for base surface free from undulations, dust, dirt etc.,
Yes No
Check for availability of equipment like screed vibrator,Power troller ,vaccum pump,suction mat,filler pads
5
and accessories etc..?
Yes No
6 Check for the size of the panels as per APPROVED POUR PLAN?
Yes No
7 Check the slope been maintained as per the requirements?
DURING CONCRETING
Yes No
1 Check cement slurry application (thick creamy) on sub-base.
Yes No
2 Check the concrete as per design mix?
Yes No
2 If the area is too large, has it been divided accordingly, to do concreting alternatively?
Yes No
3 Check for proper protection of PHE pipes, plastered surfaces.
Yes No
4 Check the concreting been done evenly and leveled with vibrating machine?
Yes No
5 Check the cube for sampling is taken as per requirements ?
Yes No
6 Check the sucking mat been spread evenly to facilitate maximum withdrawal of water?
Yes No
7 Has the mortar of 1:2 been spread evenly to cover any undulations?
Yes No
8 Check the floater been done evenly?
AFTER CONCRETING
Yes No
1 Check for easy removal of ISMC edge supports without damaging edes of concrete.
Yes No
2 Check for removal of extra concrete, wooden support, dead mortar cleaning and fixing of channels.
Yes No
3 Check for proper broom finish at top. Is it even & uniform.
Yes No
4 Check for Curing arrangements 7 days.
Yes No
5 Is the finished floor, level ?
Yes No
6 Check the floor is covered at 200 micron thick polythene sheet is coved after completion of curing period?
Signature :
Signature :
Name : Name :
Area
Grid No
Date
Drawing reference
Yes No
2 Are the Safety norms being covered as per HSEM Process?
Yes No
3 Check for availability of skilled manpower?
Yes No
4 Check for availability of equipment like groove cutting machine, blade water ect..?
Yes No
5 Check the marking as per approved layout size of panel?
Yes No
6 Check the alignment during cutting.Is it ok or deviated.
Yes No
7 Check the Groove size as per marking. Is it 6mm x 10mm?.
Yes No
8 Check the deep Cleaning of Groove.
Yes No
9 Check for application of masking tape on either sides of groove.Is proper width is maintained?
Yes No
10 Check the approved make and expriy date of filling component?
Yes No
11 Check the filling of groove by using of approved make?
Yes No
12 Check the finishing and top level. Is it matched with concrete top level.
Yes No
13 Is the masking tape is removed & disposed
Signature :
Signature :
Name : Name :
2 Are all the safety norms being covered as per HSEM process?
3 Check availability of material and manpower as per planned scope for the day.
Check for RCC surface shall be cleaned to remove all dust, foreign matter, loose
4
materials or any deposits of contamination by removing with wire brush or not?
Cleaning the joint and making it free from moisture, dampness, oil stains, paints
and any type of loose aggregates
5
During Check
1 Cleaning the joint and making it free from moisture,
BOSTIK SEAL ‘N’ FLEX1 sealant (of thickness 12.5mm & width 25mm) Expansion
3
joint system by using gun/putty blade or by hand finishing.
Post Check
1 After sealant application 24 hours curing period is done.
2 Check the level of finishing is ok
3 Check the Shalitex Board is fixIng level as per drawing/VDF top level
Signature : Vedor
2 Are all the safety norms being covered as per HSEM process?
Check for RCC surface shall be cleaned to remove all dust, foreign
3 matter, loose materials or any deposits of contamination by
removing with wire brush or not?
Check availability of material and manpower as per planned
4
scope for the day.
During Check
As per Required /Water proofing shall be done for slab and
1
surrounding inside walls
Post Check
1 Check for Curing for atleast 7 days.
Signature : Vedor
17 Check for full block course was placed at top layer & properly packed.
AFTER EXECUTION CHECKS
1 Check for room dimensions, line, right angle, plumb, level, ventilator/window/door openings of the wall.
5 Check that all work area has been cleaned and is scraped free of mortar splatters.
6 Check all waste block and mortar has been piled in designated trash area.
Contractor's Rep/ QC Checked By - PMC's Rep. : Checked By - MEP's Rep. :- Checked By - Client's Rep. :-
Signature : Signature : Signature :
Colliers Page 33 of 33