Professional Documents
Culture Documents
Faculty of technology
Girma Worku
Tessema Chala
Girma Worku
Tessema Chala
Yifredew Abreham
2006
Causes of Delays and their Impacts in Road Construction Projects in Ethiopia
Advisor
Thesis committee
External Examiner
Abstract
The main observations of this study work have been the fact that events
that cause delays during the implementation phase are related to pre-
construction and construction phase activities. Results indicate that the
main causes of delays that arise from pre-construction stage are related
to design problems, contract documents, tender documents preparation
and procurement management. Causes of delay that arise during
construction stage include: right off way problems, change orders, and
variations.
Acknowledgement
Our adviser, Ato Dereje Kidane, deserves the greatest thanks. This is due,
not only he has been an ideal advisor in discussing our thoughts
thoroughly and giving constructive comments, valuable guidance and
advice on a number of issues; but also his great support during our site visit
in arranging transportation facilities to minimize our expenditures.
We are thankful for Ato Abiy, who helped us as a co-advisor, for his
encouragement and support during our study and providing us with
relevant information and documents of the projects we studied. We are
also grateful to the counter parts of all the study projects for their unlimited
support and response during the interview and encouraged the other
practitioners to share their views and ideas on the different issues of the
study.
Finally, but not the last and the least by no means, special and great
thanks goes to our parents who have been providing us with the
necessary help during our academic career without which the education
could have been more difficult.
Girma Worku
Tessema Chala
Addis Ababa University, Faculty of Technology (S.C.), Dep’t. of CoTM IV
Causes of Delays and their Impacts in Road Construction Projects in Ethiopia
Yifredew Abreham
August 2006
Executive summary
We pushed ourselves to look in to delay issues that gave way to our motivation
to undertake such a demanding task. As a result, the problem statement of
this study was shaped and built on causes of delays and their impacts on road
construction projects.
The study instrument used was literature review (both primary and secondary
data), interviews (with project owner, contractors and consultants) and case
study. Evidences collected were analyzed by discussing the findings and
comparing them with the thoughts of different researchers discussed in
literature reviews. We chose discussion method of analyzing the findings
mainly because the number of projects considered and parties interviewed is
not representative to analyze using statistical method.
The study indicated that delays in the road construction projects occur partly
due to events that arise from the pre-construction activities. The analysis of the
data collected appears to show that the pre-construction events leading to
delay of projects are attributable to the project owner (ERA) and consultant.
Pre-construction problems causing delays due to owner related problems are
poor contract management and unclear need of the owner that lead to
change order during construction stage.
The study reviled that delays caused by consultants are mostly related to
design problem and incomplete bidding document preparation. The most
critical and frequently appearing problems related to pre-construction events
seem to be those related to design problems. There has been a significant
delay due to design changes, modifications and lack of sufficient details.
Inadequate/inaccurate soil investigation report of the proposed quarry sites
and rocky areas have contributed to delay of projects. It appears that in most
of the cases variation orders are entertained due to incompleteness of project
design during the design preparation of the projects. The study indicated that
incomplete bidding document preparation by the consultants is among the
causes of delay event.
All the projects analyzed in this study have experienced right of way
problem making it a prime claim point for extension of time and cost
compensation. The coordination of the removal of unclear obstructions
that are belonged to the different government agencies has been
significantly the causes of delays. As the exclusive responsibility of the
Clint, the contractors are entitled for time extension and cost
compensation.
reliable information will be produced and shall be the base for the
contractors pricing during tendering.
Table of Contents
Abstract………………………………………………………………………………IX
Acknowledgement……………………………………….………………………..IX
Executive Summary…………………………………………………………………IX
Table of Contents…………………………………………………………………..IX
List of Tables and Figurers…………………………………………………….…..IX
Abbreviations and/or Acronyms……………………………….……………..IX
Appendix
Chapter 1: introduction
1.1. General………………………………………………………………...1
1.2. Background…………………………………………………………...3
1.2.1. Development and Physical infrastructure……………...3
1.2.2. The Road Sector Development Program
(RSDP)………………………………………………………….3
1.2.3. SWOT analysis of RSDP……………………………………...7
1.3. The research Objective……………………………………………..8
1.4. The research justification…………………………………………...8
1.5. The research methodology………………………………………..9
1.6. The dissertation overview………………………………………….10
Chapter 2: Pre-construction Events Causing Delays During
Construction Stage
2.1. General……………………………………………………………….11
2.2. Causes of delay due to events during pre-construction
Stage………………………………………………………………….12
2.2.1. Contract document preparation………………………13
2.2.1.1. Condition of contract………………………14
2.2.1.2. Specification and drawings……………….15
2.2.1.3. Bill of quantity…………………………………17
2.2.2. Design preparation……………………………………….18
2.2.2.1 Surveying error……………………………….18
2.2.3. Tender document preparation………………………...20
2.2.4. Process of tendering…………………...………………...21
2.2.5. Contract negotiation process………………………….22
Chapter 3: Causes of delays during construction stage
3.1. General………………………………………………………………23
Addis Ababa University, Faculty of Technology (S.C.), Dep’t. of CoTM IX
Causes of Delays and their Impacts in Road Construction Projects in Ethiopia
List of Tables
List of Figures
ABBREVIATIONS
1.1. General
One of the most important problems in the construction industry is delay. Even
though owners and contractors strive to avoid delays in construction and to
minimize the time and costs associated with delays, they often find it difficult
to control the circumstances causing delays. Delays occur in every
construction projects though the magnitude varies considerably from project
to project. Some projects are only a few days behind the schedule; some are
delayed over a year. The complexity of projects, complicated schedules and
hair-splitting coordination all contribute to the necessity for this attention to
time. And when deviations in construction schedules occur — as they
invariably do for a variety of reasons — ominous shadows can emerge from
behind the clock: delay, acceleration and cumulative impact claims [1].
According to Robert Palles, delay and additional cost in construction projects
are an inevitable consequence of the risk and uncertainty associated with the
execution of any construction project, which is likely to be unique and
prototypical in nature [2].
According to A.C. Twort, a delay can affect a portion of the work or the
whole of the work. It can also be complete-such as when the engineer orders
a machine to stop working and no other work is available for it; or it can be
partial- such as when materials or services to be provided by the employer
under other contracts are not forthcoming at sufficient speed to allow the
contractor maintain normal rates of outputs [4]. Delay can be divided in to
two broad categories: delay to the compilation of the contract itself,
resulting from a delay to work which is on the critical path of the construction
program, i.e. critical delay, and delay to part of the work which does not
cause delay to overall completion, i.e. non-critical delay [5]. The critical
delay is the cause for Time Claim, which is either claim by the employer for
late completion (liquidated damages) or by the contractor for extension of
time. The study by Abebe Dinku and Girmay Kahssay as published in Journal
of EER, Vol. 20 revealed that all international projects being carried out in
Ethiopia have not been completed on time; rather all of them have been
granted time extension [6]. For instance, according to the study, the
contractor of Addis Ababa Ring Road Project (AARRP) had requested about
97.1% of the contract period for time extensions and, up to the writing of the
article, the contractor had been granted a time extensions of about 89.37%
of his demand. This and other related literatures indicate that delayed
operative tasks generate a cumulative effect, which delays the overall
delivery time making efficient time management difficult.
