4. Manpower Deployment
4.1 Planned VS deployed manpower
5. Procurement
5.1 Material delivered to site from 21th July 2017 to 20th August 2017
5.2 Planned procurement for the month of September 2017
Moving forward in this report the following parties will be identified as follows:
- Qatari Diar Real Estate Investment Company will be known as the
“Client”
- Parsons International Ltd will be known as the “Program Management
Consultant”
- Dorsch Qatar will be known as the “Supervision Consultant”
- QD-SBG CONSTRUCTIONS will be known as the “Main Contractor”
- Intertectra Qatar will be known as the “Sub-Contractor”
- Other Sub-Contractors engaged by “QD-SBG CONSTRUCTIONS” will be
known as “Other Sub-cons”
Any other parties pertinent to the project will be referred to by name.
I. At this time Intertectra Qatar deploys two shifts of eight hours; for the
purpose of this report and the subsequent reports to follow this month,
it should be noted that a “day” refers to a 16 hour work period, till
otherwise stipulated and or noted.
II. In an effort to maintain the quality of this report, re-evaluation(s) of the
quantities and dates for each of the current scopes of work will be on-
going; any corrections if required will be noted in the following month’s
report and adjusted accordingly.
c) Joints
i. Construction Joints:
- Roof Slabs: The External Waterstop will not function well due to
entrapped air so it would be replaced with a PVC Tape System lapped by
spray waterproofing for continuity. Internal Waterstop placed centrally (if
practical) and re-injectable hoses clipped to both outer edges of the
Internal Waterstop.
The materials used on this project and mentioned in this report, are as per the
current contract agreement with the Main Contractor.
For the month of August 2017, 1,904.30 m2 PVC T-lock has been installed.
For the month of August 2017, 3,001.70M2 Integritank Spray Membrane has been
applied.
Out of the Original Contractual BOQ of 58,237.00LM, for the month of August
2017, 561.70 lm Construction Joints has been installed in Base Slab & Wall, till the
20th of August 2017, a total of 14,720.35 lm has been installed.
Out of the Original Contractual BOQ of 7,812.00LM, for the month of August
2017, 727.22 lm Expansion Joints has been installed in Base Slab & Wall, till the
20th of August 2017, a total of 4,083.42 lm has been installed.
2.8.2 Repair for damaged waterproofing (Patching of tears and punctures in PVC
T-LOCK membrane)
Up to the month of August-2017, 2,086.62M2 PVC T-LOCK at Zone-4 & Zone-2 has
been installed.
DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL 1,904.30 2,346.13 469.31 394.48 727.22 780.00
DESIGN PACKAGE-E-DESIGN OF ROAD A1 TUNNEL 97,112.40 19,695.56 469.31 7,636.22 4,018.04 9,925.74
DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT 21,535.68 3,496.48 5,734.31 65.38
PAKAGE-E
36,032.48 6,616.28 2,962.05 1,336.21 3,534.06
ZONE-1
PAKAGE-F
21,535.68 3,496.48 5,734.31 65.38
ZONE-2
PAKAGE-H
13,454.30 1,349.82
ZONE-3
PAKAGE-E
61,079.92 13,079.29 469.31 4,674.17 2,681.83 6,391.68
ZONE-4
DESIGN PACKAGE-D-SUBSTATIONS
DESIGN PACKAGE-D-SUBSTATIONS
DESIGN PACKAGE-F-DESIGN OF ROAD A1 TUNNEL INCLUDING LRT 351.49 690.00 537.07 56.00 282.50
23/08/2017 to 29/08/2017-WK-70
30/08/2017 to 05/09/2017 -WK-71
06/09/2017to 12/09/2017 - WK-72
13/09/2017 to 19/09/2017- WK-73
Project Mgr. 1
QA/QC Superintendent. 1
Site Manager 1
Site Engineers 2
Document Controller 1
QA/QC Engineers 2
QA/QC Inspectors 1
HSE Personnel 1
Store Keeper 2
Supervisors 2
Foremen 2
Lead man 1
Applicators 25
5.1 Material delivered to site from 21st July– 20th August 2017
LUS-
CP7B- INT & QD-SBG to take necessary
2 All 1-Dec-16 Open
DCQ-NCR- action ASAP.
