You are on page 1of 96

Subject : MONTHLY PROGRESS REPORT (August- 2017)

Period : 21st July 2017– 20th August 2017

Contractor : QD-SBG CONSTRUCTIONS

Project : CONSTRUCTION OF CP07-B : LUSAIL TOWERS


INFRASTRUCTURE,LRT STATION,CAR PARKS &
LANDSCAPE

Scope of Work : SUPPLY & INSTALLATION OF WATERPROOFING SYSTEM


CONTENTS
1. Preface
2. Overview
2.1 Ongoing construction activities
2.2 Waterproofing materials used in the project
2.3 PVC T-Lock
2.4 Integritank spray membrane
2.5 Joint System
2.6 Eliminator Spray membrane
2.7 Additional Work
3. Total Areas Achieved
3.1 Waterproofing Area achieved this month
3.2 Total waterproofing area achieved in project
3.3 Planned Area VS Executed Area for this month
3.4 Total planned area VS executed area in project.
3.5 Total Progress of Project

4. Manpower Deployment
4.1 Planned VS deployed manpower

5. Procurement
5.1 Material delivered to site from 21th July 2017 to 20th August 2017
5.2 Planned procurement for the month of September 2017

6. Quality Management System (RFI, NCR, CAR’s, ISOR)


7. Safety Report (NCR)
8. Subcontractor concerns
9. Target of next period (August 21st to September 20th 2017)
10. Conclusion
11. Annex 1 (Detailed progress)
12. Annex 2 (Progress Photos)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 1


1. Preface
This report covers work done and problems encountered for this project on
waterproofing over the period 21st July 2017 to 20th August 2017.

Moving forward in this report the following parties will be identified as follows:
- Qatari Diar Real Estate Investment Company will be known as the
“Client”
- Parsons International Ltd will be known as the “Program Management
Consultant”
- Dorsch Qatar will be known as the “Supervision Consultant”
- QD-SBG CONSTRUCTIONS will be known as the “Main Contractor”
- Intertectra Qatar will be known as the “Sub-Contractor”
- Other Sub-Contractors engaged by “QD-SBG CONSTRUCTIONS” will be
known as “Other Sub-cons”
Any other parties pertinent to the project will be referred to by name.

I. At this time Intertectra Qatar deploys two shifts of eight hours; for the
purpose of this report and the subsequent reports to follow this month,
it should be noted that a “day” refers to a 16 hour work period, till
otherwise stipulated and or noted.
II. In an effort to maintain the quality of this report, re-evaluation(s) of the
quantities and dates for each of the current scopes of work will be on-
going; any corrections if required will be noted in the following month’s
report and adjusted accordingly.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 2


2. Overview
The sub-contractor has not received any formal program from the contractor for
the period of 21st July 2017 to 20th August 2017.

Installations of PVC T-LOCK Membrane, Construction Joints, Expansion Joints and


Application of Integritank Spray Membrane, Eliminator Spray Membrane, Surface
preparation were the main waterproofing activities we have concentrated.

Additional works (Installation of Swellable Bar, Internal Waterstop with Injection


Hoses, Patching of Tears and Punctures in PVC T-LOCK Membrane.

2.1 Ongoing construction activities, site location


The scope of the Subcontract Works comprises the provision of all
necessary supply and installation of waterproofing works for 3 Nos. of
Substations, Design of Road A1 Tunnel, Design of Road A1 Tunnel including
LRT, Design of Bridge at Junction-19 and Design of underground car park all
as detailed.

 DESIGN PACKAGE-D SUBSTATIONS-ST1,ST2 & ST3


 DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL
 DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT
 DESIGN PAKAGE-G-DESIGN OF BRIDGE AT JUNCTION-19
 DESIGN PACKAGE-H-DESIGN OF UNDERGROUND CAR PARKS

MPR- AUGUST 2017 INT/CRP/FR/011 Page 3


2.2 Waterproofing materials used in this project:

a) Waterproofing to Undersides & Sides of Concrete Substructures consisting of:

1. 2.0 mm thickness flexible PVC Keyed preformed sheet membrane to


mechanically lock into the base slabs continuously at 65mm centers and
for upturns 1000mm up the base slab edges. The upturned PVC
membrane shall be overlapped and bonded to the spray membrane wall
waterproofing for continuous tanking system. (2mm thick PVC Keyed
performed membrane will be T-LOCK Membrane, manufactured by
Naturel Muhendislik in Turkey.

b) Waterproofing to Walls and Roofs of Concrete Structures consisting of:

2. i) 2.0 mm thickness Elastomeric Cold Sprayed Liquid Waterproofing


membrane comprising primer and two (2) separately applied coats of
two (2) colors layers of 1mm each. (Spray applied membrane will be
INTEGRITANK, manufactured by Stirling Lloyd - UK)

ii) Connections with the T-Lock membrane for Continuous Tanking


System; Up-stand (1 m) using T-Lock membrane will be primed with
Metaset Structural Adhesive 200 mm wide (Manufactured by Stirling
Lloyd – UK) and overlapped by 2mm thick Integritank spray membrane in
two color coded coats.

c) Joints

i. Construction Joints:

- Slabs: 180mm wide reinforced scrim embedded into spray membrane


over the joint including Hydrophilic Swelling Gasket and re- injectable
hose fixed onto the joint face.

- Walls: 180mm wide reinforced scrim embedded into spray membrane


over the external joint including Hydrophilic Swelling Gasket and re-
injectable hose fixed onto the joint face.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 4


ii. Expansion Joints:

- Base Slabs: External PVC Waterstop welded to T-Lock PVC membrane,


Internal Waterstop placed centrally (if practical) and re-injectable hoses
clipped to both outer edges of the Internal Waterstop.

- Roof Slabs: The External Waterstop will not function well due to
entrapped air so it would be replaced with a PVC Tape System lapped by
spray waterproofing for continuity. Internal Waterstop placed centrally (if
practical) and re-injectable hoses clipped to both outer edges of the
Internal Waterstop.

- Walls: External PVC Waterstop with spray applied waterproofing


membrane overlapping the Waterstop for continuity of waterproofing.
Application of a further protection layer of 2mm PVC sheet membrane
welded to the External Waterstop and lapped by spray waterproofing
membrane. Internal Waterstop placed centrally (if practical) and re-
injectable hoses clipped to both outer edges of the Internal Waterstop.

d) Waterproofing to Top of Base Slab of Tunnels and Underpasses of Concrete


Structures consisting of:

- 2mm Stirling Lloyd MMA (Eliminator) Cold applied Spray membrane


applied to the tunnels & underpasses top of base slab.

The materials used on this project and mentioned in this report, are as per the
current contract agreement with the Main Contractor.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 5


2.3 PVC T-LOCK

Out of the Original Contractual BOQ of 194,232.00m2, 68% / 132,102.38 m2 of PVC


T-lock has been accomplished till date.

For the month of August 2017, 1,904.30 m2 PVC T-lock has been installed.

2.4 Integritank Spray Membrane

Out of the Original Contractual BOQ of 179,724.00M2/23,192.04m² applied for


Integritank spray membrane in wall Structure.

For the month of August 2017, 3,001.70M2 Integritank Spray Membrane has been
applied.

2.5 Joint System

2.5.1 Construction Joints

Out of the Original Contractual BOQ of 58,237.00LM, for the month of August
2017, 561.70 lm Construction Joints has been installed in Base Slab & Wall, till the
20th of August 2017, a total of 14,720.35 lm has been installed.

2.5.2 Expansion Joints

Out of the Original Contractual BOQ of 7,812.00LM, for the month of August
2017, 727.22 lm Expansion Joints has been installed in Base Slab & Wall, till the
20th of August 2017, a total of 4,083.42 lm has been installed.

2.6 Eliminator Spray Membrane

Up to the month of August-2017, 469.31 M2 Eliminator Spray Membrane have


been accomplished till date.

2.7 Surface Preparation

Up to the month of August-2017, 9,925.74 M2Surface preparations have been


accomplished till date.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 6


2.8 Additional Work

2.8.1 Swellable Bar for Horizontal Construction Joint

Up to the month of August-2017 we did 1,771.15 lm for Horizontal Construction


Joint in Wall.

2.8.2 Repair for damaged waterproofing (Patching of tears and punctures in PVC
T-LOCK membrane)

Up to the month of August-2017 we did 1,263.00 no’s patches in PVC T-LOCK


Membrane.

2.8.3 Internal Waterstop & Injection Hose

Up to the month of August-2017, 351.49lm Internal Waterstop & Injection Hose at


Zone-2 has been done.

2.8.4 Removal and Replacement of damaged T-lock Membrane

Up to the month of August-2017, 2,086.62M2 PVC T-LOCK at Zone-4 & Zone-2 has
been installed.

2.8.5 Removal & Replacement of Waterstop before concrete casting

Up to month of August-2017, 2lm Removal & Replacement of Waterstop before


concrete casting has been done.

2.8.9 Spray Integritank over Damaged PVC T-LOCK

Up to the month of August-2017, 1,461.20M2 Spray Integritank over damaged PVC


T-LOCK has been Installed additionally.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 7


3. Total Areas Achieved
Initial start month of the Sub-Contractor’s portion of the project is 22nd March,
2016.
A Schedule program for the subcontract work has not been received for our
procurement of materials and our planning of resources.

3.1 Waterproofing area achieved this month (21stJuly to 20thAugust)


Integritank Eliminator
Surface
UNIT PVC T-LOCK Spray Spray Cons. Joints-(lm) Exp. Joint (lm)
Preparation
Membrane -m² Membrane -m²
DESIGN PACKAGE-D-SUBSTATIONS

DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL 1,904.30 2,346.13 469.31 394.48 727.22 780.00

DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT - 655.57 167.22 -

DESIGN PACKAGE-G-DESIGN OF BRIDGE AT JUNCTION-19

DESIGN PACKAGE-H-DESIGN OF UNDERGROUND CAR PARK - -

Total Qty. 1,904.30 3,001.70 469.31 561.70 727.22 780.00

3.2 Total waterproofing area achieved in project


Integritank Eliminator
Surface
UNIT PVC-T-LOCK Spray Spray Cons. Joints-(lm) Exp. Joint (lm)
Preparation
Membrane -m² Membrane -m²
DESIGN PACKAGE-D-SUBSTATIONS

DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL 97,112.40 19,695.56 469.31 7,636.22 4,018.04 9,925.74

DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT 21,535.68 3,496.48 5,734.31 65.38

DESIGN PACKAGE-G-DESIGN OF BRIDGE AT JUNCTION-19

DESIGN PACKAGE-H-DESIGN OF UNDERGROUND CAR PARK 13,454.30 1,349.82

Total Qty. 132,102.38 23,192.04 469.31 14,720.35 4,083.42 9,925.74

3.3 Planned Area VS Executed Area for this month(August-2017)


ITEM NO. Description Executed Remark

1 PVC T-LOCK 1,904.30 There has been verbal Request

2 Integritank -m² 3,001.70 There has been verbal Request

3 Eliminator -m² 469.31 There has been verbal Request

4 Cons. Joints-(lm) 561.70 There has been verbal Request

5 Exp. Joint (lm) 727.22 There has been verbal Request

6 Surface Preparation 780.00 There has been verbal Request

MPR- AUGUST 2017 INT/CRP/FR/011 Page 8


3.4 Total Progress of Project:
Actual Balance to
Item No. Description Original BOQ (M²) % Completed
Installed QTY Complete

1 PVC T-LOCK 194,232.00 132,102.38 68% 62,129.62

2 Integritank -m² 179,724.00 23,192.04 13% 156,531.96

3 Eliminator-m² Rate only 469.31

4 Cons. Joints-(lm) 58,237.00 14,720.35 25% 43,516.65

5 Exp. Joint (lm) 7,812.00 4,083.42 52% 3,728.58

6 Surface Preparation Rate only 9,925.74

3.5 Total waterproofing area achieved in ZONES:


Integritank Eliminator
Surface
Location Pvc T-lock Spray Spray Cons. Joints-(lm) Exp. Joint (lm)
Preparation
Membrane-m² Membrane-m²

PAKAGE-E
36,032.48 6,616.28 2,962.05 1,336.21 3,534.06
ZONE-1

PAKAGE-F
21,535.68 3,496.48 5,734.31 65.38
ZONE-2
PAKAGE-H
13,454.30 1,349.82
ZONE-3
PAKAGE-E
61,079.92 13,079.29 469.31 4,674.17 2,681.83 6,391.68
ZONE-4

Total Qty. 132,102.38 23,192.04 469.31 14,720.35 4,083.42 9,925.74

MPR- AUGUST 2017 INT/CRP/FR/011 Page 9


3.6 Total Progress of Project for PVC T-lock:

3.7 Total Progress of Project for Construction Joint:

MPR- AUGUST 2017 INT/CRP/FR/011 Page 10


3.8 Total Progress of Project for Expansion joint:

3.9 Total Progress of Project for Integritank:

MPR- AUGUST 2017 INT/CRP/FR/011 Page 11


3.10 Waterproofing area achieved this month (Additional Work)
REMOVAL &
PATCHING OF
INTERNAL REMOVAL AND REPLACEMENT OF
TEARS AND Spray Integritank
WATERSTOP & REPLACEMENT OF WATERSTOP BEFORE SWELLABLE
UNIT PUNCTURES IN Over Damaged PVC T-
INJECTION DAMAGED T-LOCK CONCRETE CASTING BAR(LM)
PVC T-LOCK LOCK(M2)
HOSE(LM) MEMBRANE(M2) (EXTERNAL
MEMBRANE(NO'S)
WATERSTOP)(LM)

DESIGN PACKAGE-D-SUBSTATIONS

DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL - - 28.45 67.00 72.79

DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT 62.17 - 83.59 - 31.25

DESIGN PACKAGE-G-DESIGN OF BRIDGE AT JUNCTION-19

DESIGN PACKAGE-H-DESIGN OF UNDERGROUND CAR PARK

Total Qty. 62.17 - - 112.04 67.00 104.04

3.11 Total waterproofing area achieved in project(Additional Work)


REMOVAL &
PATCHING OF
INTERNAL REMOVAL AND REPLACEMENT OF
TEARS AND Spray Integritank
WATERSTOP & REPLACEMENT OF WATERSTOP BEFORE SWELLABLE
UNIT PUNCTURES IN Over Damaged PVC T-
INJECTION DAMAGED T-LOCK CONCRETE CASTING BAR(LM)
PVC T-LOCK LOCK(M2)
HOSE(LM) MEMBRANE(M2) (EXTERNAL
MEMBRANE(NO'S)
WATERSTOP)(LM)

DESIGN PACKAGE-D-SUBSTATIONS

DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL 1,396.62 2.00 1,234.08 1,207.00 1,178.70

DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT 351.49 690.00 537.07 56.00 282.50

DESIGN PACKAGE-G-DESIGN OF BRIDGE AT JUNCTION-19

DESIGN PACKAGE-H-DESIGN OF UNDERGROUND CAR PARK

Total Qty. 351.49 2,086.62 2.00 1,771.15 1,263.00 1,461.20

MPR- AUGUST 2017 INT/CRP/FR/011 Page 12


4. Manpower Deployment
Since we have only been given verbal requests to achieve base slab
waterproofing for the month of August 2017, we can’t plan our manpower
actually.
Manpower Deployment Schedule (Planned vs. Actual)

WEEK-70 WEEK-71 WEEK-72 WEEK-72


SL.NO Category
Planned Actual Planned Actual Planned Actual Planned Actual
1 Project Manager 1 1 1 1
2 QA/QC Superintendent. 1 1 1 1
3 Site Engiineer 2 2 2 2
4 Document Controller 1 1 1 1
5 QA/QC Engineer 2 2 2 2
6 QA/QC Field Inspector 1 1 1 1
7 HSE Personnel 2 2 2 2
8 Store Keeper 2 2 2 2
9 Supervisor 2 2 2 2
10 Foreman 2 2 2 2
11 Leadman 1 1 1 1
12 Operatives 25 25 25 25
TOTAL 42 42 42 42

23/08/2017 to 29/08/2017-WK-70
30/08/2017 to 05/09/2017 -WK-71
06/09/2017to 12/09/2017 - WK-72
13/09/2017 to 19/09/2017- WK-73

4.1 Planned Manpower VS Deployed Manpower: September- 2017


The allocation of skilled labors for each work scope is estimated as follows:

DESCRIPTION MANPOWER TURNOVER TIME


REQUIRED *BASED ON 8HRS PER DAY

Installation of PVC T-lock with an 10 2


estimated surface area of 1000 m2 or less:

Installation of Waterstops (Base Slab, Wall 6 1 (Base Slab & Roof )


& Roof) / 3 (Wall)

Application of Integritank (Wall & Roof: 15 2


500m2 Foundation: 1000m2)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 13


The constant deployment for this period on this project and the breakdown of the
categories is as follows:
Category

Project Mgr. 1
QA/QC Superintendent. 1
Site Manager 1
Site Engineers 2
Document Controller 1
QA/QC Engineers 2
QA/QC Inspectors 1
HSE Personnel 1
Store Keeper 2
Supervisors 2
Foremen 2
Lead man 1
Applicators 25

MPR- AUGUST 2017 INT/CRP/FR/011 Page 14


5. Procurement
The procurement activity is concentrated on meeting the committed quantity of
materials delivered to site as outlined by the initial BOQ and or any adjustments
made thereafter as site conditions dictate.