The nature of the work in road projects and the environment in which they
are built make such projects susceptible to delay. The influential factors can
be:
• High uncertainty associated with such projects because they require
excavations in varied soil and site conditions
• Work in these projects depends heavily on equipment and may be
delayed because of the need for equipment repair and maintenance.
• Numerous government authorities are involved in the project and
each may require the contractor to obtain different permits with
restriction on time and work area. A great deal of coordination among
these agencies is required to avoid delay.
1.2. Background
Realizing the importance of the road transport sector the government has
formulated coherent 10-years Road Sector Development Program (RSDP)
since 1997 and actively focusing on its implementation. The program was
designed to ensure the development of road construction projects and
policy reforms to the road sector of the transport industry including its
financial and institutional management system. This was due to
Governments’ beliefs that infrastructure has a key role in every effort for
economic growth and their contributions to poverty alleviation. The program
is divided in to two phases:
Phase-I (RSDP-I)
This is the first fie-year strategic plan between 1997 and 2002 Fiscal Year. Its
main objective has been improvement of the road network that has been
continuously deteriorating to hamper the efficiency of the road
transportation system. The program considered the rehabilitation, upgrading
and construction of new road and also considered major policy and
institutional reforms as the major objective. The Federal Roads has covered
52.5% by length (km) and 77.9% by cost (Millions EBirr) of the Public
Construction works according to plan in 1997/98, that is; during the start of
RSDP-I.
Table 1.1. Planned RASP-I
The main target of the first phase of the program was the rehabilitation and
upgrading of main roads, and new construction of link and regional roads. It
was targeted to rehabilitate and upgrade about 2,542 Km of trunk roads at
an estimated cost of Birr 4.6 billion, upgrade/construct 785 Km of link roads at
Birr 0.9 billion. The program also included maintenance of all types of roads,
studies, institutional capacity building and policy support projects. The
program was also targeted to increase the road density to 0.49 km per 1000
population and 27-km/1000 km2 with about 60% of the network in good
condition compared to the total classified road network as of 1996 (Table
1.2.), which was 23,812 km out of which 15,769 km (66%) was under Federal
Roads. Besides, it was only 15% of the road network found paved.
According to the result of analysis at the end of the phase, the overall
physical accomplishment of RSDP-I as of June 2002 and the corresponding
financial disbursement are 88 & 77%. Even though the construction of major
and rural road have proceeded satisfactorily exhibiting 105% and 111% rate
of accomplishment respectively, the Periodic maintenance works was
lagging behind with only 23% of the planned physical accomplishment
achieved.
Table 1.3. Physical accomplishment of RSDP-I
No. Components Km
Source: RASP-II
The total classified road network has increased by about 40 percent over the
RSDP-I; much increase, 107 percent, in the regional roads including low class
roads. The size of the road network is still one of extremes with a total land
area of over 1.1 million sq. km and a population of close to 67.2 million, the
total network has a very low density; about 30 km per 1000 sq.km. Generally
the following table (Table 1.4.) shows the percentage change in the length
of Federal and Regional Roads starting from 1996 to 2002.
Phase-II (RSDP-II)
This is the second five-year strategic plan between 2002 and 2007 Fiscal Year
mainly focused on upgrading and rehabilitating of the existing road network.
This was because Ethiopia’s roads were facing shortage of resources for
maintenance during the 1970’s and 1980’s so that most of the roads were at
the verge of total deterioration. Therefore, construction of new roads could
not be a top priority. Thus, RSDP-I has not brought change on the road
density of Ethiopia, which is still by far below most sub-Sahara African
countries. It was reported that the road density figure 30 Km per 100 Km2 for
The RASP represents a huge investment program. As the needs for the sector in
general are rapidly changing, the analysis of the characteristics of the demand
and the required types and levels of intervention becomes a complex task. In
addressing these needs, the GoE has reformed ERA and RROs, recruiting more
professionals and has given them on-the-training through attachments to
different roadwork activities and contracts. In addition, Government has
received donor assistance in providing consultancy services in terms of TA and
training to ERA staff in critical areas of program management, legal and
technical aspects of contract administration, planning and programming,
maintenance management etc.
Generally the following figure shows the strength, weakness, opportunity and trait of
RSDP.
Fig. 1.1. Internal and external factors affecting RSDP
OPPORTUNITY
STRENGTH
• Priority of the sector
• Smooth relation with donors
• Dedication of ERA and encouraging support by
Personnel most donors
• Existence of established • Dedicated and stable flow of
road authority funds for maintenance
• Encouraging government
commitments
RSDP
INTERNAL FACTORS EXTERNAL FACTORS
THREAT
SOURCE: RSDP-II
The objective of this study is to determine the causes and the level of time
extension of road project, the impacts of delay in terms of time and money
and to aid construction professionals involved to better understand the
causes of delays, to recommend practices, procedures, and methods that
can be used to avoid delays in pre-construction and during the construction
phase of highway projects and to mitigate their impacts and associated
costs.
The starting point of any research is the definition of the research issue or the
problem statement (Nick Moore, 2000 as quoted in Wubishet Jekale, 2004).
This study had also passed through the fallowing specific context:
• Understanding of the issue examined
• Determining the extent of the study focus, and
• Knowledge of the subject area
The research’s broad area of the study was related to delays on road
construction. This level assisted us to focus on the causes of delay and their
impacts on road construction through discussion together with the advisor
and reviewing relevant literatures. The specific focused attention has
enabled to determine where and which projects should the study include.
Besides, it helped to identify the target study project, how data can be
collected, and how the interview and the case study can be designed and
conducted.
Questions Answer
The key task in research is to design research process so that the information
obtained permits the assessment of their impact. The basic research design
was an exploratory research methodology using both primary and
secondary data. This design was chosen since it enables to assess the
magnitude and scope problems and facilitate for the suggestion of solutions.
Generally, the research process was designed through defining the research
problems, its objectives and questions. To accomplish these objectives the
research was made using the following methodologies:
CHAPTER 6 (CASE STUDY AND THEIR FINDINGS): This includes the findings of
the case study on the two selected road projects and recommendations on
the findings.
2.1. General
The project time objective specifies the project completion time. Time delays
in recovery of damages while early completion might earn rewards. Virtually
all road construction projects were not completed as planned. There may be
many reasons both foreseeable and unforeseeable, for non-completion of
road project timely.
The causes of delay and cost overruns arising from pre-construction stage
that lead to claims and disputes are resulted due to the existence of high
uncertainty during the early phase of a project, which posses the most
probable influencing power on the project [14]. Decisions made early in the
life of the project have the most profound effect on the project’s objectives
of delivering a safe, quality project within the time and budget allocated
[15].
