Professional Documents
Culture Documents
METHOD STATEMENT
FOR
INSTRUMENT AND TELECOM CABLING
(LAYING, GLANDING & TERMINATION)
2 30- JUN- 2020 For Approval J.H. Choi W.C. Shin W.H. Park
1 18- APR- 2020 For Approval J.H. Choi W.C. Shin W.H. Park
0 03- MAR- 2020 For Approval J.H. Choi W.C. Shin W.H. Park
Rev Date Description Prepared by Reviewed by Approved by
1
OWNER : PROJECT : EPC CONTRACTOR :
2
OWNER : PROJECT : EPC CONTRACTOR :
Table of Contents
1 PURPOSE ............................................................................................................................................. 4
2 SCOPE .................................................................................................................................................. 4
3 REFERENCE DOCUMENTS ................................................................................................................. 4
4 DEFANITIONS /ABRVIATIONS ............................................................................................................ 5
5 PLANT EQUIPMENT............................................................................................................................. 5
6 SAFETY................................................................................................................................................. 6
7 RESPONSIBILITIES.............................................................................................................................. 6
8 TESTING & MEASURING EQUIPMENTS............................................................................................. 6
9 PROCEDURE........................................................................................................................................ 7
9.1 GENERAL REQUIREMENTS .............................................................................................................. 7
9.2 STORAGE AND H ANDLING OF CABLE DRUM ..................................................................................... 8
9.3 PRE-INSTALLATION TEST ................................................................................................................ 8
9.4 INSTRUMENT CABLE INSTALLATION................................................................................................. 9
9.5 CABLE GLANDING AND TERMINATION ............................................................................................ 10
9.6 TESTING OF CABLES AFTER GLANDING AND TERMINATION.............................................................. 14
9.7 MULTI CABLE TRANSIT (MCT) ...................................................................................................... 15
9.8 LIFTING CONCRETE SLAB COVERS ................................................................................................. 15
10 INSPECTION & TEST STATUS .......................................................................................................... 16
11 ATTACHMENTS (LIST OF VERIFYING DOCUMENTS) ..................................................................... 16
11.1 JOB HAZARDS ANALYSIS (JHA) .................................................................................................... 16
3
OWNER : PROJECT : EPC CONTRACTOR :
1 PURPOSE
The purpose of this method statement is to define the laying, glanding, termination and
testing method, acceptance criteria for the Installation of Instrument and Telecom Cables
and the responsibility of construction and Quality Control relevant to this procedure.
This procedure covers work up to and including mechanical completion.
2 SCOPE
This Method Statement is applicable for Electrical,Instrumentation and Telecom Works for
SALALAH AMMONIA Project.
3 REFERENCE DOCUMENTS
Telecom System Cable Schedule-PAGA SYSTEM 645295-0000-4CEL-0004
Telecom System Cable Schedule-Closed Circuit Television & 645295-0000-4CEL-0005
Weather Monitoring System
Telecom System Cable Schedule-LAN 645295-0000-4CEL-0006
Instrument Cable Schedule N/A pending from SLI
Telecom cable drum schedule N/A pending from SLI
Instrument cable drum schedule N/A pending from SLI
Material Purchase Order N/A pending from SLI
Cable Data Sheets. N/A pending from SLI
Equipment list for Telecommunication System 645295-0000-4CEL-0001
Instrument Index 645295-0000-48EL-0001
Jetty Area control room equipment layout 645295-0000-45D3-0001
Instrument Cable & Conduit Layout drawings jetty loading N/A pending from SLI
arm
CCTV Cable & Conduit layout jetty loading arm 645295-2010-4CD7-0010
PAGA Cable & Conduit layout jetty loading arm 645295-2010-4CD7-0020
Instrument & AIR manifold location Layout jetty Area 645295-2010-48D5-0011
Jetty Loading control room Tel/Data/CCTV/PAGA system 645295-2010-4CD2-10001
Schematic Drawing
Jetty Loading control room Ground floor and first floor plan 645295-2010-4CD5-10001
Tel/Data/CCTV/PAGA plan
PAGA Equipment layout jetty Area 645295-2010-4CD6-0009
CCTV Equipment layout jetty area 645295-2010-4CD6-0018
Externalinstrument & telecom cable routing layout (section N/A pending from SLI
& detail) ammonia plant.
