Professional Documents
Culture Documents
Materials and Qualification Procedures For Ships Book B November 2023
Materials and Qualification Procedures For Ships Book B November 2023
Qualification
Procedures for
Ships
Book B
Procedure for Periodic
Inspection of Approved Works
November 2023
PLEASE NOTE: No technical amendments have been made to this version of
the MQPS book, just the date has been updated.
Except as permitted under current legislation no part of this work may be photocopied, stored in a retrieval system, published, performed in
public, adapted, broadcast, transmitted, recorded or reproduced in any form or by any means, without the prior permission of the copyright
owner. Enquiries should be addressed to Lloyd's Register Group Limited, 71 Fenchurch Street, London, EC3M 4BS.
Materials and Qualification Procedures for Ships - Book B
SECTION 1 INTRODUCTION
2 Lloyd's Register
Materials and Qualification Procedures for Ships - Book B
Section
1 Introduction
2 Inspection procedure
n Section 1
Introduction
1.1 General
1.1.1 In order that consideration may be given to the continued inclusion of a company on the LR List of Approved
Manufacturers of Materials and Recognized Proving Establishments, LR Surveyors are to carry out a periodic inspection to
determine that the works still satisfies the criteria established during the initial approval. A report is to be submitted by the Surveyor
to the LR.
1.2 Scope
1.2.1 This document provides general guidelines for the procedures to be followed in order that a satisfactory periodic
inspection of a LR approved manufacturer may be carried out.
1.2.2 The type of approved manufacturers covered by this procedure are as follows:
1 Approved Manufacturers of Steel Plates, Strip, Section and Bars.
2 Approved Manufacturers of Steel Castings.
3 Approved Manufacturers of Steel Forgings.
4 Approved Manufacturers of Steel Pipes and Tubes.
5 Approved Manufactures of Iron Castings.
6(a) Approved Manufacturers of Aluminium Alloy Refining, Semi-Finished Products, Plates, Rolled Sections, Bars and
Castings.
6(b) Approved Manufacturers of Aluminium/Steel Transition Joints.
7(a) Approved Manufacturers of Copper Alloy Castings for Propellers.
7(b) Approved Manufacturers of Copper Alloy Castings for Valves, Liners and Bushes.
7(c) Approved Manufacturers of Copper and Copper Alloy Tubes
8 Recognized Proving Establishments for Anchoring and Mooring Equipment.
9(a) Approved Manufacturers of Chain Cable.
9(b) Approved Manufacturers of Fittings for Chain Cable.
10 Approved Manufacturers of Short Link Chain Cable.
11 Approved Manufacturers of Steel Wire Rope.
1.2.3 The period between inspections of works should not exceed three years.
1.2.4 Any deviation from the recommended frequency is first to be agreed with LR. Failure to carry out an inspection prior to
the expiry date of the existing approval may lead to deletion from the approved list. Once deleted, re-approval will require full
procedure tests to be carried out.
Lloyd's Register 3
Materials and Qualification Procedures for Ships - Book B
n Section 2
Inspection procedure
2.1 Preparation for the inspection visit
2.1.1 LR will advise the local Surveyors in advance that the periodic inspection is due and will detail the current record of:
Firm's name and address.
The extent of the approval.
Approved testing machines.
2.1.2 The Surveyor is to liaise with the firm to establish a mutually acceptable time for the inspection visit with an appropriate
representative (e.g. Works Manager, Quality Manager). For the visit to be successful the Surveyor must check be accorded access
to all relevant parts of the works at all times. The arrangements with the Surveyor are to include checking all relevant production
processes including subcontracted processes.
2.1.3 The Surveyor is to ensure that the firm's representative is aware of:
The extent of the approval.
The firm's entries in the latest edition of the Approved List.
2.1.4 The Surveyor and firm's representative are to agree the accuracy of the information presented prior to the inspection of
the works taking place.
2.1.5 When the scope of approval requires to be extended (e.g. new grade, increased dimensions), then the programme of
appropriate procedure tests is to be agreed.
4 Lloyd's Register
Materials and Qualification Procedures for Ships - Book B
2.3.3 Any non-compliance requiring remedial action and all outstanding comments are to be dealt with before an extension is
given.
2.3.4 A satisfactory inspection will be indicated to the firm by the local office on the advice from LR and a prestige certificate
will be issued. The certificate will show a validity date on or before which a subsequent periodic inspection is to be carried out. The
firm will be retained on the approved list until that date provided that they comply with the Rules for the Manufacture, Testing and
Certification of Materials.
Lloyd's Register 5
© Lloyd’s Register Group Limited 2023
Published by Lloyd’s Register Group Limited
Registered office (Reg. no. 08126909)
71 Fenchurch Street, London, EC3M 4BS
United Kingdom
Lloyd’s Register and variants of it are trading names of Lloyd’s Register Group Limited, its subsidiaries and affiliates. For further details please
see http://www.lr.org/entities
Lloyd's Register Group Limited, its subsidiaries and affiliates and their respective officers, employees or agents are, individually and collectively,
referred to in this clause as ‘Lloyd's Register’. Lloyd's Register assumes no responsibility and shall not be liable to any person for any loss,
damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a
contract with the relevant Lloyd's Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.