The guidance notes for the New Engineering Contract Second Edition also
states, ‘uncertainties about what is to be done and about how the
unexpected arising in the course of construction will affect what has to be
done are inevitable in construction projects’ [16]. The literature discusses
some of the possible reasons why some construction contracts do not
achieve the original program to completion, the execution of the works on
time and within budget. These reasons are:
• The Employer’s choice of risk allocation does not place risks with the
party best placed and motivated to manage that risk
• The design is not complete or subject to late change and additions
• The overall duration of the contract program is not realistic
• Activity duration may be unrealistic
• There is lack of clarity in the declaration, ownership and use of ‘float’,
both within activity durations and in the period between the
contractor’s intended date for completion and the Contract
Completion Date
• Available site resource levels have not been considered in the
program
• The lack of resources further down the supply chain
• The program network does not respond realistically to changes
The major events that may result in delay arising from pre construction stage
are:
According to the results of the study by Sasmi M. Fereig and Nabil Kartam on
Construction Delays on International Projects, tendering projects prematurely
without the necessary construction documents being sufficiently detailed to
reflect the full scope of the work causes the timely completion of projects
difficulty when changes or additional works are encountered during the
implementation stage of the contracts [15].
will carry greater weight than that of the owner or the engineer [19 and
www.Jus.uio.no].
The use of standard conditions of contract will not only facilitate the
successful completion of a contract but will, in all probability, result in lower
tender prices, as tenderers will be familiar with the conditions that will apply
under the contract. This implies that they will not need to make financial
provision for contract conditions with which they are not familiar and whose
consequences they may have difficulty in assessing. The widespread use of
standard conditions of contract also provides a stable basis for training and
educating personnel responsible for contract management and avoids their
having to work with ever changing contract conditions [11].
When time and cost claims are made, it is commonly said that the starting
point for the analysis is the parties’ conditions of contract as it defines the
parties’ rights and responsibilities (and, most important, who was to do what).
But in the context of delay claims, the contract generally does little more
than set forth the basic ground rules for the dispute by identifying, which
party is reasonable in the event particular events or circumstances are found
to have caused the delay [21]. Generally, while the contract defines who is
responsible for what, it typically does not answer the key question–what
actually caused the project to finish late?
The specifications are the part of the contract documents that define the
qualitative requirements of the project that is to be built. Whereas drawings
define the geometry of a project, including dimensions, forms, and details.
The specifications are intended to complement this by defining the nature of
the materials that are to be used and the description of the workmanship
and procedure to be followed in constructing the project [19].
Unenforceable phrases
In some cases, the same data are covered in both the drawings and the
specifications-not a great arrangement, but it happens often enough. The
problem here is that frequently one document is changed during design and
the other is overlooked. This generally creates the problem just referred to.
The unfortunate situation is that usually where such a problem exists, it is the
drawings that were updated to receive the latest change or corrections, and
the specification may in fact be out dated and incorrect. The basic
philosophy still controls, however, and the inspector has no authority to force
the contractor to provide, that which is shown on the drawings when the bid
may have been based on the article contained in the specifications. In case
of any such conflict, the contractor is obliged to notify the owner before
continuing. However, it is well to the inspector to monitor carefully any such
possibility personally, as the contractor may honestly miss recognizing the
presence of a conflict. It would also be possible a dishonest contractor
merely to claim to miss the conflict so as to furnish the cheaper of the two
items, knowing full well that if the design firm want it changed after the
contractor has already built it in accordance with the specification, in all
likely hood, he or she will be able to claim successfully extra compensation of
time and money for such additional works [19].
FIDIC 87 clauses 44.1a & e state that the contractor is entitled for extension of
time for:
a) The amount or nature of extra or additional
e) Other special circumstances, which may occur, other than
through a default of or breach of contract by the contractor or for
which he is responsible.
These sub clauses indicate that if the drawings were not properly, clearly &
accurately set out, it leads to the event in clause 44.1a. Where as clause
44.1e indicate that if type & quality of materials, equipments, labor or
workmanship, method of fabrication, installations & erections were not
properly set on the specification, which are considered as special
On the other hand, if the quantities are mistakenly more, it will cause high
stocking, more storing places and risk of spoilage: unhealthy practices due to
over budget provisions; and manipulating in tendering [14]. If there is
difference between the actual quantity observed on the site and what is on
the bill of quantity, delay in performing the work may be encountered which
may entitle the contractor time extension according to clause 44.1a of FIDIC
87.
Generally, the major problems that arise in associated with the contract
documents and would result in delay of the project in manipulating them
are:
Design-related delays are one of the most critical delays most likely to
happen due to design-related problems. According to the survey by Sami M.
Fereig and Nabil Kartam, design-related delays are considered to be
excusable compensable delays. Consultants play a very important role in
design-related delays because they are in charge of the design process in
conjunction with the owner of the project. Design-related issues, such as
change in drawings and incomplete and faulty specifications and change
orders, have a very damaging effect on project completion times and
invariably lead to cost escalations as well [15]. The study by Abebe Dinku and
Girmay Kahssay also reveled that design changes, modifications and lack of
sufficient details are causes of critical delays. Lost traverse points and
adverse climatic conditions cover about 13%of the total critical delay [6].
Every day of the year, in many works of life, maps and plans are in common
use. These maps and plans include street maps; charts of lakes and rivers,
under ground railway maps, construction site plans and architectural plans
and sections. Cartographers, engineers, architectural draftsmen or surveyors
draw all of these plans to scale, from measurements of distances, heights
All surveying operations were subjected to error. So the sources and effects
of errors must be recognized and steps taken to eliminate or minimize them
since they are the raw data for the design work.
A) Gross errors
Mistake arising in the mind of the observer may be due to carelessness,
inexperience or fating
1. Wrong staff readings
This basically includes misplacing the decimal point, reading the wrong
meter value and reading the staff wrong way up.
2. Using the wrong cross – hair
Instead of reading the staff against the axial line, the observer reads
against one of the stadia lines.
3. Wrong booking
The reading is noted with the figures interchanged.
4. Omission or wrong entry
A staff reading can easily be writhen in the wrong column or even
omitted entirely
5. Spirit level not centered
The staff is read with out centering the bible
B. Constant errors
These errors are due to instrumental defects and will always be of the same
sign.
1. Non – verticality of the staff
This is a serious source of error. Instead of being hold vertically the staff
may be leaning forward or backward.
2. Collimation error in the instrument
3. Staff graduation error
C. Random error
1. Effect of mind and temreture
2. Soft and hand ground
3. Chang points
4. Human deficiencies
All these errors must be treated well otherwise what we surveyed will not
match with the actual case so it results to delay in performing the work such
that the contractor will be entitled for extension of time according to clause
44.1a of FIDC 98.
Knowing contract
requirments
Extension errors
8% 2%
15% Knowing work required
9%
Underevaluing cost
9% escalation
19%
Transposition errors
Generally, if more time is given to produce the tender, then many of these
mistakes could be eliminated, and contractors will be more satisfied with their
commitment and therefore less likely to make time and cost claims to try to
recover the situation.
Often two staged biddings are made for the submission of technical and
financial proposals separately and their evaluations one after the other. Pre-
Pre qualification has advantages not only for the employer but also for the
bidders.
The study by Abebe Dinku and Girmay Kahssay reveled that claims related to
time extension and compensation of additional costs were raised by the
contractor for the great difference between the actual site condition and
When the consultants believe that the Tender document is insufficient, they
use ‘disclaimer provision’ to inform the bidders that the information given in
the Tender Document is for the informational purposes only. They provide the
provision not to assume liability for any inaccurate, delayed or incomplete
information, nor for any actions in reliance thereon. The information
contained about individuals or firm has supplied firm without verification by
them. Past performance is not necessarily indicative of future performance.
