QUEZON WORKS

MASONRY WORKS QTY 450.00 SQM

MATERIALS:
CHB 6" 5,850.00 pc/s 17.50 /pc 102,375.00

LABOR:
CHB laying 450.00 sqm 140.00 /sqm 63,000.00

EQUIPMENT:

SUBTOTAL 165,375.00

STRUCTURAL STEEL QTY 1.00 LOT

MATERIALS:

LABOR:
Welding Works 1.00 set 55,000.00 /set 55,000.00

EQUIPMENT:

SUBTOTAL 55,000.00

ROOFING WORKS QTY 1.00 LOT

MATERIALS:
Roofing Materials 1.00 set/s 110,000.00 /set 110,000.00

LABOR:
Installation 1.00 set/s 18,000.00 /set 18,000.00

EQUIPMENT:

SUBTOTAL 128,000.00

PAINTING WORKS QTY 1,738.00 sqm


MATERIALS:

LABOR:
Painting Labor 1,738.00 sqm 130.00 /sqm 225,940.00

EQUIPMENT:

SUBTOTAL 225,940.00

CEILING WORKS QTY 276.00 sqm

MATERIALS:

LABOR:
Ceiling Labor 276.00 sqm 120.00 /sqm 33,120.00

EQUIPMENT:

SUBTOTAL 33,120.00

PLASTERING QTY 2,162.00 sqm

MATERIALS:

LABOR:
Plastering Labor 2,162.00 sqm 120.00 /sqm 259,440.00

EQUIPMENT:

SUBTOTAL 259,440.00

TOTAL 866,875.00
OCM 86,687.50
ADMIN 450,000.00
GRANDTOTAL 1,403,562.50