Professional Documents
Culture Documents
1. Background
Even while many transportation construction projects are eventually finished on
schedule and under budget, a closer look is likely to show that the original
budget and schedule were altered or expanded and the original goals were not
met. The grantee is responsible for completing the project in accordance with
the budget and timeline laid out in the FFGA because full funding grant
agreements (FFGA) for major transit projects issued by the Federal Transit
Administration typically require grantees to complete the work within the terms
outlined in the FFGA.
There will probably be a stronger emphasis on meeting the initial project
budget and schedule due to the heightened competition for funding for transit
projects. The FTA Project Management Oversight Program was established to
give the FTA unbiased feedback on the project's status, including scope, budget,
schedule, management procedures, and quality assurance, as well as to make
sure the grantees' Project Management Plan (PMP) is sufficient and being
carried out. Similar control procedures have been put in place by a number of
State and Local organizations that support significant transit projects.
2. The Lesson
Participants in the project are realistic about the team's performance,
recognizing clearly what can be accomplished with the resources available
at each stage of the project.
Adequate Project Management Plan and supporting documents including:
1. Well developed change order procedures and documentation. Often
changes mandated by operating departments should be controlled. In
some cases the change order process does not include features to
categorize the reasons for the changes permit the identification of trends
associated for such increases.
2. A well-developed PMP at the beginning of the project phase should be
undertaken.
3. Well developed supporting procedures with good checks and balances.
4. Adequate safety procedures and practices.
5. Adequate QA/QC procedures and practices.
DONNA MAY R. MORALES 4AR-2
Realistic constraints
1. Transit Agency Board/senior management/political leaders understand and
support the project, project staff with realistic expectations of the project
staff.
2. Independent internal project management oversight is used as a positive
management tool.
3. Design consultants are encouraged to provide independent input and
creative ideas and solutions to project issues.
4. The project scope, budget and schedule are not artificially constrained to
inhibit achievement of the project goals and objectives.
3. Applicability
Major transit-related projects are among the most difficult to plan, design,
build, and manage throughout construction. For such initiatives to be
implemented successfully, best practices in these fields must be used. This is
especially true for significant transit projects, when external pressures have a
significant impact on scope, time, cost, and quality. The public's and financial
partners' support for transit agencies' further future projects will rise as a result
of their track record of successful projects.
The "Key Factors for Successful Project Implementation" are not meant to be an
exhaustive list of factors that will positively affect a project or a "Silver Bullet"
that, if used, will ensure a project's success. However, if these elements are
included in the project's planning, development, and execution, the risks will be
lower and the likelihood of attaining the project's objectives will be higher. No of
the magnitude of the project, these factors still apply.
4. References
49 CRF Part 633 - Project Management Oversight; Final Rule
49 CRF Part 633 - Project Management Oversight; Final Rule
International Standards Organization (ISO) 9000 - Quality management and
quality assurance standards - guidelines for selections and use.
Project and Construction Management Guidelines 1996 Update, June 1996
Final Report, EG&G Dynatrend, Inc.
Best Practice Procurement Manual, December 1998
Comments submitted to FTA by John Holak, Risk Manager for Urban
Engineers, November 2015