Professional Documents
Culture Documents
Improving Frequency Resilience Through Dynamic-Adaptive Load Shedding
Improving Frequency Resilience Through Dynamic-Adaptive Load Shedding
11 September 2023
Outline
• Control Coninuum
• Conclusion
Control Continuum
Control Continuum
Inertial Control
• More of an effect than an actual control since it is governed by physical principles for most
resources and emulated by others
• Rotating mass in a typical generator combined with speed at which it is rotating creates a large
amount of stored energy
• If a decelerating force is applied (e.g., a large drop in system frequency), energy is transferred
from rotating mass and into system
• When mismatch between injected and consumed energy occurs, energy flows from rotating
masses of connected resources into power system
• Propagation of this effect across an interconnection happens within a few seconds
• Inverter-based resources are not typically governed by same physical principles → might not
possess inertia per se from → inertia can be emulated by using sensing and control
Control Continuum
Primary Control
• Commonly known as primary frequency response (PFR)
• PFR also includes inertial response described under Inertial Control as well as other types of
frequency response actions
• Does not require external inputs and begins to occur within first few seconds following a change
in system frequency (disturbance)
• Frequency response is provided by the following:
• Governor Action: governor sense changes in local system frequency and adjust energy output of the
resource to counteract that change
• Demand Response: speed of directly-connected motors will change in direct proportion to frequency
changes → as frequency drops, motors will turn slower and consume less energy
• Rapid reduction of system load may by automatic operation of under-frequency relays
Control Continuum
Secondary Control
• Some resources (e.g., hydroelectric generation or fast electrical storage) can respond faster
• Secondary control is accomplished using supervisory control and data acquisition (SCADA) and
energy management system (EMS), and manual actions taken by dispatcher to provide additional
adjustments
Control Continuum
Tertiary Control
• Tertiary Control encompasses actions taken to get resources in place to handle current and future
contingencies
• Reserve deployment and reserve restoration following a disturbance are common types of
Tertiary Control
Control Continuum
Time Control
• Frequency and balancing control are not perfect → occasional errors due to instrument
transducer inaccuracy, problems with SCADA hardware or software, or communications errors →
due to these errors and normal load and generation variation, ACE in an Interconnection cannot
be maintained at zero. In fact, the average value of ACE over many time frames is non-zero → ACE
must be managed such that its magnitude is relatively small
Control Continuum
• Power system stability is the ability of an electric power system, for a given initial
operating condition, to regain a state of operating equilibrium after being
subjected to a physical disturbance, with most system variables bounded so that
practically the entire system remains intact
Resiliency problem
Stability problem
Frequency, Hz
44
45
46
47
49
50
51
48
1/01/2014 11:27:26.496
1/01/2014 11:27:35.136
1/01/2014 11:27:43.776
1/01/2014 11:27:52.416
Resiliency and Stability
1/01/2014 11:28:01.056
1/01/2014 11:28:09.696
1/01/2014 11:28:18.336
Bangladesh grid failure, 1 Nov. 2014
1/01/2014 11:28:26.976
1/01/2014 11:28:35.616
1/01/2014 11:28:44.256
Power System Resiliency
• Resiliency is an intrinsic characteristic of a grid or portion of a grid
• Grid resilience is a foundational building block for clean energy future, which
requires renewable resources, energy storage, and electrification
• Safe operation of power systems is critical for energy security and effective
functioning of all infrastructures
Need For Resiliency
• Increased resiliency harden the power system against and quickly recover from
high-impact, low-frequency events, such as
• System recovery
• Damage Assessment • Outage Management • Visualization • Spares Strategies
• Survivability
• Basic Level of Service • Urgent Service
Frequency Resiliency
• Power system
frequency can be
considered as the
“pulse” of the system,
reflective of the
underlying health of
the system
Frequency Resiliency
• Conservative settings
• Checks speed at which threshold is exceeded: higher speed, more load shed
• Adaptive load shedding scheme sets ROCOF thresholds and size of load blocks to
be shed at different thresholds decided real time
Limitations of Adaptive/Semi-Adaptive Load Shedding
• System inertia
• Power flow in a feeder varies from peak to off-peak in a day as well as from
season to season around the year
• Cannot deal with feeder load variation due to lack of adequate adaptability
Limitations of AUFLS/S-AUFLS Schemes
• Voltage collapse
issue not
considered in
load shed
scheme
• Assumptions
• Quantity of real-time data is reasonable that can be dealt with modern infrastructure
• Lower/higher level data fusion can be applied to further reduce data bandwidth
Bangladesh power
system network (BPSN)
Dynamic-Adaptive Load Shedding Methodology
North-East
region
Northern region
Central region
South-East region
Southern region
Dynamic-Adaptive Load Shedding Methodology
Low grid voltage in BPSN at different buses at the 132 kV level
Dynamic-Adaptive Load Shedding Methodology
Low grid voltage in BPSN at different buses at the 230 kV level
Dynamic-Adaptive Load Shedding Methodology
• Parameters considered
i. Frequency excursion
Step-1: Measurement
• Active power and frequency of each generator
• At steady state, frequencies of all generating units essentially equal → fg1 = fg2 = . . . =fgi = fsys
Step-2: Detection of generation loss event
• For each generator, present and previous samples of active power generation are compared in
order to find a generation loss event