Termination drawing. N/A pending from SLI
4
OWNER : PROJECT : EPC CONTRACTOR :
4 DEFANITIONS /ABRVIATIONS
ITP: Inspection and test plan
ITR: Inspection and test record
QC: Quality control
PPE: personal protective equipment
HSSE: Health, safety, security and environment
ITP: Inspection and test plan
ITR: Inspection and test record
QC: Quality control
PPE: personal protective equipment
HSSE: Health, safety, security and environment
5 PLANT EQUIPMENT
Toolbox
Spanners
Cable roller
Drilling machine
Grinding machine
Ladder
Scaffold
Manlift
Pickup
Crane
Chipping machine
5
OWNER : PROJECT : EPC CONTRACTOR :
6 SAFETY
6.1 Installation, inspection and testing shall be carried out in accordance with Project HSSE
Plan.
6.2 Site personnel shall adhere to the site safety policies at all times with emphasis on
wearing the correct PPE and equipment appropriate to the type of the operation being
performed.
6.3 All personnel including third parties shall be safety inducted prior to entry on site.
6.4 Risk assessment shall be constantly monitored for changes in conditions.
6.5 Prior to commencements of work every day, the supervisor shall check all equipment and
tools are in good condition.
6.6 All Instrument Inspection & Test described in this document shall be conducted in a safe
manner and good engineering practice.
6.7 Precautions shall be taken during tests carried out by other disciplines (ex: Pneumatic
test of piping system).
6.8 During material handling operations, safe working of cranes and slings shall be observed.
6.9 When required, necessary work permit shall be obtained from HSSE Department as per
relevant procedure.
7 RESPONSIBILITIES
7.1 The Site Instrument Engineer/Supervisor shall be responsible for ensuring that
Instrument and Telecom Cables are installed to an acceptable standard of workmanship
and in accordance with applicable drawings, data sheets and specifications as well as
making request for inspection (RFI) to Quality Department at each stage of work as per
the applicable ITP requirements
7.2 The instrument QC Inspector shall be responsible for verifying that work carried out is
complete, correct and meets the specified requirements.
7.3 The QC Engineer or his designee shall be responsible for ensuring that all inspections and
tests are witnessed based on approved ITP, results are recorded on applicable ITR and
signed off.
6
OWNER : PROJECT : EPC CONTRACTOR :
9 PROCEDURE
9.1 GeneralRequirements
9.1.1 All material received at site shall be inspected, handled and stored upon receipt
in accordance with Project Procedure for "Site Material Control”.
9.1.2 All tests shall be conducted by skilled Instrument/Telecom Technicians under
the supervision of Site Supervisors. Including OTDR Testing and report.
9.1.3 Cable testing shall be recorded as defined herein and witnessed by the
client/contractor in accordance with the Contract Procedures.
9.1.4 All installation activities shall be executed in accordance with applicable
engineering documentation (specification, schedules and drawings).
9.1.5 The Installation shall comply with all relevant National & International codes and
in particular those relating to installation in hazardous areas where applicable
9.1.6 Cable shall be run in continuous lengths between approved termination locations
such as junction boxes, panels, instrument casings etc., and intermediate
connections are not permitted.
9.1.7 The entry of cables into enclosures shall be via gland assemblies. The
subcontractor supervisor must ensure that the glands used are the correct type
and size for the cable and are to the correct safety code if applicable.
9.1.8 Cable routes passing through outside walls of buildings via transits shall be
generally sealed on completion of the installation to prevent the ingress of water
and dust into the building. Where fireproof seals or hazardous area boundaries
are involved the method of installation shall be defined in the design
documentation.
9.1.9 Where cables are temporarily laid or stored for a short duration and or cable
routes pass through floors etc., mechanical cable protection shall be provided to
prevent cable being damaged.
9.1.10 When Steel conduit is used for cabling, the installation requirements shall be
defined in the contract documentation and installation details.
9.1.11 The earthing, continuity and insulation of metal screens in cables shall adhere to
the project design documentation.
9.1.12 Field instruments shall be considered grounded by means of the cable gland via
the field cable steel wire armor. This applies in all cases where adequate earth
continuity cannot be provided by mechanical supporting connections.
9.1.13 Cable shall not be bent to radii less than the manufacturer’s recommendation as
defined in their catalogue or on the relevant data sheet.