Prior to make any investment decision, it is recommended that you consult
directly with the individual or firm and seek advice from a qualified
investment adviser.
During contract negotiation each party may use standard terms for their
agreement but these terms may not be the same and it results in differences
when they are applicable. During such cases the rule of ‘battle of forms’
applies. And it states: where both parties use standard terms and reach
agreement except on those terms, a contract is concluded on the basis of
the agreed terms and of any standard terms which are common in
substance unless one party clearly indicates in advance, or later and without
undue delay informs the other party, that it does not intend to be bound by
such a contract [26].
3.1. General
The main aim of this chapter is to set out the various causes of delay on road
projects at implementation stage, which may lead to extension of time and
cost overruns, FIDIC 87 provisions for delay responsibilities, and sources of
information to assess causes of delays and their impacts. But before that it is
better to discuss types of delays to better understand the cause and effect
relationship among the different causes of delays.
1. Non-excusable delays
2. Excusable non-compensable delays
3. Excusable compensable delays
4. Concurrent delays
When delay is caused by factors that are not foreseeable, beyond the
contractor’s reasonable control and not attributable to the contractor’s fault
or negligence, it may be “excusable”. This means that neither party is at fault
under the terms of the contract and has agreed to share the risk and
consequences when excusable events occur. The contractor will not receive
compensation for the cost of delay, but he will be entitled for an additional
time to complete his work and is relieved from any contractually imposed
liquidated damages for the period of delay [9]. Sami M.Fereig and Nabil
Karatam also strengthen the idea of Syed M. Ahmed and Salman Azhar
stating that a contractor gets time, but not money if Non-compensable
Excusable delays occur, but he is relieved from liquidated damage [15].
Scott A. Aftuck pointed out that if the delay could have been avoided by
due care of one of the parties, the party, which did not exercise such care, is
responsible for the additional costs. The contractor may be liable for the
negligent acts of its subcontractors. However, if the subcontractor has a
direct contractual relationship with the owner of the project, the contractor
most likely will be able to recover damages, as it was not in a position to
prevent the delay [28].
made here to strictly define concurrency other than, from the definition,
more than one delay happens at the same time. The problem seems to
decide which of the delays, if any, results in delay to the completion of the
project and, if there is a multiplicity of causes, if the contractor is to recoup
loss and expenses [29].
Brian Eggleston describes that disputes related to concurrent delay arise not
so much on how long was the period of the overlap, but to what cause
should it be attributed; and to what extent it is permissible to consider the
knock-on effects of one delay to another. There are three principal
approaches to the solution of the problem: the first in line approach, the
dominant cause approach and the appointment approach [30].
The method only takes cognizance of the events that affect activities on or
near the critical path (the time of the delay) that result in the project delays.
In analyzing delay in chronological sequence, the earlier event causes the
delays that result in the following event having no additional effect on the
project completion [29].
Delayed completion of
preceding activity Delayed start
Succeeding activities
are not delayed
Project may
An activity’s not be delayed
Succeeding activities
Completion is delayed.
are delayed
Adverse weather
condition
Project is
Extended activity delayed
Management duration
decision
Insufficient
Changed site condition resource
Changes in scope
of work
Delays can occur in any and all activities, and these delays can concurrently
or simultaneously cause delays in the project completion. In other words, a
project delay is the accumulated effect of the delays in individual activities
[31].
According to Syed M Ahmed and Salman Azhar, there are two kinds of
causes of delays in construction projects: external and internal causes.
Internal causes of delays include the causes, which come from four parties
involved in the project- Owner, Designer, Contractors, and Consultants.
Other delays, which do not come from these four parties, are based on
external causes for instance from the government, material suppliers,
weather [28].
They pointed out that causes of delays that the construction industry is facing
nowadays during implementation stage are:
• Financial difficulties
• Inexperienced personnel
• Insufficient number of stuff
• Deficiency in project coordination
• Inadequate and old equipment
• Lack of high technology equipment
• Harvest time
Table 3.1. Categories of delays according to their nature and mode of occurrence
• Flood
• Hurricane
ACTS OF GOD • Fire
• Wind damage
• Change order
• Change in drawings
DESIGN-RELATED • Change in specifications
• Shop drawings approval
• Inspection
• Subsurface soil condition
• Material/fabrication delays
• Material procurement
• Lack of qualified craftsmen
• Poor subcontractor performance
CONSTRUCTION-RELATED • Defective work
• Different site condition
• Damage to structure
• Construction mistakes
• Poor supervision
• Equipment availability
• Financial process
• Financial difficulties
FINANCIAL/ECONOMIC • Delayed payments
• Economic problems
Source: Syed M. Ahmed, Salman Azhar and Mauricio Castillo, Construction Delays in
Florida: an Empirical study, Florida International University, USA, 1999
1. Planning failure (failure to hold realist and up dated work plan and
schedule)
2. Organization failure.
3. Scarcity of resources.
4. Controlling failure.
5. Coordination failure.
This failure happens due to communication gap at various levels, lack of day-
to-day decisions to fill procedural gaps, and absence of cooperation among
staff members [5].
Since most projects’ self-financing date lies near to the completion date of
the contract period, they often trapped with cash shortage during their
construction phase, such that the progress of the work may lag behind due
to lack of finance. Therefore, the project manager should for cast the cash
flow in order to find short-term capital from other finance securities [35].
The client delays completion of the work in various ways. Among these, the
following are the main ones as a report published by the construction industry
council of UK [36]:
• Rigid budgets
• Changes of mind during construction
• Ordering extra which delay the work
• Delay to provide the right of way
• Differing site conditions
• Suspension
These all are fairly common situations in construction works as a result most
condition of contracts contain provisions to allow an extension to the
contract time to cover reasons where the client has affected the completion
of the works [33].
One of the principal causes of project delay and cost overruns is that
contracts are awarded and notice to proceed given before all arrangement
for the contractor to take possession of the site and proceed, as called for in
the contract, are completed. As a consequence, contractor may encounter
impediments that lead to delay and claims.
According to Edward R Fisk, the major causes of delays that are caused by
the consultant side include the following [19]: -
3.4.4. Delays Caused by Outside the Control of Either Party to the Contract.
Because of the way construction works are carried out, there will be many
occasions, which are beyond the control of either party that may lead to
delay. Most contraction contracts including FIDIC red book (1987)
incorporate provision to grant extension to the completion date to cover
these situation. According to W. Trench Frics, events [33], which considered
as outside the control of either party to the contract, are: -
• Force majeure.
• Exceptional adverse weather condition.
• Civil commotions or strikes use of fuel or labor.
• Material market instability.
• Government legislation change.
• Government statutes that restricts use of fuel or labor
There are several version of FIDIC condition of contract fourth edition issued
in 1987 (the old red book) by the international federation of consulting
engineers is the one we used in this thesis.
