You are on page 1of 5

Installation and maintenance manual

AQA001078 – Assembly of CIP Spool

A27.11 CIP Spool . – W5-CM1


READ SEC 9 OMSM. Health and safety risks by contact with the BWMS, before continuing.

Rev. Date Author Approved Comment


0 01-01-2020 ANVI MKA First issue
A 01-04-2021 ANVI STAL Updated Size small units
B 01-09-2021 ANVI STAL General update new item no.

Figure 1

Description V10024 – V20066- V25126 V30186 V35246-


System V15064 V20086 V40366
size
Item no. 441437** 441437 441437 441436 441436
143324*
*Cu-Ni piping without valves.
**for SKM units the CIP is part of pipes.

Item Volume Flange Weight


Inlet/out
143324 1L DN50 / DN50 7,5 kg
441437 1L DN50 / DN50 12 kg
441436 2L DN50 / DN50 15 kg

Page 1 of 5
Installation and maintenance manual
AQA001078 – Assembly of CIP Spool

Handling and Installation: System placement

• Install according to PID diagram When installing be aware of mounting location.


• Secure the piping to avoid any It should always be installed horizontal and the
vibrations. valve with cap should always be in top as
shown. The operator needs to access the CIP
spool easily.

Tools and equipment needed


• Citric acid (solid)
• Protective gloves
• Protective glasses
• Wrench
• Bolt, nuts etc. (Not included CIP Spool)
• Sealing DN50 (Not included)
• 722760 - DESMI CIP 350 GR PLASTIC
BOTTLE

DANGER!

• Empty system before installing CIP


spool into system.

Page 2 of 5
Installation and maintenance manual
AQA001078 – Assembly of CIP Spool

Cleaning Operation.
DANGER!

• When operating and handling CIP unit,


glasses and gloves are required.

3. Close the bottom valve


4. Open the top Valve

1. Remove cap from top valve

5. Fill the chamber with Citric acid (solid)


according to table.

System Volume
V10024 -> V20086 0.7 kg
V25126 -> V30186 1.0 kg
V35246 -> V40366 1.4 kg
2. Drain off CIP unit into a bucket or bilge

Page 3 of 5
Installation and maintenance manual
AQA001078 – Assembly of CIP Spool

3
6. Close top valve
7. Reattach the cap on top valve

10. Press start (3)


11. Run for 300 seconds

4
1

8. On the HMI select Mode (1) 12. Press stop on the HMI (4)
9. Select Recirculation Manual mode (2) 13. Done. Successful Cleaning in place.

Page 4 of 5
Installation and maintenance manual
AQA001078 – Assembly of CIP Spool

Scheduled maintenance

Task Component Action Interval

Minimum before/after each ballast or de-ballast


P1 BWMS Cleaning
operation.

Citric acid for order


Item Description
722760 CIP 350 GR PLASTIC BOTTLE
722761 CIP 1 KG PLASTIC BUCKET
722762 CIP 5 KG PLASTIC BUCKET

Page 5 of 5