9.1.14 The minimum spacing between instrument and power cables, as defined in
Project cable routing/layout drawings shall be strictly adhered to.
7
OWNER : PROJECT : EPC CONTRACTOR :
9.1.15 Special signal cables such as co-axial and fiber optic cable shall be installed in
accordance with manufacturer's guidelines and recommendations.
9.1.16 Any deviation/exceptions to the requirements of the project specifications and
drawings require prior approval by contractor.
9.2 Storage and Handling of Cable Drum
9.2.1 Upon receipt at storage area, cable drums are inspected for mechanical damage,
drum number and cable specification.
9.2.2 Where damage to cable drum is observed, the cable drum shall be opened, and
the cable inspected for any damages.
9.2.3 Damaged drum/Cable is recorded on the “Damage Report” and reported in
accordance with the Contract Procedures
9.3 Pre‐Installation test
9.3.1 Cables shall be tested on the cable drums prior to removal to the work site.
9.3.2 Instrument cables shall be tested as follows, using insulation Tester having valid
calibration certificate.
a) The continuity of each core shall be checked.
b) All applicable drain wires and their corresponding shield shall be checked for
continuity.
c) The insulation resistance between individual core to core, core to screen shall be
checked.
d) Usually individual conductors in a cable will have similar values of insulation
resistance, however where they differ, the value recorded on test record should be the
lowest. If they differ by a significant amount, this could be an indication of damage or
poor workmanship and should be investigated.
e) After completion of the tests, the ends of the cable shall be sealed to prevent the
ingress of moisture.
f) Minimum IR value shall be as per manufacturer’s published data. As a thumb rule,
minimum acceptable value shall be calculated as follows:
Minimum IR value = [(Cable Rating/1000)+1MW] x 10
8
OWNER : PROJECT : EPC CONTRACTOR :
9
OWNER : PROJECT : EPC CONTRACTOR :
9.4.15 Cable trays and trunking shall be installed where required in accordance with
approved project drawings. Tray/trunking work shall be adequately supported
and shall not obstruct traffic, accessibility or removal of process instruments.
9.4.16 Spare space shall be provided in cable tray/Duct Bank and trench as per project
specification for future cables.
9.4.17 QC Inspector shall inspect and ensure that trenches are clean and free from
foreign debris and shall also inspect duct banks.
9.4.18 Where cables are laid on trays or racks these shall be inspected by
Instrument/Telecom QC Inspector to ensure the routing is complete and free
from any sharp edges or obstacles.
9.4.19 Throughout the cable pulling process, the Site Supervisor shall ensure that
undue stress is not applied to the cable. Where a cable winch is used, the
manufacturer’s permissible pulling tension values shall be adhered to.
9.4.20 Where instrument signal cables are run in parallel with power carrying cables,
above or below ground, segregation shall be maintained in accordance with
project specification.
9.4.21 Where instrument and power carrying cables are run in the same trench, the run
shall be inspected to ensure separation is by positive means.
9.4.22 Cables shall be identified at both ends and at specified intervals in accordance
with the instrument installation details.
9.4.23 Prior to backfilling, each layer of the cable shall be inspected to ensure dressing,
tagging, segregation etc. as per specification and installation details.
9.4.24 For underground cables, individual cable lengths shall be tested for insulation
resistance and continuity after installation, but prior to backfilling of each layer.
Test configuration, test voltage and acceptance value shall be as per 8.3. Test
results shall be recorded on the relevant ITR(IVS‐ITR‐002).
9.4.25 Warning tape and cable protection tile shall be installed and inspected prior to
trench back filling.
9.4.26 Backfilling material shall be as per project civil specification.
9.4.27 Upon completion of backfilling and compaction of the trench, route markers shall
be installed over the trench at specified intervals, each branch and each bend.
9.4.28 Above ground cables shall also be inspected to ensure dressing, tagging,
segregation etc.as per specification and installation details,
9.4.29 For underground and above ground cables, inspection results shall be recorded
on the relevant ITR(IVS‐ITR‐002).
10
OWNER : PROJECT : EPC CONTRACTOR :
9.5.1 Prior to start cable glanding activities, ensure that cable dressing throughout the
route is complete and acceptable.
9.5.2 Prior to installation, the cable glands shall be checked to ensure they are as per
the schedule and of the correct size and type for the cable on which they are to
be fitted.