The FIDIC Red book fourth edition (1987) form of contract, for works and civil
engineering construction, has two parts. Part I consists of the “General
Conditions”, i.e. clauses defining the parties right and obligation and part II
contains “conditions of particular application”, those clauses specifically
drafted o meet the needs of the contract, including conditions unique to the
locality of the project being performed, such as taxes, labour laws, local
holidays, language, etc…
FIDIC Red book 87 standard of condition contains clauses providing for the
granting of extensions of time linked with a clause for payment of liquidated
damages by the contractor in the event of late completion. In the absence
of express contractual power to extend the time for completion, the
engineer could not do so [39]. In order to avoid delay during construction,
documents should be carefully read and under stood by all parties involved
with special attention to clauses dealing with extension of time [37].
In delay the employer cannot insist that the contractor shall complete on
time if the employer has prevented him from so completing. This is then
modified by the presence of express terms for the contractor to receive
extension of time for acts or omissions of the employer or those acting on his
behalf, such as engineer, architect. The contractor therefore has the original
contract period plus the length of the delay caused to him in which to
complete the project.
In General, the event that could give rise to the contractor’s entitlement to
extension of time in FIDIC 87 are listed under sub-clause 44.1 as follows:
Under sub-clause 51.1 of FIDIC 87: - the engineer has the authority to make
variations and instruct the contractor to do any of the following:
Even though all the works that are listed above could have delaying effect on the
progress of the contractor, the contractor only could have entitled extension of
time for causes (a) and (e) [32].
The engineer has the authority to suspend the progress of the whole works or
and part of the works, If such suspension is a rising from any act or default by
the engineer or employer or any of the employer’s risks (FIDIC 87).
According to FIDIC 87 sub-clause 44.2 says the contractor should notify the
engineer within 28 days or other reasonable time that the engineer agreed in
the contract documents.
According to Gillia Birkby and Paul Brought, there are a number of sources of
information [5], which the contract administrator can use to monitor and
assess delays:
Notices of delay
The construction Programmes
Site Progress meetings
Day work sheets and contractor’s allocation sheets contractor’s
report
The contract administrator will use the construction programs both to monitor
the contractor’s progress to identify delay, and to monitor information
requirements so as to prevent delay. Subsequent revisions can be used to
monitor how the contractor intends to complete the works and as further
check on any delays that may occur after the revisions have been issued.
Site Progress meetings: - These are usually concerned with progress in the
broadest sense, i.e. how the work is proceeding so as to achieve the date for
completion, and any action to be taken by the design team so that the
contractor is not prevented from doing so. The meeting will therefore review
the provision of delay how these can, if possible, be overcome or mitigated.
The contract administrator may be told in the meeting about the causes of
delay, which he will need to weigh against the documented evidence of
delay.
Day work sheets and contractor’s allocation sheets: - Day work sheets, where
they have been used to value a variation or the contractor has presented
them for ‘record purposes’ are an excellent means, if verified, of establishing
when wok was executed. The some applies to the contractor’s allocation
sheet, if these are made available to the contract administrator and they
provide sufficient detail that can be verified.
On many projects, where time is the essence of construction, the owner and
the contractor agree under the contract terms that if the contractor fails to
complete the project by the stipulated date, it is financially liable to the
owner for a pre agreed sum for each day beyond the specified completion
date that it takes the contractor to finish the work. This amount of money
represents the financial losses to the owner for such delays, and because it is
difficult to determine the real values of the owner’s losses, the pre agreed
sum is considered as the actual damages suffered. This assessment is referred
to as liquidate damage [19].
The estimated amount of the liquidate damages per day may be a function
of many think. It can be losses to the owner in connection with revenue
producing the road. Similarly it can be a function of profit the owner gets
from that investment.
If the owner does not make a reasonable attempt to for cast its actual delay
damages, the provision may be considered as unenforceable penalty, or an
attempt to provide a negative incentive for timely contractor performance
[19].
4.1. General
In its effort to change the backward economic and social status of the
country, the Federal government of Ethiopia is undertaking various capacity
building programs and development projects with the assistance secured
from donors and international financial institutions. One of the programs is the
establishment of Road Sector Development Program (RSDP). This was
designed to ensure the sustainability of considerable and extensive capital
investment allocated for the road sector. The program has taken up the
development of road infrastructures of the country through Ethiopian Road
Authority (ERA).
The projects selected for interview were three ongoing projects: two trunk
roads and one link road. These were:
Table 4.1: Projects considered in the interview and site visit, source RSDP
Planned Planned
No. Project Project type Planned Km Financers Remark
time cost
Addis Ababa- Rehabilitation 148 out of 185 80% RSDP-I 177.7 Germen RSDP-II
1
Ginchi-Ambo Gov’t
Natherth-Assela Upgrading 75 With in 110.6 GoE+WB RSDP-II
2
RSDP-II
Construction of the ordinary fill and/or sub grade, sub base, base coarse,
prime coat, diversion road have been progressed up to km 69+000 and
construction of minor drainage structures have been undertaken through
these kilometers.
The physical progress for permanent work up to the end of May 2006 was
64.3%, which has been delayed considerably when compared to the work
program. As per the revised work program the progress should have been
72.1% at the end of May 2006. It was found out that the reasons for slippage
of the work from the planned program are both the contractor and the
consultant. Unfortunately, it was not possible to find the contractor. The
consultant’s views were summarized below.
The main causes for the delay of the project due to contractor’s failure
include:
• Lack of proper planning
• Lack of coordination
• Lack of controlling
• Low contract amount
• Failure to allocate skilled manpower
• Failure to manage its plant and equipment
c) Lack of controlling
Project progress is not monitored, as there is no effective control system. Had
there been such a control system, improvements in the day-to-day rate of
progress could have been observed. Contrary to this, the project is
experiencing slippage, which is accumulating every month.
Lack of skilled manpower was the main problem that makes the contractor
unable to achieve the desired plan. Experienced project manager is
important for planning, directing and controlling of a project. But the
contractor lacks such personnel, leaving the work for inexperienced and
unskilled engineers. According to the Assistance Resident Engineer, the
contractor has been advised repeatedly to correct the staffing to carry out
the work according to the standard with in the time frame set in the
contract.
The project has been delayed significantly due to the employer’s failure to
remove obstructions and give the site. The contractor has requested the
employer to acquire borrow pit and clear the right of way. But the employer
has delayed to give the response. Due to this the project has been delayed.
No other failure of the employer is assessed in contributing to delays.
Since the original design has a problem on the thickness of DBM and wearing
coarse it was changed. As a result the thickness of DBM was changed from
7cm to 10cm and wearing course from 3cm to 5cm.These changes result the
contract period to be revised and is extended by 11.5 months. No more
problems were discovered during the interview. If the contractor had been
there during our field visit for the interview, it would have told us so many
problems related to the consultant and the contractor.
Construction progress requires land for right of way, storage and borrow pit,
which has been acquired by the residents. And the employer has faced
problem to possess it due to the request raised by the residents for
compensation, which take some time. And the residents have made little
civil commotions, even though it doesn’t have considerable impact on the
progress of the work.
The consultant has been advising the contractor to speed up his progress
continuously even if he hasn’t brought remarkable change. The contractor
The major impacts that have come out from the project being delayed are:
• It significantly affects the economic development of the country since
it interconnects the western part of Ethiopia with the central part for
exchange of raw materials and finished goods.
• It also affects the users’ benefit that will be obtained if it has been
completed on time.