QL-00199
LUS-
4 All - 31-Jan-17 Open The same with NCR # 184
CP7B-
DCQ-NCR-
LUS-
Proposed Corrective Action
CP7B- 18-Feb-
5 1 9B Open submitted to QA-QD-SBG, awaits
DCQ-NCR- 17
final closure.
QL-00277
LUS-
CP7B- Awaits action from QD-SBG
6 2 18 6-Mar-17 Open
DCQ-NCR- Engineering Team
QL-00297
LUS-
CP7B-
7 2 11 2-Apr-17 Open Open
DCQ-NCR-
QL-00335
LUS-
CP7B- PCA & sketches submitted.
8 4 34B 6-Apr-17 Open
DCQ-NCR- Awaits final results.
QL-00342
LUS-
CP7B- 23-Apr- Awaits action from QD-SBG
9 2 10 & 11 Open
DCQ-NCR- 17 Engineering Team
QL-00361
LUS-
CP7B- 23-Apr- Awaits action from QD-SBG
10 1 5A Open
DCQ-NCR- 17 Engineering Team
QL-00366
LUS-
CP7B- 30-Apr- Awaits action from QD-SBG
11 2 17 & 18 Open
DCQ-NCR- 17 Engineering Team
QL-00376
LUS-
CP7B- 15-May- All sets for testing. INT awaits
12 All - Open
DCQ-NCR- 17 testing fee from accounts.
QL-00396
LUS-
Awaits SIKA membrane sample
CP7B- 10-Jun-
13 All - Open materials prior to proceed
DCQ-NCR- 17
further. Till now no available.
QL-00418
LUS-
CP7B- 21-Jun-
14 1 7A Open
DCQ-NCR- 17
QL-00427
LUS-
CP7B- QD-SBG to clean & clear the area
16 2 23,24 11-Jul-17 UWR
DCQ-NCR- prior to any repair works
QL-00453
LUS-
Dorsch agreed with PCA. QD-
CP7B-
17 2 15 11-Jul-17 UWR SBG to clear the area prior to
DCQ-NCR-
any repair works.
QL-00452
LUS-
CP7B- 26-Aug-
18 2 4&5 Open
DCQ-NCR- 17
QL-00487
LUS-
reinspection is required with
CP7B-
19 2 1, 2 & 3 6-Sep-17 Open approved checklist by
DCQ-NCR-
INR/witness form
QL-00496
LUS-
CP7B- Intertectra to propose
20 4 40B 6-Sep-17 Open
DCQ-NCR- corrective action.
QL-00499
LUS-
CP7B- Intertectra to propose
21 4 39B 6-Sep-17 Open
DCQ-NCR- corrective action.
QL-00500
LUS-
CP7B- Intertectra to propose
22 4 40A 7-Sep-17 Open
DCQ-NCR- corrective action.
QL-00501
OPEN =
20
UWR = 22
LUS-CP7B-
9-Feb- OpenQD-SBG to take
1 DCQ-CAR- 2 16 Open
17 necessary action
QL-00534
Proposed Corrective
LUS-CP7B-
18- Action submitted already
3 DCQ-CAR- 1 1B Open
Mar-17 to QD-SBG 31 May 2017 to
QL-00577
QA
LUS-CP7B-
DCQ-CAR- 5-Apr- Proposed Corrective
7 4B 35A Open
9QL- 17 Action to submit ASAP.
00604
No access.,QD-SBG to clear
LUS-CP7B-
8-May- the area, so INT can
9 DCQ-CAR- 1 6B, 7A Open
17 proceed the assessment &
QL-00623
repair if required
LUS-CP7B-
15-
12 DCQ-CAR- 1 7B Open QD_SBG to take action.
May-17
QL-00636
Proposed Corrective
LUS-CP7B-
17-Jun- Action to be prepared &
13 DCQ-CAR- 3 16 Open
17 coordinate with QA-
QL-00680
QD_SBG
LUS-CP7B- Correctiveactiontobeprovi
21-Jun-
14 DCQ-CAR- 2 17 & 18 Open dedby Intertectra prior to
17
QL-00693 repair
LUS-CP7B-
40A, 41A, 22-Jun-
15 DCQ-CAR- 4 Open QD-SBG to take action
41B & 42A 17
QL-00699
LUS-CP7B-
11-Jul- Intertectra to provide
17 DCQ-CAR- 3 Open
17 update ASAP
QL-00712
LUS-CP7B-
3-Aug-
20 DCQ-CAR- 2 20 UWR
17
QL-00730
Reoccurrence in future is
attached for your
reference and closure.
