Professional Documents
Culture Documents
Masaki Takaoka
Tessa van de Werve
Bolun Liu
Diogo Cotrim
Xiangnan Meng
Recommendation:
Option 3 is NPV positive under all 3 scenarios, and should be accepted.
Option 1 should only be accepted if the plant can be sold for more than the highest NPV of Option #3
Notes/Assumptions:
Assumed Risk Free Rate (Rf) = 8%
Assume favourable tax rates -> Ignore
A perpetuity is assumed for cash flows from 2004 onwards
Summary of NPVs
Option 1 Option 2 Option 3
Scenario 1 N/A $15,124,265 $199,944,823
Scenario 2 N/A $12,707,104 $195,797,691
Scenario 3 N/A -$7,850,484 $160,526,539
S2O2
Output [tpa]: 596426 656270 750118
<<< Output and Cost value
Costs: $ 78,273,866 $ 84,041,744 $ 93,086,807
Price Probability 2002 2003 2004
75 7% -$6,000,000 -$34,821,459 -$36,827,972
85 7% -$6,000,000 -$28,258,755 -$29,326,794
95 0% -$6,000,000 -$21,696,050 -$21,825,616
105 21% -$6,000,000 -$15,133,345 -$14,324,438
115 7% -$6,000,000 -$8,570,641 -$6,823,260
125 7% -$3,720,658 -$2,007,936 $677,918
135 0% $2,243,598 $4,554,768 $8,179,096
145 21% $8,207,855 $11,117,473 $15,680,274
155 29% $14,172,112 $17,680,177 $23,181,452
Cash Flows
NPV
S2O3
Output [tpa]: 596426 726478 830365
<<< Output and Cost value
Costs: $ 78,273,866 $ 78,782,874 $ 87,075,913
Price Probability 2002 2003 2004
75 7% -$8,000,000 -$24,297,019 -$24,798,526
85 7% -$8,000,000 -$17,032,238 -$16,494,875
95 0% -$8,000,000 -$9,767,458 -$8,191,223
105 21% -$8,000,000 -$2,502,677 $112,429
115 7% -$8,000,000 $4,762,104 $8,416,080
125 7% -$3,720,658 $12,026,884 $16,719,732
135 0% $2,243,598 $19,291,665 $25,023,383
145 21% $8,207,855 $26,556,446 $33,327,035
155 29% $14,172,112 $33,821,227 $41,630,687
Cash Flows
NPV
S3O2
Output [tpa]: 596426 596426 691053
<<< Output and Cost value
Costs: $ 78,273,866 $ 78,273,866 $ 87,394,086
Price Probability 2002 2003 2004
75 7% -$6,000,000 -$33,541,941 -$35,565,127
85 7% -$6,000,000 -$27,577,685 -$28,654,599
95 0% -$6,000,000 -$21,613,428 -$21,744,071
105 21% -$6,000,000 -$15,649,171 -$14,833,543
115 7% -$6,000,000 -$9,684,915 -$7,923,015
125 7% -$3,720,658 -$3,720,658 -$1,012,487
135 0% $2,243,598 $2,243,598 $5,898,041
145 21% $8,207,855 $8,207,855 $12,808,569
155 29% $14,172,112 $14,172,112 $19,719,097
Cash Flows
NPV
S3O3
Output [tpa]: 596426 660231 764981
<<< Output and Cost value
Costs: $ 78,273,866 $ 73,494,549 $ 81,856,428
Price Probability 2002 2003 2004
75 7% -$8,000,000 -$23,977,217 -$24,482,887
85 7% -$8,000,000 -$17,374,906 -$16,833,081
95 0% -$8,000,000 -$10,772,595 -$9,183,276
105 21% -$8,000,000 -$4,170,284 -$1,533,470
115 7% -$8,000,000 $2,432,027 $6,116,335
125 7% -$3,720,658 $9,034,338 $13,766,141
135 0% $2,243,598 $15,636,649 $21,415,946
145 21% $8,207,855 $22,238,960 $29,065,751
155 29% $14,172,112 $28,841,271 $36,715,557
Cash Flows
NPV
mary Tables
ption combinations
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
INANCES
LNG $11,613,329
H2 $7,584,620
FINANCES
N2 $2,158,202
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 1 - Option 2
2002 2003
15.3% 4hr cycle 100 Downtime 6.8% 3.5hr cycle 114.3
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h]
6.66 5% 144.1 133.2 6.66 5% 164.7
0.00 0% 126.5 126.5 0.00 0% 144.6
7.53 7% 126.5 107.5 7.53 7% 144.6
0.90 1% 100.0 90.0 0.90 1% 114.3
6.24 7% 89.1 89.1 6.24 7% 101.8
0.00 0% 82.9 82.9 0.00 0% 94.7
2.49 3% 82.9 82.9 2.49 3% 94.7
Final Output 80.4 Final Output
Variable Variable
Ores $31,181,636 Ores
MgO $1,549,315 MgO
LNG $12,778,587 LNG
H2 $8,345,646 H2
N2 $2,374,752 N2
Elec. $3,470,079 Elec.
Water $2,057,553 Water
Ops $1,494,175 Ops
Variable
$35,640,641 Ores $35,640,641
$1,770,869 MgO $1,770,869
$14,605,938 LNG $14,605,938
$9,539,082 H2 $9,539,082
$2,714,344 N2 $2,714,344
$3,966,304 Elec. $3,966,304
$2,351,785 Water $2,351,785
$1,707,844 Ops $1,707,844
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
LNG $11,613,329
FINANCES
H2 $7,584,620
N2 $2,158,202
FINANCES
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 1 - Option 3
2002 2003
15% 4hr cycle 100 Downtime 7% 3.5hr cycle 114.3 Downtime
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h] Out [t/h]
6.66 5% 144.1 133.2 6.66 0.29% 146.8 135.6
0.00 0% 126.5 126.5 0.00 0.29% 135.2 135.2
7.53 7% 126.5 107.5 7.53 0.29% 134.9 114.6
0.90 1% 100.0 90.0 0.90 0.29% 114.3 102.9
6.24 7% 89.1 89.1 6.24 0.29% 102.6 102.6
0.00 0% 82.9 82.9 0.00 0.29% 102.3 102.3
2.49 3% 82.9 82.9 2.49 0.29% 102.0 102.0
Final Output 80.4 Final Output 101.7
Variable Variable
Ores $31,181,636 Ores $31,759,957
MgO $1,549,315 MgO $1,656,360
LNG $12,778,587 LNG $13,015,590
H2 $8,345,646 H2 $8,896,765
N2 $2,374,752 N2 $2,931,308
Elec. $3,470,079 Elec. $3,966,304
Water $2,057,553 Water $2,351,785
Ops $1,494,175 Ops $1,707,844
Variable
Ores $31,759,957
MgO $1,656,360
LNG $13,015,590
H2 $8,896,765
N2 $2,931,308
Elec. $3,966,304
Water $2,351,785
Ops $1,707,844
Fixed $20,790,000
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
INANCES
LNG $11,613,329
H2 $7,584,620
FINANCES
N2 $2,158,202
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 2 - Option 2
2002 2003
15% 4hr cycle 100 Downtime 15% 4hr cycle 100
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h]
6.66 5% 144.1 133.2 6.66 5% 144.1
0.00 0% 126.5 126.5 0.00 0% 126.5
7.53 7% 126.5 107.5 7.53 7% 126.5
0.90 1% 100.0 90.0 0.90 1% 100.0
6.24 7% 89.1 89.1 6.24 7% 89.1
0.00 0% 82.9 82.9 0.00 0% 82.9
2.49 3% 82.9 82.9 2.49 3% 82.9
Final Output 80.4 Final Output
Variable Variable
Ores $28,338,206 Ores
MgO $1,408,035 MgO
LNG $11,613,318 LNG
H2 $7,584,613 H2
N2 $2,158,200 N2
Elec. $3,153,645 Elec.
Water $1,869,926 Water
Ops $1,357,923 Ops
Variable
$31,181,636 Ores $35,640,641
$1,549,315 MgO $1,770,869
$12,778,587 LNG $14,605,938
$8,345,646 H2 $9,539,082
$2,374,752 N2 $2,714,344
$3,470,079 Elec. $3,966,304
$2,057,553 Water $2,351,785
$1,494,175 Ops $1,707,844
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
INANCES
LNG $11,613,329
H2 $7,584,620
FINANCES
N2 $2,158,202
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 2 - Option 3
2002 2003
15% 4hr cycle 100 Downtime 15% 4hr cycle 100 Downtime
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h] Out [t/h]
6.66 5% 144.1 133.2 6.66 0.29% 128.4 118.7
0.00 0% 126.5 126.5 0.00 0.29% 118.3 118.3
7.53 7% 126.5 107.5 7.53 0.29% 118.0 100.3
0.90 1% 100.0 90.0 0.90 0.29% 100.0 90.0
6.24 7% 89.1 89.1 6.24 0.29% 89.7 89.7
0.00 0% 82.9 82.9 0.00 0.29% 89.5 89.5
2.49 3% 82.9 82.9 2.49 0.29% 89.2 89.2
Final Output 80.4 Final Output 89.0
Variable Variable
Ores $28,338,206 Ores $27,786,465
MgO $1,408,035 MgO $1,449,132
LNG $11,613,318 LNG $11,387,208
H2 $7,584,613 H2 $7,783,690
N2 $2,158,200 N2 $2,564,572
Elec. $3,153,645 Elec. $3,470,079
Water $1,869,926 Water $2,057,553
Ops $1,357,923 Ops $1,494,175
Variable
Ores $31,759,957
MgO $1,656,360
LNG $13,015,590
H2 $8,896,765
N2 $2,931,308
Elec. $3,966,304
Water $2,351,785
Ops $1,707,844
Fixed $20,790,000
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
INANCES
LNG $11,613,329
H2 $7,584,620
FINANCES
N2 $2,158,202
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 3 - Option 2
2002 2003
15% 4hr cycle 100 Downtime 15% 4hr cycle 100
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h]
6.66 5% 144.1 133.2 6.66 5% 144.1
0.00 0% 126.5 126.5 0.00 0% 126.5
7.53 7% 126.5 107.5 7.53 7% 126.5
0.90 1% 100.0 90.0 0.90 1% 100.0
6.24 7% 89.1 89.1 6.24 7% 89.1
0.00 0% 82.9 82.9 0.00 0% 82.9
2.49 3% 82.9 82.9 2.49 3% 82.9
Final Output 80.4 Final Output
Variable Variable
Ores $28,338,206 Ores
MgO $1,408,035 MgO
LNG $11,613,318 LNG
H2 $7,584,613 H2
N2 $2,158,200 N2
Elec. $3,153,645 Elec.
Water $1,869,926 Water
Ops $1,357,923 Ops
Variable
$28,338,206 Ores $32,834,262
$1,408,035 MgO $1,631,429
$11,613,318 LNG $13,455,852
$7,584,613 H2 $8,787,965
$2,158,200 N2 $2,500,614
$3,153,645 Elec. $3,653,993
$1,869,926 Water $2,166,603
$1,357,923 Ops $1,573,367
2001
4hr cycle 100 Downtime
Inflow Mass Loss Yield Loss In [t/h] Out [t/h]
Preheater 7.6% 5% 144.1 133.2
Hoppers 0% 0% 126.5 126.5
PRODUCTION
Variable
Ores $28,338,234
MgO $1,408,036
INANCES
LNG $11,613,329
H2 $7,584,620
FINANCES
N2 $2,158,202
Elec. $3,153,648
Water $1,869,928
Ops $1,357,924
Fixed $20,790,000
Scenario 3 - Option 3
2002 2003
15% 4hr cycle 100 Downtime 15% 4hr cycle 100 Downtime
Yield L [t/h] Yield Loss In [t/h] Out [t/h] Yield L [t/h] Yield Loss In [t/h] Out [t/h]
6.66 5% 144.1 133.2 6.66 0.29% 128.4 118.7
0.00 0% 126.5 126.5 0.00 0.29% 118.3 118.3
7.53 7% 126.5 107.5 7.53 0.29% 118.0 100.3
0.90 1% 100.0 90.0 0.90 0.29% 100.0 90.0
6.24 7% 89.1 89.1 6.24 0.29% 89.7 89.7
0.00 0% 82.9 82.9 0.00 0.29% 89.5 89.5
2.49 3% 82.9 82.9 2.49 0.29% 89.2 89.2
Final Output 80.4 Final Output 89.0
Variable Variable
Ores $28,338,206 Ores $25,252,639
MgO $1,408,035 MgO $1,316,987
LNG $11,613,318 LNG $10,348,817
H2 $7,584,613 H2 $7,073,901
N2 $2,158,200 N2 $2,330,710
Elec. $3,153,645 Elec. $3,153,645
Water $1,869,926 Water $1,869,926
Ops $1,357,923 Ops $1,357,923
Variable
Ores $29,259,115
MgO $1,525,935
LNG $11,990,716
H2 $8,196,216
N2 $2,700,491
Elec. $3,653,989
Water $2,166,601
Ops $1,573,365
Fixed $20,790,000