Pgi (n) – active power generation of i-th generator at n-th instant (i.e., present value)
Pgi (n–1) – active power generation of ith generator at (n–1)-th instant (i.e., previous value)
ε – threshold value (in %) to decide whether load shedding scheme should be enabled; decided based on the frequency
management strategy
Dynamic-Adaptive Load Shedding Methodology
• After detecting an actual generation loss event at any PV bus, the proposed scheme first assesses
frequency recovery due to load damping, calculated as follows
Ploss – magnitude of generation loss (in MW)
N – total number of generators incurring the loss of generation
Δf – frequency deviation from pre-disturbance frequency (in Hz)
R – governor droop (in %)
D – frequency sensitivity due to load damping factor (in MW/Hz)
• In order to keep system frequency above the lower acceptable threshold (fTH in Hz), following
condition must be satisfied
Note: load damping factor implies the percentage of load change for every 1% change in system frequency;
usually varies between 1% and 3%
Dynamic-Adaptive Load Shedding Methodology
• The required amount of total load shedding (Pshed in MW) to retain system frequency above fTH is
calculated by
Pshed – magnitude of total load shed
Δf – frequency deviation from pre-disturbance frequency
R – governor droop (in %)
D – frequency sensitivity due to load damping factor (MW/Hz)
• Total load shed is divided amongst all zones across the whole network according to their
frequency disturbance profile
Dynamic-Adaptive Load Shedding Methodology
• Frequency disturbance profiles of each zone given by rate of change of average frequency decline
• dfcoi_z/dt (Hz/s) of a zone indicates the rapidity of frequency drop due to generation loss
• Higher dfcoi_z/dt implies that this zone is more vulnerable in terms of frequency response due to
active power disturbance, and larger amount of load shed is required at that zone
Dynamic-Adaptive Load Shedding Methodology
• Total load shed size (Pshed) is distributed amongst all zones of a power system according to severity
of frequency disturbance
• Higher amount of load shed at relatively weaker bus and less amount of load at relatively stronger
bus inside a zone to maintain the voltage stability
• Total zonal load shed quantity is distributed amongst all PQ buses within a zone according to their
bus ranking (buses are ranked using Fast Voltage Stability Index (FVSI))
• Load shed size for each PQ bus (Bzk in MW) inside a zone
FVSI is a tool for bus classification, which is widely utilised in voltage stability analysis
< details of FVSI discussed later in ‘FVSI Subroutine’ section >
Dynamic-Adaptive Load Shedding Methodology
• Feeders are selected such that the summation of power flow of selected feeders is very close to
bus load shed size (Bzk)
Step-11: Dynamic correction of bus load shed size of substations within a zone
• Total power flow (ΣPi) of selected feeders is checked for close match to bus load shed size (Bzk)
• Any difference (εb) is adjusted to the next substation load shed amount
• Process continued for subsequent substations (i.e. k = 3, 4, …) until following condition is satisfied
Dynamic-Adaptive Load Shedding Methodology
• If in a zone ΣBzk is not very close to Loadz, the next zonal load shed size is modified by deviation εz
• Process continued for z3, z4, and so on until ΣBzk is very close to Loadz
• Dynamic corrections of sub-station and zonal load shed sizes are done in two phases so that total
load shed does not exceed Pshed
Dynamic-Adaptive Load Shedding Methodology
• Trip signals sent to all selected feeder circuit breakers of all zones using communication
infrastructure to arrest rapid frequency decline while maintaining voltage stability
• Step-A3: Normalization of all FVSI in a zone FVSIz_k – normalized FVSI of k-th bus of zone z
N – total number of PQ buses in zone z
• Step-A4: All PQ buses are ranked according to their normalised FVSI within their own zone
• Normalized FVSI (FVSIz_k) values are used in main scheme to distribute zonal load shed size amongst PQ
buses inside a zone
Tie-Line Security Scheme
Step-B1
• After getting signal from step-14 of main scheme, tie line security scheme waits for a while (Twait)
• This allows time for all circuit breakers selected by main scheme to operate for load shedding and
also to redistribute power flow through tie lines
• Twait considers opening time and arching time of circuit breaker, signal transmission time from
control centre to the most distant circuit breaker and so on
• Twait should be less than thermal runway time (Tthermal) of tie lines
Tie-Line Security Scheme
Step-B2
• After elapsing Twait period, this scheme measures either sending end MVA (MVAmeasured) or current (Imeasured)
• Compare magnitude of measured MVA or current with their respective permissible limits
Step-B3
• If a tie line is overloaded loads are shed at receiving-end zone
• LT-shed is distributed among buses of receiving-end zone according to bus ranking (FVSI)
Step-B5
• Summation of power flow of selected feeders maintained close to load shed amount (LT-shed)
Dynamic-Adaptive Load Shedding Methodology
Mehrabi K, Afsharnia S, Golshannavaz S. Toward a wide-area load shedding scheme: Adaptive determination of frequency
threshold and shed load values. Int Trans Electrical Energy Systems 2018;28(1):1–14.
Test Network
IEEE 39 bus test network
Case - Monitoring of tie line security for 400 MW generation loss in Zone-1
Before disturbance
• Current through two tie lines between zones 1 and 2 were 232 A and 389 A
• Current through the two tie lines decreases to 451 A and 596 A
Critical Parameters
• Disturbance size
• Governor droop
• Delays in PMUs
• Computational time
Impact of VRE
• The required amount of load shedding can be determined by the proposed algorithm
Performance Comparison
• Comparison between D-AUFLS and AUFLS for 900 MW generation loss in zone-3
• AUFLS works
based on df/dt
and under
frequency (U/F)
relays
Performance Comparison