It is clearly evident that the project has been delayed due to design
changes, contractor’s lack of experience that resulted in improper planning,
lack of coordination, lack of control, failure to allocate skilled manpower and
failure to manage its plant and equipment. Employer’s failure to remove
obstruction has also contributed to the delay. Due to such reasons
employer’s needs, economical development of the country and social
benefits of the society have been greatly affected.
The construction contract for the works was awarded to M/S SINOHYDRO
Corporation of china, (as the contractor) by the Ethiopia road authority, (the
employer). The consultancy service, (as the engineer) was awarded to M/S
RITES LTD of India in association with M/S UNICONE PLC.
The project commencement date was 22 August 2004 and the original time
for completion was 22 February 2008 with a contract period of 42 months,
plus one year defects liability period. The contract was financed with a loan
from the International Development Association (IDA).
The scope of the work includes widening, strengthen and upgrading of the
existing bituminous surfaced road to improve riding quality, strength and
safety. The designed road will have a two-lane asphalt concrete
carriageway of 7m width and 1.5 wide shoulders on either sides in rural areas;
and 7m wide carriageway with 2.5m paved shoulders on either sides in urban
area. The pavement shall consist of 50mm asphalt concrete wearing course
and 200mm crushed base course and variable thickness of sub-base, which
is to be constructed above the existing bituminous surfaced road bed or on a
well prepared sub grade and/or a 200mm thick capping layer in areas
where expansive soil is anticipated to be encountered.
minor maintenance of the diversion road have been progressed b/n 3+000
and 58+000km up to the end of May 2006.
A variety of factors in an ongoing project can lead to delay. The main causes for
the progress to be delayed mostly happen during the construction phase. The
contractor is identified as the major cause for the delay of the progress of the
work, due to the following reasons:-
• Lack of experiences in road projects
• Failure of pre-tendering planning
• Failure to mobilize plant and equipment at right time
• Failure to allocate skilled project manager
• Failure to allocate skilled technical and clerical staff
members
• Failure to hold realistic work plan and schedule
• Poor project management
• Lack of awareness about the specification during
tendering
• Shortage of construction materials (especially cement)
and plan, and how to control the project. As a result the project has failed to
go as per the schedule.
But the contractor did not identify the above information in detail before
tendering. The problem happened due to insufficiency of time for
preparation and submission of bid by assessing the real conditions that exist
on the site. Accordingly, the contractor encountered different physical
conditions (such as differing soil conditions) during construction, which
affected the progress of the work. However, if he had identified the problems
in pre-tendering planning stage, he would not have faced these problems
and the progress would not have been affected this much.
The engineer had given instruction to the contractor to assign skilled project
manager; accordingly, the contractor substituted the project manager two times,
even though the problem is not completely solved yet. Hence, the rate of
progress was greatly affected due to this cause.
In this project no major problems occurred by the side of the client except
minor errors, such as: -
• Unclear bid evaluation criteria
• Problem in site possession
4.3.4.4. Causes of delay due to reasons outside the control of the parties
Because of the way construction works are carried out, there will be many
occasions when delay occurs due to circumstances beyond the control of
either party. Surprisingly in this project no force Maguire, exceptional adverse
weather conditions, and government legislation change happen. Except
little civil commotions, this didn’t affect the progress significantly.
Early completed road projects are necessary for economic, social and
political reasons. The primary purposes of constructing roads are to
contribute to the overall economic development of the country by providing
access to economic potential areas, providing access to economic and
strategic areas, like ports and reduction of vehicle operating and
maintenance costs etc…And, also one of the ultimate impacts of the delay
of the project progress in terms of social aspect is the long distance people
travel and the time they spent increase.
The most significant effect lays on the economy of the country in such a way
that raw materials from the farmer and finished products from out side can
not be transported easily, increased wastage of scarce recourses such as
material, workman ship, equipment, and financial recourses and
Causes of delay
Project
Consultant Out side the
Contractor Owner
parties
A lot can be said about each party’s draw back not to enhance progress.
But the above problems are the main reasons that are affecting the progress.
Hence the contractor needs to restructure its’ staffing with the objective of
formulating a management team that is capable of planning, directing, and
monitoring the project. The consultant should approve drawings timely, give
instructions in written form and avoid giving erratic instruction and the client
should also remove obstruction before the contractor commences any work
on that area.
Construction of the ordinary fill and/or sub grade, sub base, base coarse,
prime coat, diversion road have been progressed at various chainages and
construction of minor drainage structures have been undertaken through the
finished surfaces.
The physical progress for permanent work has been delayed considerably
when compared to the work program .As per the work program the progress
has to be 50% at the end of May 2006 but it is only 30% of the work that has
been progressed. This figure shows that the project is lagging behind the
schedule by 20%.
It was tried to find out the reasons for slippages from the planned program
both from the contractor and the consultant, and is summarized below as
follows:
The three parties involved in the project were interviewed and the following
findings were obtained.
c) Lack of control
Project progress is not monitored, as there is no effective control system. Had
there been such a control system, improvements in the day-to-day rate of
progress could have been observed. Contrary to this, the project is
experiencing slippage, which is accumulating every month.
Both the contractor and the consultant addressed that the project has been
delayed significantly due to the employer’s failure to remove obstructions
and give the site. The contractor has requested the employer to acquire
borrow pit and clear the right of way. But the employer has delayed to give
the response. Due to this the project has been delayed.
a) Design problem
The original design states that at the ends of the chainages the under ground is
full of hard rock which requires explosion but actually there is no need to use any
explosives since the surface doesn’t compose it.
a) Civil commotions
The residents in Negele have made civil commotions resulted from request of
compensation for their land being taken by the government. And it has been
settled through negotiation and giving compensation. This process has taken
lot of time for being resolved as a result the project has delayed.
c) Market instability
Due to materials market instability the contractor’s cash flow program has
been affected and as a result, the progress of the work has been affected.
Most of the Ethiopian people are not aware about how many days they
should work in order to develop their country. The misunderstanding on their
religion rule was the main factor not to work the whole working days. The
contractor prepared the schedule by considering all working days are
useable for work but the society only worked those days, which are free of
their cultural influences.
Causes of delay
Project
Consultant Out side the
Contractor Owner
parties
• Lack of proper • Design problem • Failure to • Little civil
planning • Delay in approval remove commotions
• Lack of coordination of drawing obstructions and • Adverse
• Lack of control give the site weather
• Lack of proper site condition
Dera-Chole- organization
Magna • Market
• Failure to attain the instability
specification
• Delays in mobilizing
resources
It is clearly evident that the project has been delayed due to contractor’s
lack of experience, poor managerial practice, in addition to little adverse
climatic condition, poor working culture of the society, delay in approving
drawings by the consultant, lack of skilled man power in the area and
employers failure to remove obstruction. Due to the effect of these causes on
the progress, the economical development of the country and social
benefits of the society have been greatly affected indirectly.
• The contractor should avoid opening too many fronts beyond his
capacity.
• The consultant should approve drawings on time
• The employer has to remove obstruction and give the site to the
contractor at the right time.
• Poor working culture on the society should be improved
Among the many completed road projects that were under taken through
ERA, two of them are selected for the case study. The selection of the
projects is based on the availability of the projects data. The background
data and primary information of these projects are given below. The causes
of delay, contractor’s extension of time claims and the engineer’s
recommendation are discussed in detail in the discussion part of this chapter.