9.5.3 Particular attention shall be paid to glands intended for lead sheathed and steel-
wire armored cables to ensure the correct sealing and clamping components are
supplied with the gland.
9.5.4 Where glands are to be installed in a hazardous area, the certification of the
gland shall be verified and shall be sealed accordingly.
9.5.5 The glanding process shall be inspected randomly with 10% of all glands of each
type being checked as a minimum.
9.5.6 Secondary cabling to field instruments such as transmitters, resistance bulb and
thermocouples, CCTV, Speakers, etc. shall have excess length to allow for easy
removal of the element. This excess length of cable and also any capillary excess
length should be neatly coiled (single coil) tied and secured to the adjacent
support material.
9.5.7 Cable glands on equipment in the plant shall be mounted at the bottom to
prevent ingress of water. Where cable glands are installed in the side wall of
equipment, the cable shall enter from below. Cable coming from top shall first
drop to below the gland level. Where enclosure construction does not allow
bottom or side entry, top entry may be allowed considering IP rating of the cable
gland and the enclosure.
9.5.8 Glanding shall be done as per manufacturer’s instructions by a competent
electrician under supervision and guidance by site supervisor. Correct tools shall
be used and glands not to be over tightened.
9.5.9 All electricians involved in cable glanding activity shall undergo an in-house
training and practical test based on manufacturer’s instructions and possess a
valid identity card issued by contractor QC as an evidence of their competency.
This training session shall include a video showing cable glanding process.
9.5.10 Prior to sealing (where applicable) and tightening extended cap of the gland, the
assembly shall be checked for the following:
a) The cable tails are of the correct length and undamaged during stripping.
b) Where applicable, the lead sheath is stripped to the correct length and passes
through the body of the gland into the enclosure.
c) The steel-wire armor is stripped to the correct length such that it mates with
but does not protrude through the clamping ring.
11
OWNER : PROJECT : EPC CONTRACTOR :
d) The shield and mylar is stripped to the correct length with the sleeve installed
on drain wire.
e) Earthtag is fitted, where applicable only. Note: Earthtag is not required for
metallic junction boxes and junction boxes with internal earth continuity plate.
f) confirm spare and screens are earthed.
g) Ensure that sealing washer (IP washer) is fitted external to the equipment -
where required.
h) The outer sheath of the cable is contained within the gland.
i) The gland shroud is inserted.
9.5.11 After assembly and tightening, the gland shall be checked to ensure:
a) The body is securely fitted to the enclosure.
b) The gland is mechanically sound.
c) The clamping on the steel-wire armour is secure.
d) The outer sheath is sealed.
e) The gland shroud is properly fitted.
f) If required, earth tags are properly earthed as per requirements.
9.5.12 Cable termination shall be carried out as per termination drawings.
9.5.13 Cables termination shall be performed in an orderly manner. Cable cores shall
not be interwoven and with screw terminals the connections should be limited to
one per terminal. Common terminal shall be made by using terminal
manufacture’s bridging arrangements.
9.5.14 Termination materials shall be in accordance with project specifications.
9.5.15 All wire ends shall be identified with a marker as per termination drawing and
installation details.
9.5.16 When terminated in pressure plate terminal blocks, wire conductors shall meet
the terminal block manufacturer’s specifications for size of wire, stripping length
and torque.
9.5.17 For measurement and control input/output loops, one wire only shall be
terminated under a terminal block pressure plate. Where there are multiple
wires being connected together (such as shields, power commons or circuits
with complex connections), the terminal strip manufacturer’s jumper bars or
strips shall be used wherever possible. In any case, no more than two wires (and
always the same type and size of wire) shall be terminated under the same
pressure plate.
9.5.18 Correct type of crimping tool shall be used and all connections shall be properly
tightened.
12
OWNER : PROJECT : EPC CONTRACTOR :
9.5.19 Generally, most field instruments do not have insulated connection facilities for
the screen. The screen shall be insulated with a protective sleeve and left
unconnected at instrument end, with the same length as the signal wires. This
should create a possibility for checking interconnections between the two
different earth systems.
9.5.20 All spare wires shall be properly identified and connected to the spare terminal
blocks as indicated on termination drawing. Spare wires may be connected
together and grounded at one end.
