Professional Documents
Culture Documents
Working Capital Questions
Working Capital Questions
Q.1) Kheliya Ltd is commencing a new project for manufacture of electric toys. The
following cost information has been ascertained for annual production of 60,000 units at full
capacity-
Particulars Amount per unit (Rs)
Raw materials 20
Direct labour 15
Manufacturing overheads 29
Total cost 64
Add: Profit 16
Selling price 80
. To assess the need of Working capital, the following additional information is available:-
1. Stock of raw materials- 3 months consumption
2. Credit allowed to debtors- 1.5 months
3. Credit allowed by creditors- 4 months
4. Lag in payment of wages- 1 month
5. Lag in payment of overheads- 0.5 month
6. Cash in hand and bank expected to be Rs 1,00,000.
.
Prepare a projected statement of Working capital requirement by using TOTAL APPROACH
and CASH COST APPROACH for the first year of operations.
Q.2): From the following information, prepare a statement showing working capital
requirement using Total Approach:
Element of Cost
It may be noted that production is carried on evenly during the year and wages. Expected
cash in hand Rs. 25,000. Degree of Completion for Raw Material 100% Labour 50%
Overheads 50% You may state your assumptions, if any.
Q.3) The following information has been extracted from the records of a company:
Product cost sheet (per unit):
Particulars ₹
Raw Material 45
Direct Labour 20
Overheads 40
Total 105
Profit 15
Selling Price 120
Q.4) A newly formed company has applied to the commercial bank for the first time for
financing its working capital requirements. The following information is available about the
projections for the current year:
Q.5) You are the accountant of Ganesha Ltd. The following information is made available to
you.
a) Budgeted production: 6,00,000 units
b) Details of stock holding: Raw material- 2 months, WIP- 0.5 month, Finished goods- 1
month
c) Credit granted to customers- 2 months, Credit availed from suppliers- 1 month
d) Minimum cash balance required at all times- Rs 25,000, safety margin of 10% will be
maintained
e) Cost structure of the product is as under:
From the above you are required to forecast the working capital requirements of the
company with CASH COST approach.
Q.6) From the following information, prepare a statement in columnar form showing the
working capital requirements with Cash Cost Approach and Total Approach.
Assuming that 1) Provision for Contingencies @10% (Total Approach) 2) Provision for
Contingencies is required at 10% working capital requirement, including that provision.(Cash
cost approach).
Analysis of Costs ₹
It is estimated that Raw materials are carried in stock for three weeks and finished goods for
two weeks. Factory processing will take three weeks. Suppliers will give full five weeks
credit. Customers will require eight weeks credit.
Q.7) PQR Ltd is commencing a new project for manufacture of electric toys. The following
cost information has been ascertained for annual production of 50,000 units at full capacity-
Particulars Amount per unit (Rs)
Raw materials 150
Direct labour 100
Overheads 100
Total cost 350
Add: Profit 150
Selling price 500
. To assess the need of Working capital, the following additional information is available:-
1. Stock of raw materials- 3 months consumption , Stock of WIP - 2 months consumption
2. Credit allowable for debtors- 1.5 months
3. Credit allowable by creditors- 4 months
4. Lag in payment of wages- 1 month
5.Lag in payment of Overheads -0.5 Month
5. Cash in hand and bank expected to be Rs 1,00,000.
6..Degree of completion - Raw Material 60% ,Labour 40% ,Overheads 40%
Prepare statement of working capital requirement using Total Approach.
Q.8)The following information has been extracted from the records of a company:
Product cost sheet (per unit):
Particulars ₹
Raw Material 45
Direct Labour 20
Overheads 40
Total 105
Profit 15
Selling Price 120
Q.10) The following data relating to a consumer goods manufacturing firm is available for
the year ended 31st March.
Particulars No. of days
Raw materials in storage 30
Debtors collection period 30
Conversion process period 12
Finished goods storage period 45
Average credit period from suppliers 50
Advance payment to creditors 5
Total cash operating expenses ₹ 600 lakhs
60% of the total cash operating expenses are
due to raw material
Determine the average cash working capital needed by the firm at any point of time during
the year assuming that the firm wants to carry a cash balance of Rs 10 lacs at all the time.