5.2.2. Findings
Table 5.1 summery of extension of time claims for Modjo- Awash road project
Reasons giving rise The contractor’s
Causes of The Engineer’s
No to extension of time Extension of time
claim recommendation
claims claims
1 Variation Replacement of 212 days 124 days
overlay with
reconstruction
2 Variation New bridge work 388 days 388 days
3 Variation Construction of 631 days 12 months
road through
Nazareth town
4 Unforeseen Shortage of hard 638 days Nil
circumstances rock
5 Employer’s risk Site security 20 working days 7 days
problem
The contractor submitted over seven issues that were directly related to time
extension. Out of this time extension claims the contractor was granted 635
days. This amount is 91% of the original contract period. Each time extension
claims is discussed briefly as follows:
b) Due to the construction of a new bridge across the Mermersa River, The
contractor claimed for as extension of time under the event of (a) the
amount or nature of extra or additional work, sub-clause 44.1 of the
conditions of contract. Due to this the contractor for the execution of the
additional work claimed for an extension of time of 388 days. The
engineer found that the contractor’s extension of claim was fair. And
therefore; the engineer extended the completion date of the project due
to this variation ordered by 388 days.
c) The contractor was ordered to suspend the initiation of any work on the
road section through Nazareth town. This is done to work out a revised
design for the road in this urban area. Accordingly, the contractor
claimed an additional 631 days for completion. But the engineer
determined the time for completion of the works under the variation order
to be 12 months.
warning as regard to the varying and mixed nature of the rock along the
project road and in particular to the rock in potential quarries. According
to the conditions of the contract, the contractor is required to inspect and
examine the site and its surroundings, and to apply his own professional
knowledge in making his interpretation of the presented data and
drawings just to verify the presence of the quarries is not adequate to fulfill
the requirements of sub-clause 11.1 of the conditions of contract. As a
result, the contractor’s claim for extension of time due to shortage of hard
rock for the production of asphalt aggregate was rejected.
f) The war between Ethiopia and Eritrea was alleged to have affected the
progress of the critical activities due to non-availability of trucks for
transportation of bitumen and spare parts on site. Accordingly, the
contractor claimed an extension of time of 7 working days due to the
effect of the war on the basis of sub-clause 12.2 (a) (adverse physical
obstructions or conditions), sub-clause 20.4 (a) (i) (Employer’s Risks) and
sub-clause 44.1 (b) (Extension of time for completion). But the engineer
assessed the case and he didn’t get documents that assured that the war
affected the progress of the critical activities. Accordingly, the
contractor’s claim for extension of time was rejected.
g) The engineer informed the contractor that he, in the joint asphalt
laboratory, had tested the penetration of a consignment of 60/70
bitumen delivered to the project and the penetration test failed to
comply with the requirement. As a result, the consignment was rejected,
and the engineer had instructed the contractor that no bulk delivery
should be discharged into storage tanks without completion of
penetration tests carried out by the engineer’s staffs. The contractor
alleged that the engineer’s instruction had delayed the work. Accordingly
the contractor claimed an extension of time of 20 working days. But the
engineer assessment indicated that no delay to the works happened.
Hence the claim was rejected.
Financier……………………………….Inte
rnational Development Association
(IDA) and the Government of Ethiopia
(GOE)
Contract signing date……………. 13 May 1999
Contract commencement date…. 4 June 1999
Original time for completion……… 03 December 2001
Contract price……………………ETB188,084,957.20 (payable in the
proportion of: 30% Ethiopian Birr
and 70% US Dollars at fixed
contract exchange rate of
1US$=ETB7.572)
Actual completion date……………..28February 2005
5.3.2. Findings
The contractor has formally submitted the under listed eight applications for
extension of time for completion.
Table 5.2 summery of extension of time claims for Hirns Kulubi road project
The engineer has carried out an assessment of the contractor’s claim number
EOT 3, for an extension of the time for completion of the work due to alleged
failure of the employer to give possession of site. And has considered that the
work of the contractor has been disrupted because of delays in land
acquisition procedures, and hence recommended extension of time of 113
days in this respect and associated cost of ETB 4,147501.00.
The extra/increase in quantity and additional works, which are treated, for
time extension are stated in table.5.3
Contract Estimated
Item Description Unit Variation %
Qty Qty
Considering this the contractor has requested 597 days but the engineer
after assessing the contractor’s claim under this head has recommended
only 12 days, because these claims were not substantiated by the engineer.
EOT no.5 crushing of natural gravel for the lower sub base
The contractor contended that the requirement to construct lower sub base
was not covered by the technical specification and that, the requirement to
crush any oversize component of the natural gravel being used to construct
lower sub base should be regarded as a variation and should be subjected
to additional time of 539 days for
• Time required to import crusher and ancillary equipment to
commence the variation of work that is start, at full swing, the crushing
of material for the lower sub base works.
• Time required to crush 159,596 M3 of material for the lower sub base
works.
Item 3.1.1 of the technical specification clearly states: the maximum
allowable size for sub base shall be 40mm. As the materials encountered in
the existing borrow location has a natural grading exceeding this size, the
material shall be screened and oversize material shall be crushed and mixed
in. That is, before submission of his tender, the contractor was aware of
crushing of oversized sub base material acquired from borrow locations.
Hence, the engineer decided that the contractor is not entitled to any
additional time and payment in this respect.
The engineer has rejected the contractor’s request of payment for shoulder
with rate of ETB 159.04 per M3, and continued to certify payment the same
with a rate of natural gravel sub base rate, which is ETB 22.32 per M3. And
also has addressed that the contractor is not entitled for any additional time
since he was aware about the material during tendering.
Delays that occurred during the construction stage of the projects could be
attributed to causes from both during pre-construction stage and the
construction stage. According to the result of the case study of the two
projects, the predominant cause of delay is variation ordered. From the total
causes of delay that happened in the projects, variation order take more
than 32% of the total causes. Excessive variation order could be minimized or
reduced by improving performance during design stage and contract
document preparation process of the project. Variation order and change
of design are the result of deficient design, poor contract document
preparation (i.e. specifications) and undefined project formulation works that
could be improved during design stage and project development stage.
Variations ordered have been the frequent causes of delay for the two
projects. It is the result of inadequacy of the design works carried out by the
design consultants that caused this fundamental change of order. Adequate
site investigations at the design stage are also essential for the design
consultants to produce optimum design solutions for the projects.
Like variation order, employer’s risks that can be attributed to; site security,
war, failure to give possession of sites, and strikes are the pre dominant
causes of delay for the projects. To avoid right of way problems, the
government and private institutions should create awareness in the society to
facilitate right of way issues before the start of execution process.
According to the site visit interview and the case study survey data, the
following impacts of delay are observed. Of all projects surveyed in this study,
none has been completed on time. Rather all of them have been granted
time extension. Even though the impacts of delay in road projects are many
and diversified, the major ones are discussed bellow:
1. Financial impact to the parties
2. Economical impact on the country
3. Social impact
4. Environmental impact
5. Political impact
The most significant impact of delay in the projects has been financial
impact. For instant in Modjo-Awash and Hirna Kulubi projects, there have
been financial claims related to delay of the projects. If delay could have
been avoided, it would have saved a significant amount of money for the
employer. When projects are not completed according to the scheduled, it
would affect the parties financially.
When the contractor delays the project, he will incur additional cost as a
result of the extended duration of the performance. The additional costs
incurred by the contractor due to delay of projects include:
If roads are completed according to the time frame work, they will enhance
movement and accessibility of the people, who are living along the roads.
Due to this the economy of the people served by this road would be
improved, and then their contribution to the over all economy of the country
will increase.
These and others impacts have direct relation to the overall economy of the
people and at the same time the GDP of the country.
In addition, the effect of transmitted diseases like HIV and STD on the people
who are living in the projects areas would be high as the duration of the
projects increases. Because it is common among construction crews to find
that a high proportion of the young workers have been exposed to and
affected with such diseases. The risk of transfer to the society is similarly high.
Indirectly all the above-mentioned impacts have a direct relation ship with
political impact. When projects would not complete on time, the attitude of
the people to wards the government would be negative. Accordingly it
might have an effect during election.
Since the country is divided in to many regions, delay of road projects on one
of the regions may initiate people to think of it negatively. As a result it would
affect the country’s political integrity.
This chapter is aimed to see into the findings of the study and accordingly
give recommendations to minimize occurrences of delays and their impacts
in road construction projects. A survey of contractors, consultants and owner
was conducted to assess the causes of delay, their impacts and the party
responsible for the delay. It was found that all projects have experienced
delay. Time extension was requested by the contractors in all of those
delayed projects, and the extension were approved partially or completely
in most of the delayed projects indicating a partial assumption of
responsibility by the owner or at least that delays were excusable. This
indicates that the factors that have gone in to deciding the project
completion time limit may not have been realistically estimated.
7.1. Conclusions
The study indicated that delays in the road construction projects occur partly
due to events that arise from the pre-construction activities. The analysis of
the data collected appears to show that the pre-construction events leading
to delay of projects are attributable to the project owner (ERA) and
consultants.
The study has discovered that delays caused by pre-construction events due
to the failure of the consultants are mostly related to design problems, bill of
quantities, preparation of drawings and specifications, tender and bidding
document preparation and process of tendering.
Site surveys that are commonly required at bridge sites, major culvert sites,
earth-retaining structures, etc. were not properly conducted. This insufficient
site survey has necessitated the construction of new bridges and culverts and
resulted in potential claims for time extensions and cost compensations.
showed that the prepared bill of quantities did not itemize the works in
sufficient detail distinguishing between the different classes of works. Works of
the same nature carried out in different locations or in other circumstances
which may give rise to different consideration of cost were not properly
distinguished. The difference between the actual quantity observed on the
site and what was on the bill of quantity has caused delay in performing the
works and hence entitled the contractors time extensions according to
clause 44.1a of FIDIC 87.
The study indicated that the majority of delays in the road construction
projects occur due to events that arise during the implementation stage. The
analysis of the data collected appears to show that the construction stage
events leading to delay of projects are attributable to the three parties
involved in the projects (owner (ERA), contractors and consultants).
The client delayed completion of the works in various ways. Among these,
delay to remove obstructions and provide the ‘right of way’, change of mind
during construction and ordering extra works are the major ones.
One of the major findings of the study is the ‘rights of way’ and site handing
over problems. All the projects analyzed in this study have experienced this
problem making it a prime claim point for extension of time and cost
compensation. The lack of coordination of the removal of obstructions that
belong to the different private and government agencies has been
significantly the risk of delay. This appears to stem from inadequate
understanding of the requirements of the contract, and the impact it may
have on the overall project execution. As this process is the exclusive
responsibility of the Client, the contractors are entitled for time extension and
cost compensation.
The study also indicated that the Client orders additional works that are not
found in the original documents. Acceleration of subsequent site activities in
case of delay to make up for the lost time due to variation orders has
frequently failed due to deficiency in client’s project management
procedure. In this regard, continuous issues of design information/variation
orders by the client often frustrate the acceleration process.
The contractors carrying out the construction of the projects lack experience
in road construction projects even though they have experience in
construction of other public works like Water Works and Rail Ways. Due to the
lack of practice in road construction sector, they do not properly mobilize the
right resource at the right time and location, and their limited know-how of
the sequence of activities has been the problem in preparing realistic work
plan and schedule.
Lack of skilled project managers is found to be the other main problem for
the contractors which make them unable to achieve desired targets. They
lack experienced and professional project managers to plan, direct and
control the overall activity of the projects, and as the result time and
resources are being wasted without giving desired results. Generally, lack of
skilled project managers has affected the timely completion of the projects
due to the occurrence of communication gap at various levels, lack of day-
to-day decisions to fill procedural gaps, and absence of cooperation among
staff members.
In some cases a situation may arise at the construction site where immediate
instruction is necessary. In such instances the resident engineer should
prepare formatted written instruction whether to continue the work or
suspend it. This study revealed that, sometimes the engineers lack
confidence to give written instructions to relieve themselves from the
responsibility. This has affected the progress of the work in the projects.
7.2 Recommendations
Based on the analysis and the findings of the study, the following
recommendations are forwarded. The recommendations are aimed at the
government institutions, running professional engineers as well as practicing
professionals and consultancy firms with the view of minimizing the causes of
delays and their impacts.
the road and with the values, resources, and risks associated with the
project.
All pre bid information shall be all inclusive, detailed and exhaustive as
regard to customs clearance regulations, work permits by the different
authorities, availability of construction materials, labor related
information and other legislations. It is necessary to prepare a detailed
information bulletin that needs to be issued to all contractors as part of
the bid document. Such information availability will assist contractors to
weight their risks and hence price and program their bids
appropriately, there by minimizing the risk of time and cost overruns.
This does not mean, however, that contractor’s do not have to
Further research work on more delay and related cases are suggested
and arranging forums of discussion among parties in construction
sector is crucially important to save public money and upgrade
professional commitments of those involved in the construction sector.
APPENDIX
INTERVIEW QUESTIONS
16. For what types of delay claim for liquidated damages were requested
and approved?
17. What are the possible impacts of the delays?
In terms of economical development of the country?
In terms of social benefits?
Politically?
18. Are there any claim raised by either party in relation to delay?
19. What actions have been taken to avoid delays?
20. When do you think the project is completed?
REFERENCES
[1] Reginald M. Jones, Tom Driscoll, Jon T. Flynn and Don Fredlund;
Construction Delay, Acceleration, and Inefficiency Claims; Course for
In-House Training, 2006.
[2] Robert Palles; The Value of Critical Path Analyses in proving Delay
Claims; Construction Low Review, 2002.
[5] Gillian Birkby and Paul Brought; extensions of time explained, 1993.
[11] FIDIC; Guide to the use of Conditions of Contract for works of Civil
Engineering Construction, 1997.
[21] John W. Ralls; How to Avoid Delays and Delay Claims, 2006.
[32] Derege Kidane; Contractors Entitlement under ‘FIDIC 87’ and ‘FIDIC
99’ eace bulletin vol. 5 no. 1, pp. 37-45, 2003.
[37] Ismeal Ibrhim, construction laws, codes and standards, February 2006