5.1 Material delivered to site from 21st July– 20th August 2017

SL.NO DESCRIPTION QTY UNIT DELIVERY SITE

1 PVC STRIP (20MX2.2MX2.2MM) 2 ROLLS Site Facility


EUROSEAL PVC T-LOCK MEMBRANE
2 236 ROLLS Site Facility
(2.20 METRES WIDTH)
3 PAI PRIMER 190 KG 1 DRUM Site Facility
4 PAI PRIMER 190 KG 1 DRUM Site Facility
5 PAI PRIMER 190 KG 1 DRUM Site Facility
6 PAI PRIMER 190 KG 1 DRUM Site Facility
7 ELIMINATOR PT A TROPICAL (200 KG) 16 DRUMS Site Facility
8 ELIMINATOR PT B YELLOW (192 KG) 8 DRUMS Site Facility
9 ELIMINATOR PT B MID GREY (192 KG) 8 DRUMS Site Facility
10 BPO POWDER CATALYST 4 BOXES Site Facility
11 INTERNAL PVC WATERSTOP (CJ954) 30 ROLLS Site Facility
12 EXTERNAL PVC WATERSTOP (CJ926) 30 ROLLS Site Facility
13 AGGREGATES (50KG/BAG) 10 BAGS Site Facility

5.2 Planned Procurement for the month of September 2017


There is no Planned Procurement for this period.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 15


6. Quality Management System (RF NCR,CAR’s,ISOR)
6.1 RFI List for the month of August-2017
S.No. LOCATION UNIT CONTRACT IRF'S NO

1 ZONE-4 SEGMENT-40A TOP OF RAFT ZONE-4 ELIMINATOR SPRAY CV-21079R00

ZONE-2 SEGMENT 19(PARTIAL) RAFT VERTICAL


2 ZONE-2 INTEGRITANK SPRAY WF-041272
PLANE WEST SIDE
ZONE-2 SEGMENT 19(10 METERS FROM SEGMENT
3 ZONE-2 INTEGRITANK SPRAY WF-041244
18) WEST SIDE FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-19(10 METERS FROM SEGMENT
4 ZONE-2 INTEGRITANK SPRAY WF-041232
18) RAFT HORIZONTAL PLANE WEST SIDE
ZONE-2 SEGMENT-20 RAFT HORIZONTAL PLANE
5 ZONE-2 INTEGRITANK SPRAY WF-041235
WEST SIDE
ZONE-2 SEGMENT-21 RAFT HORIZONTAL PLANE
6 ZONE-2 INTEGRITANK SPRAY WF-041240
WEST SIDE
ZONE-2 SEGMENT-20 RAFT VERTICAL PLANE WEST
7 ZONE-2 INTEGRITANK SPRAY WF-041276
SIDE
ZONE-2 SEGMENT-21 RAFT VERTICAL PLANE WEST
8 ZONE-2 INTEGRITANK SPRAY WF-041292
SIDE
ZONE-2 SEGMENT-20 EXTERNAL WALL-1 WEST SIDE
9 ZONE-2 INTEGRITANK SPRAY WF-041246
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-21 EXTERNAL WALL-1 WEST SIDE
10 ZONE-2 INTEGRITANK SPRAY WF-041251
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-23 EXTERNAL WALL-1 WEST SIDE
11 ZONE-2 INTEGRITANK SPRAY CV-21010R00
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-22 EXTERNAL WALL-1 WEST SIDE
12 ZONE-2 INTEGRITANK SPRAY CV-21009R00
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-22 RAFT HORIZONTAL &
13 ZONE-2 INTEGRITANK SPRAY CV-21007R00
VERTICAL PLANE WEST SIDE
ZONE-2 SEGMENT-23 RAFT HORIZONTAL 7
14 ZONE-2 INTEGRITANK SPRAY CV-21008R00
VERTICAL PLANE WEST SIDE
ZONE-2 SEGMENT-1 RAFT HORIZONTAL & VERTICAL
15 ZONE-2 INTEGRITANK SPRAY CV-20875R00
PLANE EAST SIDE
ZONE-2 SEGMENT-1 EXTERNAL WALL-2 EAST SIDE
16 ZONE-2 INTEGRITANK SPRAY CV-20872R00
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-2 EXTERNAL WALL-2 EAST SIDE
17 ZONE-2 INTEGRITANK SPRAY CV-20873R00
FROM TOP OF RAFT
ZONE-2 SEGMENT-2 RAFT HORIZONTAL & VERTICAL
18 ZONE-2 INTEGRITANK SPRAY CV-20876R00
PLANE EAST SIDE
ZONE-2 SEMENT-3 EXTENAL WALL-2 EAST SIDE
19 ZONE-2 INTEGRITANK SPRAY CV-20874R00
FROM TOP OF RAFT TO 2.5M HEIGHT
ZONE-2 SEGMENT-3 RAFT HORIZONTAL & VERTICAL
20 ZONE-2 INTEGRITANK SPRAY CV-20877R00
PLANE EAST SIDE
ZONE-2 SEGMENT-6 & 7 DELAYED STRIP AT RAFT
21 ZONE-2 INTEGRITANK SPRAY CV-20656R00
VERTICAL PLANE WEST SIDE

MPR- AUGUST 2017 INT/CRP/FR/011 Page 16


ZONE-2 SEGMENT-6 & 7 DELAYED STRIP AT RAFT
22 ZONE-2 INTEGRITANK SPRAY CV-20658R00
VERTICAL PLANE EAST SIDE
23 ZONE-2 SEGMENT-15 RAFT EAST SIDE ZONE-2 INTEGRITANK SPRAY WF-034001
ZONE-4 SEGMENT-20A ,20B AT EXTERNAL EAST SIDE
24 ZONE-2 INTEGRITANK SPRAY WF-041864
FROM TOP BLINDING TO TOP OF WALL
ZONE-4 SEGMENT-28A,28B,29A,29B,30A,30B
25 EXTERNAL WEST SIDE FROM TOP OF RAFT SURFACE ZONE-4 INTEGRITANK SPRAY CV-20532R00
TO 1.8M HEIGHT OF WALL
ZONE-4 SEGMENT-28A,28B,29A,29B,30A,30B
26 EXTERNAL WEST SIDE FROM TOP BLINDING TO TOP ZONE-4 INTEGRITANK SPRAY CV-20530R00
OF RAFT
ZONE-4 SEGMENT-20B WALL-11 EXTERNAL WEST
27 ZONE-4 INTEGRITANK SPRAY WF-040818
SIDE FROM TOP OF BLINDING TO TOP OF WALL
ZONE-4 SEGMENT-20A WALL-11 EXTERNAL WEST
28 ZONE-4 INTEGRITANK SPRAY WF-040817
SIDE FROM TOP OF BLINDING TO TOP OF WALL
ZONE-4 SEGMENT-11A &11B EXTERNAL WEST SIDE
29 ZONE-1 INTEGRITANK SPRAY WF-042164
FROM TOP OF RAFT TO TOP OF WALL
ZONE-1 SEGMENT-12A EXTERNAL WEST SIDE FROM
30 ZONE-1 INTEGRITANK SPRAY WF-041048
TOP OF BLINDING TO TOP OF WALL
ZONE-1 SEGMENT-12B EXTERNAL WEST SIDE FROM
31 ZONE-1 INTEGRITANK SPRAY WF-041509
TOP OF BLINDING TO TOP OF WALL
ZONE-4 SEGMENT 39A OUTER FACE EAST SIDE
32 ZONE-4 INTEGRITANK SPRAY CV-20899R00
FROM TOP OF RAFT TO TOP OF WALL-7

6.2 NCR (Non-conformance Report) issues up to the month of August-2017

List of NCR’S up to the month of August-2017.


S.I NCR NO. LOCATION SEGMENT DATE DATE STATUS REMARK
ISSUE CLOSED

Dorsch required one more test


LUS-
to be done (Density test)
CP7B- 20-Nov-
1 4 - Open Intertectra insist N/A. QD-SBG
DCQ-NCR- 16
suggested to brought up with
QL-00184
the Clients

LUS-
CP7B- INT & QD-SBG to take necessary
2 All 1-Dec-16 Open
DCQ-NCR- action ASAP.
QL-00199

LUS- Awaits Sika PVC flat membrane


CP7B- from QD-SBG & INT to take
3 All - 30-Jan-17 Open
DCQ-NCR- further action. Till now, no
QL-00262 available samples.

LUS-
4 All - 31-Jan-17 Open The same with NCR # 184
CP7B-
DCQ-NCR-

MPR- AUGUST 2017 INT/CRP/FR/011 Page 17


QL-00263

LUS-
Proposed Corrective Action
CP7B- 18-Feb-
5 1 9B Open submitted to QA-QD-SBG, awaits
DCQ-NCR- 17
final closure.
QL-00277

LUS-
CP7B- Awaits action from QD-SBG
6 2 18 6-Mar-17 Open
DCQ-NCR- Engineering Team
QL-00297

LUS-
CP7B-
7 2 11 2-Apr-17 Open Open
DCQ-NCR-
QL-00335

LUS-
CP7B- PCA & sketches submitted.
8 4 34B 6-Apr-17 Open
DCQ-NCR- Awaits final results.
QL-00342

LUS-
CP7B- 23-Apr- Awaits action from QD-SBG
9 2 10 & 11 Open
DCQ-NCR- 17 Engineering Team
QL-00361

LUS-
CP7B- 23-Apr- Awaits action from QD-SBG
10 1 5A Open
DCQ-NCR- 17 Engineering Team
QL-00366

LUS-
CP7B- 30-Apr- Awaits action from QD-SBG
11 2 17 & 18 Open
DCQ-NCR- 17 Engineering Team
QL-00376

LUS-
CP7B- 15-May- All sets for testing. INT awaits
12 All - Open
DCQ-NCR- 17 testing fee from accounts.
QL-00396

LUS-
Awaits SIKA membrane sample
CP7B- 10-Jun-
13 All - Open materials prior to proceed
DCQ-NCR- 17
further. Till now no available.
QL-00418

LUS-
CP7B- 21-Jun-
14 1 7A Open
DCQ-NCR- 17
QL-00427

15 LUS- 4 42B Open


22-Jun- QD-SBG to take action to
CP7B-

MPR- AUGUST 2017 INT/CRP/FR/011 Page 18


DCQ-NCR- 17 replace.
QL-00437

LUS-
CP7B- QD-SBG to clean & clear the area
16 2 23,24 11-Jul-17 UWR
DCQ-NCR- prior to any repair works
QL-00453

LUS-
Dorsch agreed with PCA. QD-
CP7B-
17 2 15 11-Jul-17 UWR SBG to clear the area prior to
DCQ-NCR-
any repair works.
QL-00452

LUS-
CP7B- 26-Aug-
18 2 4&5 Open
DCQ-NCR- 17
QL-00487

LUS-
reinspection is required with
CP7B-
19 2 1, 2 & 3 6-Sep-17 Open approved checklist by
DCQ-NCR-
INR/witness form
QL-00496

LUS-
CP7B- Intertectra to propose
20 4 40B 6-Sep-17 Open
DCQ-NCR- corrective action.
QL-00499

LUS-
CP7B- Intertectra to propose
21 4 39B 6-Sep-17 Open
DCQ-NCR- corrective action.
QL-00500

LUS-
CP7B- Intertectra to propose
22 4 40A 7-Sep-17 Open
DCQ-NCR- corrective action.
QL-00501

OPEN =
20

UWR = 22

MPR- AUGUST 2017 INT/CRP/FR/011 Page 19


6.3 CAR’s(Corrective Action Report) issues up to the month of August-2017
List of CAR’S up to the month of August-2017.
S.I CAR NO. LOCATION SEGMENT DATE DATE STATUS REMARK
ISSUE CLOSED

LUS-CP7B-
9-Feb- OpenQD-SBG to take
1 DCQ-CAR- 2 16 Open
17 necessary action
QL-00534

QD-SBG to clear the area,


LUS-CP7B-
21- so INT can proceed the
2 DCQ-CAR- 1 7A Open
Feb-17 assessment & repair if
QL-00548
required

Proposed Corrective
LUS-CP7B-
18- Action submitted already
3 DCQ-CAR- 1 1B Open
Mar-17 to QD-SBG 31 May 2017 to
QL-00577
QA

QD-SBG to clear the area,


LUS-CP7B- 40A, 40B,
22- so INT can proceed the
4 DCQ-CAR- 4B 41A, 41B, Open
Mar-17 assessment & repair if
QL-00585 42A & 42B
required

To follow up with QA-QD-


LUS-CP7B-
41B, 42A, 30- SBG the approved INRs &
5 DCQ-CAR- 4 Open
42B Mar-17 Intertectra will check
QL-00597
additional documents.

LUS-CP7B- Proposed Corrective


33A, 32A, 3-Apr-
6 DCQ-CAR- 4B Open action submitted to QA-
32B. 31B 17
QL-00602 QD-DBG, 25 April 2017

LUS-CP7B-
DCQ-CAR- 5-Apr- Proposed Corrective
7 4B 35A Open
9QL- 17 Action to submit ASAP.
00604

LUS-CP7B- Intertectra to provide


23-
8 DCQ-CAR- 4A 25A Open documents for possible
Apr-17
QL-00612 closure ASAP.

No access.,QD-SBG to clear
LUS-CP7B-
8-May- the area, so INT can
9 DCQ-CAR- 1 6B, 7A Open
17 proceed the assessment &
QL-00623
repair if required

The area is accessible


LUS-CP7B-
7B, 8A & 15- therefore, Intertectra’s to
10 DCQ-CAR- 1 Open
8B May-17 assess possible damages &
QL-00634
repair ASAP.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 20


The area is accessible
LUS-CP7B-
15- therefore, Intertectra’s to
11 DCQ-CAR- 1 8A Open
May-17 assess possible damages &
QL-00635
repair ASAP.

LUS-CP7B-
15-
12 DCQ-CAR- 1 7B Open QD_SBG to take action.
May-17
QL-00636

Proposed Corrective
LUS-CP7B-
17-Jun- Action to be prepared &
13 DCQ-CAR- 3 16 Open
17 coordinate with QA-
QL-00680
QD_SBG

LUS-CP7B- Correctiveactiontobeprovi
21-Jun-
14 DCQ-CAR- 2 17 & 18 Open dedby Intertectra prior to
17
QL-00693 repair

LUS-CP7B-
40A, 41A, 22-Jun-
15 DCQ-CAR- 4 Open QD-SBG to take action
41B & 42A 17
QL-00699

OpenQD-SBG to clear the


LUS-CP7B-
5-Jul- area, so INT can proceed
16 DCQ-CAR- 1 1A Open
17 the assessment & repair if
QL-00705
required.

LUS-CP7B-
11-Jul- Intertectra to provide
17 DCQ-CAR- 3 Open
17 update ASAP
QL-00712

QD-SBG to clear the area,


LUS-CP7B-
16-Jul- so INT can proceed the
18 DCQ-CAR- 4 39A to 44A Open
17 assessment & repair if
QL-00723
required.

LUS-CP7B- QD-SBG to Provide proper


22-Jul-
19 DCQ-CAR- 1 16A & 17B Open access way for the workers
17
QL-00724 along the working area

LUS-CP7B-
3-Aug-
20 DCQ-CAR- 2 20 UWR
17
QL-00730

"Intertectra and QD-SBG


team done the inspection
to assess the possible
LUS-CP7B- damages after the
22-
21 DCQ-CAR- 4 20 UWR completion of mass
Aug-17
QL-00747 concrete. The applied
spray was found free from
damages.

• The under taking letter

MPR- AUGUST 2017 INT/CRP/FR/011 Page 21


from Intertectra for
continuous monitoring
and to avoid

Reoccurrence in future is
attached for your
reference and closure.

OPEN = 19

UWR = 2

6.4 INTERTECTRA SITE OBSERVATION REPORT (ISOR) issues up to the month of


August-2017
Project Name : LUSAIL INFRASTRUCTURE, LRT STATION, CAR PARK & LANDSCAPE- QD-SBG
Area :
Weather :
Reported by : MICHAEL WORKU
Temperature : Issue date:
Note: Observations not addressed within reasonable time to be elevated to NON-CONFORMANCES
Issues/Observations:
Item PHOTOS ACTION
DESCRIPTION
1

Informed
qd-sbg to
Installing shutter jack without
placed
any protection on the spray
protection
membrane on wall 8
board

Repaired for
it has been found damages of
damages of
spray membrane during shutter
spray
fixing by drilling material
membrane

MPR- AUGUST 2017 INT/CRP/FR/011 Page 22


3

Inform to
QD-SBG
No proper protection for upturn
constructio
T-lock on east ramp
n team

Inform to
QD-SBG
No proper protection for
constructio
sprayed area
n team to
provide
proper
protection

Water table submerge the


Informed
upturn T-lock
QD-SBG for
dewatering

repaired for
damaged spray membrane damages of
spray
membrane

MPR- AUGUST 2017 INT/CRP/FR/011 Page 23


7. Safety Report (NCR)
DATE INCHARGE
S.I NCR NO. LOCATION DATE ISSUED STATUS
CLOSED PERSON
1. March-16 0 0 0
2. April-16 0 0 0
3. May-16 0 0 0
4. June-16 0 0 0
5. July-16 0 0 0
6. August-16 0 0 0
7. September-16 0 0 0
8. October-16 0 0 0
9. November-16 0 0 0
10 December-16 0 0 0
11 January-17 0 0 0
12 February-17 0 0 0
13 March-17 0 0 0
14 April-17 0 0 0
15 May-17 0 0 0
16 June-17 0 0 0
17 July-17 0 0 0
18 August 0 0 0

NCR(s)

There were No NCRs issued up to August 2017.

THE INTERTECTRA HSE DEPARTMENT STRONGLY SUPPORT THE HSE VISION


OF TARGET ZERO ACCIDENT.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 24


8. Subcontractor Concerns
 A construction schedule and detailed drawing were requested in order to
develop a procurement plan and quantity calculation for the project. Such
construction schedule has not been received.

 Spray Work: Due to poor site management by QD-SBG “Especially provide


us Air Compressor and lights. At appropriate time the spray work always
delays between 2-3 hours every time we have spray activities. Accordingly,
we are requesting QD-SBG to provide us one compressor for spray team
permanently.

 QD-SBG start fixing of cement board as permanent shutter for west walls
from Station 6+029 to Station 6+218 without any coordination with
Intertectra. For this reason ,we advise the following:

1. The void performed between piles and cement board shall be


fill with concrete or sand cement.

2. The head of fixation bolt shall be located 5mm below of


cement board surface.

3. The Cavity drain membrane and perforated pipe shall be used


to drain the water away from cement board.

4. Coordination with Intertectra site team is essential for work


success. So, please make sure that all preparation steps for
permanent shutter are known and agreed by Intertectra

MPR- AUGUST 2017 INT/CRP/FR/011 Page 25


9. Target of next period (August 21st to September 20th 2017)
Manpower Deployment Schedule
There has not been any schedule received from the Main Contractor for the
period of August 21st to September 20th2017.

The manpower deployment schedule in this will be updated accordingly if the


main Contractor sends an appropriate schedule and forecast for this period.

The Sub-Contractor will maintain the same staffing levels for this period and may
be subject to revision should the necessity to curtail the financial loss of
productivity dictate this measure.

The staffing levels will remain as categorized below:


Category
Project Mgr. 1
QA/QC Superintendent. 1
Site Engineers 2
Document Controller 1
QA/QC Engineers 3
QA/QC Inspectors 1
HSE Personnel 2
Store Keeper 2
Supervisors 2
Foremen 2
Lead man 1
Applicators 25

10. Conclusion

The work done for this period was minimal to us for our resources on site.

A revised construction schedule and detailed drawing are needed to develop


a better procurement plan and quantity calculation for the project,
Better on site protection of waterproofing membrane is necessary.

