Professional Documents
Culture Documents
Part 20 Combined Strikethrough PDF en
Part 20 Combined Strikethrough PDF en
"adjacent to an means within a distance less than or equal to the overall depth of the
excavation" excavation, measured from a vertical line through the toe of the excavation
face;
“application drawings” also known as erection drawings, means drawings that contain the
information necessary for the erection, use and dismantling of
formwork, falsework, reshoring and associated components and
equipment of the formwork, falsework and reshoring;
"asbestos-containing has the same meaning as in section 6.1;
material"
"construction project" means any erection, alteration, repair, dismantling, demolition, structural or
routine maintenance, painting, land clearing, earth moving, grading,
excavating, trenching, digging, boring, drilling, blasting, concreting, the
installation of any machinery or any other work deemed to be construction by
the Board;
"demolition" means tearing down, destruction, breakup, razing or removal of the whole or
part of a building or structure, or of free standing machinery or equipment that
is directly related to the function of the structure;
"excavation" means any cut, cavity, trench or depression in the earth’s surface resulting
from rock or soil removal;
“falsework” means a temporary support structure used to support loads during a
construction project;
"fill" means any soil or other loose material that is constructed to form an
embankment or a part of the foundation of a structure or improvement;
"formwork" includes the foundation, supporting structure, and mould into which concrete
will be placed; means a temporary support system used to contain cast-
in-place concrete during a construction project, but does not include
falsework;
"formwork designer" means the professional engineer responsible for the design of formwork;
“reshoring” means a temporary support system used to support a slab or other
structure and withstand loads during a construction project after
formwork and falsework have been removed;
"stockpile" means any soil or other loose material that is placed in an area for storage
but that is not intended to function as fill;
"tilt-up construction" means a system of building construction in which concrete wall panels are
placed in position in the permanent structure and temporarily braced or
supported;
"trench" means an excavation less than 3.7 m (12 ft) wide at the bottom, over 1.2 m
(4 ft) deep, and of any length.
Page 1
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Page 2
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Page 3
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Page 4
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
(2) The certificate required by subsection (1) must be available at the site
for inspection by an officer.
(3) If a gang form is being reused on the same jobsite with any modification
to the gang form design or method of erection, subsection (1) applies in
relation to the reuse of the gang form.
(4) If a gang form is being reused on the same jobsite without modification
to the gang form design or method of erection certified under subsection
(1), immediately before placement of concrete or other intended
loading, the employer must ensure that the gang form is inspected by a
qualified person who
(a) confirms that the gang form has been erected in accordance with
the latest approved erection drawings and supplementary
instructions, and
(b) documents the inspection and the confirmation under paragraph
(a), including the specific location at which the gang form is being
reused and the date of inspection.
(5) The documents required by subsection (4)(b) must be available at the
site for inspection by an officer.
“specified formwork” means formwork of a type listed in section 20.17 (1) (a) to (n);
“worksite specific plans” means the worksite specific application drawings and any associated
specifications and supplementary instructions.
Application 20.16.2 Sections 20.17 to 20.26 apply only to cast-in-place concrete.
Worksite 20.17 (1) The employer must ensure that worksite specific plans are
specific plans prepared for the following types of formwork and any associated
required for falsework or reshoring:
specified
(a) flyforms;
formwork
(b) ganged forms;
(c) jump forms;
(d) vertical slip forms;
(e) formwork over 4 m (13 ft.) in height;
(f) suspended forms for beams, slabs, stairs and landings;
(g) single sided, battered or inclined forms over 2 m (6.5 ft.) in
height;
(h) cantilever forms;
(i) bridge deck forms;
(j) shaft lining forms;
(k) tunnel lining forms;
(l) formwork into which concrete will be pumped through an
injection port below the upper concrete surface;
(m) formwork over 3 m (10 ft.) in height into which self-
consolidating concrete will be placed;
(n) formwork designated by the designer of the structure.
(2) The employer must ensure that a professional engineer certifies
the following in accordance with section 20.18:
Page 5
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Page 6
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Page 7
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Flyform 20.22 (1) Application drawings and supplementary instructions for flyforms
handling must show a step by step procedure for all phases of each cycle of
assembly, flying, use, dismantling and reuse of each flyform panel,
including special procedures for non-typical floors.
(2) If any flyform panel is not inherently stable for all possible
conditions of load, special notation on the flyform application
drawings and supplementary instructions must draw attention to
the procedure for obtaining stability.
(3) The employer must ensure that the application drawings and
supplementary instructions required by subsections (1) and (2),
including special procedures required for non-typical floors, are
made available to workers involved in any part of the assembly,
flying, use, dismantling and reuse of each flyform panel.
Supervision 20.23 The employer must ensure that
(a) a qualified supervisor supervises the erection, use and
dismantling of formwork, falsework and reshoring, and
(b) workers are instructed in
(i) the hazards that they may be exposed to, and
(ii) the precautions to be taken while around or on formwork,
falsework and reshoring.
Equipment 20.24 The employer must ensure that equipment, materials and hardware
requirements used in the erection, use and dismantling of formwork and any
associated falsework and reshoring meet the requirements specified in
the worksite specific plans.
Concrete 20.25 (1) The employer must ensure that protruding objects that create a
placing risk of injury are removed or effectively guarded.
hazards
(2) During placement of concrete or other significant loads on the
formwork, a person must be restricted from the areas underneath
where the loads are placed.
(3) After placement of concrete or other significant loads on the
formwork, a person must be restricted from the areas underneath
where the loads were placed until it can be confirmed by a
qualified person that the formwork is withstanding the loads.
(4) Placement of concrete or other loads
(a) must stop if any of the following occurs:
(i) weakness;
(ii) undue settlement;
(iii) excess distortion of specified formwork or any associated
falsework or reshoring;
(iv) other similar unanticipated or dangerous condition, and
(b) may only restart after the formwork, falsework or reshoring has
been repaired or strengthened as specified by a professional
engineer.
(5) Loads must not be applied to uncured concrete structures except
as permitted by the worksite specific plans.
Inspections 20.26 (1) Subject to subsection (4), immediately before placement of
concrete or other intended loading of specified formwork and any
associated falsework or reshoring, the employer must ensure that
Page 8
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
EXPLANATORY NOTES:
The collapse of concrete formwork, falsework and reshoring is a significant worksite hazard. When plans
and construction methods do not account for loads imposed, these temporary support structures can
collapse during erection, use or dismantling. Fatalities, serious injuries and near miss incidents
associated with the erection, use and dismantling of concrete formwork and falsework have occurred in
B.C.
Sections 20.17 – 20.26 of the Occupational Health and Safety Regulation (“OHSR”) currently state
requirements for the erection, use and dismantling of concrete formwork, falsework and reshoring.
Section 20.17 lists specific types of formwork requiring erection drawings and supplementary instructions
certified by a professional engineer.
Inspections and investigations by WorkSafeBC have identified formwork not erected or used in
accordance with the required erection drawings and supplementary instructions. Furthermore, there are
currently no requirements in the OHSR for plans to address the loads imposed on formwork due to self-
consolidating concrete (a product exerting greater pressure on formwork than regular concrete), the
properties of the concrete mix, or the method of concrete placement.
The purpose of the proposed amendments is to ensure the safe erection, use and dismantling of concrete
formwork, falsework and reshoring. Overall, the proposed amendments intend to clarify the
responsibilities of employers and professional engineers.
Page 9
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
The new requirement for worksite specific plans for formwork into which self-consolidating concrete will
be placed was revised from 2 m (6.5 ft.) in height to 3 m (10 ft.) following public consultation. This change
was based on feedback received relating to financial impacts on industry and the limited availability of
engineers to certify the required plans.
Further, the proposed “gang forms” are renamed “ganged forms” to clarify the proposed regulations apply
to the assembly of ganged forms rather than to just a single panel.
Proposed subsection (2) states it is the employer’s responsibility to ensure the worksite specific plans, as
well as any changes to them, are certified by a professional engineer. Further details on this obligation
are prescribed in proposed section 20.18.
Proposed subsection (3) embodies the current requirement in section 20.17(2) to ensure plans are
available at the worksite during erection, use and dismantling of formwork, falsework and reshoring.
Proposed subsection (4) requires any changes to the worksite specific plans to be available at the
worksite as soon as practicable, and before the pre-pour inspection.
Proposed subsection (5) incorporates a new requirement for the employer to ensure the formwork,
falsework and reshoring are erected, used and dismantled in accordance with up-to-date plans. This
ensures the worksite specific plans are followed.
Finally, housekeeping amendments were made to Policy Item R20.17-1 RE: Construction, Excavation
and Demolition - Concrete Formwork and Falsework - Specifications and Plans in order to reflect the
proposed amendments to section 20.17.
