DOCUMENT REVIEW REPORT (DRR)

PROJECT PROPOSED CONDOMINIUM DEVELOPMENT FOR SOUTH BEACH DRR NO: SBW-BS-DRR-058
WELIGAMA PROPERTIES (PVT)LTD

PROJECT NO 19005

EMPLOYER SOUTH BEACH WELIGAMA PROPERTIES (PVT) LTD REVISION

PROJECT ARCHITECT BALMOND STUDIO DATE 17.07.23

TO ATTENTION

BUILDMART LANKA PVT LTD Contractors Representative

Global Project Management consultants Mr. Sanath Priyadharshana

DOCUMENT REFERENCE FROM DESCRIPTION APPROVED

APPROVAL SUBJECT TO CONDITIONS

SBW-RFMAS-020 MAIN Method Statement for Ceiling Installation. REVISE AND SUBMIT
CONTRACTOR

REJECTED

COMMENTS

A) General
1. Powder Coated Edge Bead Detail Recommended for 10mm Periphery Gap between Wall and
Bulkhead
2. Mock Up Work to Proceed in compliance with Design & Balmond Studio comments &
instructions given for RICF-633 (based on Visual inspections of the sample) this is not the final
approval for work item since submissions and rectifications are pending from the contractor.
3. The contractor is expected to Demonstrate a High level of surface finishing and seamless joint
finishing and continuity especially with regard to concealed joints between Ceiling to Ceiling ,
Ceiling to Wall etc. development of separation cracks will not be accepted.

Notes : Refer to Marked up comments in submitted MS.

From Balmond Studio Handled by


3rd Floor , 14 Sir Baron Jayatilaka Mawatha, Colombo | Tel: +94 11 2 302 500 Junior Archt. Hashini Wijesinghe
Checked by
E-mail: sbw@balmondstudio.net
S. Archt. Raveendra Handagama
Web Site: www.balmondstudio.com

Acknowledgement Receipt
Date: …………………………………………………………………
Signature: ………………………………………………

Name: ………..………………………………………………………

Page 1 of 1
PROPOSED SOUTH BEACH
CONDOMINIUM DEVELOPMENT
PROJECT AT WELIGAMA

METHOD STATEMENT
FOR CELLING INSTALLATION WORK
Method Statement for Ceiling Installation Work

TABLE OF CONTENT PAGE NO

1 Purpose .................................................................................................................... 3
2 Specification and Drawing Reference ................................................................... 3
3 Ceiling Materials…………………………………………………………………3
4 Equipment ............................................................................................................... 4
5 PPE Materials……………………………………………………………………...3
6 Manpower…………………………………...……………………………………..4
7 Methodology……………………………………………..…...……………………3

Annexures

1. Annexure 01- Check list for Ceiling Work

Buildmart Lanka (Pvt) Ltd Page 2


Method Statement for Ceiling Installation Work

1 Purpose

• The main purpose of this method statement is to outline the procedure of


suspended ceiling installation work associated with the project.

2 Specification and Drawing Reference


• CIDA specification and BOQ.
• Tender specifications
• Working Drawings – Approved Structural Drawings, Architectural & Interior
Design Drawings

3 Ceiling Materials
➢ Furring System for Gypsum Board and Calcium Silicate Concealed Ceiling
• 6 mm Anchor Bolt
• 4mm dia. Adjustable G.I. hanger rods with angle brackets and hanger clips
• Perimeter Wall Angle
• FGMV Main Carrier
• FGCV Cross Furring Channel
• MegaClip Connector
• 10x10 mm Al Powder Coated “U” Channel *Use of Powder-coated Edge bead recommended.

• Dry Wall Screw


• Joint Tape

➢ Ceiling Boards
• 12 mm thick Elephant Standard Gypsum Board
• 9 mm thick FujiBoard calcium Silicate Board

➢ Bulkhead Ceiling
• GI Channel - 25x45x25 mm
• Al Powder Coated “U” Chanel – 10x10 mm *

➢ Paint Materials
Maintain number of
• AERO FLEX AF-11 Skim Coat White Coats as per
Architectural
• Dulux Acrylic Wall Filler Specifications
• Dulux Pentalite Emulsion Paint

Buildmart Lanka (Pvt) Ltd Page 3


Method Statement for Ceiling Installation Work

4 Equipment

• Drills
• Screw Drivers
• Knives (must be in good quality)
• Levelling Tools – Laser Level
• Finishing Trowels
• Sand Papers
• Scrapers
• Roller Brushes

5 PPE Materials

➢ Following PPE (Personal Protective Equipment) should be provided in order to all


work.
• Safety Helmets
• Safety Boots
• Safety Masks
• Hand Gloves
• High visibility Jacket

6 Manpower
• Site Engineers
• Site supervisors
• Technicians
• Helpers
• Painters

Buildmart Lanka (Pvt) Ltd Page 4


Method Statement for Ceiling Installation Work

7 Methodology – Suspended Ceiling Installation

➢ Work to do Prior to the Suspended Ceiling Installation

Before start of suspended ceiling works the following works need to be completed
and assessed by the relevant officials from all concerned parties.