MPR- AUGUST 2017 INT/CRP/FR/011 Page 26


11. ANNEX 1
DETAILED PROGRESS

MPR- AUGUST 2017 INT/CRP/FR/011 Page 27


SUMMERY OF PVC T-LOCK

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
T-Lock Membrane Summary 20-Aug-17
Previous Month Current Month Todate
Location Structure Reference Segments
Qty(M 2) Qty(M 2) Qty(M 2)

ZONE-1 PACKAGE-E

Base Slab-PVC T- Lock -Segment 1A 1A

Raft Slab Base -TYPE-1 724.92 724.92


East Wall 2-Upturn 7.35 7.35
West Wall 1-Upturn 7.77 7.77
Base-Road A1-8

BASE SLAB PVC T-LOCK-SEGMENT-1B 1B

ROAD A1-1(BASE -TYPE-1) 695.21 695.21


WALL-1-UPTURN 14.00 14.00
WALL-2-UPTURN 14.63 14.63

BASE SLAB PVC T-LOCK-SEGMENT-2A 2A 698.71 698.71


BASE -TYPE-1
WALL-1-UPTURN 13.95 13.95
WALL-2-UPTURN 14.54 14.54
-
BASE SLAB PVC T-LOCK-SEGMENT-2B 2B 704.25 704.25
BASE -TYPE-1
WALL-1-UPTURN 13.93 13.93
WALL-2-UPTURN 14.56 14.56

BASE SLAB PVC T-LOCK-SEGMENT-2B(REPAIR WORK) 2B 704.51 704.51


BASE -TYPE-1
WALL-1-UPTURN 13.78 13.78
WALL-2-UPTURN 14.76 14.76

BASE SLAB PVC T-LOCK-SEGMENT-3A 3A 716.45 716.45


BASE -TYPE-1
WALL-1-UPTURN 13.97 13.97
WALL-2-UPTURN 14.56 14.56

BASE SLAB PVC T-LOCK-SEGMENT-3B 3B 730.38 730.38


BASE -TYPE-1
WALL-1-UPTURN 13.98 13.98
WALL-2-UPTURN 14.50 14.50

MPR- AUGUST 2017 INT/CRP/FR/011 Page 28


BASE SLAB PVC T-LOCK-SEGMENT-4A 4A 743.72 743.72

BASE -TYPE-1
WALL-1-UPTURN 14.00 14.00
WALL-2-UPTURN 14.51 14.51

BASE SLAB PVC T-LOCK-SEGMENT-4A(REPAIR WORK) 4A 37.50 37.50


BASE -TYPE-1

BASE SLAB PVC T-LOCK-SEGMENT-4B 4B 756.65 756.65

BASE -TYPE-1
WALL-1-UPTURN 14.49 14.49
WALL-2-UPTURN 14.00 14.00

BASE SLAB PVC T-LOCK-SEGMENT-4B(REPAIR WORK) 4B 757.97 757.97


BASE -TYPE-1
WALL-1-UPTURN 14.68 14.68
WALL-2-UPTURN 13.87 13.87

BASE SLAB PVC T-LOCK-SEGMENT-5A 5A 550.11 550.11


BASE -TYPE-2
Base-Road A1-4 118.76 118.76
WALL-1-UPTURN 11.55 11.55

WALL-2-UPTURN 10.91 10.91


EAST WALL-3-UPTURN 5.38 5.38
WEST RAMP 5.38 5.38

BASE SLAB PVC T-LOCK-SEGMENT-5A(REPAIR WORK) 5A(REPAIR WORK) 60.00 60.00


BASE -TYPE-2

BASE SLAB PVC T-LOCK-SEGMENT-5B 5B 561.15 561.15


BASE -TYPE-2
EAST RAMP ROAD A1-4 119.78 119.78
EAST WALL 2-UPTURN 10.89 10.89
WEST WALL 1-UPTURN 11.55 11.55
EAST WALL-3-UPTURN 5.39 5.39
WEST RAMP UPTURN 5.38 5.38

BASE SLAB PVC T-LOCK-SEGMENT-6A 6A 623.46 623.46

BASE -TYPE-3
Base-Road A1-4 190.91 190.91

WALL-1-UPTURN 17.73 17.73

WALL-2-UPTURN 17.02 17.02

WALL-3-UPTURN 8.45 8.45

BASE SLAB PVC T-LOCK-SEGMENT-6B 6B 637.59 637.59


BASE -TYPE-13
Base-Road A1-4 197.22 197.22
WALL-1-UPTURN 17.70 17.70
WALL-2-UPTURN 17.02 17.02
East Wall 3-Upturn 8.45 8.45

MPR- AUGUST 2017 INT/CRP/FR/011 Page 29


BASE SLAB PVC T-LOCK-SEGMENT-7A 7A 857.63 857.63
BASE -TYPE-13
Base-Road A1-4 183.81 183.81
WALL-1-UPTURN 16.42 16.42
WALL-2-UPTURN 15.65 15.65
WALL-03-UPTURN 7.74 7.74

BASE SLAB PVC T-LOCK-SEGMENT-7B 7B 824.13 824.13


BASE -TYPE-13
WALL-01-UPTURN 15.85 15.85
WALL-02-UPTURN 14.43 14.43
EAST RAMP 168.28 168.28
EAST WALL 3-UPTURN 7.06 7.06

BASE SLAB PVC T-LOCK-SEGMENT-8A 8A 921.54 921.54


BASE -TYPE-14
Base-Road A1-4 198.54 198.54
WALL-1-UPTURN 16.96 16.96
WALL-2-UPTURN 16.90 16.90
WALL-03-UPTURN 16.89 16.89

BASE SLAB PVC T-LOCK-SEGMENT-8B 8B 906.27 906.27


BASE -TYPE-14
Base-Road A1-4 190.17 190.17
WALL-1-UPTURN 16.40 16.40
WALL-2-UPTURN 16.90 16.90
WALL-03-UPTURN 7.78 7.78

BASE SLAB PVC T-LOCK-SEGMENT-9A 9A

ROAD A1-1 (BASE -TYPE-14) 1,046.34 1,046.34


WEST WALL-1-UPTURN 18.71 18.71
EAST WALL-2-UPTURN 18.13 18.13
EAST WALL-3-UPTURN 9.43 9.43
WEST WALL-8-UPTURN 9.30 9.30
EAST WALL 2-BACK SIDE-2 LAYERS 180.00 180.00

Base -TYPE-15 9B 826.16 826.16


Base-Road A1-4 236.52 236.52
Base-Road A1-4 249.54 249.54
East Wall 3-Upturn 8.81 8.81
West Wall 1-Upturn 9.30 9.30
East Wall 2-Upturn 8.81 8.81
West Wall 8-Upturn 9.30 9.30
EAST WALL 2-BACK SIDE-2 LAYERS 90.00 90.00

Base -TYPE-15 10A 1,324.43 1,324.43


East Wall 3-Upturn 8.68 8.68
West Wall 1-Upturn 9.23 9.23
East Wall 2-Upturn 73.52 73.52
West Wall 8-Upturn 43.88 43.88

MPR- AUGUST 2017 INT/CRP/FR/011 Page 30


Base Slab-PVC T- Lock -Segment 10B 10B

Base -TYPE-15 1,334.07 1,334.07


Wall 3-Upturn 8.66 8.66
Wall 1-Upturn 9.17 9.17
Wall 2-Upturn 84.82 84.82
Wall 8-Upturn 63.14 63.14

Base Slab-PVC T- Lock -Segment 11A 11A

Base -TYPE-16 1,157.90 1,157.90


Base-Road A1-8
East Wall 3-Upturn 8.72 8.72
West Wall 1-Upturn
West Wall 8-Upturn 9.13 9.13

Base Slab-PVC T- Lock -Segment 11B 11B

Base -TYPE-16 1,110.88 1,110.88


Base-Road A1-8
East Wall 3-Upturn 8.14 8.14
West Wall 1-Upturn
West Wall 8-Upturn 8.63 8.63

Base Slab-PVC T- Lock -Segment 12A


12A
Base -TYPE-16
Base-Road A1-1 1,251.65 1,251.65
Base-Road A1-2
East Wall 3-Upturn 8.96 8.96
West Wall 8-Upturn 9.56 9.56

Base Slab-PVC T- Lock -Segment 12B


Base -TYPE-16 12B 1,258.80 1,258.80
Base-Road A1-1
Base-Road A1-2
East Wall 3-Upturn 8.96 8.96
West Wall 8-Upturn 9.35 9.35

Base Slab-PVC T- Lock -Segment 13A


Base -TYPE-17 1,346.20 1,346.20
Base-Road A1-2
East Wall 3-Upturn 9.25 9.25
West Wall 1-Upturn
West Wall 8-Upturn 58.81 58.81

Base Slab-PVC T- Lock -Segment 13B


Base -TYPE-17 13B 1,361.89 1,361.89
Base-Road A1-2
East Wall 3-Upturn 9.22 9.22
West Wall 1-Upturn
West Wall 8-Upturn 58.78 58.78

MPR- AUGUST 2017 INT/CRP/FR/011 Page 31


Base Slab-PVC T- Lock -Segment 14A 14A

Base -TYPE-18 1,364.06 1,364.06


Base-Road A1-2 -
East Wall 3-Upturn 9.22 9.22
West Wall 1-Upturn -
West Wall 8-Upturn 58.78 58.78

Base Slab-PVC T- Lock -Segment 14B 14B

Base -TYPE-18 1,350.89 1,350.89


Base-Road A1-2 -
East Wall 3-Upturn 9.22 9.22
West Wall 1-Upturn -
West Wall 8-Upturn 9.75 9.75

Base Slab-PVC T- Lock -Segment 15A 15A

Base -TYPE-18 906.16 388.35 1,294.51


Base-Road A1-2
East Wall 3-Upturn 9.13 9.13
West Wall 1-Upturn
West Wall 8-Upturn 9.60 67.18 76.78

Base Slab-PVC T- Lock -Segment 15B 15B

Base -TYPE-18 914.67 914.67


Base-Road A1-2 - -
East Wall 3-Upturn 9.53 9.53
West Wall 1-Upturn - -
West Wall 8-Upturn 80.60 80.60

Base Slab-PVC T- Lock -Segment 16 16 1,034.91 1,034.91


Base -TYPE-19
Base-Road A1-2
Base-Road A1-3
East Wall 3-Upturn
West Wall 1-Upturn
West Wall 8-Upturn 12.67 12.67
East Wall 9-Upturn 11.75 11.75

Base Slab-PVC T- Lock -Segment 17A


Base -TYPE-20A 1,209.42 1,209.42
Base-Road A1-2
Base-Road A1-3
East Wall 3-Upturn
West Wall 1-Upturn
West Wall 8-Upturn 14.32 14.32
East Wall 9-Upturn 14.27 14.27

SUB TOTAL(M²) 34,338.94 1,693.54 36,032.48


ZONE-2 PACKAGE-F

Base Slab-PVC T- Lock -Segment 01 ( Sec-15) SEG-01

Base ( from STA 6+625 to STA 6+640 ) 925.20 925.20


North bound Upturn 7.50 7.50
Southth bound Upturn 7.50 7.50

MPR- AUGUST 2017 INT/CRP/FR/011 Page 32


Base ( STA 6+600 to 6+625)-SEG-02 & 03 SEC-14 SEG-02 & 03 1,542.00 1,542.00
North bound Upturn 12.50 12.50
Southth bound Upturn 12.50 12.50

Base ( ST.6+582 to ST. 6+600.00)-SEG-04 & 05 SEC-13 SEG-04 &05 1,110.24 1,110.24
North bound Upturn 9.00 9.00
Southth bound Upturn 9.00 9.00

Base ( ST.6+560 to ST. 6+582.00)-SEG-16 SEC-12 SEG-06 1,356.96 1,356.96


North bound Upturn 11.00 11.00
Southth bound Upturn 11.00 11.00

Base ( ST.6+538.30 to ST. 6+560.00)-SEG-07 SEC-11 SEG-07 1,316.54 1,316.54


North bound Upturn 10.85 10.85
Southth bound Upturn 10.85 10.85

Base Slab-PVC T- Lock -Segment 08 & 09 ( Sec-10) SEG-08 & 09

Base ( ST.6+510.00 to ST. 6+538.30) 1,716.96 1,716.96


North bound Upturn 14.15 14.15
Southth bound Upturn 14.15 14.15

BASE SLAB PVC T-LOCK-SEG-10 & 11 SEC-9 SEG-10 & 11 1,294.84 1,294.84
Base ( ST.6+488.30 to ST. 6+510.00)
South Bound upturn 10.85 10.85
North Bound upturn 56.42 56.42

Base Slab-PVC T- Lock -Segment 12 & 13 ( Sec-8) SEG-12 & 13

Base ( ST.6+450.00 to ST. 6+488.30) 2,285.36 2,285.36


North bound Upturn 99.58 99.58
Southth bound Upturn 19.15 19.15

BASE SLAB PVC T-LOCK-SEG-14 & 15 SEC-7 SEGTION-14 &15 1,646.89 1,646.89
Base ( ST.6+422.40 to ST. 6+450.00)
North bound Upturn 71.76 71.76
Southth bound Upturn 13.80 13.80

Base Slab-PVC T- Lock -Segment 16 & 17 ( Sec-6) SECTION-16 & 17 1,965.71 1,965.71
Base ( ST.6+390 to ST. 6+422.40)
WEST WALL UPTURN 8.10 8.10
EAST WALL UPTURN 8.10 8.10

Base Slab-PVC T- Lock -Segment 18 SEGMENT-18

Base ( ST.6+370 to ST.6+390) 1,246.80 1,246.80


North bound Upturn 5.00 5.00
Southth bound Upturn 5.50 5.50

MPR- AUGUST 2017 INT/CRP/FR/011 Page 33


Base Slab-PVC T- Lock -Segment 19 & 20 SEGMENT-19 &20

Base ( ST.6+340 to ST.6+370) 2,003.25 2,003.25


North bound Upturn 7.50 7.50
Southth bound Upturn 7.50 7.50

Delayed Strip-PVC T- Lock -B/W Segment 19 & 20 SEGMENT-19 &20

Base ( ST.6+340 to ST.6+370) 200.33 200.33


North bound Upturn 0.75 0.75
Southth bound Upturn 0.75 0.75

Base Slab-PVC T- Lock -Segment 21 & 22 SEGMENT-21 & 22

Base ( ST.6+340 to ST.6+315.2) 1,001.63 1,001.63


North bound Upturn 3.75 3.75
Southth bound Upturn 3.75 3.75

Base Slab-PVC T- Lock -Segment 23 (Sec-2) SEGMENT-23

Base ( ST.6+305 to ST.6+315.2) 681.10 681.10


North bound Upturn 5.10 5.10
Southth bound Upturn 5.10 5.10

Base Slab-PVC T- Lock -Segment 24 ( Sec-1) SEGMENT-24

Base (ST.6+293.50 to ST.6+305.00 ) 767.91 767.91


North bound Upturn 5.75 5.75
Southth bound Upturn 5.75 5.75

SUB TOTAL(M²) 21,535.68 - 21,535.68


ZONE-3 PACKAGE-H

Base Slab-PVC T- Lock


Base Slab (GL 29-30) 547.20 547.20
Upturn(GL - BD) 4.50 4.50
Upturn(GL - AU) 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 30-31) 568.50 568.50
Upturn(GL - AU) 4.50 4.50
Upturn(GL - BD) 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 31-32) 554.54 554.54
Upturn(GL - AU) 4.50 4.50
Upturn(GL - BD) 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 32-33) 565.61 565.61
Upturn(GL - AU) 4.50 4.50
Upturn(GL - BD) 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 33-34) 585.95 585.95
Upturn(GL - BD) 4.52 4.52
Upturn(GL - AU) 4.52 4.52

MPR- AUGUST 2017 INT/CRP/FR/011 Page 34


Base Slab-PVC T- Lock
Base Slab (GL 34-35) 609.65 609.65
Upturn(GL - BD) 4.52 4.52
Upturn(GL - AU) 4.52 4.52

Base Slab-PVC T- Lock


Base Slab (GL 35-36) 638.80 638.80
Upturn(GL - BE) 4.52 4.52
Upturn(GL - AT) 4.52 4.52

Base Slab-PVC T- Lock


Base Slab (GL 36-37) 674.01 674.01
Upturn(GL - BE) 4.50 4.50
Upturn(GL - AT) 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 37-38) 785.06 785.06
Upturn(GL - BE) 4.50 4.50
Upturn(GL - AT) 4.50 4.50
Base Slab-PVC T- Lock
Base Slab (GL 38-39) 370.23 370.23
Upturn(GL - AX) 4.50 4.50
Upturn(GL - AU) 4.72 4.72
Base Slab-PVC T- Lock
Base Slab (GL 38-39) 370.23 370.23
Upturn(GL - BE) 4.50 4.50
Upturn(GL - BA) 4.72 4.72
Base Slab-PVC T- Lock
Base Slab (GL 39-40) 372.60 372.60
Upturn(GL - AX) 4.50 4.50
Upturn(GL - AS) 4.77 4.77
Base Slab-PVC T- Lock
Base Slab (GL 39-40) 372.60 372.60
Upturn(GL - BF) 4.50 4.50
Upturn(GL - BA') 4.77 4.77

Base Slab-PVC T- Lock


Base Slab (GL 40-41) 424.77 424.77
Upturn(GL - AS) 4.84 4.84
Upturn(GL - AX') 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 40-41) 424.77 424.77
Upturn(GL - AX') 4.50 4.50
Upturn(GL - BF) 4.84 4.84

Base Slab-PVC T- Lock


Base Slab (GL 41-42) 463.61 463.61
Upturn(GL - AS) 4.92 4.92
Upturn(GL - AX') 4.50 4.50

MPR- AUGUST 2017 INT/CRP/FR/011 Page 35


Base Slab-PVC T- Lock
Base Slab (GL 41-42) 459.47 459.47
Upturn(GL - AX') 4.50 4.50
Upturn(GL - BF) 4.92 4.92

Base Slab-PVC T- Lock


Base Slab (GL 42-43) 502.83 502.83
Upturn(GL - AS) 5.00 5.00
Upturn(GL - AX') 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 43-44) 541.69 541.69
Upturn(GL - AS') 5.00 5.00
Upturn(GL - AX') 4.50 4.50

Base Slab-PVC T- Lock


Base Slab (GL 42'-44') 1,078.34 1,078.34
Upturn(GL - BA') 9.00 9.00
Upturn(GL - BE') 9.00 9.00

Base Slab-PVC T- Lock


Delayed Strip (GL 38'-44') 147.50 147.50

Base Slab-PVC T- Lock


Base Slab (GL 44-46) 624.26 624.26
Upturn(GL - AR') 9.34 9.34
Upturn(GL - AU') 10.60 10.60

Base Slab (GL 44-46, AU'-AX) 815.03 815.03

Base Slab-PVC T- Lock


Base Slab (GL 44-46, BA'-BD) 744.49 744.49
Upturn(GL - BH'')

SUB TOTAL(M²) 13,454.30 - 13,454.30


ZONE-4

Base Slab-PVC T- Lock -Segment 18A 18A

Base -TYPE-25A 994.65 994.65


Base-Road A1-2
Base-Road A1-3
East Wall 4 upturn
West Wall 5 upturn
East Wall 10-Upturn 11.00 11.00
West Wall 11-Upturn 11.81 11.81

MPR- AUGUST 2017 INT/CRP/FR/011 Page 36


Base Slab-PVC T- Lock -Segment 18B 18B

Base -TYPE-25B 561.22 561.22


Base-Road A1-2
Base-Road A1-3
East Wall 4 upturn
West Wall 5 upturn
East Wall 10-Upturn 5.75 5.75
West Wall 11-Upturn 7.21 7.21

Base Slab-PVC T- Lock -Segment 18C 18C

Base -TYPE-25B 629.60 629.60


Base-Road A1-2
Base-Road A1-3
East Wall 4 upturn
West Wall 5 upturn
East Wall 10-Upturn 7.40 7.40
West Wall 11-Upturn 7.20 7.20

Base Slab-PVC T- Lock -Segment 18D 18D

Base -TYPE-25B 481.06 481.06


Base-Road A1-2
Base-Road A1-3
East Wall 4 upturn
West Wall 5 upturn
East Wall 10-Upturn 5.65 5.65
West Wall 11-Upturn 5.53 5.53

Base Slab-PVC T- Lock -Segment 19A 19A

Base -TYPE-23 990.60 990.60


Base-Road A1-2
Base-Road A1-3
West Wall 5 upturn
East Wall 4 upturn
East Wall 10-Upturn 10.76 10.76
West Wall 11-Upturn 12.26 12.26

Base Slab-PVC T- Lock -Segment 19B 19B

Base -TYPE-23 986.35 986.35


Base-Road A1-2
Base-Road A1-3
East Wall 4 upturn
West Wall 5 upturn
East Wall 10-Upturn 10.82 10.82
West Wall 11-Upturn 11.85 11.85

Base Slab-PVC T- Lock -Segment 20A 20A

Base -TYPE-23 864.32 864.32


Base-Road A1-2
Base-Road A1-3
West Wall 5 upturn
East Wall 4 upturn
East Wall 10-Upturn 9.56 9.56
West Wall 11-Upturn 9.97 9.97

MPR- AUGUST 2017 INT/CRP/FR/011 Page 37


PVC T-LOCK-SEGMENT-20B(TYPE 23) 20B

ROAD A1-1 854.26 854.26


ROAD A1-2
ROAD A1-3
WALL-05-UPTURN
WALL-11-UPTURN 9.98 9.98
WALL-10-UPTURN 9.51 9.51
WALL-04-UPTURN

PVC T-LOCK-SEGMENT-21A(TYPE 22) 21A


ROAD A1-1 861.19 861.19
ROAD A1-2
ROAD A1-3
WALL-05-UPTURN
WALL-11-UPTURN 9.94 9.94
WALL-10-UPTURN 9.48 9.48
WALL-04-UPTURN

