UDC 624(083.75) SARS 1200 C-1980


(As amended 1982)

SOUTH AFRICAN BUREAU OF STANDARDS

STANDARDIZED SPECIFICATION

for

C I V I L ENGINEERING CONSTRUCTION

C : SITE CLEARANCE

Approved by the O b t a i n a b l e from t h e


COUNCIL OF THE SA BUREAU OF STANDARDS
SOUTH AFRICAN P r i v a t e Bag X191
BUREAU OF STANDARDS Pretoria
on 27 F e b r u a r y 1980 0001 Republic of South A f r i c a
R e p r i n t 1982

Telegrams : Comparator, P r e t o r i a
P u b l i s h e d and p r i n t e d i n the R e p u b l i c of South Africa by t h e
S o u t h A f r i c a n Bureau of S t a n d a r d s

ISBN 0-626-06215-2 Gr 5
© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.

3 SABS 1200 C-1980

CONTENTS

Page Number

1 . ...................................... 5
SCOPE
2 . ............................ 5
INTERPRETATIONS
2.1 .................. 5
Supporting S p e c i f i c a t i o n s
2.2 ................................ 5
Application
2.3 ................................ 5
Definitions
3. ..................................
MATERIALS 5
3.1 .......................
D i s p o s a l of Material 5
4. ......................................
PLANT 5
5. ...............................
5.1
CONSTRUCTION
............ 55
Areas t o b e C l e a r e d and Grubbed
5.2 ........................... 5
C u t t i n g of Trees
5.2.1 P r o t e c t i o n of P e r s o n s . Animals. and
................................
Structures
............ 55
Branches overhanging B o u n d a r i e s
5.2.2
5.2.3 ...................... 65
P r e s e r v a t i o n of Trees
...................................
Clearing
5.3
5.4 ...................................
Grubbing
................... 66
R e c l e a r i n g of V e g e t a t i o n
5.5
5.6 .................... 6
C o n s e r v a t i o n of T o p s o i l
5.7 Landscape P r e s e r v a t i o n and C o n s e r v a t i o n of
.....................................
Flora 6
5.8 ................... 6
D e m o l i t i o n of S t r u c t u r e s
6. ................................. 6
TOLERANCES
7. ....................................
TESTING 6
8. .................... 6
MEASUREMENT AND PAYMENT
8.1 ........................... 6
Basic P r i n c i p l e s
8.2 ............................ 6
Scheduled I t e m s

APPENDIX A . APPLICABLE STANDARDS ....................... 8

R e p r i n t i n c o r p o r a t i n g Amendment No .1 : 19 May 1982

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.
5 SARS 1200 C-1950
S i t e clearance
Amendment No. 1 : 19 >lay 1982

SOUTH AFRICAN BUKEMJ OF STANDAKDS

STANDARDIZED SPECXFICAI'ION
for
C I V I L E N G I N E E R I N G CONSTKUCTLON

C : S I T E CLEARANCE

1. SCOPE
3
1.1 This s p e c i f i c a t i o n covers t h e removal of v e g e t a t i o n , boulders of s i z e up t o 0,15 m , and s u r f a c e
o b s t r u c t i o n s , and t h e demolition and removal of s t r u c t u r e s (including t h e i r basements, i f any) not
d i r e c t l y a s s o c i a t e d w i t h o r i n c i d e n t a l t o a n y excavation.
NOTE: The s t a n d a r d s r e f e r r e d t o i n t h e s p e c i f i c a t i o n a r e l i s t e d i n Appendix A.

2. INTERPRETATIONS
2.1 SUPPORTING SPECIFICATIONS. Where t h i s s p e c i f i c a t i o n i s required f o r a p r o j e c t , t h e following speciEi-
c a t i o n s s h a l l , i n t e r a l i a , form p a r t of t h e c o n t r a c t document:
a ) P r o j e c t s p e c i Eica t ion;
b ) SABS 1200 A o r SABS 1200 AA, a s a p p l i c a b l e ;
c ) SARS 1200 D o r SARS 1200 DA, a s a p p l i c a b l e .

