Professional Documents
Culture Documents
Scott
Week 2: Possession
Silbereis
1
Contract analysis by obligations
• Five essential obligations
oPay/Build
oDesign/Follow design
oInstruct/Obey
oSet deadlines/Meet deadlines
oGive possession/Take possession
Possession
• What is “possession” of land?
oOwnership?
Possession
• What are the estates in land?
oFreehold
̶ “the estate fee simple absolute in possession”
̶ equivalent to an absolute owner
̶ A freehold estate is one where the duration
of ownership is indeterminate
oLeasehold
̶ Right to exclusive possession for a fixed term
(usually in exchange for an annual ground rent fee)
2
• How else can you be on land?
o Easement
o Licence
Possession
• The contract gives Contractor a licence, but…
• What is “possession”?
o A copy set of keys?
o Permission?
o “Exclusive possession”?
o Occupation?
3
Why does possession matter?
• The obvious – to build it!
• Tells us when to “start the clock”
oLate starting?
– Employer pays Contractor
oStart on time and late finish?
– Contractor pays Employer
Obligation to insure
“Occupation” Occupier’s Liability Acts
Some Examples:
4
Non Construction Example 1
• Adult dives in to shallow lake on land he had
trespassed and suffered severe head injuries.
But signs had been erected all around the
lake, some advising that swimming was
dangerous and others simply warning: 'No
swimming'. Despite this, Mr Tomlinson dived
in and received his injury.
o Who is liable?
• Who is Liable?
5
Non Construction Example 2
Construction Example
6
What if…
…the Employer doesn’t give possession?
1. Breach of Contract
Condition or Warranty?
= Repudiatory Breach
What if…
…the Employer doesn’t give possession?
2. Deferment
“Pause” the clock
̶ Default in SBC 2016: Up to 6 weeks
7
How does JCT deal with Possession
• Differently!!!!
Implied
What if…
…the Employer gives possession of part?
• Key question:
oPlanned & agreed (“sections”)
or
oForced & imposed?
What if…
…the Employer gives possession of part,
without having agreed it first?
8
What if…
…the Employer wants possession partially
returned?
• Project nearing completion, Employer wants
to move into the finished part
o If contract doesn’t provide for it, huge risk
(English Industrial Estates v Wimpey (1973))
o JCT SBC 2016 allows it, but logistic issues re
access, insurance, valuing part-complete
work, etc
o Alternative: JCT “Use or Occupy”
What if…
…all parties want to proceed, the
Contractor is ready to move on site and
the Employer ready to give possession
BUT
the Contract is not yet signed.
• What can they do?
9
Letters of Intent
• Generally not advisable
• But commercial reality sometimes
means…
10