• Plaster works to walls up to the required height Upto RCC slab soffit

• Skim coat and wall filler application to walls up to the required height
Upto RCC slab soffit
• All M.E.P. works of first fix services should be completed and clearance should
be granted by relevant parties (Inspection shall be carried out at different work
levels and clearance shall be obtained at progressive levels as mentioned
therein)

• Protection of flooring

➢ Fixing of Suspension Grids Inspection request Was


due on 11.07.2023-
delayed
• Ceiling bottom level should be marked and checked
• Wall angles should be fixed at the correct level
• Adjustable hanger rods to be fixed to the soffit at relevant intervals with
anchors
• Main carriers to be hang with hanger rods at 1200mm intervals
• Cross furring channels to be fixed at 400mm intervals to the main carriers
with Megaclip connectors
• Levelling of the ceiling to be done and checked
• Al powder coated “U” channels to be fixed at wall edges where applicable
• Suspension system of the ceiling should not be in direct contact with M.E.P.
services

➢ Fixing of Gypsum Boards or Calcium Silicate Boards

Before starting of the board fixing of false ceiling, M.E.P. clearance will be
obtained by the relevant parties. M.E.P. services to be completed, inspected and
approved by consultants before grant the M.E.P. Clearance.

Inspection of suspension frame work of false ceiling should be carried out by the
consultant and should be rectified to comments if given by them.

• Relevant ceiling boards to be fixed (Gypsum boards or Calcium Silicate


boards) to furring channels with screws at 100mm C/C and wall angles at
perimeter of walls.
• Extra supports should be provided around access panels and other openings.

Buildmart Lanka (Pvt) Ltd Page 5


Method Statement for Ceiling Installation Work

➢ Finishing of Gypsum Boards or Calcium Silicate Boards

Before start of the finish works including filler and paint, services ceiling marking
will be made by M.E.P. sub-contractors as per the approved M.E.P. coordination
drawings for all type of fittings and fixtures and positions of the access panels as
well.

Inspection by the consultant and contractor to be done and final approval to be


obtained for cutting boards before painting start.
All Wall & Ceiling Board Joints to be reinforced with Joint Tape and to received Paint system
• All the joints and wall edge joints to be covered with joint tapes.
• Apply joint filler over the joint tapes and screw positions to fill the gaps
• Materials should be mixed as per specifications and first coat of skim coat
needs to be applied
• After the specified curing time second coat of skim coat needs to be applied
• When the surface is dry, sanding to be done to get the even surface
• Approved filler coat to be applied on the cleaned surface
• After the specified curing time two coats of emulsion paint to be applied on
ceiling boards

Tape between Soffit


and Ceiling board
intersection.
not observed in
samples and on going
work as of 18.07.2023

Skim coat sequencing


accordingly

Tape between Soffit


and Ceiling board
intersection.
not observed in
samples and on going
work as of 18.07.2023

Skim coat sequencing


accordingly

Above applicable in all similar


areas of intersection and

Buildmart Lanka (Pvt) Ltd Page 6


BUILDMART LANKA(PVT) LTD
Proposed South Beach Condominium Development Project At Weligama
Inspection Check List for Ceiling Installation Work
Location/ Grid
Floor
Inspection Date
Inspection Time
Item
Site Engineer Result of Re-Inspection
Checked Consultant Checked Description of Site Engineer
General Item Consultant Checked
Inspection Defects/ Relevent Checked
Result Signature Result Signature Result Signature Result Signature

Ceiling Work Check layout approvals


Check specifications
Check material approvals
Check method statement

Check whether the wall finishes


done upto required height

Check M.E.P. first fixing is


completed and clearance grnated
to start ceiling work
Check the correct height
Inspection & approval for the
leveling of suspension grids
Inspection & approval for marked
locations of fittings & fixures on
ceiling
Check the correct number of paint
coats applied
Check that the finish is upto the
required standard

Remarks

Site Engineer(Contractor) Consultant Approved

Name:................................................................ Name:.......................................................................
Signature:.......................................................... Signature:.................................................................
Date:.................................................................. Date:.........................................................................