Professional Documents
Culture Documents
BETWEEN
AND
GROUNDS OF DECISION
Introduction
[4] For ease of reference, they will be referred below by the acronym
KK and TMTS respectively.
1
[2019] 1 LNS 1705 Legal Network Series
(268 katil) Kuala Krai, Kelantan (Reka & Bina) at the lump sum of
RM4,600,000.00.
[6] There were disputes and differences that arose between them under
the Sub Contract and as a result, TMTS on 10 January 2019 initiated
adjudication proceedings pursuant to the Construction Industry Payment
and Adjudication Act 2012 (“CIPAA”).
[11] KK has since commenced a suit in KL Sessions Court suit no. WA-
B52C-43-08/2019 (“Suit”) for final determination of the same disputes and
differences that have arisen pursuant to the Sub Contract.
[13] The affidavits that were filed in respect of the Application are as
follows:
2
[2019] 1 LNS 1705 Legal Network Series
(2) The High Court may grant a stay of the adjudication decision
or order the adjudicated amount or part of it to be deposited with the
Director of the KLRCA or make any other order as it thinks fit.”
[17] KK submitted that by having instituted the Suit, it has met the
threshold requirement of s. 16 of the CIPAA as interpreted by Lee Swee
3
[2019] 1 LNS 1705 Legal Network Series
Seng J (now JCA) in Terminal Perintis Sdn Bhd v. Tan Ngee Hong
Construction Sdn Bhd & Other Case [2017] 1 LNS 177 as follows:
...
4
[2019] 1 LNS 1705 Legal Network Series
[58] Here, the Court finds that the Plaintiff has simply not offered
any reason, cogent or worthy of examination, to warrant a stay. As
amply shown in case law from other jurisdictions, reasons must be
offered. Each of those reasons will be examined. If those reasons
pertain to the financial status of the Defendant as one of doubtful
solvency or near insolvency, the Court still needs to examine why
that may be the case. In our present case, the Plaintiff has not even
offered those reasons for the Court’s consideration. Instead, it has
offered evidence of its own financial status; that it is in the position
to pay up.”
[18] Accordingly, KK contended that since the Sub Contract has been
completed, the Court should grant a stay by reason that the cash flow which
is required for the works under the Sub Contract is no longer critical
following the Singapore Court of Appeal case of SA Shee & Co Pte Ltd v.
Kaki Bukit Industrial Park Pte Ltd [2000] 1 SLR (R) 192 where Chao Hick
Tin JA held as follows:
5
[2019] 1 LNS 1705 Legal Network Series
6
[2019] 1 LNS 1705 Legal Network Series
[119] That would undo all that the construction industry had sought
to do including changing the culture and mindset of deliberate or
designed delay in making payments to the Contractor the Work
already done and to do so with impunity. That would be to turn back
the hands of the clock to pre-CIPAA regime and it would be a great
disservice done to the CIPAA.”
[22] TMTS contended that the merits of KK’s case in the Suit is
irrelevant. The nature of the adjudication decision is purely monetary and
hence the general principles stay of enforcement as set out in the Federal
Court case of Kosma Palm Oil Mill Sdn Bhd v. Kooperasi Serbausaha
Makmur Berhad [2004] 1 MLJ 257 apply here.
7
[2019] 1 LNS 1705 Legal Network Series
[24] In the premises, TMTS concluded that KK did not demonstrate the
existence of any special circumstance. The Application is hence without
merit and must be accordingly dismissed.
[25] It is not in dispute that KK met the threshold requirements set out in
s. 16 of the CIPAA.
[26] As to the need for cash flow, it is axiomatic that every construction
project requires cash flow. Malaysian construction industry contracting
financing is pyramidal and layered. Project cash flow is not synonymous
with corporate cash flow. Project cash flow is part of the larger corporate
cash flow. The project cash flow which is derived from progress payments
generally sustains the execution of the project to completion only.
However, the continuing subsistence and survival of the construction
company as an ongoing concern to undertake projects is dependent on
corporate cash flow. Besides progress payments, corporate cash flow is
critically dependent too on the penultimate and final payment after the
project completion. The profit of the construction company realizable from
the project is often only recovered in the final payment after settling the
debts of sub contractors and suppliers. These are the harsh Malaysian
construction industry realities. Without corporate cash flow, it is therefore
8
[2019] 1 LNS 1705 Legal Network Series
[27] I am hence of the view that there is neither a difference nor lesser
importance of cash flow needs after the project completion contrary to that
as contended by KK. The Singapore case of SA Shee & Co Pte Ltd v Kaki
Bukit Industrial Park Pte Ltd (supra) relied on by KK is distinguishable
because it concerned a summary judgment application prior to the advent
of statutory adjudication. More pertinently and with respect, I hold that the
discussion and determination therein based just on project cash flow
without corporate cash flow considerations is artificially restrictive and
simplistic.
9
[2019] 1 LNS 1705 Legal Network Series
26. In a number of the authorities which I have cited above the point
has been made that each case must turn on its own facts. Whilst I
respectfully agree with that, it does seem to me that there are a
number of clear principles which should always govern the exercise
of the court’s discretion when it is considering a stay of execution in
adjudication enforcement proceedings. Those principles can be set
out as follows:
10
[2019] 1 LNS 1705 Legal Network Series
[63] It would appear that about the only special circumstance in the
context of justifying a stay of execution of such a judgment would be
when there is cogent evidence pointing to a reasonable probability
that the successful Claimant might not be in a position to pay back
the judgment sum should the Respondent in the adjudication succeed
on appeal or that the Claimant is already in liquidation.”
[30] From the affidavit evidence adduced by TMTS, I find that albeit
TMTS has a positive current assets position which is a few times larger
than the adjudicated sum, the financial status is derived from that of its
audited balance sheet for the financial year ending 2017. TMTS did not
disclose its audited balance or even its draft balance sheet for the financial
year ending 2018 which should have been produced by now. No
explanation for its failure to do so has been put forth by TMTS. In addition,
I noticed that 2 new open bank charges have been added to secure loans
11
[2019] 1 LNS 1705 Legal Network Series
taken by TMTS in new 2019 but the borrowed sums have not been
disclosed.
Conclusion
12
[2019] 1 LNS 1705 Legal Network Series
Counsel:
For the plaintiff - K. Selva Kumaran, G. Shankar & Yan Jie Luan; M/s
Rose Hussin
For the defendant - James Ding Tze Wen, Tey Siaw Ling; M/s C. H. Tay &
Partners
13