You are on page 1of 1

COMPLIANCE STATEMENT

Project:
Film Studio Water pipeline connection Project

Transmittal: SEAPGMC-WTRAN-000073

Date: 27/Dec/23

SL NO Document Number SEA Comment BOC Reply

1
1) Proposed material is highlighted with Selected stamp at page
1. PROPSED MATERIALS SHALL BE HIGHLIGHTED IN THE CATALOG. No 22
2. MANHOLE DETAIL DRAWING SHALL BE ATTACHED WITH ALL THE INFORMATION AS 2) Drawing is provided at Page No 3
MP2FDINFI9003-BOC-PB03-PW-000-MM-ME-
PER IFC DRAWING. 3) Physical Sample will be submitted after approval of this MAR
000007(Rev-1) 3. PHYSICAL SAMPLE SHALL BE SUBMITTED FOR FINAL APPROVAL. 4) Inscription style is there on page No 21 for sewer but any other
4. INSCRIPTION OF INTENDED APPLICATION WRITTEN IN ENGLISH AND ARABIC SHALL style like waterline can be prescribed as per provided client
BE PROVIDED. instruction.
5. PROVIDE/ATTACHED APPROVED MANUFACTURER PRE-QUALIFICATION 5) PQD is attached at Page No 2

Classification | PUBLIC