You are the PM for a new project and have figured out the following dependencies.
• Activity A can start immediately and has an estimated duration of four weeks.
Activity B can start after activity A is completed and has an estimated duration of
three weeks.
• Activity C can start after activity A is completed and has an estimated duration of
five weeks.
• Activity D can start after Activity B is completed and has an estimated duration
of eight
weeks.
2. What is the duration of the critical path. The critical path is the longest path
through the network. (22
weeks).
A (4)
/\
C (5) B (3)
\/
D (😎
3.What is the float of activity C? Float (slack) is the total time that a task can be
delayed without delaying the project. For Activity C, it is the time between the
earliest start and the latest start without delaying the project, which is 0 weeks.
4. Activity B is on the critical path, so it has 0 float. Any delay in Activity B will
5. The path with the longest float is the one not on the critical path.
E (5)
29/11/2023
-------------------------------------------//-------------------------------------------------------
--------
Ghi chú: Dùng FoxReader hoặc công cụ mở file PDF, dùng chế độ comment để trả
lời trực tiếp
vào file PDF này – xong lưu lại với tên file Ho_va_Ten_XXXX_Ex.pdf và nộp lên
E-
to increase to 10 weeks, will extend the critical path to A-C-D-E with a new
duration of
10 + 5 + 8 + 5 = 28
weeks.________________________________________________
_______
Learning
7. Activity F is on the critical path (A-C-D-E), so adding it will indeed increase the
correct.
8.Adding Activity F will increase the project duration by its duration, which is 11