You are on page 1of 4

Doc No KS-WI-RD-02-03-FAT

Initiation Date January 19, 2023


Revision 0
PT. KOROSI SPECINDO Revision Date -
Jl. Pangeran Jayakarta No. 76 Page 1 of 4
Jakarta 10730

FACTORY ACCEPTANCE TEST PROCEDURE

PROJECT NAME :-
CLIENT :-
END USER :-
QUOTATION NO :-
PO NO :-

1. Scope:

This procedure is used as Factory Acceptance Test procedure for:


- DCI Datalogger (DCI-Dx)
- DCI Transmitter (DCI-Tx)
The requirements included in this procedure are safety, test equipment, test preparation, test
procedure and acceptability.

2. References:

• KS-WI-RD-02-03 : DCI Inspection & Testing


• KS-RND-MNL-03/04/05/06/07/08 : Inspection & Operation Manual
• Manufacturing standard

3. Safety:

a. Wear personal protective equipment during the test preparation and application
b. Make sure that test equipment still has valid calibration

4. Test Equipment:

a. Function Test:
• IOM / Manual
• Power supply
• Probe types: Dummy test probe, specified probe with the PO or at least manufacturing
calibrated tubular and flush probe
Doc No KS-WI-RD-02-03-FAT
Initiation Date January 19, 2023
Revision 0
PT. KOROSI SPECINDO Revision Date -
Jl. Pangeran Jayakarta No. 76 Page 2 of 4
Jakarta 10730

b. Reading test:
• KSHHU (Portable hand held unit)
• Multimeter
• HART communicator / HART modem / 4-20mA display

5. Function & Reading Test:

5.1. Function Testing: Also refer to the Client’s specification, whether any additional feature for
difference with the standard product (example: Corrosion rate display, 2 wire system
transmitter, etc).
Datalogger:
• It shall communicate with KSHHU for configuration setting. For overall menu please
refer to IOM of DCI-Dx
• Test with dummy probe hourly for readings for 3 hours, and all readings must be within
specification of reference Sample and Check value.
• Test with probe that include in PO/WO with interval 5 minutes, and all Metal loss data
must be within spec (shall be no negative value) and specified interval time.
• Test with capability to save all 4000 data
• All data must be able to transfer to KSHHU
• For datalogger that has transmitter function, they shall be checked with output of
corrosion meter and dummy with different readings

Transmitter:
• Test loop with using Fluke 709H, ex test 4 mA fluke 709H must measurement 4 mA and
display showing loop current 4 mA and metal loss 0.00
• Test with probe that include in PO/WO, and all Metal loss data must be within spec
(shall be no negative value)

5.2. Reading Test


It shall be checked with output of corrosion meter and dummy test probe with different
readings (can select from optional probe type below as per intended probe application)

For LPR, it shall read as corrosion rate mentioning in LPR dummy test probe supplied along
with each DCI.
Doc No KS-WI-RD-02-03-FAT
Initiation Date January 19, 2023
Revision 0
PT. KOROSI SPECINDO Revision Date -
Jl. Pangeran Jayakarta No. 76 Page 3 of 4
Jakarta 10730

6. Acceptability:

It shall have feature as mentioning in IOM and also value reading as listed in 5.2

7. Factory setting before shipment

a. For datalogger, it will be set from manufacturer with Tag name: Serial Number, with
interval 1 hours
b. For transmitter, there is no specified initial set. Customer will need to configure
transmitter before usage.

Prepared by Checked by Approved by

Fatima Ananda Zara Al- Bambang Untoro Juli Supriyanto


Ansory
(Operational Engineering) (QC Manager) (Engineering Manager)
Date: January 19, 2023 Date: January 19, 2023 Date: January 19, 2023
Doc No KS-WI-RD-02-03-FAT
Initiation Date January 19, 2023
Revision 0
PT. KOROSI SPECINDO Revision Date -
Jl. Pangeran Jayakarta No. 76 Page 4 of 4
Jakarta 10730

App.1. Summary form of Datalogger/Transmitter inspection Form

Data Logger Serial/Tag


Sr.No. Reading Status Remarks
No.

1. OK Not OK

2. ☐ ☐

3. ☐ ☐

4. ☐ ☐

5. ☐ ☐

Sr.No. Transmitter Serial/Tag No. Reading Status Remarks

1. OK Not OK

2. ☐ ☐

3. ☐ ☐

4. ☐ ☐

5. ☐ ☐