Q.11) You are the accountant of ABC Ltd. The following information is made available to
you.
a) Budgeted production: 54,000 units
b) Details of stock holding: Raw material- 2 months, WIP- 0.5 month, Finished goods- 1
month
c) Credit granted to customers- 2 months, Credit availed from suppliers- 1 month
d) Minimum cash balance required at all times- Rs 25,000
e) Cost structure of the product is as under:
Cost per unit Rs
Raw materials 10.00
Direct Labour 2.50
Overheads (of which depreciation is₹ 0.25 paise) 7.50
Total costs 20.00
Profit margin 5.00
Selling price 25.00
From the above you are required to forecast the working capital requirements of the
company with CASH COST approach.
Q.12): STN Ltd is a readymade garment manufacturing company. Its production cycle
indicates that materials introduced in the beginning of the production phases, Wages and
overheads accrue evenly throughout the period of cycle. The following figures for the months
ending 31st March are given:
Calculate the amount of working capital for the company on cash cost basis.
.13) The following data relating to a consumer goods manufacturing firm is available for the
year ended 31st March.
Particulars No. of days
Raw materials in storage 145
Debtors collection period 68
Conversion process period 24
Finished goods storage period 93
Average credit period from suppliers 106
Advance payment to creditors 26
Total cash operating expenses Rs 979 lacs
60% of the total cash operating expenses are
due to raw material
Determine the average cash working capital needed by the firm at any point of time during
the year assuming that the firm wants to carry a cash balance of Rs 10 lacs at all the time.
Q.14) The following information is provided by Sarvavyapi Limited for the year ended 31st
March-
Particulars ₹
Raw Material Storage Period 55 days
Work-in-Progress Conversion Period 18 days
Finished Goods Storage Period 22 days
Debt Collection Period 45 days
Creditors Payment Period 60 days
Annual Operating Cost (including ₹21,00,000
Depreciation of ₹ 2,10,000)
The fixed assets are valued at ₹3 Lakhs. Production during the previous year is 1 lakh units.
The same level of activity is intended to be maintained during the current year.
The raw materials ordinarily remain in stores for 2 months before production. Every unit of
production remains in process for 2 months. Finished goods remain in the warehouse for 4
months. Credit allowed by creditors is 3 months from the date of delivery of raw materials
and credit given to debtors is 3 months from the date of dispatch.
Selling price is ₹ 6 per unit. Both the production and sales are in a regular cycle.
Q16 ).MN Ltd. is commencing a new project for manufacture of electric toys. The following
cost information has been ascertained for annual production of 60,000 units at full capacity-
In the first year of operations, expected production and sales are 40,000 units and 35,000
units respectively. To assess the need of working capital, the following additional information
is available:
Stock of raw materials – 3 months Lag in payment of wages – 1 month
consumption
Credit allowable for debtors – 1.5 months Lag in payment of overheads – 0.5 month
Credit allowable by creditors – 4 months Cash in hand and bank expected to be
₹60,000
Provision for contingencies is required at 10% of working capital requirement, including that
provision.
Prepare a projected statement of working capital requirement for the first year of operations.
Debtors are taken at cost.
Q17) Joe Ltd is a pipe manufacturing company. Its production cycle indicates that materials
are introduced in the beginning of the production cycle, wages and overheads accrue evenly
throughout the period of the cycle. Wages are paid in the next month following the month of
accrual. Work in process includes full units of raw materials used in the beginning of the
production process and 50% of the wages and overheads are supposed to be conversion costs.
Details of production process and the components of working capital are as follows:
Production 10,00,000 units p.a.
Duration of the production cycle 1 month
Raw materials inventory held 1 month consumption
Finished goods inventory held for 2 months
Credit allowed by the creditors 1 month
Credit given to debtors 2 months
Cost price of raw materials Rs 60 per unit
Direct wages Rs 10 per unit
Overheads Rs 20 per unit
Selling price of finished pipes Rs 100 per unit
You are required to calculate the amount of working capital requirement for the company BY
USING TOTAL APPROACH
Q.18) The following information has been extracted from the records of a company: