Professional Documents
Culture Documents
KS MNL ENG 01 02 (Corr - Monitoring)
KS MNL ENG 01 02 (Corr - Monitoring)
KOROSI SPECINDO
Corrosion Monitoring Systems
Engineering Doc. No.:
KS-MNL-ENG-01-02-Rev0
SECTION I
ACCESS FITTING INSTALLATION
I. Introduction
This procedure covers the positioning Flanges and welding of the Korosi Specindo‘s
Flarweld, Buttweld, Socketweld and NPT access fitting to the wall of pipe or vessel.
See fig 1.
1) Set the fitting on vertical position with the top (ACME thread end) up. Other
axial orientations may be specified for the location, consult the project
documentation before installation. Ensure that there will be adequate clearance
above the fitting to operate the retriever, as follows:
5) Where the mounting is placed vertically below the line or vessel, a 4‘‘ (1.2 m)
minimum diameter working space must be provided. The fitting to be off center
1‘ (300 mm) from the edge of the area at the closest bottom point and 3‘‘ (1 m)
at the farthest point.
KS-MNL-ENG-01-02-Rev0 Page 1 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
1/16‘‘ 1/16‘‘
FLARWELD BUTTWELD
A/F A/F
1/16‘‘ 1/16‘‘
When installing flanges, suggestion sequence for tightening flange bolts as shown in
fig. 2. To provide even sealing pressure on the flange gasket,
1 the bolt should be traverse hand tightened according to the
5 8 sequence until the flange faces are in contact with the gasket.
Then firmly tighten the bolts in the same sequence.
3 4
3 Note: ―Hot Flow‖ of gasket material may occur operating
conditions. Resulting in loss of bolts pressure. Bolts should be
7 6 retightened after operating temperature has been reached.
7 2
2
Fig.2. Flange Bolts
KS-MNL-ENG-01-02-Rev0 Page 2 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
5. Observe the operation, to make sure the foregoing conditions is followed during
performance of the job operation.
6. If hot tapping, determine the capabilities of the hot tapping machine. Hot tapping
tools are limited to use within their pressure and temperature ratings.
1. Ensure the correct equipment or line has been selected to be welded or hot
tapped.
6. Determine the proper fitting for use in making the connection. Korosi
recommended use a Flarweld or Buttweld. Because they only require only one
weld, thus reducing the changes of distortion and warpage. Also more efficient in
time and money.
KS-MNL-ENG-01-02-Rev0 Page 3 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
7. Design the connection, according to the proper code ASME Boiler and Pressure
Vessel Code or API Standard 650, Welded Steel Tanks for oil storage, ASME
B31.3 Chemical Plant & Refinery Piping.
1. The Korosi Specindo plug must be removed from the fitting during welding and
stress relieving operations. The body must be inspected to ensure that there has
been no damage to the external Acme thread, the upper shoulder and lip of the
fitting, the internal thread or internal seal shoulder during its shipment. If damage
is found the fitting must be replaced.
2. The external Acme thread and upper shoulder of the fitting must be protected
from weld spatter during welding. Wrap heat resistance cloth around the external
Acme thread and stuff the bore of the fitting with a retrievable wad of heat
resistant material to a point just below the internal seat. This is to prevent weld
spatter onto thread and seal areas.
3. The internal thread and internal bore below and the internal shoulder must be
protected from weld spatter during welding.
4. The welding procedure should be designed so that the upper portion of the fitting
temperature does not exceed 1000 oF (540 oC) during welding. Higher
temperatures encountered during stress relieving are acceptable.
d. Welding Process
2. Weld Gap, Korosi Specindo Access Fitting body or connecting fitting must be
raised off the surface of the pipe or vessel wall to establish a proper weld gap.
This can be done by placing four (4 ea) 1/16‖ (1.6 mm) spacers or rods under the
fitting to provide the proper gap between the curvature of the pipeline or surface
of the pressure vessel wall and root or base of the fitting. Normal weld gap is
1/16‖ (1.6 mm) per ANSI B31.1. 1973.
3. Arc welding should be used if at all possible for all grades and types of steel.
Because this will minimize warpage and distortion of the Access Fitting body
cause of its localization of concentrated heat. Care should be exercised so that
the body is properly positioned to prevent misalignment of the hot tapping tool is
used at a right angle or perpendicular to the work area. Also, avoid excessive
arcing because arc spots on the body can cause stress and consequently body
warpage while cooling. Recommended procedures for welding and special hole
cutting considerations for various metals as follow:
a. Carbon Steel
1) Tack Weld. Preheat the fitting to 315 oC (600 oF). Tack welds the fitting to
the line between the spacers using 3 mm (1/8‖) welding rods. Remove the
spacers and weld slag from the tack welds.
KS-MNL-ENG-01-02-Rev0 Page 4 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
2) Stringer Bead. Apply a stringer bead completely around the base of the
fitting using 3 mm (1/8‖) diameter rod for 3 mm maximum layer. Remove
weld slag.
3) Cover Beads. Apply continuous cover beads to fill the bevel and provide a
smooth tapered weld.
b. Stainless Steel
Do not preheat!, otherwise; use the same procedure as shown for carbon steel
with the following considerations:
1) In the hole cutting procedure, a hollow drill or drill bit should be used to cut
small size openings. Abrasive cutting wheels are generally used to make
larger sized holes.
2) Arc cutting or injections of iron powder into an acetylene flame are other
methods used. If however, any of these flame or arc method are used, the
hole should be cut under size ¼‖ (6.5 mm) on the diameter to allow for
removing the heat affected areas by grinding before welding.
3) Either the heli-arc (electric arc) or metallic (TIG and MIG) methods may be
use for welding. The sequence of welding passes for both alloy and
stainless is the same as outlined for carbon steel.
1. The post-heat and cooling period must be in accordance with relevant welding
procedures and engineering standards.
2. Inspect the external ACME thread to ensure it is free from weld spatter. If there is
any weld spatter it must be carefully removed by chipping and filing.
3. Inspect internal (UNF) thread, internal bore above seat and internal seat to
ensure it is free from weld spatter. If there is any weld spatter it is recommended
to use a thread tap assembly to repair/clean the threads or use a seat reamer for
reaming the bore and seat.
4. Inspect the internal bore of the body below the seat, the interior surface of the
weld area and the internal surface of the hole through the pipe or vessel wall.
These surfaces shall be ground or reamed as necessary to ensure a full ID of
1.377‖ (35.00 mm). Care must be taken to eliminate any damage to the internal
thread, bore and shoulder during grinding operations.
5. A hydrostatic test must be carried out. (Normally 1-1/2 time line pressure)
KS-MNL-ENG-01-02-Rev0 Page 5 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
shoulder of plug (below the hex nut) is flush with top lip of the fitting (15 turns
(360o ) of plug), If the plug is tight, the fitting may have been distorted during the
welding process and the internal threads must be chased with the correct thread
chaser. After chasing, if the plug still cannot be inserted easily, the fitting must be
blanked – off and a new access fitting point installed at another point.
f. General
1. When the installation has been completed and a hollow plug is to be installed,
the probe or bore-sealing nut provides the pressure barrier. The use of a
stainless steel ½‖ NPT plug is not recommended.
1. Cleaning internal threads (UNF) by using a thread brush (refer to section V. IV. E
Special Procedures for Access Fitting)
2. Cleaning and repair seat seal plug on the access fitting by using a Seat Reamer
(refer to section V. IV. E Special Procedures for Access Fitting)
3. Cleaning and repair internal threads (UNF) by using a Thread Tap Assembly
(refer to section V. IV. E Special Procedures for Access Fitting).
4. Grease external thread (ACME)
5. Check access fitting face up end (O-ring seat Protective cover) for scratch, use a
smooth sand paper and bastard to repair.
KS-MNL-ENG-01-02-Rev0 Page 6 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
SECTION II
HOT TAPPING
I. Introduction
This procedure describes Hot Tapping work to ensure the safety of personnel,
plant and equipment during Hot Tapping operations. Hot Tapping is defined as
using an under pressure drilling machine to cut a hole in an operating pipeline
allowing for a new take off from the original pipe. This process should be done
without any product leakage or loss. Hot tapping can be proceeding after NDT and
or Hydrostatic test has been conduct.
II. Safety
a. Personnel
1. Safe operation requires minimum 2-trained operator.
2. Test and check should be done to all equipment before attempting to use in field.
3. Do not use this hot tapping equipment unless you have been trained in its safe.
4. Make sure you have complied with all plant safety requirements and
environmental regulations.
5. Identify the type media its pressure and temperature. Review material safety data
information on the media prior to operation.
6. Ensure you have all the required safety equipment and used, i.e.: protective
clothing, safety helmet, safety glasses, safety gloves, ear plug, safety shoes and
breathing apparatus when toxic atmosphere exists.
7. Insure you have enough clearance for safe operation; there must be sufficient
space available for head room as well as enough shoulder room to allow free
movement of the equipment as well as of the operator
8. Ensure you have scaffolding if the Access fitting that to be hot tapping is mounted above
the operator.
b. General
―Hot Tapping‖ is used to cut a hole in an operating line under pressure. This
method is only used when no other suitable means of accomplishing the objective
is available. All personnel concerned should be aware of the precautions to be
taken, which are:
All Hot Tapping work must be conducted under conditions of the Work
Permit System and the condition of such permits must be strictly adhered
to.
A Production Operation must be present during Hot Tapping work.
KS-MNL-ENG-01-02-Rev0 Page 7 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
Hot Tapping must also be avoided upstream of rotating equipment unless such
equipment is protected from the cutting by means of filters or traps.
III. Operation
3.1 Preparation
Re-checked all equipment condition before proceed the work.
Determine the condition of area.
Clean the area that is going to be weld or hot tapping.
Determine the wall thickness of the pipeline/vessel before conducting any
welding or hot tapping (Do Not weld if less than 3 mm according to
manufacturer recommendation).
Ensure that after welding process there‘s no intrusive weld inside access
fitting, repair if any.
Pour cutting oil into access fitting body approx. 1‖ depth.
3.2 Process
The HOT TAP MACHINE is a manual feed machine. Clockwise rotation of the
feed tube extends the boring bar and counterclockwise rotation retracts the
boring bar. With the socket head set-screw tightened, turning the hex drive
clockwise both turns and extends the boring bar. One revolution of the hex
drive will extend the boring bar 1/8‖.
KS-MNL-ENG-01-02-Rev0 Page 8 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
NOTE: The socket head set screw is to be tightened only when operating
high pressure. Do not tap or drill with the set-screw tightened.
CAUTION:
When tapping, be sure you do not OVERFEED. 0ver feeding, and
underfeeding also, will damage the hollow drill or cutter.
Ensure that cutter do not interfere with ball of the service valve.
Measurement drilling depth must be made prior to hot tapping operation.
1. Connect the service valve to the fitting. Lift the service valve and place it on
the access fitting body. Turn the hammer nut clockwise until the service
valve is securely seated. Tap the hammer nut tight using a brass hammer.
The valve should be in ―OPEN‖ position.
2. Attach machine to service valve. Operate service valve to make sure it
opens and closes without interference from tip of cutter. Be sure valve is in
full open position before continuing to next step.
3. Begin Tap
Drive drill through service valve and access fitting until drill contact with
pipe surface. Determine measurement of drilling depth by using a caliper
and paint marker. Measurement drilling depth is defined by actual wall
thickness and added ½‖ than actual wall thickness (mark across on
measurement body tube). Connect air motor (if possible) or manual driven
by attach ratchet handle to 3/4" hex drive. While a ratchet handle is
furnished, best results will be obtained if handle is rotated 360° while
cutting. Turn clockwise only. The rate of advance for the hollow drill is
determined by the advance of the feed tube. Do not overfeed to prevent
damage to the cutter. Eight revolutions of the feed tube will lower the cutter
one inch. Rotate slowly during last inch of travel to prevent damage to the
tip of the cutter.