OPEN = 19
UWR = 2
Informed
qd-sbg to
Installing shutter jack without
placed
any protection on the spray
protection
membrane on wall 8
board
Repaired for
it has been found damages of
damages of
spray membrane during shutter
spray
fixing by drilling material
membrane
Inform to
QD-SBG
No proper protection for upturn
constructio
T-lock on east ramp
n team
Inform to
QD-SBG
No proper protection for
constructio
sprayed area
n team to
provide
proper
protection
repaired for
damaged spray membrane damages of
spray
membrane
NCR(s)
QD-SBG start fixing of cement board as permanent shutter for west walls
from Station 6+029 to Station 6+218 without any coordination with
Intertectra. For this reason ,we advise the following:
The Sub-Contractor will maintain the same staffing levels for this period and may
be subject to revision should the necessity to curtail the financial loss of
productivity dictate this measure.
10. Conclusion
The work done for this period was minimal to us for our resources on site.
ZONE-1 PACKAGE-E
BASE -TYPE-1
WALL-1-UPTURN 14.00 14.00
WALL-2-UPTURN 14.51 14.51
BASE -TYPE-1
WALL-1-UPTURN 14.49 14.49
WALL-2-UPTURN 14.00 14.00
BASE -TYPE-3
Base-Road A1-4 190.91 190.91
Base ( ST.6+582 to ST. 6+600.00)-SEG-04 & 05 SEC-13 SEG-04 &05 1,110.24 1,110.24
North bound Upturn 9.00 9.00
Southth bound Upturn 9.00 9.00
BASE SLAB PVC T-LOCK-SEG-10 & 11 SEC-9 SEG-10 & 11 1,294.84 1,294.84
Base ( ST.6+488.30 to ST. 6+510.00)
South Bound upturn 10.85 10.85
North Bound upturn 56.42 56.42
BASE SLAB PVC T-LOCK-SEG-14 & 15 SEC-7 SEGTION-14 &15 1,646.89 1,646.89
Base ( ST.6+422.40 to ST. 6+450.00)
North bound Upturn 71.76 71.76
Southth bound Upturn 13.80 13.80
Base Slab-PVC T- Lock -Segment 16 & 17 ( Sec-6) SECTION-16 & 17 1,965.71 1,965.71
Base ( ST.6+390 to ST. 6+422.40)
WEST WALL UPTURN 8.10 8.10
EAST WALL UPTURN 8.10 8.10
24B
40A-RE-WORK
BASE SLAB PVC T-LOCK-SEGMENT-40A(RE-WORK) -
BASE -TYPE-5 545.01 545.01
WALL-12-UPTURN 15.65 15.65
-
BASE SLAB PVC T-LOCK-SEGMENT-41A 41A 888.15 888.15
BASE -TYPE-4 - -
East Ramp 213.65
WALL-06-UPTURN 16.25 16.25
WALL-12-UPTURN 66.30 66.30
WALL-07-UPTURN 16.83 16.83
BASE -TYPE-4 - -
WALL-06-UPTURN 16.51 16.51
Base -TYPE-4 - -
-
BASE SLAB PVC T-LOCK-SEGMENT-42A 42A 854.86 854.86
BASE -TYPE-3 - -
WALL-06-UPTURN 13.18 13.18
BASE -TYPE-3 - -
Base -TYPE-15
Base-Road A1-1,A1-2,A1-4 S-10 69.85 69.85
East Wall 3 18.33 18.33
West Wall 1 8.38 8.38
East Wall 2 16.06 16.06
West Wall 8
ZONE 1
BASE -TYPE-1 S-1 54.36 54.36
FOR WALL-01(VERTICAL CJ) 13.93 13.93
FOR WALL-02(VERTICAL CJ) 14.59 14.59
FOR WALL-01(HORIZONTAL CJ) 14.57 14.57
FOR WALL-02(HORIZONTAL CJ) 14.24 14.24
Base-TYPE-16 S-12
For Wall - 03 (Vertical CJ) 85.25 85.25
For Wall - 01 (Vertical) CJ 23.55 23.55
For Wall - 08 (Vertical) CJ
For Wall - 03 (Horizontal CJ) 4.97 4.97
For Wall - 01 (Horizontal CJ) 35.90 35.90
For Wall - 08 (Horizontal CJ)
ZONE-4
ZONE-3
Base Slab (GL 29-30) 69.68 69.68
Vertical 8.00 8.00
Base Slab (GL 30-31) 81.17 81.17
Vertical 8.00 8.00
Base Slab (GL 31-32) 79.62 79.62
8.00 8.00
Base Slab (GL 32-33) 80.85 80.85
8.00 8.00
Base Slab (GL 33-34) 82.77 82.77
8.00 8.00
Base Slab (GL 34-35) 85.39 85.39
ZONE-1
Segment 5 - T2 S-5
For Wall - 3 58.33 58.33
For Wall - 2 -
For Wall - 1 303.99 303.99
T-lock for Road A1-8
Type-16 S-11
For Wall - 3
For Wall - 2
For Wall - 8 93.01 172.72 265.73
For Wall - 1
Type-16 S-12
For Wall - 3
For Wall - 2
For Wall - 8 244.75 244.75
For Wall - 1
ZONE-2
Type - 23 S-20
For Wall - 4 -
For Wall - 10 337.11 337.11
For Wall - 11 363.06 363.06
For Wall - 5 -
Type - 22 S-21
For Wall - 4
For Wall - 10 317.63 317.63
For Wall - 11 336.21 336.21
For Wall - 5
Segment-24 S-24
For Wall 12 126.69 126.69
- -
Segment-25 S-25
For Wall 12 185.10 185.10
-
Segment 26 - T11 S-26
Wall 4
Wall 12 250.51 250.51
Wall 10
Wall 11
Wall 13
Wall 5
Segment 31 - T9 S-31
Wall 12
Wall 13 79.16 79.16
Wall 5
Segment 33 - T8 S-33
Wall 12 -
Wall 13 434.06 434.06
Segment 34 - T7 S-34 -
Wall 12 318.09 318.09
Wall 13 254.85 254.85
Wall 6 99.69 99.69
Segment 35 - T6 S-35 - -
For Wall - 7 213.74 213.74
For Wall - 12 304.65 304.65
For Wall - 13 165.21 165.21
For Wall - 6 265.82 265.82
Segment 38 - T5 S-38
For Wall - 7 335.50 335.50
For Wall - 12 181.07 181.07
For Wall - 13 82.28 82.28
For Wall - 6 217.92 217.92
Segment 40 - T5 S-40 - -
For Wall - 7 445.91 445.91
For Wall - 12 100.98 100.98
For Wall - 13 - -
For Wall - 6 529.81 529.81
DAMAGED AREA'S
Previous Month Current Month Todate
LOCATION Structure Reference SEGMENT
Qty Qty Total Qty
ZONE-1
Type-1 S-1B
For Wall - 2 14.02 14.02
For Wall - 1 14.51 14.51
Type-1 S-2
For Wall - 2 28.00 28.00
For Wall - 1 29.09 29.09
Type-1 S-3
For Wall - 2 14.03 14.03
For Wall - 1 14.52 14.52
Type-1 S-4
For Wall - 2 14.05 14.05
For Wall - 1 14.43 14.43
TYPE-13 S-6
For Wall - 2 (0.8m from BL) 27.27 27.27
For Wall - 1 (0.8m from BL) 25.91 25.91
TYPE-13 S-7
For Wall - 2 (0.8m from BL) 24.10 24.10
Type-14 S-8
For Wall - 2 (0.8m from BL) 27.04 27.04
Type-16 S-11
For Wall - 8 (0.5m from BL) 17.76 17.76
Type-16 S-12
For Wall - 8 (0.5m from BL) 18.92 18.92
ZONE-2
ZONE-4
Type - 23 S-20
For Wall - 4
For Wall - 10 19.04 19.04
For Wall - 11 19.98 19.98
For Wall - 5
Type - 23 S-21
For Wall - 10 18.99 18.99
For Wall - 11 19.91 19.91
Type-12 S-24
For Wall - 12 15.00 15.00
Type-12 S-25
For Wall - 12 15.00 15.00
Type-11 S-26
For Wall - 12 (0.3m from BL) 9.00 9.00
Type-2 S-27
For Wall - 13 (0.8m from BL) 23.99 23.99
For Wall - 12(0.8m from BL) 24.18 24.18
Type-10 S-28
For Wall - 13 (0.8m from BL) 24.02 24.02
For Wall - 12(0.8m from BL) 24.26 24.26