9.5.21 Cable terminations shall be inspected to verify following:
a) Correct size of wire/terminal lugs used and ensure that lug is suitable for the
wire size. (Too small or large lug is not acceptable)
b) Correct color code/core numbering followed.
c) No physical damage or kinks on conductor inside the enclosure.
d) Conductor is not touching with the cable entry component.
e) Properly insulated at cable entry point.
f) Properly dressed inside the enclosure.
g) Verify wire twisting is maintained close (50mm) to termination point.
h) Correct core markers provided.
i) Screen/ shield are properly insulated/ terminated or cut off as applicable.
j) No loose crimping or connections.
k) Wires are terminated at correct terminals and properly tightened. (see 8.6.4)
9.5.22 Inspection Result shall be recorded on (IVS‐ITR‐003).
13
OWNER : PROJECT : EPC CONTRACTOR :
14
OWNER : PROJECT : EPC CONTRACTOR :
Hard barricade need to be installed after removal of concrete slabe with mandatory signages
15
OWNER : PROJECT : EPC CONTRACTOR :
16
Job Hazard Analysis
JOB DESCRIPTION Instrument & telecom cable laying and termination DATE PREPARED 30- Jun- 20
W RITTEN BY SIGNATURE
REVIEW ED BY SIGNATURE
APPROVED BY SIGNATURE
Confined Space Entry Hot Work Excavation Electrical Work Not Applicable
W ork Area Equipment & Tools Equipment & Tools Weather ConditionsHazardous Materials Energy Environment
Communications Aerial mobile platform Elevated Platforms Heat / Cold Compressed gas Electrical Contaminant release to water
Working alone Boom lifts / scissor lifts Man- basket Windy Flammable / combustible Mechanical Contaminant release to soil
Remote location Forklifts Scaffolding Tidal Oxidizing Pneumatic Atmospheric emission
Hoes / bobcats Toxic Erosion / sedimentation
Simultaneous operations Ladders Sea storm Hydraulic
Superposed works Excavators Hand tools Snowing / freezing Corrosive Thermal Noise / vibration / light
COVERALL, SAFETY SHOE, SAFETY HELMET, SAFETY GOGGLES,LEATHER GLOVES, GIN WHEEL, LIFTING BAG, FULL BODY HARNESS ALONG WITH LANYARD, HAND TOOLS, CHIPPING MACHINE
Face shield and ear protection required for chipping activity
Rigging and Banksman, Fork Lift Operator, Crane Operator, Working at Height
• Obtain proper work permit before start of work. Permit should be availed
from the concerned authority.
• Method statement to be explained to all employees and it must be made
available at the site during the activities.
• Job specific control measures to be communicated to all personnel
involved in the job through Tool Box Meeting.
• Ensure necessary engineering drawing are available with work permit.
Personal Injury, • Barricade Work Area & post necessary sign boards.
Hazardous/Critical Property Damages, • Personnel must be undergone “Work At Height “ training prior to access
Project Incharge
activities without Environmental elevated place.
PTW Application 2 4 M 1 1 L Site Incharge
sufficient preparation Spills, Fire, PTW • Use only green tagged scaffolding platform. Use adequate work platform.
Site HSE Officer
& safety measures. Breaches, Gas Do not use scaffold if it is red tagged.
releases • Proper "PPE" (Double lanyard full body harness).
• Ensure that material is stored securely.
• Ensure stable position is adopted while lifting material.
• Throwing of component not permitted.
• Ensure that minimum two scaffolders engaged in erection.
• Don’t climb on guardrail.
• Ensure all clamps securely tighten
• Limit number of workers on scaffold
Use of hand tools. • Conduct TBT and Educate Crew before commencing activities.
Tools breaking or • No improvised tools
coming apart in use, • All works Subjected to work permit system. Project Incharge
Personal
slipping tools (which • Sharp or pointed tools should be handled with care Site Incharge
Injury/Damaged 3 3 M 2 2 L
can occur when • Use right tool for the right job Site Supervisor
tools
pressure is applied to • The Hand Tools must be tied to the technician wrist while working at Site HSE Officer
them) height.
• Where manual lifting required more than two persons to be assigned with
Material Handling
Poor Material suitable period for rest will be taken in order to avoid fatigue.
Project Incharge
Over weight Lifting handling, • Ensure load carrying routes are free from obstruction.
Site Incharge
strain/Fatigue/Pinch muskuloskeletal 3 4 M • Utilize correct manual handling techniques to avoid over strain and 1 1 L
Site Supervisor
points injuries, Uncleaer fatigue.
