Professional Documents
Culture Documents
Q D E G H M H Z P C
V L T E A M D Y X O
S P B V N O I T C A
V Y W F U N S P D C
T H S H W E A L T H
I B L T J Y O U G F
M J O Y E H S C N G
Q D E G H M H Z P C
V L T E A M D Y X O
S P B V N O I T C A
V Y W F U N S P D C
T H S H W E A L T H
I B L T J Y O U G F
M J O Y E H S C N G
BPM109
Contract Administration
Study Guide 2
Completion
Delay
Extension of Time
Liquidated Damages 3
Lecture Outline
Commencement of Work
Due diligence by Contractor
Completion date
Extension of Time (EOT)
Delay & Concurrent Delay
Liquidated Damages
4
Learning Objective
At the end of this unit, you are expected to:
7
Commencement of Work
• Contractor to commence work on Contact Commencement Date
8
Commencement of Work
Rapid Building Group v Ealing Family Housing (1984)
• Contract did not provide for EOT due to the Employer’s breach of
contract due to late site possession
Implication
• Time became at large
10
Completion Date as Stipulated in Contract
Contractor:
• Must complete the Project “On or
Before” the Contract Completion Date”
• Is to be issued a:
– Completion Certificate
(SIA)
– Certificate of Substantial
Completion (PSSCOC)
• Rectify outstanding defects
12
Significance of Issuance of Completion Certificate
• Commencement of
maintenance period
13
‘Let’s look at
Extension of Time’
14
Extension of Time
Contractor must:
• Complete on time unless Owner intervenes
15
Extension of Time Conditions
EOT will be given if:
16
Extension of Time
17
SIA Form of Contract and Extension of Time
18
SIA Form of Contract and Extension of Time
Example: SIA Measurement Contract (9th Ed)
19
PSSCOC Form of Contract and EOT
Contractor must:
• Notify (SO) within 60 days of the
delaying event
20
PSSCOC Form of Contract and EOT
In deciding EOT, SO has to consider:
• Effect or extent of any work omitted
• If event will delay the completion
• If there are Concurrent delays by Contractor
• If extension is fair, reasonable and necessary for completion
SO :
• Inform Contractor (in writing) of his decision….
• within the next 60 days from the date of the application.
• May request for further information
21
Grounds for EOT claims
a) Force majeure
b) Exceptionally adverse weather conditions
c) Fire, Storm, lightning, high winds, earthquake or aircraft or
aerial objects
d) War, hostilities, insurgency, terrorism, civil commotion or
riots
e) Industrial action by workmen, strike or embargoes
f) To comply with instructions
g) Failure on the part of the Employer to give site possession
h) Contractor did not receive necessary drawings and
information from Architect within a reasonable time
i) Shortage of labour (foreign or domestic), etc.
j) Any other grounds for EOT mentioned in the Contract
Document 22
SITUATIONS WHERE AD ARE GIVEN (SIA)
i. Ensure Contract Compliance
ii. Secure Safe methods of working and temporary works where
the Contractor is using unsafe or unsatisfactory method of
working
iii. Vary permanent/temporary work to assist the Contractor as
his request to overcome difficulty
iv. Vary permanent/temporary work as a consequence of
defective work or other default or breach of contract by the
Contractor
v. Suspend/postpone work in order to carry out investigations as
a reasonable consequence of defective work or other default
or breach of contract by the Contractor
vi. Alter or vary any previous direction
SITUATIONS WHEN AI ARE ISSUED (SIA)
i. To vary permanent or temporary work
ii. To vary temporary works/methods where desired by Architect
and where Contractor is entitled to use different
methods/temporary works
iii. To postpone or suspend work, to carry out investigations
required by architect, and not as a consequence of default/
defective work by Contractor.
iv. To carry out work or supply goods required under a P.C.
sum/item by Nominated or Designated Sub-
contractor/Suppliers
v. To carry out work or supply goods required under a Provisional
or Contingency sum/item, by Nominated Sub-contractor/
suppliers or the Contractor himself.
vi. To alter or vary any previous instruction
24
‘Let’s look at
Delay’
25
REASONS for DELAYS
1. Employer’s Delay
– Failure to give timely
possession of Site
– Failure by Architect to
provide plan, drawings and
information within
reasonable time.
