Professional Documents
Culture Documents
CONDITIONS OF CONTRACT
Prepared by
ID No.55393
MARCH 2010
Claims Avoidance Techniques using Abu Dhabi General Conditions of Contract
Technical Paper for CCE Exam on March 05, 2010 (Rev-1)
TABLE OF CONTENTS
PAGE
1. ABSTRACT ...................................................................................................3
2. INTRODUCTION..............................................................................................4
7. CONCLUSION ...............................................................................................16
8. REFERENCES………………………………………………………….……….…16
1. Abstract
In Abu Dhabi, The General Conditions of Contract for Civil Engineering Works, „Abu
Dhabi GCCCW‟ is the core of the contractual relationship between the Department
and the Contractor in Construction Contracts. These conditions have been prepared
in accordance with the rules and regulations in force in the Emirate of Abu Dhabi and
the U.A.E and in general legal regulations.
Abu Dhabi GCCCW addresses the rights and duties of the contracting parties, and
so, is of special concern to claims avoidance / treatment practices in construction
contracts. It deals with numerous issues which are of paramount importance.
Author‟s topic - Construction Claims Avoidances using Abu Dhabi General
Conditions of Contract Civil, communicate the various claim avoidance techniques
to be practiced by the Engineer (Consultant), as per the Articles of Abu Dhabi
GCCCW.
Author concludes that the Engineer‟s practice of active claim avoidance techniques
based on the correct interpretations and applications of the Conditions of Contract
and the utilization of a thorough claim review process can effectively abate the
occurrence and impact of contractor claims.
2. Introduction
Contract preparations.
Thorough knowledge of the contract.
Consistent application of contract provisions.
Effective communications.
Conducting inspections of the work.
Prompt review and return of submittals.
Assuring the quality of materials and workmanship.
Utilizing practical techniques for tracking submittals.
Organization and maintenance of accurate project records.
Obtaining information from various construction participants.
Keeping the Client informed of the project status.
Conducting progress meetings and preparing minutes.
Estimating, budgeting and controlling the project costs.
Planning, scheduling and controlling the time.
Assuring the scope of works.
Authority and decision making.
Close out the Contract.
Author considers that continuous application of the above will be better able to
contribute to claims avoidances.
EXECUTIVE
COUNCIL
CLAIMS
COMMITTEE
GENERAL FINANCE
PLANNING
PROJECTS DEPARTMENT
DEPARTMENT
COMMITTEE
EXECUTING DEPARTMENTS
CONSULTANTS
CONTRACTORS
Project works are executed under the authority of the appropriate Department, with
the control of payments resting with the Finance Department. Authority over the
Government‟s construction projects rests with the Executive Council of Abu Dhabi.
The claims review and resolution in Abu Dhabi which presents the opportunity for the
amicable settlement of Contractor Claims, usually carried out by any of the following
ways:
The resolution of claims at the Department level occurs when the Engineer
assess the claims and the Department and Contractor can agree the terms of
settlement of the claims. The General Projects Committee must approve
settlements involving an amendment of the Contract‟s time for completion and
settlements which amend the Contract value with Executive Council approval.
If the Department and the Contractor cannot agree the terms of a settlement
of the contractor‟s claims recommended by the Engineer, the Contractor can
request that his claims be referred to the Claims Committee for further review.
The Claims Committee is comprised of representatives of the concerned
Departments and is chaired by a member of the Executive council: The
Claims Committee utilizes independent claims experts and analysis in its
evaluation of claims. Claims Committee recommendations require Executive
Council approval.
Usually, in Abu Dhabi, the construction claims analysis procedure is divided into five
parts:
Notice.
Acknowledgment.
Merit Evaluation.
Cost and Time Evaluation.
Resolution.
Notice
The first phase of the claims process involves the Contractor‟s notice of the
claim. This phase is important as the Contractor‟s compliance with contractual
notice requirements may affect his entitlement. Such notice is commonly
imposed by construction contracts as a condition on the Contractor‟s
entitlement to relief.
Acknowledgement
Merit Evaluation
Resolution
After the Department / Engineer has evaluated the Contractor‟s claim with
respect to merit, cost and time, serious consideration should be given to
resolving all disputed issues. Generally, it will be in the best interest of the
Department to resolve claims as soon as possible. The early resolution of
claims will have the benefits to the Department. Any settlement of a claim will
reflect the relative positions and strengths of each party.
The Abu Dhabi GCCCW is divided into 12 chapters and is contained in 53 Articles
and is governed in „Arabic‟ (the ruling language of the country).
The Author has prepared a brief summary of the definitions of the following Major
Articles from the Abu Dhabi GCCCW in English (analysis of entire Articles of
GCCCW will lengthen the report and hence are not included).
Article Summary
Article 1 identifies the four elements which form the Contract. All four elements are
taken together as a unit to form the contract. According to Article 1, the four elements
are:
Drawings.
Make certain that the four elements of the contract are consistent.
Review the various documents to identify and correct ambiguities.
Make sure that the drawing and specifications are complete.
Convey a clear understanding of the scope of the project.
Treat seriously and respond in writing to clarifications / correspondences.
Correct inconsistencies when discovered during the tender phase.
Article Summary
Article 2 identifies the time upon which all of the works shall be competed.
Make certain that the time for completion is reasonable and achievable.
Carefully evaluate the likely time for completion of the project.
Perform an independent schedule evaluation.
Determine the shortest possible duration for the completion of the project.
Article Summary
Article 3 provides for the Extension of Time for completion of the Works, at the
discretion of the Department, for certain identified factors.
Article Summary
Article 4 provides that if the Contractor fails to satisfy any provision of the Contract or
specifications or otherwise fails to advance progress on the works, the Engineer may
suspend all or part of the Works. Any such suspension will remain in effect until the
Contractor has provided a remedy for such identified deficiencies. It is important to
note that the Contractor will have no right to claim for a time extension for any delays
by suspensions in accordance with this article.
Article Summary
Article 6 sets out the contract‟s mechanism for payment to the contractor for work
performed. The Contractor is required to the Engineer, who then verifies the
Contractor‟s statement and issues a payment certificates. Payment is made on the
basis of 90% of the value of executed works and 75% of the value of materials on
site, provided they comply with the specifications. Payment is to be made within 45
days of the submission of the payment certificate by the Engineer. Note that UAE
national contractors are exempted from any retention of funds if they provide a bank
guarantee in lieu thereof.
Article Summary
Articles 7 through 10, which collectively provide for changes and variations to the
contract as may be required by the Department. Articles 7 and 8 relate to
amendments of quantities. Articles 9 and 10 relate to amendments of the time for
completion.
Understand the type of contract employed (Lump sum, Unit Rates etc..),
Study the meaning and intention of the articles, and apply it fairly.
Endeavour to resolve differences amicably, if at all possible..
Be clear with the Contractor so that he understands that the threshold.
Article Summary
Maintain a clear record of any part handed over separately to avoid disputes.
Check whether the guarantee period has lapsed for a given part of the works.
Diligently record any notices of default and notices of intent to cure.
Article Summary
Article 17 addresses the requirements for the submission, review and approval of the
Contractor‟s proposed construction schedule. This article also identifies the
obligations of the Contractor and the Department with respect to the use of the
schedule following approval by the Department.
Article Summary
Article 18 describes the authority of the Engineer to issue instructions affecting the
Works.
Article Summary
Article 21 describes the Contractor‟s responsibility for the execution of the Works
according to the specifications. Article sets out the responsibilities of the parties with
respect to the testing of materials to ensure compliance with the specifications.
Record the reasons for resulting delays in materials, goods and workmanship.
Approval of alt. materials should expressly state Contractor‟s responsibility.
Alternative materials shall not entitle him to an extension of time, if possible.
Article Summary
Article 22, Work Progress Reports, requires the Contractor to submit to the Engineer
periodic detailed reports with respect to the progress of the works. The timing and the
form of the reports are to be specified by the Engineer.
Article Summary
Article 24 - Inspection of Site requires the Contractor to declare in writing that he has
inspected the site, determined that the soil is suitable for foundations in accordance
with the drawings and checked the drawings for the foundation requirements.
Typical Examples of Specific Risks and Treatment under Abu Dhabi GCCCW
Author has also provided a list of specific risks and its treatment under Abu Dhabi
GCCCW observed during his contract administration of the involved projects.
The case below illustrates some claims issues raised by the Contractor in one of the
Author‟s contract. Note that the conclusions reached in respect of any particular case
depend upon the circumstances present and the applicable contract provisions. It
cannot be assumed that similar issues would result in the same conclusions if
presented in the context of other projects where other circumstances and contract
provisions would apply.
This Claim Review Report has been prepared in response to „The Arab Contractors‟
Abu Dhabi (The Contractor) claim for extension of time and extra costs. The report
Contract Information
Contractor Submission
The Contractor has claimed a total 156 days extension of time as the difference
between the total lengths of the approval process for GRP Pipe materials against 30
days mentioned in the Contract, together with extra cost and losses in the amount of
AED 3, 524,686.
AED.
Delay in Approval of Materials 156 days
3,524,686.00
The Contractor has neither stated the specific Articles of the General Conditions of
Contract which he considers gives entitlement to his claim nor a reasoned
explanation as to their relevance. Also, the Contractor has not submitted any break-
down of his financial compensations.
The Engineer analyzes from the site records that there was a delay of 66 days due to
third party involvement in the approval of the pipe material submittal but disagrees
with the calculation of 156 days. The Engineer considers a reasonable assessment
to be 36 days (66 days - 30 days). However, from monitoring activities on site during
this „claimed delay period‟ appeared to have no effect on the overall progress, as the
Contractor was on schedule.
7. Conclusion
Author concludes that the Abu Dhabi GCCCW can be consistently interpreted and
applied by the Engineer for claims avoidances purposes, throughout the project
phase.
It can be achieved through the demonstration of the links between proper project
management and the use of specific policies and procedures.
Author reiterates that the practice of active claim avoidance techniques and the
utilization of a thorough claim review process can effectively abate the occurrence
and impact of Contractor claims.
8. Reference