Site HSE Officer
path • Keep body parts out of the line of fire
• Pre-task briefing and TBT on day to day basis
Project Incharge
• Ensure proper communication have been developed about load and its
Dropped load, Site Incharge
Material Handling Poor communications 2 3 M lifting strategy 1 2 L
personal injury Site Supervisor
• Ergonomics condition must be in safe manners while handling the material
Site HSE Officer
• Only TUV or Third party certified riggers and operators are allowed to enter
the barricaded area.
• The designated rigger should be giving hand signals to the crane operator.
• Use tag lines to control loads.
- Fall of loads
• Personnel are not allowed to ride over and stay under the load. Project Incharge
- Rigging hardware - Struck by
3 3 M • Use approved elevating platform like man lift or ladders in removing slings, 1 1 L Site Incharge
failure. - Caught in
shackles and other rigging hardware tied on the structure. Site HSE Officer
between
• Lifting plan must be prepared by certified rigger and must be at site during
installation of cablr ladder tray and perforate lifting.
tray • Use proper personal protective equipment.
• Rigging hardware is regularly properly inspected prior to use
68-SS-CC. Need to be more specific about job scope
Do not exceed SWLL, basic lift plan to be in place and load chart to be in
crane cab at all times
Project Incharge
Crane roll over, • More than 80 ton and tandem lifts are considered critical lifts and shall
Exceed SWLL 3 3 M 1 1 L Site Incharge
personal injury have a prepared lift plan authorized by SLI and OQ where applicable.
Site HSE Officer
• SLI shall be notified of all critical lifts and SLI lift supervisor to be present
during critical lifts.
• Visual inspection has to be conducted by crane operator and lifting Project Incharge
Soil/ground
Hydraulic Failure 3 4 M supervisor prior to lifting operation 1 2 L Site Incharge
contamination
• Any Hydraulic spillage should be removed and disposed properly Site HSE Officer
• Loads should be secured properly
• Equipment’s should be inspected by SNC LAVALIN Safety department
prior to start The activity. Project Incharge
falling objects,
UnSecured Loads 5 5 H •Third party inspection Certification is required Supervisor & Team 1 1 L Site Incharge
personal injury
• Check list procedures need to be followed at the site Site HSE Officer
• More than 16 ton we should submit the rigging plan and it should be
approved by SNC LAVALIN HSE team
• Lifting activity should be stopped during rain and wind speed around
7mtrs/sec
High Winds, • Before initialization of the work,lifting supervisor has to check the work Project Incharge
Adverse weather
Extreme Heat & 3 3 M location and soil condition in adverse weather condition. 1 2 L Site Incharge
condition
Cold, Raining • During inclement weather, work should be suspended and wait for the Site HSE Officer
HSE SNC LAVALIN Instruction.
Transportation of materials and • Never leave any Loose / Unsecured Materials.
facilities
Unauthorized person Incompetency, • Trained 3rd party certified riggersshould be assigned for the activity Project Incharge
Operating Accident, Poor Job 3 3 M • All the crane operators have to be trained and certified by 3rd party. 1 1 L Site Incharge
Equipment Planning • Maintain 3mtrs distance from all moving equipment’s Site HSE Officer
• No unauthorized persons are allowed to enter inside loading and
unloading area. Project Incharge
Struck by Personal Injury,
3 3 M • No unauthorized person in allowed to operate any equipment 1 1 L Site Incharge
equipment’s Asset Damage
Site HSE Officer
• Area need to be inspected and outrigger pads need to be used for the out
riggers. Project Incharge
Personal injury,
Uneven ground 3 3 M • Proper compaction should be ensured before placing the crane on a 1 L Site Incharge
crane roll over
backfilled area Site HSE Officer
• Check for any underground utilities before placing the crane
1
Project Incharge
Crane roll over, Do not exceed SWLL, basic lift plan to be in place and load chart to be in
Exceed SWLL 3 3 M 1 1 L Site Incharge
personal injury crane cab at all times
Site HSE Officer
Operating forklift/Telehandler
• Visual inspection has to be conducted by crane operator and lifting Project Incharge
Soil/ground
Hydraulic Failure 3 4 M supervisor prior to lifting operation 1 2 L Site Incharge
contamination
• Any Hydraulic spillage should be removed and disposed properly Site HSE Officer
Project Incharge
Personal Injury,
• Ensure the area is barricaded to prevent anyunauthorized personnel entry. Site Incharge
Fall of materials. Material and Tools 4 4 H 3 3 M
• Materials to be secured. Site Supervisor
Damages
Site HSE Officer
• Use only green tagged scaffolding platform. Use adequate work platform.