PVC T-LOCK-SEGMENT-21B(TYPE 22) 21B 843.69 843.69


ROAD A1-21 B
ROAD A1-2
ROAD A1-3
WALL-05-UPTURN
WALL-11-UPTURN 9.83 9.83
WALL-10-UPTURN 9.51 9.51
WALL-04-UPTURN

PVC T-LOCK-SEGMENT-22A(TYPE-22) 22A

Base-Road A1-1 934.05 934.05


Base-Road A1-2
Base-Road A1-3
WALL-05-UPTURN
WALL-11-UPTURN 11.08 11.08
WALL-10-UPTURN 10.62 10.62
WALL-12-UPTURN
WALL-04-UPTURN

PVC T-LOCK-SEGMENT-22B(TYPE-21A) 22B 931.64 931.64


Base-Road A1-2 499.92 499.92
Base-Road A1-3 533.75 533.75
WALL-05-UPTURN 22.78 22.78
WALL-11-UPTURN 22.39 22.39
WALL-10-UPTURN 20.94 20.94
WALL-12-UPTURN
WALL-04-UPTURN 20.64 20.64

Base -TYPE-21 B 23A 643.88 643.88


Base-Road A1-2 346.55 346.55
Base-Road A1-3&A1-13
West Wall 5 upturn 7.52 7.52
East Wall 4 upturn
East Wall 10-Upturn 15.01 15.01
West Wall 11-Upturn 14.94 14.94
East Wall 12-Upturn
East Wall 10 (above spray wall area) 34.52 34.52
West Wall 11 (above spray wall area) 37.35 37.35

MPR- AUGUST 2017 INT/CRP/FR/011 Page 38


Base -TYPE-21 B 23B 645.00 645.00
Base-Road A1-2 353.17 353.17
Base-Road A1-3&A1-13 392.94 392.94
West Wall 5 upturn 7.50 7.50
East Wall 4 upturn 7.50 7.50
East Wall 10-Upturn 7.50 7.50
East Wall 13-Upturn
West Wall 11-Upturn 7.40 7.40
East Wall 12-Upturn 7.51 7.51
East Wall 10 (above spray wall area) 34.50 34.50
West Wall 11 (above spray wall area) 37.00 37.00

Base -TYPE-12 24A 646.41 646.41


Base-Road A1-2 & A1-9 358.45
ROAD A1-3 187.95 187.95
ROAD A1-13 205.58 205.58
West Wall 5 upturn 7.51 7.51
East Wall 4 upturn 7.49 7.49
East Wall 10-Upturn 7.50 7.50
West Wall 11-Upturn 7.51 7.51
East Wall 12-Upturn 7.50 7.50
West Wall 13-Upturn 7.50 7.50
Wall 13-Back side -2 layers 38.00 38.00

24B

Base -TYPE-12 645.18 645.18


Base-Road A1-2 & A1-9 359.80
ROAD A1-3 190.13 190.13
ROAD A1-13 203.27 203.27
West Wall 5 upturn 7.51 7.51
East Wall 4 upturn 7.49 7.49
East Wall 10-Upturn 7.50 7.50
West Wall 11-Upturn 7.51 7.51
East Wall 12-Upturn 7.50 7.50
West Wall 13-Upturn 14.57 14.57
Wall 13-Back side -2 layers 45.00 45.00

Base -TYPE-12 25A 642.62 642.62


Base-Road A1-2 & A1-9 363.29
Base-Road A1-3 190.72 190.72
Base-Road A1-13

MPR- AUGUST 2017 INT/CRP/FR/011 Page 39


West Wall 5 upturn 7.50 7.50
East Wall 4 upturn -
East Wall 10-Upturn 7.50 7.50
West Wall 11-Upturn 7.51 7.51
East Wall 12-Upturn 7.50 7.50
West Wall 13-Upturn 7.52 7.52

Base Slab-PVC T- Lock -Segment 25A (REPAIR-WORK)


Base -TYPE-12 25A(REINSTALLATION) 455.18 455.18

Base Slab-PVC T- Lock -Segment 25 B 25B

Base -TYPE-12 639.67 639.67


Base-Road A1-2 & A1-9 359.87 359.87
Base-Road A1-3 190.29 190.29
Base-Road A1-13
West Wall 5 upturn 14.99 14.99
East Wall 4 upturn
East Wall 10-Upturn 15.01 15.01
West Wall 11-Upturn 15.02 15.02
East Wall 12-Upturn 15.01 15.01
West Wall 13-Upturn 15.00 15.00

Base -TYPE-11 26A 633.98 633.98


Base-Road A1-2 173.95 173.95
Base-Road A1-9 187.38 187.38
Base-Road A1-3 190.10 190.10
Base-Road A1-13
West Wall 5 upturn 7.60 7.60
East Wall 4 upturn
East Wall 10-Upturn 7.50 7.50
West Wall 11-Upturn 7.50 7.50
East Wall 12-Upturn 7.50 7.50
West Wall 13-Upturn 7.51 7.51

Base -TYPE-11-SEGMENT-26B 26B

Base-Road A1-1 628.30 628.30


Base-Road A1-2 174.44 174.44
Base-Road A1-9 186.29 186.29
Base-Road A1-3 188.27 188.27
Base-Road A1-13
West Wall 5 upturn
East Wall 4 upturn
East Wall 10-Upturn 7.44 7.44
West Wall 11-Upturn 7.51 7.51
East Wall 12-Upturn 7.50 7.50
West Wall 13-Upturn 7.51 7.51

Base -TYPE-10 27A 971.27 971.27


Base-Road A1-9 161.01 161.01
Base-Road A1-13

MPR- AUGUST 2017 INT/CRP/FR/011 Page 40


West Wall 12 upturn 15.00 15.00
East Wall 13 upturn 14.83 14.83
East Wall 5-Upturn 7.92 7.92
West Wall 4-Upturn

Base -TYPE-10 27B 962.74 962.74


Base-Road A1-9
Base-Road A1-13
West Wall 5 upturn
East Wall 4 upturn
East Wall 12-Upturn 15.22 15.22
West Wall 13-Upturn 14.90 14.90

Base -TYPE-10 28A 935.63 935.63


Base-Road A1-9 158.16 158.16
Base-Road A1-13
West Wall 5 upturn 7.50 7.50
East Wall 4 upturn
East Wall 12-Upturn 15.00 15.00
West Wall 13-Upturn 15.00 15.00

BASE SLAB PVC T-LOCK-SEGMENT-28B 28B 921.27 921.27


BASE -TYPE-10 158.78 158.78
Base-Road A1-13
WALL-05-UPTURN 7.50 7.50
WALL-04-UPTURN
WALL-12-UPTURN 15.33 15.33
WALL-13-UPTURN 15.10 15.10

BASE SLAB PVC T-LOCK-SEGMENT-29A 29A 915.18 915.18


BASE -TYPE-9
Base-Road A1-9 160.79 160.79
WALL-05-UPTURN 7.51 7.51
WALL-13-UPTURN 15.00 15.00
WALL-12-UPTURN 15.20 15.20

BASE SLAB PVC T-LOCK-SEGMENT-29B 29B 873.32 873.32


BASE -TYPE-9
WALL-05-UPTURN
WALL-13-UPTURN 15.04 15.04
WALL-12-UPTURN 14.85 14.85
WEST RAMP 166.60 166.60
WEST WALL 5 UPTURN 7.51 7.51

BASE SLAB PVC T-LOCK-SEGMENT-30A 30A 856.62 856.62


BASE -TYPE-9
WALL-05-UPTURN
WALL-13-UPTURN 15.11 15.11
WALL-12-UPTURN 15.38 15.38
WEST RAMP 173.59 173.59
WEST WALL 5 UPTURN 7.51 7.51

MPR- AUGUST 2017 INT/CRP/FR/011 Page 41


BASE SLAB PVC T-LOCK-SEGMENT-30B 30B 802.30 802.30
BASE -TYPE-9
West Ramp 176.20 176.20
WALL-05-UPTURN 7.51 7.51
WALL-13-UPTURN 14.95 14.95
WALL-12-UPTURN 14.68 14.68

BASE SLAB PVC T-LOCK-SEGMENT-31A 31A 795.72 795.72


BASE -TYPE-9
West Ramp 177.81
WALL-05-UPTURN 15.01 15.01
WALL-13-UPTURN 15.08 15.08
WALL-12-UPTURN 15.35 15.35

BASE SLAB PVC T-LOCK-SEGMENT-31B 31B 750.68 750.68


BASE -TYPE-9
West Ramp 174.99
WALL-05-UPTURN 14.98 14.98
WALL-13-UPTURN 14.94 14.94
WALL-12-UPTURN 14.72 14.72
-
Base Slab-PVC T- Lock -Segment 31C & D 31C &D

Raft Slab Base -TYPE-9 2,052.38 2,052.38


West Wall 12-Upturn 39.90 39.90
East Wall 13-Upturn 39.86 39.86
-
BASE SLAB PVC T-LOCK-SEGMENT-32A 32A 410.73 410.73
BASE -TYPE-8 - -
WALL-13-UPTURN 8.04 8.04
WALL-12-UPTURN 8.04 8.04

Base Slab-PVC T- Lock -Segment 32B 32B

Raft Slab Base -TYPE-8 411.52 411.52


West Wall 13-Upturn 8.05 8.05
East Wall 12-Upturn 8.05 8.05

BASE SLAB PVC T-LOCK-SEGMENT-33A 33A 663.79 663.79


BASE -TYPE-9 - -
WALL-13-UPTURN 12.99 12.99
WALL-12-UPTURN 12.99 12.99
-
BASE SLAB PVC T-LOCK-SEGMENT-33B 33B 664.30 664.30
BASE -TYPE-8 - -
WALL-13-UPTURN 13.00 13.00
WALL-12-UPTURN 13.00 13.00
-
BASE SLAB PVC T-LOCK-SEGMENT-34A 34A 597.91 597.91
BASE -TYPE-7 - -
WALL-12-UPTURN 12.18 12.18
WALL-13-UPTURN 12.18 12.18
WEST RAMP 165.65 165.65
WEST WALL 5 UPTURN 6.11 6.11

MPR- AUGUST 2017 INT/CRP/FR/011 Page 42


BASE SLAB PVC T-LOCK-SEGMENT-34B 34B 619.31 619.31
BASE -TYPE-7 - -
WALL-12-UPTURN 12.17 12.17
WALL-13-UPTURN 13.20 13.20
WEST RAMP 179.59 179.59
WEST WALL 6 UPTURN 6.49 6.49
- -
BASE SLAB PVC T-LOCK-SEGMENT-35A 35A 656.83 656.83
BASE -TYPE-6 - -
WALL-13-UPTURN 14.20 14.20
WALL-12-UPTURN 14.19 14.19
West Ramp 201.26 201.26
East Wall 7-Upturn 7.10 7.10
East Ramp 217.19 217.19
West Wall 6-Upturn 7.13 7.13
-
BASE SLAB PVC T-LOCK-SEGMENT-35B 35B 648.12 648.12
BASE -TYPE-6 - -
Base-Road A1-16 217.28 217.28
ROAD A1-15 194.09 194.09
WALL-06-UPTURN 7.11 7.11
WALL-13-UPTURN 14.20 14.20
WALL-12-UPTURN 14.19 14.19
WALL-7-UPTURN 7.11 7.11
-
BASE SLAB PVC T-LOCK-SEGMENT-36A 36A 641.78 641.78
BASE -TYPE-6 - -
Base-Road A1-16 217.49 217.49
ROAD A1-15 191.21 191.21
WALL-6-UPTURN 7.11 7.11
WALL-13-UPTURN 14.22 14.22
WALL-12-UPTURN 14.22 14.22
WALL-7-UPTURN 7.11 7.11
-
BASE SLAB PVC T-LOCK-SEGMENT-36B 36B 634.08 634.08
BASE -TYPE-6 - -
Base-Road A1-16 217.22 217.22
ROAD A1-15 190.71 190.71
WALL-6-UPTURN 7.10 7.10
WALL-13-UPTURN 14.20 14.20
WALL-12-UPTURN 14.20 14.20
WALL-7-UPTURN 7.10 7.10
-
BASE SLAB PVC T-LOCK-SEGMENT-37A 37A -
ROAD A1-1(BASE -TYPE-6) 630.97 630.97
ROAD A1-15(BASE TYPE-6 189.63 189.63
ROAD A1-16 217.24 217.24
WALL-6-UPTURN 14.20 14.20
WALL-13-UPTURN 14.19 14.19
WALL-12-UPTURN 14.20 14.20
WALL-7-UPTURN 7.10 7.10

MPR- AUGUST 2017 INT/CRP/FR/011 Page 43


BASE SLAB PVC T-LOCK-SEGMENT-37B -
ROAD A1-1(BASE -TYPE-6) 37B 630.70 630.70
ROAD A1-15 189.99 189.99
ROAD A1-16 217.28 217.28
WALL-6-UPTURN 14.22 14.22
WALL-13-UPTURN 14.18 14.18

WALL-12-UPTURN 14.20 14.20

WALL-7-UPTURN 7.10 7.10


-
BASE SLAB PVC T-LOCK-SEGMENT-38A 38A 666.44 666.44
BASE -TYPE-5 - -
ROAD A1-15 200.37 200.37
ROAD A1-16 227.68 227.68

WALL-07-UPTURN 7.51 7.51


WALL-06-UPTURN 15.01 15.01
WALL-12-UPTURN 14.98 14.98
WALL-13-UPTURN 14.99 14.99

BASE SLAB PVC T-LOCK-SEGMENT-38B 38B

BASE -TYPE-5 664.67 664.67


West Ramp 200.12 200.12
ROAD A1-16 224.82 224.82
WALL-07-UPTURN 15.01 15.01
WALL-06-UPTURN 15.01 15.01
WALL-12-UPTURN 15.02 15.02
WALL-13-UPTURN 14.99 14.99
-
BASE SLAB PVC T-LOCK-SEGMENT-39A 39A 657.01 657.01
BASE -TYPE-5 - -
West Ramp 198.80 198.80
WALL-07-UPTURN 15.10 15.10
WALL-06-UPTURN 14.90 14.90
WALL-12-UPTURN 15.09 15.09
WALL-13-UPTURN 14.94 14.94
EAST RAMP 228.24 228.24
-
BASE SLAB PVC T-LOCK-SEGMENT-39B -
ROAD A1-1(BASE TYPE-5) 39B 645.46 645.46
ROAD A1-16 226.67 226.67
West Ramp 198.04
WALL-07-UPTURN 15.17 15.17
WALL-06-UPTURN 14.90 14.90
WALL-12-UPTURN 15.07 15.07
WALL-13-UPTURN 14.94 14.94

MPR- AUGUST 2017 INT/CRP/FR/011 Page 44


BASE SLAB PVC T-LOCK-SEGMENT-40A 40A 636.90 636.90
BASE -TYPE-5 - -
ROAD A1-16 218.55 218.55
West Ramp 194.74
WALL-07-UPTURN 15.39 15.39
WALL-06-UPTURN 14.68 14.68
WALL-12-UPTURN 15.21 15.21
WALL-13-UPTURN 14.81 14.81
-

40A-RE-WORK
BASE SLAB PVC T-LOCK-SEGMENT-40A(RE-WORK) -
BASE -TYPE-5 545.01 545.01
WALL-12-UPTURN 15.65 15.65

WALL-13-UPTURN 15.36 15.36

BASE SLAB PVC T-LOCK-SEGMENT-40B 40B

BASE -TYPE-5 630.03 630.03


West Ramp 189.74
East Ramp 204.26
WALL-07-UPTURN 15.40 15.40

WALL-06-UPTURN 14.69 14.69


WALL-12-UPTURN 15.22 15.22

WALL-13-UPTURN 14.79 14.79

-
BASE SLAB PVC T-LOCK-SEGMENT-41A 41A 888.15 888.15
BASE -TYPE-4 - -
East Ramp 213.65
WALL-06-UPTURN 16.25 16.25
WALL-12-UPTURN 66.30 66.30
WALL-07-UPTURN 16.83 16.83

BASE SLAB PVC T-LOCK-SEGMENT-41A(REPAIR WORK) 41A(REPAIR WORK) 880.07 880.07

BASE -TYPE-4 - -
WALL-06-UPTURN 16.51 16.51

WALL-12-UPTURN 16.47 16.47


-

Base Slab-PVC T- Lock -Segment 41B 41B 864.62 864.62

Base -TYPE-4 - -

East Ramp 208.74


Wall 7-Upturn 16.84 16.84
Wall 6-Upturn 16.22 16.22
Wall 12-Upturn 50.10 50.10

-
BASE SLAB PVC T-LOCK-SEGMENT-42A 42A 854.86 854.86
BASE -TYPE-3 - -
WALL-06-UPTURN 13.18 13.18

WALL-07-UPTURN 13.92 13.92

BASE SLAB PVC T-LOCK-SEGMENT-42B 42B 829.26 829.26

BASE -TYPE-3 - -

WALL-07-UPTURN 13.90 13.90

WALL-06-UPTURN 13.19 13.19

MPR- AUGUST 2017 INT/CRP/FR/011 Page 45


Base Slab-PVC T- Lock -Segment 43A 43A

Base -TYPE-3 854.48 854.48

East Wall 7-Upturn 6.96 6.96

West Wall 6-Upturn 6.59 6.59

Base Slab-PVC T- Lock -Segment 43B 43B

Base -TYPE-3 861.29 861.29

East Wall 7-Upturn 7.89 7.89

West Wall 6-Upturn 7.19 7.19

Base Slab-PVC T- Lock -Segment 44A 44A

Raft Slab Base -TYPE-3 789.18 789.18

East Wall 7-Upturn 7.48 7.48

West Wall 6-Upturn 6.80 6.80

Base Slab-PVC T- Lock -Segment 44B 44B

Raft Slab Base -TYPE-3 791.19 791.19

East Wall 7-Upturn 7.42 7.42

West Wall 6-Upturn 7.06 7.06

SUB TOTAL (M²) 60,869.16 210.76 61,079.92

General Summary of PVC T-Lock:


1 ZONE-1-PACKAGE-E 34,338.94 1,693.54 36,032.48
2 ZONE-2-PACKAGE-F 21,535.68 - 21,535.68
3 ZONE-3-PACKAGE-H 13,454.30 - 13,454.30
4 ZONE-4-PACKAGE-E 60,869.16 210.76 61,079.92

Total Workdone Quantity (M²) 130,198.08 1,904.30 132,102.38

MPR- AUGUST 2017 INT/CRP/FR/011 Page 46


SUMMERY OF EXPANSION JOINT

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L

Expansion joint 20-Aug-17

Previous Month Current Month Todate


Location Structure Reference Segments
Qty(LM) Qty(LM) Qty(LM)
ZONE-1
BASE TYPE-1 S-1 51.462 51.46

Road A1- 8-Base -

FOR WALL-01 13.115 13.12

FOR WALL-02 13.424 13.42

BASE TYPE-1 S-2 50.15 50.15


Road A1- 8-Base -
FOR WALL-01 12.24 12.24
FOR WALL-02 12.75 12.75

BASE TYPE-1 S-3 50.91 50.91


Road A1- 8-Base -
FOR WALL-01 10.94 10.94
FOR WALL-02 11.87 11.87

BASE TYPE-1 S-4 53.07 53.07


Road A1- 8-Base -
FOR WALL-01 11.10 11.10
FOR WALL-02 12.03 12.03

BASE TYPE-2 S-5 52.82 52.82


Base-Road A1-4 10.78 10.78
Road A1- 8-Base -
FOR WALL-01 10.78 10.78
FOR WALL-02 8.00 8.00
FOR WALL-03 4.00 4.00