Page 10
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
The reference to CSA Standard S269.1-16, Falsework and formwork replaces the 1975 version of the
standard and CSA Standard CAN/CSA S269.3 M92, Concrete Formwork. This better reflects current
industry practice while maintaining worker safety.
The proposed amendments include a new requirement to specify in the plans the maximum concrete
slump the form or mould is able to withstand. The amendment originally proposed required the plans to
specify the properties of concrete mix the form or mould was able to withstand. This requirement was
revised based on public consultation feedback. Industry needs to be able to adjust concrete mixes on
short notice to address changes in weather and other site-specific issues. The changes provide more
flexibility to adjust to changing site conditions while still ensuring the formwork is not overloaded by
concrete exceeding the maximum permissible slump specified by the professional engineer. Concrete
slump is the key property affecting the lateral pressure exerted on formwork.
Proposed subsection (2) states if any information cannot be provided, then the plans must include special
notation of the incomplete information requiring further design. The language originally proposed was
“field design”. Based on feedback received during public consultation, and for further clarity, the term
“field designed” was replaced with “further design”. This proposed requirement addresses situations
where it is not possible for the professional engineer to specify at the time some of the site-specific
information required by subsection (1). This would typically include information dependent on conditions
at the construction site such as, for example, ground conditions. Any further design will need to be
certified under section 20.18.
Page 11
PROPOSED AMENDMENTS FOR PART 20: CONSTRUCTION, EXCAVATION AND DEMOLITION
IN THE OCCUPATIONAL HEALTH AND SAFETY REGULATION
Proposed subsection (1) provides it is the employer’s responsibility to ensure protruding objects creating
a risk of injury are removed or effectively guarded. This proposed requirement addresses risks created by
steel reinforcement bars, anchor bolts and any other protruding objects.
Proposed subsections (2) and (3) expand the current requirements restricting worker access to areas
underneath formwork during and after the placement of concrete or other intended loading to apply to all
persons. Furthermore, the access restriction after placement stated in proposed subsection (3) remains in
place until a qualified person confirms the formwork is withstanding the loads. The term “qualified” is
defined in section 1.1 of the OHSR as being knowledgeable of the work, the hazards involved and the
means to control the hazards, by reason of education, training, experience or a combination thereof.
Proposed subsection (4) specifies under which circumstances the placement of concrete or other loads
must stop: when there is weakness, undue settlement, excess distortion, or other similar unanticipated or
dangerous condition. The phrase “or other similar unanticipated or dangerous condition” was added
following public consultation based on feedback received.
Finally, proposed subsection (5) ensures loads are only applied to uncured concrete structures as
permitted by the worksite specific plans.
The term “other intended loading” used in subsection (1) is explained in OHS Guideline G20.26
Inspections. It refers to loads such as trusses, beams, and similar elements which require temporary
support until they can be tied in and secured to perform as an effective structural system, and be self-
supporting.
Page 12
PREVENTION MANUAL
BACKGROUND
1. Explanatory Notes
Section 20.17 sets out the requirements for specifications and plans for concrete
formwork and falsework falsework and formwork.
2. The Regulation
Section 20.17:
(1) The employer must ensure that a set of plans and specifications meeting
the requirements of CSA Standard S269.1-1975, Falsework for
Construction Purposes and CSA Standard CAN/CSA-S269.3-M92,
Concrete Formwork is prepared for the formwork for each job and for all
items of concrete work, the failure of which could cause injury.
(3) The following types of concrete formwork require erection drawings and
supplementary information certified by a professional engineer:
(a) flyforms;
Page 1
POLICY ADVICE AND RECOMMENDATIONS
PRIVILEGED AND CONFIDENTIAL
ATTACHMENT 3
(1) The employer must ensure that worksite specific plans are
prepared for the following types of formwork and any
associated falsework or reshoring:
(a) flyforms;
Page 2
POLICY ADVICE AND RECOMMENDATIONS
PRIVILEGED AND CONFIDENTIAL
ATTACHMENT 3
(4) The employer must ensure that any changes to the certified
worksite specific plans are available at the worksite
(5) The employer must ensure that the formwork, falsework and
reshoring are erected, used and, if applicable, dismantled in
accordance with up-to-date certified worksite specific plans.
POLICY
Page 3
POLICY ADVICE AND RECOMMENDATIONS
PRIVILEGED AND CONFIDENTIAL
ATTACHMENT 3
Officers will order concrete placing stopped if the inspection certificate is not
available at the site or is not valid.
Page 4