Do not use scaffold if it is red tagged.
• Ensure the area is barricaded to prevent anyunauthorized personnel entry. Project Incharge
Property Damage,
Collapse of • No one else is permitted to alter any scaffolding without the approval of Site Incharge
Fatality, Poor 4 4 H 2 3 L
scaffolding scaffolding inspector. Site Supervisor
Planning
• Scaffoldings must be fitted with toe boards to prevent the fall of materials Site HSE Officer
and tools. All tools andmaterials shall be properly secured in the scaff
platform.
- pinch points
-cut injury due to
sharp edges. • Provide wedge or stopped in the cable drum.
-Injury due to • Proper cable management.
-Sharp Edges.
sudden movement. • Store cables in the proper location and never store in an uneven surface.
- Manual Handling Project Director
- Slip, trip, fall due
Preparing Cables -Hot Environment. 3 3 M • Periodic Rest and job rotation. 2 3 L Site supervisor incharge
to poor cable
-Poor Cable • Follow manual handling techniques. Site HSE Officer
management.
Management • Ensure competent supervision.
-Repetitive strain
injury. • Ensure frequent break, TBT for heat stress and cool water for work men.
- Heat Strokes/
dehydration.
-Crash injury due to
trap in running NLP
points. • Provide guard for rotating parts inapplicable.
-Rotating parts. -personal injury due • Keep the body away from the rotating parts.
Project Director
- in running nip point. to the fall of the • Periodic rest.
Rotating of cable pulling winch and cable roller 3 3 M 1 1 L Site supervisor incharge
-fall of cable drum. cable drum. • Never use loose cloth.
Site HSE Officer
- Manual handling. -Repetitive strain • Secure the cable drum.
injury. • Follow manual handling techniques.
-Musculoskeletal
disorder.
-Sharp Edges.
- Non insulated hand • Competent electrician.
tools. -Injury due to sharp • Use insulated handtools.
- Unuthorized working edges. • Use good multi meters and meggers.
with cable lines. -Burn due to • Isolation In case of any repair in the line. Project Director
Testing of cables using multi meter and megge -Poor manual electric shock. 3 3 M • supervision must be available all the times. 2 2 L Site supervisor incharge
handling. -Stress and fatigue. • Maintain a good houskeeping. Site HSE Officer
-Incompetent -Waste • Use proper Manual Handling.
Electrician. accumilation. • Use mandatory and Specific PPE for the task.
-Defective Meters. • TBT for electrical hazard and safe working or near electrical system.
-Falure to use PPE.
-Sharp Edges.
- Non Insulated
handtool. ● Competent electrician.
- Unauthorized -Injury due to sharp ● Use insulated handtools.
working with HV.LV edges. ● Use good multi meters and meggers.
line. -Burn due to ● Isolation In case of any repair in the line. Project Director
Cable glanding , Termination & Cable joint: -Poor manual electric shock. ● supervision must be available all the times. 1 2 L Site supervisor incharge
handling. -Stress and fatigue. ● Maintain a good housekeeping. Site HSE Officer
-Poor houskeeping. -Waste ● Use proper Manual Handling.
● Use mandatory and Specific PPE for the task.
-Incompetent accumilation.
● Ensure designated waste area and clearing of accumulated waste on daily basis.
electrician.
-Defective meters.
-Falure to use PPE
Personal Injury, • Must do housekeeping after completion & before the start the work. Project Incharge / Site Incharge
Slip/trip/fall 3 3 M 2 2 L
Housekeeping Fire • Use proper ppe Site Supervisor / Site HSE Officer
Environment • Must do housekeeping after completion & before the start the work. Project Incharge / Site Incharge
Dust & Flying objects 3 3 M 1 2 L
pollution • Use proper ppe Site Supervisor / Site HSE Officer
I confirm that I have presented this Job Hazard Analysis to the workers under my supervision who will execute the work described in this JSA and that all control measures have correctly been
implemented:
Supervisor : Date:
I confirm that I have read and understood the Job Hazard Analysis which is provided for this work: