Exercise in class (Individual): ____________ID#___________Draw a network

diagram and answer the questions below.

You are the PM for a new project and have figured out the following dependencies.

• Activity A can start immediately and has an estimated duration of four weeks.

Activity B can start after activity A is completed and has an estimated duration of
three weeks.

• Activity C can start after activity A is completed and has an estimated duration of
five weeks.

• Activity D can start after Activity B is completed and has an estimated duration
of eight

weeks.

• Activity E can start after Activity D is completed and after Activity C is


completed. This

activity takes five weeks.

1. Draw the PERT network diagram.

2. What is the duration of the critical path. The critical path is the longest path
through the network. (22

weeks).

A (4)

/\

C (5) B (3)

\/
D (😎

3.What is the float of activity C? Float (slack) is the total time that a task can be

delayed without delaying the project. For Activity C, it is the time between the

earliest start and the latest start without delaying the project, which is 0 weeks.

4. Activity B is on the critical path, so it has 0 float. Any delay in Activity B will

directly impact the project duration.

5. The path with the longest float is the one not on the critical path.

E (5)

29/11/2023

-------------------------------------------//-------------------------------------------------------
--------

Ghi chú: Dùng FoxReader hoặc công cụ mở file PDF, dùng chế độ comment để trả
lời trực tiếp

vào file PDF này – xong lưu lại với tên file Ho_va_Ten_XXXX_Ex.pdf và nộp lên
E-

6. Changing the resource on Activity A to a less experienced one, causing its


duration

to increase to 10 weeks, will extend the critical path to A-C-D-E with a new
duration of

10 + 5 + 8 + 5 = 28
weeks.________________________________________________

_______

Learning
7. Activity F is on the critical path (A-C-D-E), so adding it will indeed increase the

project duration by its duration, which is 11 weeks. Therefore, management's


concern is

correct.

8.Adding Activity F will increase the project duration by its duration, which is 11

weeks. Therefore, the project will take 28 + 11 = 39 weeks.