Road A1-1- Base-TYPE-13 S-6 59.41 59.41


Road A1-4- Base-TYPE-13 14.43 14.43
FOR WALL-01 14.07 14.07
FOR WALL-02 10.31 10.31
FOR WALL-03 6.66 6.66

BASE TYPE-13 S-7 61.26 61.26


Road A1-4- Base-TYPE-13 15.89 15.89
FOR WALL-01 13.57 13.57
FOR WALL-02 9.70 9.70
FOR WALL-03 8.46 8.46

BASE TYPE-14 S-8 57.75 57.75


Road A1-4- Base-TYPE-14 13.07 13.07
For Wall - 01 14.26 14.26
For Wall - 02 8.44 8.44
For Wall - 03 10.28 10.28

MPR- AUGUST 2017 INT/CRP/FR/011 Page 47


Road A1-1- Base-TYPE-14 S-9 59.59 59.59
Road A1-4- Base-TYPE-14 12.52 12.52
Road A1-2- Base-TYPE-14
For Wall - 01 13.13 13.13
For Wall - 02 2.51 2.51 5.02
For Wall - 03 4.82 4.82 9.64

Road A1-1- Base-TYPE-15 S-09B 49.13 49.13


Road A1-4- Base-TYPE-15 14.46 14.46
Road A1-8- Base-TYPE-15 13.85 13.85
For Wall - 01 13.28 13.28
For Wall - 03 15.07 15.07

Base -TYPE-15
Base-Road A1-1,A1-2,A1-4 S-10 69.85 69.85
East Wall 3 18.33 18.33
West Wall 1 8.38 8.38
East Wall 2 16.06 16.06
West Wall 8

Road A1-1-Base-Type-16 S-11B 68.44 68.44


Road A1-2-Base-Type-16
For Wall - 3 21.53 21.53
For Wall - 8 6.29 6.29
For Wall - 1

Road A1-1-Base-Type-16 S-12B 70.77 70.77


Road A1-2-Base-Type-16
For Wall-3 20.38 20.38
For Wall-8 6.95 6.95
For Wall-1

Road A1-1-Base-Type-17 S-13B 72.78 72.78


Road A1-2-Base-Type-17 12.75 12.75
For Wall-3 10.95 10.95 21.90
For Wall-8 4.56 4.56 9.12
For Wall-1 -
For Wall-9

SUB TOTAL 1,297.31 38.90 1,336.21


ZONE-2
Base slab -sec 15 S-01 65.38 65.38

SUB TOTAL 65.38 - 65.38

MPR- AUGUST 2017 INT/CRP/FR/011 Page 48


ZONE-4

Road A1-1- Base-TYPE-23 19B 47.13 47.13


Road A1-2- Base-TYPE-23
Road A1-3- Base-TYPE-23
For Wall -04
For Wall - 10 9.12 9.12
For Wall - 11
For Wall - 05

PVC T-LOCK-SEGMENT-20B(TYPE 23) S-20


ROAD A1-1 47.13 47.13
ROAD A1-2
ROAD A1-3
WALL-05-UPTURN
WALL-11-UPTURN 8.15 8.15
WALL-10-UPTURN 7.89 7.89
WALL-04-UPTURN -

PVC T-LOCK-SEGMENT-21B(TYPE 22) S-21 48.40 48.40


ROAD A1-21 B
ROAD A1-2 16.62 16.62
ROAD A1-3 22.07 22.07
WALL-05-UPTURN
WALL-11-UPTURN
WALL-10-UPTURN
WALL-04-UPTURN

PVC T-LOCK-SEGMENT-22B(TYPE-21A) S-22B 47.56 47.56


Road A1-2- Base-TYPE-23 22.90 22.90
Road A1-3- Base-TYPE-11 27.87 27.87
WALL-05-UPTURN
WALL-11-UPTURN 15.57 15.57
WALL-10-UPTURN 16.20 16.20
WALL-12-UPTURN
WALL-04-UPTURN

Road A1-1- Base-TYPE-21B S-23 46.99 46.99


Road A1-2& A1-9- Base-TYPE-21B 26.39 26.39
Road A1-3- Base-TYPE-21B 16.55 16.55
Road A1-13- Base-TYPE-21B 15.74 15.74
For Wall - 10 16.20 16.20
For Wall - 11 15.57 15.57

Base-TYPE-12 S-24 44.01 44.01


Road A1-2-Base-type-12 12.39 12.39
Road A1-9-Base-type-12 13.48 13.48
ROAD A1-13 13.98 13.98
ROAD A1-3 14.20 14.20
Road A1-09 -
For Wall - 04 (Vertical CJ)
For Wall - 05 (Vertical) CJ 18.26 18.26
For Wall - 10 (Vertical CJ)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 49


For Wall - 11 (Vertical) CJ
For Wall - 12 (Vertical) CJ 2.80 2.80
For Wall - 13 (Vertical) CJ

Base -TYPE-12 25A 47.93 47.93


Base-Road A1-13 13.98 13.98
Base-Road A1-3 14.20 14.20
Base-Road A1-09 -
West Wall 5 upturn 18.26 18.26
East Wall 4 upturn
East Wall 10-Upturn
West Wall 11-Upturn
East Wall 12-Upturn 5.04 5.04
West Wall 13-Upturn

Road A1-1- Base-TYPE-11 S-26 44.24 44.24


Road A1-2- Base-TYPE-11
Road A1-9- Base-TYPE-11
Road A1-3- Base-TYPE-11
Road A1-13- Base-TYPE-11
For Wall - 04
For Wall - 05
For Wall - 12 13.11 13.11
For Wall - 10
For Wall - 11
For Wall - 13

Road A1-1- Base-TYPE-10 S-27 65.34 65.34


Road A1-13- Base-TYPE-10
Road A1-9- Base-TYPE-10 12.43 12.43
For Wall- 13
For Wall - 04
For Wall - 05 9.85 9.85
For Wall - 12 12.33 12.33

Road A1-1- Base-TYPE-10 S-28 65.34 65.34


Road A1-13- Base-TYPE-10
Road A1-9- Base-TYPE-10 12.43 12.43
For Wall - 04
For Wall - 05 8.14 8.14
For Wall - 13
For Wall - 12 11.25 11.25

Road A1-1- Base-TYPE-9 S-29 64.09 64.09


Road A1-9- Base-TYPE-9 12.45 12.45
For Wall - 05 8.29 8.29
For Wall - 12 15.15 15.15
For Wall - 13 12.51 12.51

MPR- AUGUST 2017 INT/CRP/FR/011 Page 50


Road A1-1- Base-TYPE-9 S-30 55.70 55.70
Road A1-9- Base-TYPE-9 12.20 12.20
For Wall - 05 4.32 4.32
For Wall - 12 14.72 14.72
For Wall - 13 8.91 8.91

Road A1-1-BASE TYPE-9 S-31B 52.34 52.34


Road A1-9-BASE TYPE-9 11.97 11.97
FOR WALL-05 2.81 2.81
FOR WALL-13 10.30 10.30
FOR WALL-12 14.52 14.52

BASE TYPE-9 S-31D 52.34 52.34


FOR WALL-13 14.52 14.52
FOR WALL-12 10.30 10.30

BASE TYPE-8 S-32 52.10 52.10


FOR WALL-13 13.68 13.68
FOR WALL-12 13.63 13.63

BASE TYPE-8 S-33 52.10 52.10


FOR WALL-13
FOR WALL-12 13.69 13.69

BASE TYPE-7 S-34 52.12 52.12


Road A1-15 14.33 14.33
FOR WALL-12 12.96 12.96
FOR WALL-13 8.94 8.94
FOR WALL-6 3.87 3.87

BASE TYPE-6 S-35 49.90 49.90


Road A1-15- Base-TYPE-6 15.74
Base-Road A1-16 17.93 17.93
FOR WALL-13 13.42 13.42
FOR WALL-12 14.91 14.91
FOR WALL-6 4.87 4.87
FOR WALL-7 3.63 3.63

BASE TYPE-6 S-36


ROAD A1-1 49.45 49.45
ROAD A1-15 15.64 15.64
ROAD A1-16 17.85 17.85
FOR WALL-13 13.17 13.17
FOR WALL-12 14.13 14.13
FOR WALL-6 6.81 6.81
FOR WALL-7 4.68 4.68

BASE TYPE-6 S-37 49.34 49.34


Road A1-15- Base-TYPE-6 15.66 15.66
Road A1-16- Base-TYPE-6 18.34 18.34
FOR WALL-13 14.67 14.67
FOR WALL-12 14.13 14.13
FOR WALL-6 8.30 8.30
FOR WALL-7 6.09 6.09

MPR- AUGUST 2017 INT/CRP/FR/011 Page 51


BASE TYPE-5 S-38 49.72 49.72
ROAD-A1-15 13.71 13.71
ROAD A1-16 15.67 15.67
FOR WALL-6 12.59 12.59
FOR WALL-7 9.74 9.74
FOR WALL-12 16.12 16.12
FOR WALL-13 18.46 18.46

BASE TYPE-5 S-39 48.66 48.66


Road A1-15- Base-TYPE-5 16.11
Road A1-16- Base-TYPE-5 15.14 15.14
FOR WALL-13 19.96 19.96
FOR WALL-12 17.43 17.43
FOR WALL-6 12.79 12.79
FOR WALL-7 11.67 11.67

BASE TYPE-5 S-40 47.61 47.61


ROAD A1-1
ROAD A1-15 15.48 15.48
ROAD A1-16 14.62 14.62
FOR WALL-13 20.92 20.92
FOR WALL-12 19.91 19.91
FOR WALL-6 16.09 16.09
FOR WALL-7 12.69 12.69

Road A1-1- Base-TYPE-4 S-41 44.76 44.76


Road A1-16- Base-TYPE-4 15.75 15.75
For Wall - 06 16.39 16.39
For Wall - 07 16.69 16.69
For Wall - 12 5.58 5.58

BASE TYPE-3 S-42 40.53 40.53


FOR WALL-6 16.65 16.65
FOR WALL-7 16.35 16.35

Road A1-1- Base-TYPE-3 S-43 57.90 57.90


For Wall - 06 16.87 16.87
For Wall - 07 16.52 16.52

Road A1-1- Base-TYPE-3 53.68 53.68


For Wall - 06 8.56 8.56
For Wall - 07 -

SUB TOTAL 1,993.51 688.32 2,681.83

General Summary of Expansion Joint:


1 ZONE-1-PACKAGE-E 1,297.31 38.90 1,336.21
2 ZONE-2-PACKAGE-F 65.38 - 65.38
3 ZONE-3-PACKAGE-H
4 ZONE-4-PACKAGE-E 1,993.51 688.32 2,681.83

TOTAL QUANTITY ( M ) 3,356.20 727.22 4,083.42

MPR- AUGUST 2017 INT/CRP/FR/011 Page 52


SUMMERY OF CONSTRUCTION JOINT

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L

Construction joint 20-Aug-17

Previous Current Todate


Location Structure Reference SEGMENTS
Qty(LM) Qty(LM) Qty(LM)

ZONE 1
BASE -TYPE-1 S-1 54.36 54.36
FOR WALL-01(VERTICAL CJ) 13.93 13.93
FOR WALL-02(VERTICAL CJ) 14.59 14.59
FOR WALL-01(HORIZONTAL CJ) 14.57 14.57
FOR WALL-02(HORIZONTAL CJ) 14.24 14.24

BASE -TYPE-1 S-2 54.93 54.93

FOR WALL-01(VERTICAL CJ) 13.61 13.61

FOR WALL-02(VERTICAL CJ) 14.40 14.40

FOR WALL-01(HORIZONTAL CJ) 57.96 57.96

FOR WALL-02(HORIZONTAL CJ) 56.00 56.00

BASE -TYPE-1 S-3 55.88 55.88


FOR WALL-01(VERTICAL CJ) 13.92 13.92
FOR WALL-02(VERTICAL CJ) 14.65 14.65
FOR WALL-01(HORIZONTAL CJ) 57.66 57.66
FOR WALL-02(HORIZONTAL CJ) 57.60 57.60

BASE -TYPE-1 S-4 57.71 57.71


FOR WALL-01(VERTICAL CJ) 14.68 14.68
FOR WALL-02(VERTICAL CJ) 14.97 14.97
FOR WALL-01(HORIZONTAL CJ) 28.91 28.91
FOR WALL-02(HORIZONTAL CJ) 28.11 28.11

Base-TYPE-2 S-5 53.37 53.37


Road A1-4 13.54 13.54
For Wall - 01 (Vertical CJ) 13.15 13.15
For Wall - 02 (Vertical) CJ 12.07 12.07
For Wall - 03 (Vertical) CJ 6.44 6.44
For Wall - 01 (Horizontal CJ) 22.33 22.33
For Wall - 02 (Horizontal CJ) 41.28 41.28
For Wall - 03 (Horizontal CJ) 21.60 21.60

BASE -TYPE-3 S-6 70.12 70.12


FOR WALL-1-(VERTICAL CJ) 13.81 13.81
FOR WALL-2-(VERTICAL CJ) 6.46 6.46
FOR WALL-3-(VERTICAL CJ) 6.74 6.74
FOR WALL-01(HORIZONTAL CJ) 35.43 35.43
FOR WALL-02(HORIZONTAL CJ) 68.38 68.38
FOR WALL-03(HORIZONTAL CJ) 34.27 34.27

MPR- AUGUST 2017 INT/CRP/FR/011 Page 53


BASE -TYPE-13 S-7 72.49 72.49
FOR WALL-1-(VERTICAL CJ) 14.78 14.78
FOR WALL-2-(VERTICAL CJ) 5.34 5.34
FOR WALL-3-(VERTICAL CJ) 8.59 8.59
FOR WALL-01(HORIZONTAL CJ) 64.56 64.56
FOR WALL-02(HORIZONTAL CJ) 60.22 60.22
FOR WALL-03(HORIZONTAL CJ) 59.24 59.24

Base-TYPE-14 S-8 73.60 73.60


For Wall - 01 (Vertical CJ) 13.91 13.91
For Wall - 02 (Vertical) CJ 4.40 4.40
For Wall - 03 (Vertical) CJ 11.95 11.95
For Wall - 01 (Horizontal CJ) 66.70 66.70
For Wall - 02 (Horizontal CJ) 64.98 64.98
For Wall - 03 (Horizontal CJ) 31.65 31.65

BASE TYPE-14 S-9 77.96 77.96


For Wall - 01 (Vertical CJ) 12.15 12.15
For Wall - 02 (Vertical) CJ 2.44 2.44
For Wall - 03 (Vertical) CJ 14.87 14.87
For Wall - 01 (Horizontal CJ) 37.10 37.10 74.20
For Wall - 02 (Horizontal CJ) 70.52 70.52
For Wall - 03 (Horizontal CJ) 31.65 31.65

Base-TYPE-15 S-10 78.99 78.99


For Wall - 03 (Vertical CJ) 19.87 19.87
For Wall - 01 (Vertical) CJ 15.74 15.74
For Wall - 02 (Vertical) CJ 3.66 3.66
For Wall - 03 (Horizontal CJ) 35.35 35.35
For Wall - 01 (Horizontal CJ) 73.77 73.77
For Wall - 02 (Horizontal CJ)
For Wall - 08 (Horizontal CJ) 72.74 72.74

Base-TYPE-16 S-11 82.55 82.55


For Wall - 03 (Vertical CJ) 21.83 21.83
For Wall - 01 (Vertical) CJ
For Wall - 08 (Vertical) CJ 4.77 4.77
For Wall - 03 (Horizontal CJ) 34.81 34.81
For Wall - 01 (Horizontal CJ)
For Wall - 08 (Horizontal CJ) 36.34 36.34

Base-TYPE-16 S-12
For Wall - 03 (Vertical CJ) 85.25 85.25
For Wall - 01 (Vertical) CJ 23.55 23.55
For Wall - 08 (Vertical) CJ
For Wall - 03 (Horizontal CJ) 4.97 4.97
For Wall - 01 (Horizontal CJ) 35.90 35.90
For Wall - 08 (Horizontal CJ)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 54


Base-TYPE-17 S-13
For Wall - 03 (Vertical CJ) 87.04 87.04
For Wall - 01 (Vertical) CJ 23.64 23.64
For Wall - 08 (Vertical) CJ 14.35 14.35
For Wall - 03 (Horizontal CJ) 7.29 7.29
For Wall - 01 (Horizontal CJ) 37.85 37.85
For Wall - 08 (Horizontal CJ) 38.70 38.70
38.95 38.95
Base-TYPE-18 S-15
Addional Superswell & Injection hose 58.73 58.73
For Wall - 03 (Vertical CJ) 26.89 26.89
For Wall - 01 (Vertical) CJ -
For Wall - 08 (Vertical) CJ -
For Wall - 03 (Horizontal CJ) -
For Wall - 01 (Horizontal CJ) -
For Wall - 08 (Horizontal CJ) -

Base-TYPE-19 S-16 55.15 55.15


For Wall - 03 (Vertical CJ)
For Wall - 09 (Vertical) CJ
For Wall - 08 (Vertical) CJ
For Wall - 01 (Vertical) CJ
For Wall - 03 (Horizontal CJ)
For Wall - 09 (Horizontal CJ)
For Wall - 08 (Horizontal CJ)

SUB TOTAL 2,717.18 244.87 2,962.05

ZONE-4

Base-TYPE-24 S-19 48.45 48.45

For Wall - 04 (Vertical CJ) -

For Wall - 10 (Vertical) CJ -

For Wall - 11 (Vertical) CJ -

For Wall - 05 (Vertical) CJ -

For Wall - 04 (Horizontal CJ) -

For Wall - 10 (Horizontal CJ) 41.90 41.90

For Wall - 11 (Horizontal CJ) 45.27 45.27

For Wall - 5 (Horizontal CJ) -

Base-TYPE-23 S-20 51.82 51.82

For Wall - 04 (Vertical CJ)

For Wall - 10 (Vertical) CJ 5.27 5.27

For Wall - 11 (Vertical) CJ 7.32 7.32

For Wall - 05 (Vertical) CJ

For Wall - 04 (Horizontal CJ)

For Wall - 10 (Horizontal CJ) 38.50 38.50

For Wall - 11 (Horizontal CJ) 39.94 39.94

For Wall - 5 (Horizontal CJ)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 55


Base-TYPE-23 S-21 46.00 46.00

For Wall - 04 (Vertical CJ)

For Wall - 05 (Vertical CJ) 20.18 20.18

For Wall - 10 (Vertical) CJ 5.81 5.81

For Wall - 11 (Vertical) CJ 6.52 6.52

For Wall - 04 (Horizontal CJ)

For Wall - 5 (Horizontal CJ)

For Wall - 10 (Horizontal CJ) 75.94 75.94

For Wall - 11 (Horizontal CJ) 39.53 39.53

Base-TYPE-22 & 21 A S-22 47.98 47.98

For Wall - 04 (Vertical CJ)

For Wall - 05 (Vertical) CJ

For Wall - 10 (Vertical CJ) 5.19 5.19

For Wall - 11 (Vertical) CJ 4.21 4.21

For Wall - 04 (Horizontal CJ)

For Wall - 05 (Horizontal CJ)

For Wall - 10 (Horizontal CJ) 42.17 42.17

For Wall - 11 (Horizontal CJ) 44.55 44.55

For Wall - 12 (Horizontal CJ)

Base-TYPE-21B S-23 83.93 83.93

For Wall - 04 (Vertical CJ)