For Wall - 5 4.95 4.95
Type-09 S-29
For Wall - 13 (0.8m from BL) 24.05 24.05
For Wall - 5 4.95 4.95
Type-09 S-30
Wall 13 24.05 24.05
For Wall - 5 4.95 4.95
Type-09 S-31
For Wall - 13 (0.8m from BL) 12.01 12.01
Segment 33 - T8 S-33
For Wall - 13 (0.8m from BL) 10.40 10.40
Type-7 S-34
For Wall - 13 (0.8m from BL) 20.30 20.30
For Wall - 06 (0.5m from BL) 12.15 12.15
Type-6 S-35
For Wall - 12 22.72 22.72
For Wall - 06 (0.8m from BL) 22.72 22.72
For Wall - 07 (0.8m from BL) 22.72 22.72
Type-6 S-36
For Wall - 12 (0.8m from BL) 22.73 22.73
For Wall - 13 (0.5m from BL) 14.21 14.21
For Wall - 06 (0.8m from BL) 22.73 22.73
For Wall - 07 (0.8m from BL) 22.72 22.72
Type-5 S-39
For Wall - 13 (0.8m from BL) 24.00 24.00
For Wall - 07 (0.8m from BL) 12.00 12.00
For Wall - 06 (0.8m from BL) 12.00 12.00
Type-5 S-40
For Wall - 12 (0.5m from BL) 15.20 15.20
For Wall - 13 (0.5m from BL) -
For Wall - 6 23.53 23.53
For Wall - 07 (0.8m from BL) 23.53 23.53
Type-4 S-41
For Wall - 6 26.04 26.04
For Wall - 7 26.89 26.89
Type-3 S-42
For Wall - 6 21.17 21.17
For Wall - 7 22.17 22.17
ZONE-1
Base-TYPE-2 S-05
For Wall - 02 (Horizontal CJ) 20.64 20.64
Base-TYPE-13 S-06
For Wall - 02 (Horizontal CJ) 34.19 34.19
Base-TYPE-13 S-07
For Wall - 01 (Horizontal CJ) 32.28 32.28
Base-TYPE-14 S-08
For Wall - 02 (Horizontal CJ) 32.49 32.49
Base-TYPE-14 S-09A 0 -
For Wall - 02 (Horizontal CJ) 35.276 35.28
Base-TYPE-15
For Wall - 08 (Horizontal CJ) S-09B 19.874 19.87
Base-TYPE-15 0 -
For Wall - 02 (Horizontal CJ) 17.88 17.88
For Wall - 08 (Horizontal CJ) S-10B 18.33 18.33
Base-TYPE-21B S-23
For Wall - 11 (Horizontal CJ) - (1) 29.74 29.74
Base-TYPE-12 S-24
For Wall - 10 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00
Base-TYPE-12
For Wall - 10 (Horizontal CJ) - (1) S-25 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00
Base-TYPE-11
For Wall - 10 (Horizontal CJ) - (1) S-26 30.00 30.00
For Wall - 11 (Horizontal CJ) - (1) 30.00 30.00
For Wall - 13 (Horizontal CJ) - (1) 30.00 30.00
Base-TYPE-10 S-28
For Wall - 13 (Horizontal CJ) 30.00 30.00
Base -TYPE-9
For Wall - 12 (Horizontal CJ) - (1) S-30 15.04 15.04
For Wall - 13 (Horizontal CJ) 30.04 30.04
Base-TYPE-6 S-35
For Wall - 12 (Horizontal CJ) 28.38 28.38
For Wall - 13 (Horizontal CJ) 61.34 61.34
For Wall - 6 (Horizontal CJ) Barrier 28.45 28.45
- -
Base-TYPE-6
For Wall - 12 (Horizontal CJ) S-36 28.41 28.41
For Wall - 13 (Horizontal CJ) 56.84 56.84
Base-TYPE-6
For Wall - 12 (Horizontal CJ) 28.40 28.40
For Wall - 13 (Horizontal CJ) - (1) S-37 56.80 56.80
Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-38 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.08 30.08
Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-39 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.05 30.05
Base-TYPE-5