T h i s s p e c i f i c a t i o n c o n t a i n s c l a u s e s t h a t are gerierally a p p l i c a b l e t o s i t e c l e a r a n c e .
2.2 APPLICATION.
l n t e r p r e t a t i o n s and v a r i a t i o n s o f t h i s s p e c i f i c a t i o n a r e s e t o l l t i n P o r t i o n 2 of t h e p r o j e c t
s p e c i f i c a t i o n which precedes t h i s s p e c i f i c a t i o n i n a c o n t r a c t iiment.
I
2.3 DEFINITIONS. For t h e purposes of t h i s s p e c i f i c a t i o n t h e d e f i n i t i o n s and a b b r e v i a t i o n s given i n the
a p p l i c a b l e of t h e s p e c i f i c a t i o n s l i s t e d i n 2 . l ( b ) and ( c ) and t h e following d e f i n i t i o n s s h a l l apply:
Cleared s u r f a c e . The n a t u r a l s u r f a c e of t h e ground a f t e r c l e a r i n g of s u r f a c e v e g e t a t i o n has been
completed.
Designated s i t e / a r e a . A s i t e o r an a r e a t h e p o s i t i o n of which i n r e l a t i o n t o t h e work t o be c a r r k d
out i s shown o n t h e drawing o r i s described i n t h e p r o j e c t s p e c i f i c a t i o n and i s t h e r e f o r e known t o t h e
C o n t r a c t o r a t the time of tendering.
Finished l e v e l . The l e v e l of t h e f i n i s h e d earthworks a s shown on t h e drawings o r s t a t e d i n t h e p r o j e c t
specification.
Grubbing. The o p e r a t i o n of digging out t h e r o o t s of v e g e t a t i o n .
O r i g i n a l ground l e v e l . The l e v e l of the s u r f a c e of an a r e a b e f o r e t h e commencement of c l e a r i n g .

3. MATERIALS
3.1 DISPOSAL. OF MATERIAL. M a t e r i a l obtained from c l e a r i n g and grubbing and from t h e demolition of
s t r u c t u r e s s h a l l be disposed of i n borrow p i t s o r o t h e r s u i t a b l e p l a c e s i n d i c a t e d by t h e Engineer and
s h a l l be covered with s o i l o r g r a v e l . Where no such place f o r t h e d i s p o s a l of m a t e r i a l i s i n d i c a t e d by
t h e Engineer, t h e C o n t r a c t o r s h a l l make h i s own arrangements f o r the p r o v i s i o n of a s u i t a b l e place.
The d i s p o s a l , o r burning i f s p e c i f i c a l l y p e r m i t t e d , of combustible m a t e r i a l on s i t e may be done only I
with t h e p r i o r w r i t t e n approval of the Engineer. Care s h a l l be taken t o observe t h e p r o v i s i o n s of t h e
Atmospheric P o l l u t i o n Prevention Act, 1965 (Act 4 5 of 1965), and any r e g u l a t i o n s published i n terms of
t h e Act.
A l l t r e e trunks and branches of g i r t h exceeding 0.5 m s h a l l he s t r i p p e d of secondary branches, sawn
i n t o t r a n s p o r t a b l e l e n g t h s and stacked a t designated s i t e s . Such timber s h a l l n o t be used by t h e
C o n t r a c t o r f o r a n y purpose, and s h a l l remain t h e property of the Employer.
Fencing wire s h a l l be n e a t l y wound i n t o r o l l s o r c o i l s and a l l such wire, t o g e t h e r with a l l f e n c e p o s t s
I
and o t h e r re-usable m a t e r l a l from s t r u c t u r e s , e t c . , s h a l l be stacked a t designated s i t e s .

4. PLANT
4.1 The C o n t r a c t o r s h a l l provide saws f o r c u t t i n g t r e e s and branches a s ordered, and p l a n t t h a t is s u i t a b l e
f o r grubbing r o o t s and f o r digging out and removing o t h e r o b s t r u c t i o n s on t h e S i t e .

5. CONSTRUCT I O N
5.1, AKFAS TO BE CLEARED AND GRUBBED. Both borrow a r e a s and t h e p o r t i o n s of t h e S i t e on which excavations
a r e t o be c a r r i e d out and embankments and s t r u c t u r e s c o n s t r u c t e d , s h a l l be c l e a r e d o r grubbed, o r both,
but t h e C o n t r a c t o r s h a l l not commence c l e a r i n g o r grubbing u n t i l t h e Engineer has d e s i g n a t e d , i n
w r i t i n g and i n d e t a i l , t h e exact a r e a s t o be c l e a r e d o r grtibbed and t h e t i m e a t which t h e work i s t o be
s t a r t e d . The Contractor s h a l l ensure t h a t t h e genera1 shape, p r o f i l e , and l e v e l s of t h e a r e a are not
m a t e r i a l l y a l t e r e d d u r i n g c l e a r i n g and grubbing o p e r a t i o n s . (See t h e requj rements f o r computation of
q u a n t i t i e s given i n Subclause 8.2 of SABS 1200 D o r SABS 1200 DA, as r e l e v a n t . )
I n o r d e r t o avoid r e c l e a r i n g o r t o c o n t r o l d u s t o r e r o s i o n t h e C o n t r a c t o r may have t o c l e a r and grub a t
t h e l a t e s t p r a c t i c a b l e s t a g e of c o n s t r u c t i o n .

5.2 CUTTING OF TREES


5.2.1 P r o t e c t i o n of Persons, Animals, and S t r u c t u r e s . The C o n t r a c t o r s h a l l t a k e t h e necessary p r e c a u t i o n s t o
prevent i n j u r y t o persons and animals and damage t o s t r u c t u r e s and o t h e r p r i v a t e and p u b l i c property.
Where necessary, trees s h a l l be cut i n s e c t i o n s from t h e top downwards.
5.2.2 Branches overhanging Boundaries. The branches of trees to be l e f t s t a n d i n g s h a l l be so trimmed a s not
t o encroach upon t h e space (of h e i g h t a t l e a s t 7 rn) v e r t i c a l l y above any carriageway, railway formation,
o r o t h e r designated- area.
5.2.3 P r e s e r v a t i o n of Trees
5.2.3.1 General. No t r e e s h a l l be cut down u n t i l t h e Engineer h a s given w r i t t e n a u t h o r i z a t i o n f o r such work t o
commence.
5.2.3.2 I n d i v i d u a l trees. I n d i v i d u a l trees i n d i c a t e d and marked by t h e Engineer a s trees t o be preserved s h a l l
be l e f t standing and uninjured. The amount s t a t e d i n t h e p r o j e c t s p e c i f i c a t i o n s h a l l be deducted from
monies due t o t h e C o n t r a c t o r as a p e n a l t y i n r e s p e c t of every such t r e e t h a t i s damaged o r removed
unnecessarily.

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.
SABS 1200 C-1950 6
S i t e c l earnnce
Amendment No. I : 19 May 1982

5.2.7.7 Indigcanous f o r e s t . B e f o r e commencing t h e c l e a r i n g of . i n iiidigen )US f o r e s t o r a p a r t 01 siich f o r r s t t h e


C o n t r d c t o r s h a l l o b t a i n from t h e E n g i n e e r
a ) n copy of t h e w r i t t e n conE i r m a t i o n of t h e D i r e c t o r Cenc:ral o f tlie Department iJf Environment , i f f a i r s
t h a t work may p r o c e e d ; o r
h ) t h e i n s t r u c t i o n s on which t h e C o n t r a c t o r i s reqriirc!d t o a c t .

5.3 CLEARING. (;leari.iig s h a l l c o n s i s t o f :


a ) The removal. o f a 1 1 trees nnd h u s h e s ( c o m p l k t e v i t h r o o t s ) , o t ! i f r v e g e t a t i o n , r u b b i s h , f e n c r s , and
a l l o t h e r material t h a t may i n t e r f e r e w i t h t h e c o n s t r u c t i o n of o t h e r wurks;
h ) t h e d i s p o s a l of a l l material r e s u l t i n g f r u m t h e c l e a r i . n g ;
c ) t h e removal and d i s p o s a l o f s t r u c t u r e s t h a t e n c r u a c h upon o r nay o t h e r w i s e o b s t r u c t o t h e r work on
t h e S i t e and t h a t c a n he c l e a r e d by meaus of a b u l l d o z e r of mass a p p r o x i m a t e l y 20 1: a n d f l y w h e e l power
a p p r o x i m a t e l y 130 kW ( s t r u c t u r e s t h a t c a n n o t h e so c l e a r e d s h a l l . he b r o k e n down -in a c c o r d a n c e w i t h t h e
r e q u i r e m e n t s of 5.8 o r t h e r e q u i r e m e n t s f o r t h e removal and dispr)siil of structures g i v e n i.n t h e pro:ject
s pe c i E i c a t i o n ) ;
d ) t h e removal of a l l r o c k s and b o u l d e r s of s i z e up t o 0 , 1 5 m3 t h a t are l y i n g on t h e s u r f a c e t o he
c l e a r e d o r exposed d u r i n g t h e c l e a r i n g o p e r a t i o n s ;
e ) where f e n c e s h a v e t o he t a k e n down, t h e s o r t i n g , c o i l i n g , and s t a c k i n g of t h e m a t r r i . a l . ; and
f ) t l i e removal a n d s t a c k i n g of o t h e r r e - u s a b l e materials as s c h e d u l e d .
The moving of a c e r t a i n amount of s o i l o r g r a v e l may h e i n h e r e n t i n o r u n a v o i d a b l e d u r i n g t h e p r o c e s s
of c l e a r i n g . No e x t r a payment w i l l h e made f o r t h e removal of s u c h s o i l o r g r a v e l .

5.4 G R U B B I N G . A l l s t u m p s and r o o t s l a r g e r t h a n 7 5 mm i n d i a m e t e r s h a l l h e removed t o a d e p t h of a t l e a s t


600 mm h e l o w t h e f i n i s h e d l e v e l and a t l e a s t 100 mm b e l o w o r i g i - n a l ground l e v e l . Where a road b e d o r
o t h e r area h a s t o h e compacted, a l l s t u m p s and r o o t s i n c l u d i n g m a t t e d r o o t s s h a l l h e removed t o a d e p t h
o f a t ] . e a s t 200 mm h e l o w t h e c l e a r e d s u r f a c e .
Except i n b o r r o w areas, c a v i t i e s r e s u l t i n g from g r u b b i n g s h a l l h e h a c k f i l l e d w i t h a p p r o v e d material and
c.ompacted t o a d e n s i t y a t l e a s t e q u a l t o t h a t of t h e s u r r o u n d i n g ground.

5.5 RECLEARING OF VEGETATION. I f d u r i n g t h e c o n t r a c t p e r i o d v e g e t a t i o n s h o u l d a g a i n grow on any p o r t i o n of


t h e S i t e , horrow a r e a s , o r o t h e r a r e a s t h a t have been c l e a r e d i n accordance with t h e s p e c i f i c a t i o n , t h e
E n g i n e e r may, i f he c o n s i d e r s i t n e c e s s a r y , o r d e r t h a t s u c h a r e a ( s ) h e r e c l e s r e d .
Such r e c 1 , e a r i n g s h a l l i n c l u d e t h e removal and d i s p o s a l of g r a s s , s h r u b s , a n d o t h e r v e g e t a t i o n , a s i n
the f i r s t clearing operation.

5.6 CONSERVKTION OF TOPSOIL. Where c o n s e r v a t ion of t o p s o i l i s r e q u i r e d , t h e r e l e v a n t terms of S u b c l a u s e


5.2.1.7 of SARS 1200 D o r 5.2.2 o f SAHS 1200 DA, a s a p p l i c a b l e , s h a l l a p p l y .

5.7 IANDSCAPE PRI?SEHVA'rION AND CONSERVATION OF FLORA. h%en s o r e q u i r e d in terms of t h e p r o j e c t s p e c i f i -


c a t i o n , c e r t a . i n d e s i g n a t e d f l o r a e n c o u n t e r e d i n a r e a s t o b e c l e a r e d , i n c l r t d i u g h o r r o w areas, s h a l l h e
p r e s e r v e d by t h e C o n t r a c t o r . He s h a l l c a r e f u l l y removc and p l a n t t h e f l o r a i n a p r o t e c t e d arid f e n c e d -
o f f a r e a , and o n c o m p l e t i o n of t h e Works h e s h a l l r e p l a n t t h e f l o r a on t h e S i t e o r i n t h e h o r r o w a r e a s
( a s r e l e v a n t ) i n accordance w i t h t h e Engineer's i n s t r u c t i o n s .

5.R DKMOLITION OF STKL!!CTURES. B e f o r e moving p l a n t o n t o t h e S i t e arid commencing o p e r a t i o n s t h e C o n t r a c t o r


s h a l l e s t a b l i s h t o t h e E n g i n e e r ' s s a t i s f a c t i o n t h a t t h e method cE demo:titiorl p r o p o s e d by t h e C o n t r a c t o r
i s s u c h t h a t h e c a n keep any n u i s ~ ~ n ca r i s i n g from d u s t , n o i s e , and v i . b r a t i o n t o a n a c c e p t a b l e l e v e l
and e n s u r e t h e s a f e t y of s t r u c t u r t ' s a d j a c e n t t o t h o s e t o h e d e m c l i s h e d .

6. TOLERANCES
6.1 Not a p p l i c a h l e t o t h i s s p e c i f i c a t i o n .

7. TESTING
7.1 Not a p p l i c a b l e t o t h i s s p e c i E i c a t i o n .

8. PEASUKEMENT AND PAYPE7lT


8.1 BASIC PRINCIPLES. The i t e m s s c h e d u l e d f o r c l e a r a n c e :and d e m o 1 . i : i o n w i l l be c l a s s i f i e d a c c o r d i n g t o t h e
n a t u r e of t h e materials i n v o l v e d and t h e methods of t h e i r d i s p o s a l .
Only t h o s e areas d e s i g n a t e d to h e c l e a r e d i n terms of 5.1 w i l l he measured f o r payment. The area of
s u r f a c e d roads', paved areas, r a i l w a y f o r m a t i o n s , a n d m a j o r s t r u ~ t u r e sf a l l i n g w i t h i n s u c h d e s i g n a t e d
a r e a s will n o r m a l l y h e d e d u c t e d from s u c h measurements.
Where c o n s e r v a t i o n of t o p s o i l w i t h o u t p r i o r c l e a r i n g i s o r d e r e d . t h e removal of t o p s o i l f r o m t h e
s p e c i f i e d area w i l l h e measured as e x c a v a t i o n and n o payment w i l . 1 be made f o r c l e a r i n g and g r u h h i n g .

0.2 SCHEDULED ITEMS


8.2.1 Clear and gruh................................................., ,............... I J n i t : h a o r m o r km
The area d e s i g n a t e d by t h e E n g i n e e r and c l e a r e d and grubbed w i l ' l b e measured t o t h e nearest 0.1 h a o r ,
i n t h e case of p i p e l i n e s , etc., where t h e w i d t h i s s p e c i f i e d , t o t h e n e a r e s t metre o r k i l o m e t r e .
The r a t e s h a l l c o v e r t h e c o s t of c l e a r i n g t h e s u r f a c e , removing b o u l d e r s of s i z e up t o 0,15 m3,
g r u b b i n g of trees and t r e e s t u m p s ( e x c e p t l a r g e trees and s t u m p s as s p e c i f i e d i n 8.2.2 h e l o w ) , c u t t i n g
of t r u n k s and b r a n c h e s e x c e e d i n g 0 , s m i n g i r t h i n t o t r a n s p o r t a b l e l . e n g t h s , h a c k f i l l i n g of c a v i t i e s ,
d e m o l i s h i n g s t r u c t u r e s ( e x c e p t where o t h e r w i s e p r o v i d e d f o r i.n t h e p r o j e c t s p e c i f i c a t i o n ) a n d removing,
t r a n s p o r t i n g ( e x c e p t where 8.2.9 i s a p l i c a b l e ) , a n d d i s p o s i n g oE material. t h u s c l e a r e d , g r u b b e d , c u t ,
3
and d e m o l i s h e d . B o u l d e r s o v e r 0.15 m w i l l h e d e a l t w i t h as e x c a v a t i o n i n terms of t h e i t e m s s c h e d u l e d
f o r b u l k e x c a v a t i o n o r r e s t r i c t e d e x c a v a t i o n . as a p p l i c a b l e , i n C l a u s e 8 of SABS 1200 D o r SABS 1200
DA, a s a p p l i c a b l e .

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.

i SABS 1 2 0 0 C-1980

Remove and grub l a r g e t r e e s and t r e e stumps of g i r t h


8.2.2
a) over 1 m and up t o and including 2 m
b) o v e r 2 m and u p t o and includlng 3 m
.....................................................
..................................................... Unit: No.
Unit: No.
c ) over 3 in, in steps of 1 m ................................................................ Unit: No.
The g i r t h of a tree O K stump w i l l be measured a t the narrowest point of t h e t r e e o r stump i n t h e f i r s t
metre of i t s h e i g h t above ground l e v e l . Trees and stumps of g i r t h exceeding 1 m w i l l be measured
i n d i v i d u a l l y and c l a s s i f i e d according t o site in increments of 1 m a s i n d i c a t e d above.
The r a t e s h a l l cover t h e c o s t of c l e a r i n g and grubbing trees and stumps of a l l s i z e s , c u t t i n g branches,
b a c k f i l l i n g h o l e s , and removing, t r a n s p o r t i n g , and d i s p o s i n g of a l l such trees, stumps, and branches

8.2.3
and a s s o c i a t e d m a t e r i a l .
Remove and grub a l l t r e c s and t r e e stumps r e g a r d l e s s o€ g i r t h ............................... Unit: ha
In exceptional circumstances, where c o n s t r u c t i o n i s c a r r i e d out through p l a n t a t i o n s o r where t h e
q u a n t i t y of t r e e s o€ g l r t h exceeding 1 m renders i n d i v i d u a l measurement impracticable. t h e p r o j e c t
s p e c i f i c a t i o n may provide t h a t the c l e a r h g and grubbing of t r e e s be measured in hectares. If this
method of measurement is used. t h e a r e a s t o which i t i s a p p l i c a b l e w i l l be defined c l e a r l y on t h e
drawings. and t h e reason For adopting t h e method of measurement w i l l be s t a t e d i n the p r o j e c t speci-
f ication.
The rate s h a l l cover t h e c o s t of a l l o p e r a t i o n s s p e c i f i e d In 8.2.2.
8.2.4 Reclear s u r f a c e s (only on i n s t r u c t t o n s from the Engineer) ............................ Unit: h a o r m OK km
The r e c l e a r i n g of a r e a s which have been previously c l e a r e d w i l l be measured t o the n e a r e s t 0.1 ha o r ,
in the case of p i p e l i n e s , etc. where t h e width is s p e c i f i e d , t o the n e a r e s t metre O K kilometre.
The rate s h a l l cover t h e c o s t of c l e a r i n g t h e s u r f a c e . grubbing i f necessary, b a c k f i l l i n g h o l e s , and
removing, t r a n s p o r t i n g , and disposing of m a t e r i a l a r i s i n g from t h e s e operations.
8.2.5 Take down e x i s t i n g fences ...................................................................
The rate s h a l l cover t h e c o s t of taking down t h e fences, c o i l i n g wire, s o r t i n g and s t a c k i n g a l l
Unit: km

m a t e r i a l a t sites i n d i c a t e d by the Engineer and t h e c o s t of loading, t r a n s p o r t i n g . and o f f l o a d i n g such


material.
8.2.6 Clear hedge OK fence o r both where not scheduled s e p a r a t e l y
Separate items w i l l be scheduled € O K each type and s i z e of hedge or fence.
................................. Unit: m

The rate s h a l l COVeK t h e c o s t of uprooting and disposing of each hedge complete with r o o t s o r t h e
removing of each fence complete w i t h a l l wire. p o s t s , and o t h e r materials, a s a p p l i c a b l e .
8.2.7 ................
Dismantle and remove p i p e l i n e s , e l e c t r i c i t y transmisslon l i n e s , c a b l e s , etc.
Separate items w i l l be scheduled f o r each type and diameter ( o r group of diameters) of p i p e l i n e
Unit: m

(encased in concrete o r not encased), each type of transmission line, c a b l e , etc.


The rate s h a l l cover t h e c o s t of dismantling, l i f t i n g , and disposing of each p i p e l i n e , t r a n s m i s s i o n
l i n e , and c a b l e and t h e a d d i t i o n a l c o s t of precautions required during excavation in t h e i r v i c i n i t y ,
but not t h e c o s t of excavation and b a c k f i l l i n g . Excavation and b a c k f i l l i n g w i l l be measured s e p a r a t e l y .
8.2.8 Demolish and remove s t r u c t u r e s / b u i l d i n R s and dismantle steelwork, e t c . ......................
Separate items w i l l be scheduled f o r steelwork and f o r each s t r u c t u r e t h a t is too l a r g e t o b e included
Unit: Sum

as part of t h e c l e a r i n g operations covered by 5 . 3 .


The rate s h a l l cover t h e c o s t of a l l such s e p a r a t e items s p e c i f i e d in the p r o j e c t s p e c i f i c a t i o n .
8.2.9 .............
Transport m a t e r i a l s and d e h r i s t o unspecified s i t e s and dume ( P r o v i s i o n a l ) Unit: t.km O K m3.km
Where t h e l o c a t i o n of d i s p o s a l o r dumping s i t e s is n o t a t t h e d i s c r e t i o n of the Contractor O K is not
s p e c i f i e d a t the t e n d e r s t a g e by t h e Engineer in terms of Subclause 3.1, c a r t a g e w i l l be scheduled
separately.
The t o t a l d i s t a n c e and t h e t o t a l mass O K volume, as r e l e v a n t , w i l l be computed from the d i s t a n c e by the
s h o r t e s t r o u t e in one d i r e c t i o n measured t o the n e a r e s t 0.1 km and t h e capacity of the v e h i c l e s being
used f o r t r a n s p o r t , as agreed hetween t h e Engineer and t h e Contractor b e f o r e the removal commences.
Zhe r a t e s h a l l cover t h e c o s t of loading, t r a n s p o r t i n g . dumping, and any charges f o r t h e use of t h e
dumping s i t e .
8.2.10 Remove t o p s o i l t o nominal d e p t h of 150 mm and s t o c k p i l e ..................................... Unit: m3
The rate s h a l l cover t h e c o s t oE removing t o p s o i l , t o g e t h e r with such v e g e t a t i o n and s m a l l r o o t s a s
occur wlthin the s p e c i f i e d depth, and of s t o c k p i l i n g on designated s i t e s .

© SABS. This standard may only be used and printed by subscribers to the SABS’ Complete Collection of Standards and Related Documents.
© SABS. This standard may reside on a LAN, WAN, intranet, internet or ECM server and is exclusively available to subscribers to the SABS’ Complete Collection
of Standards and Related Documents in accordance with a formal copyright exploitation agreement to be renewed annually. Only staff members
employed by the Subscriber may make paper copies of the standard. No paper copy may be photocopied or reproduced in any way.

SABS 1200 C-1980 8

APPENDIX A. APPLICABLE STANDARDS

Reference is made to the l a t e s t issues of the Following standards:

SABS 1200 A Civil engineering construction : General


SABS 1200 AA Civil engineering construction : General (small works)
SABS 1200 D Civil engineering construction : Earthworks
SABS 1200 DA Civil engineering construction : Earthworks (small works)

ISBN 0-626-06215-2

rabr pta