Professional Documents
Culture Documents
Risk Handling
Types of Risk
Risk Management
risk plan
...what’s that?
Introduction
Risk, is a measure of the probability and consequence of not achieving a specific project
goal.
The project manager must:
Manage risk through the project life cycle
Identify the present risks in the project and in the environment
Transfer or reduce unacceptable risk
Set up monitoring and control systems to manage residual risk
Risk analysis a basic function of the human cognitive process - compares possible gains and
losses and makes a subjective decision
Risk = f (event, uncertainty, consequences)
Risk acts like a barrier to the development of effective strategy
Exposure: when a realised change in a variable within a given time scale will result
in a change in one or more of its key performance indicators
The greater the potential change in performance, the greater the exposure
Sensitivity: A function of three elements:
1) Significance (severity) of the organisations exposures to different events
2) Likelihood of different events occurring
3) Ability to manage the implications of these different events
Having an effective Risk Management Programme implies better possibilities of taking
advantage of risky opportunities in the marketplace
Risk can lead to both positive & negative outcomes, and it raises the need for an effective
way of managing risk to make sure it is effectively addressed and used.
Risk forecasting and prediction
Management
Response
Risk Management
Strategy
Risk Management System-1.Risk Identification
finding all risks that are likely to impact on a given project and explore the linkages and interdependencies
between them
risk identification typologies for project risk:
Much risk evaluation is subjective and therefore dependent on the risk attitude
of the risk taker and the perceived level of risk faced
Risk takers can be:
Risk seeking
Risk neutral
Risk averse
Risk attitude is also dependent on the type of setting the decision is made:
A Group will take accept more
risk than an individual.
A Multidisciplinary Group will be
even more risky decisions.
Teams tend to take more risky
decisions the longer they
are together.
Risk Management System-5.Risk response
Risk response: response depends on the nature of risk, detail of analysis and the attitude of the risk taker
Variables that affect risk response:
1- Risk retention
In general, risk retention applies to low impact, low probability risks
Ex.: manufacturers retaining the risk of 5% defect rate, but allows this risk transferred back by a
guarantee or warranty
2- Risk reduction
Engineering it out
Training and development
A risk-reduction matrix comprises 3 categories: risk, how to reduce probability, how to reduce impact
3- Risk transfer
Contractual clauses (damages clauses) or through negotiation
Most common: insurance contracts
4- Risk avoidance
Involves removing the risk in all forms from the project
Risk Management System-6.Risk Control
Risk control, policy and reporting
Process of using the information that has been learned on a project to assist in the later
development of the project.
The storage and classification of learned information is crucial to any risk management
system
Risk control involves monitoring risks that have been dealt with at a previous stage,
Experience with risk and risk management is often documented into a “risk handbook”,
which may be incorporated into the organisations “best practice” documentation
There must be frequent reporting on high impact, high probability risks present
Risk reports should be produced to a time-table and be controlled by an overall strategy,
with the frequency depending on the significance of the risk
A risk policy establishes a number of elements:
Breach: where one party acts in contravention with one ore more terms or conditions
Frustration: where a contract cannot be performed, even if both parties wish to do so.
Rescission: where there has been and error or misunderstanding in the preparation of the
original contract. The courts can then elect to rescind one or more contract terms if
they are not acceptable, for example in the case of contradictory terms
Rectification: where a contract term has been wrongly worded or phrased
Void: e.g. when the contract goods are illegal
Termination/determination: under certain circumstances a contract may be determined,
and this means that both parties to the contract cease works, and the party that has
determined the contract can seek reimbursement against the party who has been
determined (e.g. determination by the contractor because the client has not paid
agreed sums of money
Procurement
Process by which goods and services are acquired,
Good procurement leads to good suppliers and in turn
leads to increased performance/profitability
Most large organisations have a legal section
responsible for procurement, preparation and
execution of contracts.
Procurement act at 2 levels :
Punitive
Liquidated (cash)
Ascertained (based on actual losses incurred)
Typical examples of client risk include: