Brick Work for 3rd to 5th Floor level Mulund (w) Socitey

Sr.no Discription No L B D/H


Brick work in superstructure in cm (1:6)
1 Brick work Flat No.B-109 1 34.8 0.15 2.3
3.05*5=15.25 , 3.20+0.15*2=6.7
2.9+0.15*2=6.1 ,2.4=2.4
2.25*2= 4.5 ,1.4=1.4
1.2*3=3.6 ,
, 1=1
1.5=1.5
2.1=2.1

Deductions
Door1=0.90+0.15 3 3.15 0.15 2.1
Toilet=0.75+0.15 1 0.9 0.15 2
WC=0.75+0.15 1 0.9 0.15 2
W1=2.40+0.15 2 5.1 0.15 1.2
W2=2.25+0.15 1 2.4 0.15 1.2
W3=1.80+0.15 1 1.95 0.15 1.2
V=0.60+0.15 2 1.5 0.15 0.6

2 Brick work Flat No.


3.05+0.15*=3.35 , 2.75+0.15*2=3.05 34.4 0.15 2.3
2.9+0.15*2=3.2 ,2.3+0.15=2.45, 3.45+0.15=
2.25+0.15*2= 2.55 ,1.4+0.15=1.55
1.2+0.15=1.35 , 3.65+0.15=3.8
3.05+0.15*2=3.35 , 1+0.15=1.15
1.50+0.15*2=1.8 , 1.2+0.15*2=1.5
2.1+0.15=2.25

Deductions
Door1=0.90+0.15 5 5.25 0.15 2.1
Toilet=0.75+0.15 1 0.9 0.15 2
WC=0.75+0.15 1 0.9 0.15 2
W1=2.40+0.15 3 7.65 0.15 1.2
W2=2.25+0.15 1 2.4 0.15 1.2
W3=1.80+0.15 1 1.95 0.15 1.2
V=0.60+0.15 2 1.5 0.15 0.6

3 Brick work Flat No.


3.05+0.15=3.2 , 3.65+0.15*2=3.95 38.35 0.15 2.3
2.9+0.15*2=3.2 ,3.5+0.15=3.65, 3.45+0.15=3.6
2.25+0.15*2= 2.55 ,1.2+0.15=1.35
2.1+0.15=2.25 , 4.20+0.15*2=4.50
3.05+0.15*2=3.35 , 1+0.15=1.15
1.55+0.15*2=1.85 , 1.2+0.15*2=1.5
2.1+0.15=2.25

Deductions
Door1=0.90+0.15 3 3.15 0.15 2.1
Toilet=0.75+0.15 1 0.9 0.15 2
WC=0.75+0.15 1 0.9 0.15 2
W1=2.40+0.15 2 5.1 0.15 1.2
W2=2.25+0.15 1 2.4 0.15 1.2
W3=1.80+0.15 1 1.95 0.15 1.2
V=0.60+0.15 2 1.5 0.15 0.6

4 Brick work Flat No.


3.05+0.15=3.2 , 3.65+0.15*2=3.95 45.65 0.15 2.3
2.9+0.15*2=3.2 ,3.5+0.15=3.65, 3.45+0.15=3.6
2.25+0.15*2= 2.55 ,1.2+0.15=1.35
2.1+0.15=2.25 , 4.65+0.15*2=4.95
3.05+0.15*2=3.35 , 1+0.15=1.15
1.50+0.15=1.65 , 1.2+0.15*2=1.5
2.1+0.15=2.25, 3.5+0.15*2=3.8
2.9+0.15*2=3.2

Deductions
Door1=0.90+0.15 3 3.15 0.15 2.1
Toilet=0.75+0.15 1 0.9 0.15 2
WC=0.75+0.15 1 9 0.15 2
W1=2.40+0.15 2 5.1 0.15 1.2
W2=2.25+0.15 1 2.4 0.15 1.2
W3=1.80+0.15 1 1.95 0.15 1.2
V=0.60+0.15 2 1.5 0.15 0.6

5 Staircase brick work


5.40+0.15*2=11.1 , 3.45+0.15=3.6 14.7 0.15 2.3

6 Lift brick work


1.8+0.15*2=3.9 ,1.10+0.15=1.25 5.15 0.15 2.3

Deduction
Lift Door=0.90+0.15*2=2.1 2.1 0.15 2.3

deduction T-Junction n=32 2.4


1/2*32*0.15

Total M3
Sr.no Discription No Qty Total No
1 No of Brick for 3rd to 5th floor 3 22177.13 66531.38
Qtym3 Total Qty

12.006

0.99225
0.27
0.27
0.918
0.432
0.351
0.135 8.63775

11.868

1.65375
0.27
0.27
1.377
0.432
0.351
0.135 7.37925

13.23075
0.99225
0.27
0.27
0.918
0.432
0.351
0.135 9.8625

15.74925

0.99225
0.27
2.7
0.918
0.432
0.351
0.135 9.951

5.0715 5.0715

1.77675

0.7245 1.05225

2.4 2.4

44.35425