For Wall - 05 (Vertical) CJ

For Wall - 10 (Vertical CJ) 2.15 2.15

For Wall - 11 (Vertical) CJ 2.33 2.33

For Wall - 04 (Horizontal CJ)

For Wall - 05 (Horizontal CJ) 37.80 37.80

For Wall - 10 (Horizontal CJ) 35.94 35.94

For Wall - 11 (Horizontal CJ) 37.39 37.39

For Wall - 12 (Horizontal CJ)

Base-TYPE-12 S-24 79.27 13.99 93.26

For Wall - 04 (Vertical CJ) -

For Wall - 05 (Vertical) CJ 21.67 21.67

For Wall - 10 (Vertical CJ) 3.37 3.37

For Wall - 11 (Vertical) CJ 2.86 2.86

For Wall - 12 (Vertical) CJ 4.72 4.72

For Wall - 13 (Vertical) CJ 0.78 0.78

For Wall - 04 (Horizontal CJ)

For Wall - 05 (Horizontal CJ) 30.00 30.00

For Wall - 10 (Horizontal CJ)

For Wall - 11 (Horizontal CJ)

For Wall - 12 (Horizontal CJ) 60.00 60.00

For Wall - 13 (Horizontal CJ)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 56


Base-TYPE-12 S-25 92.87 92.87

For Wall - 04 (Vertical CJ) 16.11 16.11

For Wall - 05 (Vertical) CJ 20.75 20.75

For Wall - 10 (Vertical CJ) 1.90 1.90

For Wall - 11 (Vertical) CJ 1.67 1.67

For Wall - 12 (Vertical) CJ 6.67 6.67

For Wall - 13 (Vertical) CJ 1.68 1.68

For Wall - 04 (Horizontal CJ)

For Wall - 05 (Horizontal CJ) 30.00 30.00

For Wall - 10 (Horizontal CJ) 30.00 30.00

For Wall - 11 (Horizontal CJ) 30.00 30.00

For Wall - 12 (Horizontal CJ) 30.00 30.00

For Wall - 13 (Horizontal CJ)

Base-TYPE-11 S-26 46.22 46.22

For Wall - 04 (Vertical CJ)

For Wall - 05 (Vertical) CJ 18.21 18.21

For Wall - 10 (Vertical CJ) 2.26 2.26

For Wall - 11 (Vertical) CJ 2.31 2.31

For Wall - 12 (Vertical) CJ 8.65 8.65

For Wall - 13 (Vertical) CJ

For Wall - 04 (Horizontal CJ)

For Wall - 05 (Horizontal CJ) 30.00 30.00

For Wall - 10 (Horizontal CJ)

For Wall - 11 (Horizontal CJ)

For Wall - 12 (Horizontal CJ) 30.00 30.00

For Wall - 13 (Horizontal CJ)

BASE -TYPE-10 S-27 46.94 46.94

For Wall - 04 (Vertical CJ)

For Wall - 05 (Vertical) CJ 6.88 6.88

For Wall - 12 (Vertical) CJ 4.96 4.96

For Wall - 13 (Vertical) CJ 3.54 3.54

FOR WALL-05-(HORIZONTAL CJ) 30.86 30.86

FOR WALL-04-(HORIZONTAL CJ)

FOR WALL-12-(HORIZONTAL CJ) 15.11 15.11

FOR WALL-13-(HORIZONTAL CJ) 15.11 15.11

BASE -TYPE-10 S-28 78.66 78.66

FOR WALL-05-(VERTICAL CJ) 12.09 12.09

FOR WALL-04-(VERTICAL CJ)

FOR WALL-12-(VERTICAL CJ) 10.61 10.61

FOR WALL-13-(VERTICAL CJ) 4.46 4.46

FOR WALL-05-(HORIZONTAL CJ) 30.00 30.00

FOR WALL-04-(HORIZONTAL CJ)

FOR WALL-12-(HORIZONTAL CJ) 30.00 30.00

FOR WALL-13-(HORIZONTAL CJ)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 57


BASE -TYPE-9 S-29 64.95 64.95

FOR WALL-05-(VERTICAL CJ) 9.69 9.69

FOR WALL-12-(VERTICAL CJ) 16.53 16.53

FOR WALL-13-(VERTICAL CJ) 5.78 5.78

FOR WALL-05-(HORIZONTAL CJ) 30.00 30.00

FOR WALL-12-(HORIZONTAL CJ) 30.20 30.20

FOR WALL-13-(HORIZONTAL CJ) 30.00 30.00

BASE -TYPE-9 S-30 50.96 50.96


For Wall 5 (Vertical CJ) 7.98 7.98
For Wall 12 (Vertical CJ) 16.19 16.19
For Wall 13 (Vertical CJ) 7.00 7.00
For Wall - 05 (Horizontal CJ) 30.02 30.02
For Wall - 12 (Horizontal CJ) 30.08 30.08
For Wall - 13 (Horizontal CJ) 60.08 60.08

Base -TYPE-9 S-31 13.84 13.84


For Wall 5 (Vertical CJ) 1.27 1.27
For Wall 12 (Vertical CJ) 3.18 3.18
For Wall 13 (Vertical CJ) 8.35 8.35
For Wall - 05 (Horizontal CJ) 30.02 30.02
For Wall - 12 (Horizontal CJ) 30.05 30.05
For Wall - 13 (Horizontal CJ) 60.00 60.00

BASE -TYPE-8 S-32 57.09 57.09


FOR WALL-12(VERTICAL CJ) 14.91 14.91
FOR WALL-13(VERTICAL CJ) 14.81 14.81
FOR WALL-12(HORIZONTAL CJ) 16.70 16.70
FOR WALL-13(HORIZONTAL CJ) 16.70 16.70

Base -TYPE-8 S-33 57.10 57.10


For Wall 12 (Vertical CJ) 14.99 14.99
For Wall 13 (Vertical CJ) 14.52 14.52
For Wall - 12 (Horizontal CJ) 25.98 25.98
For Wall - 13 (Horizontal CJ) 25.98 25.98

Base -TYPE-7 S-34 68.09 68.09


For Wall - 06 (Vertical CJ) 5.88 5.88
For Wall 12 (Vertical CJ) 14.98 14.98
For Wall 13 (Vertical CJ) 8.26 8.26
For Wall - 06 (Horizontal CJ) 24.70 24.70
For Wall - 12 (Horizontal CJ) 48.68 48.68
For Wall - 13 (Horizontal CJ) 52.76 52.76

Base-TYPE-6 S-35 47.88 47.88


For Wall - 06 (Vertical CJ) 9.91 9.91
For Wall - 07 (Vertical) CJ
For Wall - 12 (Vertical) CJ 8.30 8.30
For Wall - 13 (Vertical) CJ 6.57 6.57
For Wall - 06 (Horizontal CJ) 28.48 28.48
For Wall - 07 (Horizontal CJ) 14.25 14.25
For Wall - 12 (Horizontal CJ) 42.57 42.57
For Wall - 13 (Horizontal CJ) 46.01 46.01

MPR- AUGUST 2017 INT/CRP/FR/011 Page 58


Base-TYPE-6 S-36 79.55 79.55
For Wall - 06 (Vertical CJ) 11.63 11.63
For Wall - 07 (Vertical) CJ 9.64 9.64
For Wall - 12 (Vertical) CJ 7.25 7.25
For Wall - 13 (Vertical) CJ 5.09 5.09
For Wall - 06 (Horizontal CJ) 28.35 28.35
For Wall - 07 (Horizontal CJ) 28.44 28.44
For Wall - 12 (Horizontal CJ) 56.82 56.82
For Wall - 13 (Horizontal CJ) 56.84 56.84

Base-TYPE-6 S-37 40.45 40.45


For Wall - 06 (Vertical CJ) 13.36 13.36
For Wall - 07 (Vertical) CJ 11.12 11.12
For Wall - 12 (Vertical) CJ 5.83 5.83
For Wall - 13 (Vertical) CJ 3.58 3.58
For Wall - 06 (Horizontal CJ) 28.31 28.31
For Wall - 07 (Horizontal CJ) 28.40 28.40
For Wall - 12 (Horizontal CJ) 56.80 56.80
For Wall - 13 (Horizontal CJ) 56.80 56.80

Base-TYPE-5 S-38 78.88 78.88


For Wall - 06 (Vertical CJ) 15.43 15.43
For Wall - 07 (Vertical) CJ 12.82 12.82
For Wall - 12 (Vertical) CJ 3.84 3.84
For Wall - 13 (Vertical) CJ 1.04 1.04
For Wall - 06 (Horizontal CJ) 30.40 30.40
For Wall - 07 (Horizontal CJ) 30.16 30.16
For Wall - 12 (Horizontal CJ) 45.12 45.12
For Wall - 13 (Horizontal CJ) 30.00 30.00

Base-TYPE-5 S-39 54.60 54.60


For Wall - 06 (Vertical CJ) 17.06 17.06
For Wall - 07 (Vertical) CJ 14.70 14.70
For Wall - 12 (Vertical) CJ 2.34 2.34
For Wall - 13 (Vertical) CJ 3.06 3.06
For Wall - 06 (Horizontal CJ) 14.95 14.95
For Wall - 07 (Horizontal CJ) 14.95 14.95
For Wall - 12 (Horizontal CJ) 18.00 18.00
For Wall - 13 (Horizontal CJ)

Base-TYPE-5 S-40 75.07 75.07


For Wall - 06 (Vertical CJ) 18.19 18.19
For Wall - 07 (Vertical) CJ 16.30 16.30
For Wall - 12 (Vertical) CJ
For Wall - 13 (Vertical) CJ
For Wall - 06 (Horizontal CJ) 29.50 29.50
For Wall - 07 (Horizontal CJ) 30.50 30.50
For Wall - 12 (Horizontal CJ)
For Wall - 13 (Horizontal CJ) 30.00 30.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 59


Base-TYPE-4 S-41 72.00 72.00
For Wall - 06 (Vertical CJ) 17.26 17.26
For Wall - 07 (Vertical) CJ 14.61 14.61
For Wall - 12 (Vertical) CJ 0.95 0.95
For Wall - 06 (Horizontal CJ) 65.16 65.16
For Wall - 07 (Horizontal CJ) 67.14 67.14
For Wall - 12 (Horizontal CJ) 30.00 30.00

Base-TYPE-3 S-42 68.15 68.15


For Wall - 06 (Vertical CJ) 17.62 17.62
For Wall - 07 (Vertical) CJ 17.42 17.42
For Wall - 06 (Horizontal CJ) 27.97 27.97
For Wall - 07 (Horizontal CJ) 58.60 58.60

Base-TYPE-3 S-43 64.21 64.21


For Wall - 06 (Vertical CJ) 17.86 17.86
For Wall - 07 (Vertical) CJ 17.54 17.54
For Wall - 06 (Horizontal CJ) 29.00 29.00
For Wall - 07 (Horizontal CJ) 30.00 30.00

SUB TOTAL 4,524.56 149.61 4,674.17


ZONE-2
Base Slab Level-2 (SEC-15) SEG-01 66.88 66.88
East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 30.00 30.00
West side Walls - Horizontal 30.00 30.00

Base Slab Level-2 (SEC-14) SEG-02 66.88 66.88


East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 60.00 60.00
West side Walls - Horizontal 60.00 60.00

Base Slab Level-2 (SEC-14) SEG-03 66.88 66.88


East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 30.00 30.00
West side Walls - Horizontal 30.00 30.00

BASE SLAB LEVEL-2 (SEC-13) SEG-04 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 76.60 76.60
WEST SIDE WALLS-HORIZONTAL 76.60 76.60
BASE SLAB LEVEL-1-SB 9.64 9.64
BASE SLAB LEVEL-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-13) SEG-05 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 27.60 27.60 55.20
WEST SIDE WALLS-HORIZONTAL 27.60 27.60 55.20
BASE SLAB LEVEL-1-SB 9.64 9.64
BASE SLAB LEVEL-1-NB 10.25 10.25

MPR- AUGUST 2017 INT/CRP/FR/011 Page 60


Base Slab Level-2 (SEC-12) SEG-06 66.88 66.88
East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 55.20 55.20
West side Walls - Horizontal 55.20 55.20
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)
East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

Base Slab Level-2(Delayed Strip) - Bet. Segments 6&7 133.76 133.76


East side Walls - Vertical 49.20 49.20
West side Walls - Vertical 50.80 50.80
East side Walls - Horizontal 12.00 12.00
West side Walls - Horizontal 12.00 12.00

BASE SLAB LEVEL-2 (SEC-11) SEG-07 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 86.80 86.80
WEST SIDE WALLS-HORIZONTAL 86.80 86.80
BASE SLAB LEVEL-1-SB 9.64 9.64
BASE SLAB LEVEL-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-10) SEG-08 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 56.60 56.60
WEST SIDE WALLS-HORIZONTAL 56.60 56.60
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)
East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

BASE SLAB LEVEL-2(DELAYED STRIP)-


SECTION-10 SEG-08 133.76 133.76

BASE SLAB LEVEL-2 (SEC-10) SEG-09 66.88 66.88


EAST SIDE WALLS-VERTICAL 27.60 27.60
WEST SIDE WALLS-VERTICAL 28.40 28.40
EAST SIDE WALLS-HORIZONJTAL 56.60 56.60
WEST SIDE WALLS-HORIZONTAL 56.60 56.60
Base Slab Level-1-SB 9.64 9.64

MPR- AUGUST 2017 INT/CRP/FR/011 Page 61


Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)
East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

BASE SLAB LEVEL-2 (SEC-09) SEG-10 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 44.00 44.00
WEST SIDE WALLS-HORIZONTAL 44.00 44.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-09) SEG-11 66.88 66.88


EAST SIDE WALLS-VERTICAL 24.60 24.60
WEST SIDE WALLS-VERTICAL 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL 44.00 44.00
WEST SIDE WALLS-HORIZONTAL 44.00 44.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-08) SEG-12 66.88 66.88


East side Walls - Vertical (SEC 08) 24.60 24.60
West side Walls - Vertical (SEC 08) 25.40 25.40
EAST SIDE WALLS-VERTICAL(SEC-08) 20.00 20.00
WEST SIDE WALLS-VERTICAL(SEC-08) 20.00 20.00

BASE SLAB LEVEL-2(DELAYED STRIP) SEG-12A 66.88 66.88

BASE SLAB LEVEL-2 (SEC-08) SEG-12B 66.88 66.88

BASE SLAB LEVEL-2 (SEC-08) SEG-13 66.88 66.88


East side Walls - Vertical (SEC 08) 24.60 24.60
West side Walls - Vertical (SEC 08) 25.40 25.40
East side Walls - Horizontal (SEC 08) 60.00 60.00
West side Walls - Horizontal (SEC 08) 60.00 60.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-07) SEG-14 66.88 66.88


East side Walls - Vertical (SEC 07) 27.60 27.60
West side Walls - Vertical (SEC 07) 28.40 28.40
East side Walls - Horizontal (SEC 07) 60.00 60.00
West side Walls - Horizontal (SEC 07) 60.00 60.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 62


East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

Base Slab Level-2 (SEC-7) SEG-15 66.88 66.88


East side Walls - Vertical (SEC 07) 27.98 27.98
West side Walls - Vertical (SEC 07) 28.78 28.78
East side Walls - Horizontal (SEC-07) 60.00 60.00
West side Walls - Horizontal (SEC-07) 60.00 60.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)
East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

Base Slab Level-2 (SEC-6) SEG-16 66.88 66.88


EAST SIDE WALLS-VERTICAL(SEC-07) 24.60 24.60
WEST SIDE WALLS-VERTICAL(SEC-07) 25.40 25.40
EAST SIDE WALLS-HORIZONJTAL(SEC-07) 30.00 30.00
WEST SIDE WALLS-HORIZONTAL(SEC-07) 30.00 30.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25
East side Wall 01- Vertical (Level-1)
West side Wall 05- Vertical (Level-1)
East Wall - 01 (Horizontal CJ)-Level-1 15.00 15.00
West Wall - 05 (Horizontal CJ)-Level-1 15.00 15.00

BASE SLAB LEVEL-2 (SEC-06) SEG-17 66.88 66.88


East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 60.00 60.00
West side Walls - Horizontal 60.00 60.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25

BASE SLAB LEVEL-2 (SEC-05) SEG-18 66.88 66.88


East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 60.00 60.00
West side Walls - Horizontal 60.00 60.00
Base Slab Level-1-SB 9.64 9.64
Base Slab Level-1-NB 10.25 10.25

Base Slab Level-2(SEC-06) SEG-19 66.88 66.88


East side Walls - Vertical 24.60 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 60.00 60.00
West side Walls - Horizontal 60.00 60.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 63


Base Slab Level-2(SEC-05) SEG-20 66.88 66.88
East side Walls - Vertical 12.30 12.30
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 15.00 15.00
West side Walls - Horizontal 30.00 30.00

Base Slab Level-2(SEC-04) SEG-21 66.88 66.88


East side Wall-2 - Vertical 12.30 12.30
East side Wall-1 - Vertical 10.45 10.45
West side Walls - Vertical 25.40 (0.40) 25.00
East side Walls - Horizontal 15.00 15.00 30.00
West side Walls - Horizontal 30.00 30.00

Base Slab Level-2(SEC-03) SEG-22 66.88 66.88


East side Walls - Vertical 12.30 12.30 24.60
West side Walls - Vertical 25.40 25.40
East side Walls - Horizontal 15.00 15.00 30.00
West side Walls - Horizontal 30.00 30.00

SUB TOTAL 5,567.09 167.22 5,734.31

ZONE-3
Base Slab (GL 29-30) 69.68 69.68
Vertical 8.00 8.00
Base Slab (GL 30-31) 81.17 81.17
Vertical 8.00 8.00
Base Slab (GL 31-32) 79.62 79.62
8.00 8.00
Base Slab (GL 32-33) 80.85 80.85
8.00 8.00
Base Slab (GL 33-34) 82.77 82.77
8.00 8.00
Base Slab (GL 34-35) 85.39 85.39

Base Slab (GL 35-36) 88.61 88.61

Base Slab (GL 36-37) 96.50 96.50


Vertical 8.00 8.00
Vertical (37-38) 8.00 8.00
Base Slab (GL 38-39)-AT-AX 92.94 92.94

Base Slab (GL 38-39)-BA-BF 93.78 93.78

Base Slab (GL 39-40)-AT-AX 58.61 58.61

Base Slab (GL 40'-42') 96.39 96.39

Base Slab (GL-42') - BA-BF 51.50 51.50

Base Slab (GL-44') - AR-AX 59.00 59.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 64


Base Slab (GL-44') - BA-BG 59.00 59.00

Base Slab GL-37''-44' - bet. AX - BA 118.00 118.00

SUB TOTAL 1,349.82 - 1,349.82

General Summary of Construction Joint:


1 ZONE-1-PACKAGE-E 2,717.18 244.87 2,962.05
2 ZONE-2-PACKAGE-F 5,567.09 167.22 5,734.31
3 ZONE-3-PACKAGE-H 1,349.82 - 1,349.82
4 ZONE-4-PACKAGE-E 4,524.56 149.61 4,674.17

TOTAL QUANTITY 14,158.65 561.70 14,720.35

SUMMARY OF INTEGRITANK SPRAY MEMBRANE

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
Integritank-Spray Membrane Summary 20-Aug-17
Previous Month Current Month Todate
Location Structure Reference Segments
Qty(M 2) Qty(M 2) Qty(M 2)

ZONE-1

Segment 1-Type-1 S-1


For Wall - 2 316.14 108.39 424.53
For Wall - 1 358.58 62.75 421.33

Segment 2-Type-1 S-2


For Wall - 2 321.39 110.19 431.58
For Wall - 1 363.34 63.58 426.92

Segment 3-Type-1 S-3


For Wall - 2 336.81 115.48 452.29
For Wall - 1 381.48 66.76 448.24

Segment 4-Type-1 S-4


For Wall - 2 336.16 115.26 451.42
For Wall - 1 387.94 67.89 455.83

Segment 5 - T2 S-5
For Wall - 3 58.33 58.33
For Wall - 2 -
For Wall - 1 303.99 303.99
T-lock for Road A1-8

MPR- AUGUST 2017 INT/CRP/FR/011 Page 65


Segment 6 TYPE-3 S-6
WALL-1 534.71 534.71
WALL-2 295.04 295.04
WALL-3 217.93 217.93

Segment 7 -TYPE-3 S-7


WALL-1 364.38 364.38
WALL-2 234.82 234.82
WALL-3 295.59 295.59

Segment 8- Type-14 S-8


For Wall - 3
For Wall - 2 214.88 214.88
For Wall - 1

Segment 9A- Type-14 S-9


For Wall - 3
For Wall - 2 39.87 39.87
For Wall - 1

Segment 9B- Type-15 S-9B


For Wall - 3
For Wall - 2 34.12 34.12
For Wall - 1

Type-16 S-11
For Wall - 3
For Wall - 2
For Wall - 8 93.01 172.72 265.73
For Wall - 1

Type-16 S-12
For Wall - 3
For Wall - 2
For Wall - 8 244.75 244.75
For Wall - 1

SUB TOTAL 5,488.51 1,127.77 6,616.28

ZONE-2

Base -SEC-02 ( ST.6+305.00 to ST.6+315.20) 23


E NB-East Side-Level-2 -
W SB-West Side-Level-2 67.03 67.03

Base -SEC-03 ( ST.6+315.20 to ST.6+340) 22


E NB-East Side-Level-2 -
W SB-West Side-Level-2 162.50 162.50

MPR- AUGUST 2017 INT/CRP/FR/011 Page 66


Base -SEC-12 ( ST.6+340 to ST.6+370)
E North bound 19 & 20
W Southth bound 32.94 167.70 200.64

Base -SEC-12 ( ST.6+370 to ST.6+390 )


E North bound 18 131.76 131.76
W Southth bound 131.76 131.76

Base ( Sec-6) ( ST.6+390 to ST. 6+422.40)


E North bound 16 & 17 213.45 213.45
W Southth bound 213.45 213.45

Base ( Sec-7) ( ST.6+422.40 to ST. 6+450.00)


E North bound 14 & 15 181.83 181.83
W Southth bound 181.83 181.83

Base -SEC-08 ( ST.6+450.00 to ST. 6+488.30)


E North bound 12 & 13 252.32 252.32
W Southth bound 252.32 252.32

Base SEC-09 ( ST.6+488.30 to ST. 6+510.00)


E North bound 10 & 11 95.31 95.31
W Southth bound 142.96 142.96

Base -SEC-10 ( ST.6+510.00 to ST. 6+538.30)


E North bound 08 & 09 155.37 155.37
W Southth bound 170.90 170.90

Base -SEC-11 ( ST.6+538.30 to ST. 6+560.00)


E North bound 07 47.65 47.65
W Southth bound 142.96 142.96

Base -SEC-14 ( STA 6+600 to STA 6+625 )


E North bound 02 & 03 54.90 110.40 165.30
W Southth bound

Base -SEC-13 ( STA 6+582 to STA 6+600 )


E North bound 04 & 05 79.06 79.06
W Southth bound 118.58 118.58

Base -SEC-12 ( STA 6+560 to STA 6+582 )


E North bound 06 96.62 48.91 145.53
W Southth bound 144.94 0.59 145.53

Base -SEC-15 ( STA 6+625 to STA 6+640 ) 01 98.44 98.44


E NB-East Side-Level-2
W SB-West Side-Level-2

SUB TOTAL 2,840.91 655.57 3,496.48

MPR- AUGUST 2017 INT/CRP/FR/011 Page 67


ZONE-4

Type - 23 S-20
For Wall - 4 -
For Wall - 10 337.11 337.11
For Wall - 11 363.06 363.06
For Wall - 5 -

Type - 22 S-21
For Wall - 4
For Wall - 10 317.63 317.63
For Wall - 11 336.21 336.21
For Wall - 5

Segment 22 - T21A S-22


For Wall - 4
For Wall - 10 306.49 306.49
For Wall - 11 265.17 265.17
For Wall - 5

Segment-23 Type-21B S-23


For Wall - 10 85.34 85.34
For Wall - 11 69.90 69.90

Segment-24 S-24
For Wall 12 126.69 126.69
- -
Segment-25 S-25
For Wall 12 185.10 185.10
-
Segment 26 - T11 S-26
Wall 4
Wall 12 250.51 250.51
Wall 10
Wall 11
Wall 13
Wall 5

Segment-27 Type-10 S-27


For Wall - 13 157.18 157.18
For Wall - 12 364.30 364.30
For Wall - 5
For Wall - 4

Segment-28 Type-10 S-28


For Wall - 13 188.70 188.70
For Wall - 12 308.14 308.14
For Wall - 5 114.79 114.79
For Wall - 4

MPR- AUGUST 2017 INT/CRP/FR/011 Page 68


Segment-29 Type-09 S-29
For Wall - 13 232.31 232.31
For Wall - 12 433.64 433.64
For Wall - 5 112.90 112.90
For Wall - 4

Segment-30 Type-09 S-30


Wall 12
Wall 13 270.67 270.67
Wall 5 113.06 113.06

Segment 31 - T9 S-31
Wall 12
Wall 13 79.16 79.16
Wall 5

Segment 33 - T8 S-33
Wall 12 -
Wall 13 434.06 434.06

Segment 34 - T7 S-34 -
Wall 12 318.09 318.09
Wall 13 254.85 254.85
Wall 6 99.69 99.69

Segment 35 - T6 S-35 - -
For Wall - 7 213.74 213.74
For Wall - 12 304.65 304.65
For Wall - 13 165.21 165.21
For Wall - 6 265.82 265.82

Segment 36-Type-6 S-36 - -


For Wall - 7 251.29 251.29
For Wall - 12 341.60 341.60
For Wall - 13 192.97 192.97
For Wall - 6 315.48 315.48

Segment 37-Type-6 S-37 - -


For Wall - 7 278.65 278.65
For Wall - 12 149.76 149.76
For Wall - 13 142.89 142.89
For Wall - 6 357.07 357.07

Segment 38 - T5 S-38
For Wall - 7 335.50 335.50
For Wall - 12 181.07 181.07
For Wall - 13 82.28 82.28
For Wall - 6 217.92 217.92

MPR- AUGUST 2017 INT/CRP/FR/011 Page 69


Segment 39 - T5 S-39
For Wall - 7 206.32 177.44 383.76
For Wall - 12 88.95 88.95
For Wall - 13
For Wall - 6 334.15 334.15

Segment 40 - T5 S-40 - -
For Wall - 7 445.91 445.91
For Wall - 12 100.98 100.98
For Wall - 13 - -
For Wall - 6 529.81 529.81

Segment 41-Type-4 S-41


For Wall - 7 597.17 597.17
For Wall - 12
For Wall - 6 81.39 81.39

Segment 42-Type-3 S-42


For Wall - 7 530.35 530.35
For Wall - 6 66.16 66.16
SUB TOTAL 11,860.93 1,218.36 13,079.29

General Summary of Integritank Spray Membrane:


1 ZONE-1-PACKAGE-E 5,488.51 1,127.77 6,616.28
2 ZONE-2-PACKAGE-F 2,840.91 655.57 3,496.48
3 ZONE-3-PACKAGE-H
4 ZONE-4-PACKAGE-E 11,860.93 1,218.36 13,079.29

TOTAL WORK DONE QUANTITY 20,190.34 3,001.70 23,192.04

SUMMARY OF DAMAGE AREA’S FOR INTEGRITANK

DAMAGED AREA'S
Previous Month Current Month Todate
LOCATION Structure Reference SEGMENT
Qty Qty Total Qty

ZONE-1
Type-1 S-1B
For Wall - 2 14.02 14.02
For Wall - 1 14.51 14.51

Type-1 S-2
For Wall - 2 28.00 28.00
For Wall - 1 29.09 29.09

Type-1 S-3
For Wall - 2 14.03 14.03
For Wall - 1 14.52 14.52

Type-1 S-4
For Wall - 2 14.05 14.05
For Wall - 1 14.43 14.43

MPR- AUGUST 2017 INT/CRP/FR/011 Page 70


Type-2 S-05
For Wall - 2 (0.5m from BL) 10.92 10.92
For Wall - 1 (0.8m from BL) 18.48 18.48

TYPE-13 S-6
For Wall - 2 (0.8m from BL) 27.27 27.27
For Wall - 1 (0.8m from BL) 25.91 25.91

TYPE-13 S-7
For Wall - 2 (0.8m from BL) 24.10 24.10

Type-14 S-8
For Wall - 2 (0.8m from BL) 27.04 27.04

Type-16 S-11
For Wall - 8 (0.5m from BL) 17.76 17.76

Type-16 S-12
For Wall - 8 (0.5m from BL) 18.92 18.92

SUB TOTAL 294.13 18.92 313.05

ZONE-2

Base -SEC-15 ( STA 6+625 to STA 6+640 ) 01


E NB-East Side-Level-2 7.50 7.50
W SB-West Side-Level-2

Base -SEC-14 ( STA 6+600 to STA 6+625 ) 02 & 03


E NB-East Side-Level-2 6.25 6.25 12.50
W SB-West Side-Level-2 -

Base -SEC-13 ( STA 6+582 to STA 6+600 ) 04 & 05


E NB-East Side-Level-2 9.00 9.00
W SB-West Side-Level-2 9.00 9.00

Base -SEC-12 ( STA 6+560 to STA 6+582 ) 06


E NB-East Side-Level-2 11.00 11.00
W SB-West Side-Level-2 11.00 11.00

Base -SEC-11 ( ST.6+538.30 to ST. 6+560.00) 07


E NB-East Side-Level-2 10.85 10.85
W SB-West Side-Level-2 10.85 10.85

Base -SEC-10 ( ST.6+510.00 to ST. 6+538.30) 08 & 09


E NB-East Side-Level-2 14.15 14.15
W SB-West Side-Level-2 14.15 14.15

MPR- AUGUST 2017 INT/CRP/FR/011 Page 71


Base SEC-09 ( ST.6+488.30 to ST. 6+510.00) 10 & 11
E NB-East Side-Level-2 10.85 10.85
W SB-West Side-Level-2 10.85 10.85

Base -SEC-08 ( ST.6+450.00 to ST. 6+488.30) 12 & 13


E NB-East Side-Level-2 19.15 19.15
W SB-West Side-Level-2 19.15 19.15

Base ( Sec-7) ( ST.6+422.40 to ST. 6+450.00) 14 & 15


E NB-East Side-Level-2 13.80 13.80
W SB-West Side-Level-2 13.80 13.80

Base ( Sec-6) ( ST.6+390 to ST. 6+422.40) 16 & 17


E NB-East Side-Level-2 16.20 16.20
W SB-West Side-Level-2 16.20 16.20

Base -SEC-12 ( ST.6+370 to ST.6+390 ) 18 & 19


E NB-East Side-Level-2 10.00 10.00
W SB-West Side-Level-2 10.00 10.00

Base -SEC-12 ( ST.6+340 to ST.6+370) 20 & 21


E NB-East Side-Level-2 -
W SB-West Side-Level-2 15.00 15.00

Base -SEC-03 ( ST.6+315.20 to ST.6+340) 22


NB-East Side-Level-2 12.40 12.40
SB-West Side-Level-2

Base -SEC-02 ( ST.6+305.00 to ST.6+315.20) 23


NB-East Side-Level-2 5.10 5.10
SB-West Side-Level-2

SUB TOTAL 251.25 31.25 282.50

ZONE-4

Type - 23 S-20
For Wall - 4
For Wall - 10 19.04 19.04
For Wall - 11 19.98 19.98
For Wall - 5

Type - 23 S-21
For Wall - 10 18.99 18.99
For Wall - 11 19.91 19.91

Segment 22 - T21A S-22


For Wall - 10(0.8 from B.L) 10.62 10.62
For Wall - 11(0.8 from B.L) 11.08 11.08

MPR- AUGUST 2017 INT/CRP/FR/011 Page 72


ZONE-4
Type-21B S-23
For Wall - 10 23.97 23.97
For Wall - 11 24.05 24.05

Type-12 S-24
For Wall - 12 15.00 15.00

Type-12 S-25
For Wall - 12 15.00 15.00

Type-11 S-26
For Wall - 12 (0.3m from BL) 9.00 9.00

Type-2 S-27
For Wall - 13 (0.8m from BL) 23.99 23.99
For Wall - 12(0.8m from BL) 24.18 24.18

Type-10 S-28
For Wall - 13 (0.8m from BL) 24.02 24.02
For Wall - 12(0.8m from BL) 24.26 24.26
For Wall - 5 4.95 4.95

Type-09 S-29
For Wall - 13 (0.8m from BL) 24.05 24.05
For Wall - 5 4.95 4.95

Type-09 S-30
Wall 13 24.05 24.05
For Wall - 5 4.95 4.95

Type-09 S-31
For Wall - 13 (0.8m from BL) 12.01 12.01

Segment 33 - T8 S-33
For Wall - 13 (0.8m from BL) 10.40 10.40

Type-7 S-34
For Wall - 13 (0.8m from BL) 20.30 20.30
For Wall - 06 (0.5m from BL) 12.15 12.15

Type-6 S-35
For Wall - 12 22.72 22.72
For Wall - 06 (0.8m from BL) 22.72 22.72
For Wall - 07 (0.8m from BL) 22.72 22.72

Type-6 S-36
For Wall - 12 (0.8m from BL) 22.73 22.73
For Wall - 13 (0.5m from BL) 14.21 14.21
For Wall - 06 (0.8m from BL) 22.73 22.73
For Wall - 07 (0.8m from BL) 22.72 22.72

MPR- AUGUST 2017 INT/CRP/FR/011 Page 73


Type-6 S-37
For Wall - 13 (0.8m from BL) 22.73 22.73
For Wall - 07 (0.5m from BL) 14.21 14.21
For Wall - 06 (0.8m from BL) 22.73 22.73
-
Type-5 S-38 -
For Wall - 13 (0.8m from BL) 24.00 24.00
For Wall - 07 (0.8m from BL) 24.00 24.00

Type-5 S-39
For Wall - 13 (0.8m from BL) 24.00 24.00
For Wall - 07 (0.8m from BL) 12.00 12.00
For Wall - 06 (0.8m from BL) 12.00 12.00

Type-5 S-40
For Wall - 12 (0.5m from BL) 15.20 15.20
For Wall - 13 (0.5m from BL) -
For Wall - 6 23.53 23.53
For Wall - 07 (0.8m from BL) 23.53 23.53

Type-4 S-41
For Wall - 6 26.04 26.04
For Wall - 7 26.89 26.89

Type-3 S-42
For Wall - 6 21.17 21.17
For Wall - 7 22.17 22.17

SUB TOTAL 811.78 53.87 865.65

General Summary of Integritank Spray Membrane:


1 ZONE-1-PACKAGE-E 294.13 18.92 313.05
2 ZONE-2-PACKAGE-F 251.25 31.25 282.50
3 ZONE-3-PACKAGE-H
4 ZONE-4-PACKAGE-E 811.78 53.87 865.65

TOTAL WORK DONE QUANTITY 1,357.16 104.04 1,461.20

MPR- AUGUST 2017 INT/CRP/FR/011 Page 74


Summary of Swellable Bar for Horizontal Construction Joint in Wall

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
Swellable Bar for Horizontal Construction Joint In
20-Aug-17
Wall

Previous Current Todate


Locations STRUCTURE REFERENCE Segments
Qty(LM) Qty(LM) Qty(LM)

ZONE-1

Base-TYPE-2 S-05
For Wall - 02 (Horizontal CJ) 20.64 20.64

Base-TYPE-13 S-06
For Wall - 02 (Horizontal CJ) 34.19 34.19

Base-TYPE-13 S-07
For Wall - 01 (Horizontal CJ) 32.28 32.28

Base-TYPE-14 S-08
For Wall - 02 (Horizontal CJ) 32.49 32.49

Base-TYPE-14 S-09A 0 -
For Wall - 02 (Horizontal CJ) 35.276 35.28

Base-TYPE-15
For Wall - 08 (Horizontal CJ) S-09B 19.874 19.87

Base-TYPE-15 0 -
For Wall - 02 (Horizontal CJ) 17.88 17.88
For Wall - 08 (Horizontal CJ) S-10B 18.33 18.33

SUB TOTAL 210.96 - 210.96


ZONE-4

Base-TYPE-21B S-23
For Wall - 11 (Horizontal CJ) - (1) 29.74 29.74

Base-TYPE-12 S-24
For Wall - 10 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00

Base-TYPE-12
For Wall - 10 (Horizontal CJ) - (1) S-25 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00

Base-TYPE-11
For Wall - 10 (Horizontal CJ) - (1) S-26 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00

Base -TYPE-10 S-27A


For Wall - 13 (Horizontal CJ) 15.11 15.11
For Wall - 12 (Horizontal CJ) - (1) 6.00 6.00

Base-TYPE-10 S-28
For Wall - 13 (Horizontal CJ) 30.00 30.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 75


Base -TYPE-9
For Wall - 12 (Horizontal CJ) - (1) S-29 15.04 15.04
For Wall - 13 (Horizontal CJ) 30.00 30.00

Base -TYPE-9
For Wall - 12 (Horizontal CJ) - (1) S-30 15.04 15.04
For Wall - 13 (Horizontal CJ) 30.04 30.04

Base -TYPE-9 S-31


For Wall - 13 (Horizontal CJ) 30.00 30.00

Base -TYPE-7 S-34


For Wall - 13 (Horizontal CJ) 52.76 52.76

Base-TYPE-6 S-35
For Wall - 12 (Horizontal CJ) 28.38 28.38
For Wall - 13 (Horizontal CJ) 61.34 61.34
For Wall - 6 (Horizontal CJ) Barrier 28.45 28.45
- -
Base-TYPE-6
For Wall - 12 (Horizontal CJ) S-36 28.41 28.41
For Wall - 13 (Horizontal CJ) 56.84 56.84

Base-TYPE-6
For Wall - 12 (Horizontal CJ) 28.40 28.40
For Wall - 13 (Horizontal CJ) - (1) S-37 56.80 56.80

Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-38 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.08 30.08

Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-39 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.05 30.05

Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-40 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.63 30.63

Base-TYPE-4
For Wall - 12 (Horizontal CJ) - (1) S-41 30.00 30.00

SUB TOTAL 994.67 28.45 1,023.12

MPR- AUGUST 2017 INT/CRP/FR/011 Page 76


ZONE-2

S-04/SEC-13 S-04

Base Slab Level-1 37.80 37.80

S-05/SEC-13 S-05

Base Slab Level-1 37.80 37.80

East side Walls - Vertical(Damage Repair) 8.00 8.00

S-06/SEC-12 S-06

Base Slab Level-1 37.79 37.79

S-07/SEC-11 S-07

Base Slab Level-1 37.79 37.79

SEG-08/SEC-10 S-08

Base Slab Level-1 37.79 37.79

SEG-09/SEC-10 S-09

Base Slab Level-1 37.79 37.79

SEG-10/SEC-9 S-10

Base Slab Level-1 37.79 37.79

SEG-11/SEC-9 S-11

Base Slab Level-1 37.79 37.79

SEG-13/SEC-8 S-13

Base Slab Level-1 37.79 37.79

SEG-14/SEC-7 S-14

Base Slab Level-1 37.79 37.79

SEG-15/SEC-7 S-15

Base Slab Level-1 37.79 37.79

SEG-16/SEC-6 S-16

Base Slab Level-1 37.79 37.79

SEG-17/SEC-6 S-17

Base Slab Level-1 37.79 37.79

SEG-18/SESC-5 S-18

Base Slab Level-1 37.79 37.79

SUB TOTAL 453.49 83.59 537.07


TOTAL QUANTITY 1,659.11 112.04 1,771.15

MPR- AUGUST 2017 INT/CRP/FR/011 Page 77


Summary of Surface Preparation

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR


PARKS & LANDSCAPE

Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
Surface Preparation 20-Aug-17
Previous Month Current Month Todate
Location Structure Reference
Qty Qty Total Qty

ZONE-1 Segment 2-Type-1


Segment(2A,2B) 400.00 400.00
For Wall - 2 473.13 473.13

Segment 4-Type-1
Segment(4A,4B) 350.00 350.00
Wall 1-Upturn 484.93 484.93

Segment 5A-5B
Wall 1 370.00 370.00

Segment 6A,6B
Wall-1 West Side 536.00 536.00

Segment 7A,7B
Wall-1 West Side 920.00 920.00

Sub Total for Zone-1 3,534.06 - 3,534.06

ZONE-4
Segment 24A & 24B
West Side Wall-05(Raft 2m Height) 210.00 210.00

Segment 25A & 25B


West Side Wall-05(Raft 2m Height) 210.00 210.00

Segment 25A & 25B


West Side Wall-05(Raft 2m Height) 210.00 210.00

Segment-28,29,30A
West Side Raft Foundation at Wall-5 130.00 130.00
For Wall - 05(1.5m Height) 630.00 630.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 78


Segment-27 Type-10
For Wall - 13 157.18 157.18

Segment-29 Type-09
For Wall - 13 232.31 232.31
For Wall - 12

Segment-28 Type-10
For Wall - 13 188.70 188.70
For Wall - 12
For Wall - 5
For Wall - 4

Segment 30A - T9 -
Segment(30A,30B) 290.00 290.00
Wall 13 135.33 135.33

Segment 31 - T9
Segment 31A 142.00 142.00
Wall 13 310.66 310.66

Segment 33A-33B & 34A-34B


Wall 13 366.50 366.50
Wall 12 390.00 390.00

Segment 35B - T6
Wall-6 95.00 95.00
Wall-7 45.00 45.00

Segment 36A&B - T6
Wall-6 228.00 228.00
Wall-7 163.00 163.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 79


Segment 37A&B - T6
Wall-6 278.00 278.00
Wall-7 206.00 206.00

Segment 38A&38B - T5
Wall-6 365.00 365.00
Wall-7 268.00 268.00

Segment 39A&B - T5
Wall-6 408.00 408.00
Wall-7 172.00 150.00 322.00

Segment 40A&B - T5
Wall-6 440.00 440.00
Wall-7 381.00 381.00

Segment 41A
Wall-7 220.00 220.00

Sub Total for Zone-4 6,241.68 780.00 6,391.68

General Summary of Surface Preparation:


1 ZONE-1-PACKAGE-E 3,534.06 - 3,534.06
2 ZONE-2-PACKAGE-F
3 ZONE-3-PACKAGE-H
4 ZONE-4-PACKAGE-E 6,241.68 780.00 6,391.68

TOTAL QUANTITY 9,775.74 780.00 9,925.74

MPR- AUGUST 2017 INT/CRP/FR/011 Page 80


SUMMERY OF PATCHING OF TEARS AND PUNCTURES IN PVC T-LOCK MEMBRANE

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
SUMMERY OF PATCHING OF TEARS AND PUNCTURES IN PVC T-LOCK MEMBRANE 20-Aug-17
ITEM LOCATION AREA SIZE OF PATCHES WORK START WORK FINISHED NO'S OF PATCHES
1 ZONE-1 SEGMENT 10B (10cm X 10cm) March 29, 2017 March 29, 2017 6.00
2 ZONE-1 SEGMENT 11B (10cm X 10cm) March 29, 2017 March 29, 2017 1.00
3 ZONE-1 SEGMENT 12B (10cm X 10cm) March 29, 2017 March 29, 2017 28.00
4 ZONE-1 SEGMENT 1B EAST RAFT VERTICAL PLAN (10cm X 10cm) March 30, 2017 March 30, 2017 14.00
5 ZONE-1 SEGMENT 1B WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 19.00
6 ZONE-1 SEGMENT 2A WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 63.00
7 ZONE-1 SEGMENT 2B WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 33.00
8 ZONE-1 SEGMENT 2A & 2B EAST SIDE RAFT (10cm X 10cm) March 27, 2017 March 27, 2017 39.00
9 ZONE-1 SEGMENT 3A WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 33.00
10 ZONE-1 SEGMENT 3B WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 46.00
11 ZONE-1 SEGMENT 3A & 3B EAST RAFT (10cm X 10cm) March 27, 2017 March 27, 2017 54.00
12 ZONE-1 SEGMENT 4A WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 13.00
13 ZONE-1 SEGMENT 4B WEST RAFT VERTICAL PLAN (10cm X 10cm) April 12, 2017 April 12, 2017 16.00
14 ZONE-1 SEGMENT 4A & 4B EAST RAFT (10cm X 10cm) March 27, 2017 March 27, 2017 43.00
15 ZONE-1 SEGMENT 9A & 9B EAST RAFT (10cm X 10cm) March 29, 2017 March 29, 2017 40.00
16 ZONE-4 SEGMENT 21B WEST RAFT (10cm X 10cm) February 7, 2017 February 7, 2017 10.00
17 ZONE-4 SEGMENT 21A WEST RAFT (10cm X 10cm) July 10, 2017 July 10, 2017 7.00
18 ZONE-4 SEGMENT 21B EAST RAFT (10cm X 10cm) February 4, 2017 February 4, 2017 10.00
19 ZONE-1 SEGMENT 5B EAST RAFT (10cm X 10cm) December 3, 2016 December 3, 2016 20.00
20 ZONE-1 SEGMENT 5A EAST RAFT (10cm X 10cm) July 31, 2017 July 31, 2017 39.00
21 ZONE-4 SEGMENT 21 A&B EAST SIDE WALL (10cm X 10cm) August 3, 2017 August 3, 2017 7.00
22 ZONE-4 SEGMENT 21B WEST (10cm X 10cm) February 6, 2017 February 6, 2017 10.00
23 ZONE-4 SEGMENT 21A WEST SIDE WALL 11 (10cm X 10cm) July 9, 2017 July 9, 2017 4.00
24 ZONE-4 SEGMENT 20B WEST SIDE WALL AND RAFT (10cm X 10cm) July 28, 2017 July 28, 2017 9.00
25 ZONE-4 SEGMENT 20A WEST SIDE WALL AND RAFT (10cm X 10cm) July 28, 2017 July 28, 2017 8.00
26 ZONE-4 SEGMENT 21B EAST SIDE WALL 10 (10cm X 10cm) July 15, 2017 July 15, 2017 3.00
27 ZONE-4 SEGMENT 21A EAST SIDE WALL 10 (10cm X 10cm) July 15, 2017 July 15, 2017 3.00
28 ZONE-4 SEGMENT 30A WEST SIDE WALL 05 (10cm X 10cm) July 31, 2017 July 31, 2017 8.00
29 ZONE-4 SEGMENT 30B WEST SIDE WALL 05 (10cm X 10cm) July 31, 2017 July 31, 2017 3.00
30 ZONE-4 SEGMENT 29A WEST SIDE WALL 05 (10cm X 10cm) July 31, 2017 July 31, 2017 8.00
31 ZONE-4 SEGMENT 29B WEST SIDE WALL 05 (10cm X 10cm) July 31, 2017 July 31, 2017 3.00
32 ZONE-4 SEGMENT 29A WEST SIDE WALL 05 (10cm X 10cm) July 31, 2017 July 31, 2017 1.00

Sub TOTAL QTY'S (UPTO PREVIOUS MONTH) 534.00


CURRENT MONTH QTY 67.00
Sub Total Zone-1 601.00

1 ZONE-2 SEGMENT 8 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 27, 2017 April 27, 2017 9.00
2 ZONE-2 SEGMENT 9 WEST RAFT VERITCAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 7.00
3 ZONE-2 SEGMENT 10 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 4.00
4 ZONE-2 SEGMENT 7 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 9.00
5 ZONE-2 SEGMENT 8 EAST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 6.00
6 ZONE-2 SEGMENT 9 EAST RAFT VERTICALPLANE (10cm X 10cm) April 29, 2017 April 29, 2017 12.00
7 ZONE-2 SEGMENT 10 EAST RAFT VERTICAL PLANE (10cm X 10cm) April 29, 2017 April 29, 2017 9.00
Sub TOTAL QTY'S (UPTO PREVIOUS MONTH) 56.00
CURRENT MONTH QTY. 0.00
Sub Total Zone-2 56.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 81


1 ZONE-4 SEGMENT-18B (50cm X 100cm) April 30, 2017 April 30, 2017 4.00
2 ZONE-4 SEGMENT-18B (50cm X 100cm) April 30, 2017 April 30, 2017 2.00
3 ZONE-4 SEGMENT 23B WEST SIDE (10cm X 10cm) April 2, 2017 April 2, 2017 10.00
4 ZONE-4 SEGMENT 35A WEST SIDE (10cm X 10cm) December 17, 2016 December 17, 2016 48.00
5 ZONE-4 SEGMENT 36A EAST SIDE (10cm X 10cm) January 12, 2017 January 12, 2017 115.00
6 ZONE-4 SEGMENT 36B EAST SIDE (10cm X 10cm) January 12, 2017 January 12, 2017 66.00
7 ZONE-4 SEGMENT 37A EAST SIDE (10cm X 10cm) December 15, 2016 December 15, 2016 19.00
8 ZONE-4 SEGMENT 37B EAST SIDE (10cm X 10cm) December 15, 2016 December 15, 2016 7.00
9 ZONE-4 SEGMENT 35B WEST RAFT VERTICAL PLANE (10cm X 10cm) November 14, 2016 November 14, 2016 27.00
10 ZONE-4 SEGMENT 36A WEST SIDE (10cm X 10cm) October 25, 2016 October 25, 2016 24.00
11 ZONE-4 SEGMENT 36B WEST SIDE (10cm X 10cm) October 25, 2016 October 25, 2016 16.00
12 ZONE-4 SEGMENT 37A WEST SIDE (10cm X 10cm) October 25, 2016 October 25, 2016 17.00
13 ZONE-4 SEGMENT 37B WEST SIDE (10cm X 10cm) October 19, 2016 October 19, 2016 18.00
14 ZONE-4 SEGMENT 38A WEST SIDE (10cm X 10cm) October 19, 2016 October 19, 2016 18.00
15 ZONE-4 SEGMENT 38B WEST SIDE (10cm X 10cm) October 19, 2016 October 19, 2016 18.00
16 ZONE-4 SEGMENT 25B (10cm X 10cm) March 29, 2017 March 29, 2017 6.00
17 ZONE-4 SEGMENT 23A (10cm X 10cm) March 30, 2017 March 30, 2017 9.00
18 ZONE-4 SEGMENT 23B (10cm X 10cm) March 29, 2017 March 29, 2017 37.00
19 ZONE-4 SEGMENT 18B (10cm X 10cm) April 30, 2017 April 30, 2017 7.00
20 ZONE-4 SEGMENT 24A & 24B (10cm X 10cm) May 13, 2017 May 13, 2017 4.00
21 ZONE-4 SEGMENT 34A WEST RAMP AT UPTURN T-LOCK (10cm X 10cm) May 20, 2017 May 20, 2017 6.00
22 ZONE-4 SEGMENT 34B WEST RAMP (10cm X 10cm) May 13, 2017 May 13, 2017 8.00
23 ZONE-4 SEGMENT 35A WEST SIDE (10cm X 10cm) May 13, 2017 May 13, 2017 5.00
24 ZONE-4 SEGMENT 37A EAST RAFT (10cm X 10cm) May 17, 2017 May 17, 2017 3.00
25 ZONE-4 SEGMENT 37B EAST RAFT (10cm X 10cm) May 17, 2017 May 17, 2017 1.00
26 ZONE-4 SEGMENT 38A EAST RAMP (10cm X 10cm) May 14, 2017 May 14, 2017 3.00
27 ZONE-4 SEGMENT 38B EAST RAMP (10cm X 10cm) May 14, 2017 May 14, 2017 3.00
28 ZONE-4 SEGMENT 39B EAST RAFT (10cm X 10cm) May 15, 2017 May 15, 2017 11.00
29 ZONE-4 SEGMENT 40A EAST RAFT (10cm X 10cm) May 9, 2017 May 9, 2017 7.00
30 ZONE-4 SEGMENT 40B EAST RAFT (10cm X 10cm) May 7, 2017 May 7, 2017 6.00
31 ZONE-4 SEGMENT 41A EAST RAFT (10cm X 10cm) May 7, 2017 May 7, 2017 40.00
32 ZONE-4 SEGMENT 42A EAST RAFT (10cm X 10cm) May 2, 2017 May 2, 2017 20.00
33 ZONE-4 SEGMENT 42B EAST RAFT (10cm X 10cm) May 4, 2017 May 4, 2017 21.00

Sub TOTAL QTY'S (UPTO PREVIOUS MONTH) 606.00


CURRENT MONTH QTY. 0.00
Sub Total Zone-2 606.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 82


SUMMARY OF INTERNAL WATERSTOP & INJECTION HOSE QUANTITY

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
SUMMARY OF INTERNAL WATERSTOP & INJECTION HOSE
20-Aug-17
QUANTITY

Previous Current Todate


LOCATION STRUCTURE REFERENCE
Qty Qty Qty
ZONE-2

INTERNAL WATER STOP & INJECTION HOSES

ZONE-2

Storm Water Tank- Base-Type-A & B

East Wall(STA.6+406.217 to 6+325.417) 80.80 80.80

West Wall(STA.6+406.217 to 6+325.417) 93.33 93.33

North Wall 38.67 38.67

South Wall 38.71 38.71

Internal Wall 22.20 22.20

Outer Wall at Thrust Block 15.61 15.61

ZONE-2

Fire Fighting Tank

East wall (Base) 10.24 10.24

West Wall (Base) 10.24 10.24

North Wall (Base) 13.90 13.90

South Wall (Base) 13.90 13.90

Centre Wall (Base) 13.90 13.90

TOTAL QUANTITY 289.32 62.17 351.49

MPR- AUGUST 2017 INT/CRP/FR/011 Page 83


SUMMARY OF REMOVAL AND REPLACEMENT OF DAMAGED T-LOCK MEMBRANE QUANTITY

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
SUMMARY OF REMOVAL AND REPLACEMENT OF DAMAGED T-LOCK MEMBRANE
20-Jun-17
QUANTITY
Previous Current Todate
LOCATION STRUCTURE REFERENCE WORK DONE
Qty(M 2) Qty(M 2) Qty(M 2)

ZONE-2 ZONE-2
Base Slab-PVC T- Lock -Segment 04 08-03-17 690 690.00

TOTAL QUANTITY 690.00 - 690.00


ZONE-4 ZONE-4
Base Slab-PVC T- Lock -Segment 18D -
20-06-17
Base -TYPE-25B 84 84.00

Base Slab-PVC T- Lock -Segment 25 B -


Base -TYPE-12 639.67 639.67

Base-Road A1-2 & A1-9 359.87 359.87

Base-Road A1-3 190.29 190.29

Base-Road A1-13 - -

West Wall 5 upturn 23-03-17 7.50 7.50

East Wall 4 upturn - -

East Wall 10-Upturn 45.02 45.02

West Wall 11-Upturn 45.06 45.06

East Wall 12-Upturn 7.51 7.51

West Wall 13-Upturn 7.50 7.50

- -

PVC T- Lock -Segment 29 A - -

East Wall 13-Upturn 08-03-17 3.00 3.00

- -

PVC T- Lock -Segment 36 A - -

East Wall 12-Upturn 08-03-17 7.20 7.20

-
TOTAL QUANTITY 1,312.62 - 1,312.62

MPR- AUGUST 2017 INT/CRP/FR/011 Page 84


SUMMARY OF EXTERNAL WATERSTOP QUANTITY

Project: CP07-B:LUSAIL TOWERS INFRASTRUCTURE,LRT STATION,CAR PARKS & LANDSCAPE


Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L

SUMMARY OF EXTERNAL WATERSTOP QUANTITY 20-May-17

Previous Current Todate


LOCATION Structure Reference WORK DONE UNITS(LM)
Qty Qty Qty
ZONE-4
EXTERNAL WATERSTOP -
ZONE-4

SEGMENT-31A

For Wall - 12 LM 2.00 2.00

-
TOTAL QUANTITY 2.00 - 2.00

MPR- AUGUST 2017 INT/CRP/FR/011 Page 85


12. ANNEX 2
PROGRESS PHOTOS

MPR- AUGUST 2017 INT/CRP/FR/011 Page 86


CAPTION: T-LOCK
LOCATION: FOUNDATION AT ZONE-3 SEGMENT-19

CAPTION:T-LOCK
LOCATION:ZONE-4 SEGMENT-21B WEST RAMP

MPR- AUGUST 2017 INT/CRP/FR/011 Page 87


CAPTION:INSTALLATION OF PVC T-LOCK AT SPRAY TERMINATION
LOCATION:ZONE-1 SEGMENT-12A&2

CAPTION: INSTALLATION OF T-LOCK AT WALL SPRAY TERMINATION


LOCATION:ZONE-4 SEGMENT-20A&B

MPR- AUGUST 2017 INT/CRP/FR/011 Page 88


CAPTION:INSTALLATION OF T-LOCK AT FOUNDATION
LOCATION:ZONE-4 SEGMENT-21B EAST RAMP

MPR- AUGUST 2017 INT/CRP/FR/011 Page 89


CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-2 SEGMENT-12A&B AT DELAY STRIP WALL

CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-1 SEGMENT-17A1

MPR- AUGUST 2017 INT/CRP/FR/011 Page 90


CAPTION:REPAIR OF T-LOCK & APPLY SIKADUR AT T-LOCK TERMINATION
LOCAITON:ZONE-2 SEGMENT-22 & 23

CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-5 WEST CARPARK

MPR- AUGUST 2017 INT/CRP/FR/011 Page 91


CAPTION:INSTALLATION OF T-LOCK IN WALL TERMINATION PRIOR TO SPRAY
LOCATION: ZONE-1 SEGMENT-11A & B

CAPTION:APPLICATION OF PRIMER PRIOR TO INTEGRITANK WATERPROOFING SPRAY


LOCATION:ZONE-1 SEGMENT-11A &B

MPR- AUGUST 2017 INT/CRP/FR/011 Page 92


CAPTION:INSTALLATION OF T-LOCK AT FOUNDATION
LOCATION:ZONE-4 SEGMENT-21B WEST RAMP

CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-3 SEGMENT-19

MPR- AUGUST 2017 INT/CRP/FR/011 Page 93


CAPTION: INSTALLATION OF SUPERSWELL IN INTERNAL WALL HORIZONTAL
LOCATION: ZONE-2 SEGMENT-23

CAPTION:INSTALLATION OF INTERNAL WATERSTOP AT THE KICKER


LOCATION:ZONE-2 SEGMENT 4 DECK SLAB (STORM WATER TANK)

MPR- AUGUST 2017 INT/CRP/FR/011 Page 94

You might also like