Professional Documents
Culture Documents
UID: 2020300026
Exp. No: 7
AIM: Determine project completion time and critical path using CPM
Earliest start time (ES): This is simply the earliest time that a task can be
started in your project. You cannot determine this without first knowing if
there are any task dependencies
Latest start time (LS): This is the very last minute in which you can start a
task before it threatens to delay your project timeline
Earliest finish time (EF): The earliest an activity can be completed, based on
its duration and its earliest start time
Latest finish time (LF): The latest an activity can be completed, based on its
duration and its latest start time
Forward Pass In Cpm:
Use the CPM diagram and the estimated duration of each activity to determine
their earliest start (ES) and earliest finish (EF). The ES of an activity is equal
to the EF of its predecessor, and its EF is determined by the CPM formula EF
= ES + t (t is the activity duration). The EF of the last activity identifies the
expected time required to complete the entire project.
ACTIVITIES:
UI Design UI - 7
Frontend Development FD UI 14
Database Selection DS - 1
Frontend Testing FT FD 3
Unit Testing UT I 2
CPM: UI:
0 7 7
UI
0 0 7
DS:
0 1 1
DS
12 12 13
FD:
7 14 21
FD
7 0 21
API:
1 8 9
API
13 12 21
EXI:
1 7 8
EXI
14 13 21
DBS:
1 2 3
DBS
19 18 21
FT:
21 3 24
FT
21 0 24
BT:
9 3 12
BT
21 12 24
I:
24 5 29
24 5 29
UT:
29 2 31
UT
29 0 31
HFV:
31 2 33
HFV
31 0 33
Therefore by analyzing our CPM tables and including the activities with slack
time 0 in the critical path, the critical path comes out to be:
UI -> FD -> FT -> I -> UT -> HFV
The total number of days required to complete the technical work as per the
CPM analysis comes out to be 33 days.
CONCLUSION: The experiment demonstrated that the Critical Path Method (CPM) offers a
structured and systematic approach to project planning and scheduling. By
identifying the critical path, project managers can allocate resources
efficiently and reduce the risk of delays.