For Wall - 13 (Horizontal CJ) - (1) S-40 30.00 30.00
For Wall - 12 (Horizontal CJ) - (1) 30.63 30.63
Base-TYPE-4
For Wall - 12 (Horizontal CJ) - (1) S-41 30.00 30.00
S-04/SEC-13 S-04
S-05/SEC-13 S-05
S-06/SEC-12 S-06
S-07/SEC-11 S-07
SEG-08/SEC-10 S-08
SEG-09/SEC-10 S-09
SEG-10/SEC-9 S-10
SEG-11/SEC-9 S-11
SEG-13/SEC-8 S-13
SEG-14/SEC-7 S-14
SEG-15/SEC-7 S-15
SEG-16/SEC-6 S-16
SEG-17/SEC-6 S-17
SEG-18/SESC-5 S-18
Contractor:QD-SBG CONSTRUCTIONS
Subcontractor: Intertectra Qatar W.L.L
Surface Preparation 20-Aug-17
Previous Month Current Month Todate
Location Structure Reference
Qty Qty Total Qty
Segment 4-Type-1
Segment(4A,4B) 350.00 350.00
Wall 1-Upturn 484.93 484.93
Segment 5A-5B
Wall 1 370.00 370.00
Segment 6A,6B
Wall-1 West Side 536.00 536.00
Segment 7A,7B
Wall-1 West Side 920.00 920.00
ZONE-4
Segment 24A & 24B
West Side Wall-05(Raft 2m Height) 210.00 210.00
Segment-28,29,30A
West Side Raft Foundation at Wall-5 130.00 130.00
For Wall - 05(1.5m Height) 630.00 630.00
Segment-29 Type-09
For Wall - 13 232.31 232.31
For Wall - 12
Segment-28 Type-10
For Wall - 13 188.70 188.70
For Wall - 12
For Wall - 5
For Wall - 4
Segment 30A - T9 -
Segment(30A,30B) 290.00 290.00
Wall 13 135.33 135.33
Segment 31 - T9
Segment 31A 142.00 142.00
Wall 13 310.66 310.66
Segment 35B - T6
Wall-6 95.00 95.00
Wall-7 45.00 45.00
Segment 36A&B - T6
Wall-6 228.00 228.00
Wall-7 163.00 163.00
Segment 38A&38B - T5
Wall-6 365.00 365.00
Wall-7 268.00 268.00
Segment 39A&B - T5
Wall-6 408.00 408.00
Wall-7 172.00 150.00 322.00
Segment 40A&B - T5
Wall-6 440.00 440.00
Wall-7 381.00 381.00
Segment 41A
Wall-7 220.00 220.00
1 ZONE-2 SEGMENT 8 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 27, 2017 April 27, 2017 9.00
2 ZONE-2 SEGMENT 9 WEST RAFT VERITCAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 7.00
3 ZONE-2 SEGMENT 10 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 4.00
4 ZONE-2 SEGMENT 7 WEST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 9.00
5 ZONE-2 SEGMENT 8 EAST RAFT VERTICAL PLAN (10cm X 10cm) April 29, 2017 April 29, 2017 6.00
6 ZONE-2 SEGMENT 9 EAST RAFT VERTICALPLANE (10cm X 10cm) April 29, 2017 April 29, 2017 12.00
7 ZONE-2 SEGMENT 10 EAST RAFT VERTICAL PLANE (10cm X 10cm) April 29, 2017 April 29, 2017 9.00
Sub TOTAL QTY'S (UPTO PREVIOUS MONTH) 56.00
CURRENT MONTH QTY. 0.00
Sub Total Zone-2 56.00
ZONE-2
ZONE-2
ZONE-2 ZONE-2
Base Slab-PVC T- Lock -Segment 04 08-03-17 690 690.00
Base-Road A1-13 - -
- -
- -
-
TOTAL QUANTITY 1,312.62 - 1,312.62
SEGMENT-31A
-
TOTAL QUANTITY 2.00 - 2.00
CAPTION:T-LOCK
LOCATION:ZONE-4 SEGMENT-21B WEST RAMP
CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-1 SEGMENT-17A1
CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-5 WEST CARPARK
CAPTION:INSTALLATION OF T-LOCK
LOCATION:ZONE-3 SEGMENT-19