– Variations ordered
3. Contractor’s Delay
– Late Mobilisation
– Insufficient resources
– Improper sequencing &
Planning of work
Indonesia Bans Land Sand Exports to Singapore, 6 Feb 2007
Indonesian export ban leaves Singapore short of granite
JAN 31, 2014
Boutique developer wound up in Singapore property market
slowdown, JUL 26, 2016
Employer :
• Can deduct LD from
Contractor after DC is issued
• Cannot deduct LD if DC is not
issued
• Can deduct LD from
Contractor at any time
• Can record LD in subsequent
Payment certificates
32
PSSCOC Form of Contract and Delay
• No requirement to issue a Delay Certificate
33
Concurrent Delay
• Means different types of delay overlapping over a period of time
34
1. Dominant Cause
When a Concurrent Delay occurs…
• Dominant Cause (or Real Cause) will prevail over the other cause
Example,
– Owner ask Contractor to stop work (Condo soft launch)
– Contractor facing severe labour shortage (Real cause)
– Owner may not award EOT
35
2. Apportioned Delay Approach
This Approach
• Considers the relative importance and degree of responsibility
for each delay
36
3. Malmaison Approach
Malmaison Approach:
• Considers only the Relevant Event
Example,
– Owner asks Contractor to stop work (Relevant Event)
– Contractor face labour shortage (Non-Relevant Event)
– Court will grant EOT to Contractor
37
SIA Form of Contract on Concurrent Delay
Delay is grouped into:
• Owner-caused Delays and Neutral events
• Contractor-caused Delays
38
SIA Form of Contract on Concurrent Delay
Others
Architect Employer Contractor
Unanticipated
• Poor design • Excessive • Poor weather
• Incomplete performance
changes Changing Market
design • Lack of
• Delays in conditions
resources
• Slow approval Unforeseeable
• Mismanageme
response • Prolonged nt conditions
planning • Labor Force majeure
• Delayed shortage
payment • Default 39
Further Delay or Further EOT
SIA Contract provides for Further Delay or Further EOT…
Architect must issue:
• Delay Certificate after the latest date for completion…. (LD
commences)
• “Termination of Delay Certificate” (“TDC”) if EOT is granted, and (LD
stops operating)
• A Revised Completion date
• “Further Delay Certificate” (“FDC”) if Contractor is unable to
compete by the revised completion date (LD commences again)
• Issue ‘Completion Certificate’ when all the Works (including
variation works) are completed (LD stops operating)
40
Further Delay or Further EOT
Scenario 1
• Contract period – 18 months
Question:
State the Contract Completion date and the
Extended Completion date.
42
Scenario 1
• Contract period – 18 months
Ans:
43
Scenario 2
• Contract period – 18 months
• Contract Commencement date - 12 Jan 2015
• EOT of 20 days granted to Contractor
• Contractor failed to complete the Works by the
Extended Completion date.
• Architect granted a further EOT from 10th - 13th of Aug
2016 for additional works
• Actual completion date - 18 Aug 2016
Question:
44
Scenario 2
• Contract period – 18 months
• Contract Commencement date - 12 Jan 2015
• EOT of 20 days granted to Contractor
• Contractor failed to complete the Works by the
Extended Completion date
• Architect granted a further EOT from 10th to 13th of
August 2016 for additional works
• Actual completion date - 18 Aug 2016
Ans:
Issue Delay Certificate – 1 Aug 2016
Issue Termination of Delay Certificate –10 Aug 2016
Issue Further Delay Certificate –14 Aug 2016
Issue Completion Certificate – 18 Aug 2016
45
Scenario 3
• 18-month contract period
• Contract Commencement date - 12 Jan 2015
• EOT of 20 days granted to Contractor
• Contractor failed to complete the Works by the Extended
Completion date
• Architect granted a further EOT from 10th to 13th of August
2016 for additional works
• Actual completion date - 18 Aug 2016
• Liquidated damages rate is $5000 per day.
Question:
Calculate the amount of liquidated damages chargeable
to the Contractor.
46
Scenario 3
• 18-month contract period
• Contract Commencement date - 12 Jan 2015
• EOT of 20 days granted to Contractor
• Contractor failed to complete the Works by the Extended
Completion date
• Architect granted a further EOT from 10th to 13th of August
2016 for additional works
• Actual completion date - 18 Aug 2016
• Liquidated damages rate is $5000 per day.
Answer:
Contract Period
Delay Certificate
(1 Aug 16)
Contract
Commencement Termination of
Date (12 Jan 15) Delay Certificate
(10 Aug 16) Further Delay
Certificate
Completion
(14 Aug 16)
Certificate
(18 Aug 16)
PSSCOC Form of Contract on Concurrent Delay
SO must:
• Inform EOT decision within a
reasonable time
51
‘Let’s look at
Liquidated Damages’
52
What is Liquidated Damages?
• Monetary amount fixed and agreed by the parties in advance, as
the damages payable in the event of a breach of contract
• Victim has to prove the actual loss caused to him by the delay
54
Liquidated Damages
Dunlop Tyre Co. Ltd v New Garage Ltd (1914)
Held:
• LD clause was considered a ‘penalty’ and unenforceable
55
What if there is No LD Clause In Contract?
• Employer has to go through the hassle of having to prove his claim
for damages
56
Summary
• Commencement of Work, Completion date
• Due diligence by Contractor
• Extension of Time (SIA Contract and PSSCOC form of Contract)
• Delay (SIA Contract and PSSCOC form of Contract)
• Concurrent Delay
– Dominant Cause
– Apportioned delay Approach
– Malmaison Approach
• Liquidated Damages
57
Reminder - Read
Contract Administration and Procurement in the
Singapore Construction by Lim Pin, Chapter 9.
58
Quiz Time
59
End of Seminar 2
60