As pilot drill penetrates pipe wall, line fluid will completely fill valve, fitting
and adapter. Connect a diverter hose to release pressure and metal chips.
After all air is purged, CLOSE Bleeder Valve. Vent pressure bleed valve
away from work area and personnel in a spill container. Stand clear of vent
when bleeder valve is opened. Otherwise, personal injury may result from
blowing material. Each time cutter drilling approx. 5 mm release pressure to
prevent too much metal chips during hot tapping on hot tap machine.
4. Complete Tap
When second mark or lower mark (total travel distance) is reached on body
tube, tap should be complete. At this point, the feed tube should turn with
little effort. The "feel" and rate of feed confirm the tap to be complete.
5. Retract Cutter
By rotating feed tube counterclockwise, retract cutter until feed tube is at
the zero mark on body tube or until it comes to firm stop. If line is under
high pressure, it may be necessary to tighten the set-screw and retract the
cutter by using the ratchet handle.
6. Recovery Sequence
Close the service valve
KS-MNL-ENG-01-02-Rev0 Page 9 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
IV. Maintenance
The T KS6000 T-HT Hot Tap Machine has been designed for rugged service and
requires a minimum amount of maintenance. A reasonable amount of care will
keep the machine in top operating condition for a long period of time. Following are
recommendations for proper care and handling.
a. The exposed end of the boring bar should be protected when machine is not
in use.
b. Use an open end or adjustable type flat wrench on the two flat surfaces
provided when attaching the machine to a service valve or adapter hammer
nut.
c. After each use, clean dirt and foreign material from exterior of machine.
d. Care should be taken not to damage hex drive at top of machine.
e. Lubricate ratchet handle regularly with oil.
f. After each tap, inspect cutter holder for any damage.
g. Disassemble and lubricate each part every six (6) months or Twenty (20)
taps, whichever comes first, following the procedures.
h. High temperature tap — after each high temperature tap above 350° F, or
taps in corrosive fluids, replacement of packing is recommended. Procedures
for packing replacement follow.
i. The cutter holder and cutter are parts to be protected from corrosion by an oil
coating. These parts should be inspected regularly and recoated with oil
before storing.
KS-MNL-ENG-01-02-Rev0 Page 10 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
KS-MNL-ENG-01-02-Rev0 Page 11 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
SECTION III
CORROSION COUPON HANDLING
I. Introduction
This practice covers procedures for preparation, analysis and interpretation of Corrosion Coupons
in Oilfield Operation.
II. Equipment
Analytical balance with accuracy ± 0.1 mgr
Depth gauge
Microscope
Pitting Gauge
AAS / ICP
Titrator
Glass Ware
Digestion Sampler
III. Operation
3.1 During Installation
Preparation
Prepare coupon for corrosion testing.
Coupon should be new.
Do not re-used coupons after exposure and analysis.
Choose the method preparation of the metal
1. Open the envelope and take out coupon carefully. Avoid contamination of
coupon caused by contact with other materials, oil or chemicals.
2. Record the following information:
- Coupon serial number.
- Installation date.
- Name of system.
- Location of the coupon in the system (including fluid or vapor phase),
name of the platform, sketches the position of the coupon in the pipeline
(put all data on the Envelope), or take a picture of that location.
- See the typical corrosion coupon report from Envelope & Appendix A
3. Record the physical condition of pipeline such as:
- Dimension of pipeline,
- Fluid / water temperature,
- Pressure,
- Density,
- Viscosity
- Flow rate.
KS-MNL-ENG-01-02-Rev0 Page 12 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
Note : Coupon must not be handled with the bare hand, and
maximum cleanliness must be maintained during installation
and removal process. The use of surgical or rubber glove is
recommended while handling coupons.
KS-MNL-ENG-01-02-Rev0 Page 13 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
Normal life time for coupon wrapped properly in VCI Paper can remain protected
two years, for best result after two years storage coupon should be blasting.
KS-MNL-ENG-01-02-Rev0 Page 14 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
SECTION IV
INSTRUMENTS AND CORROSION PROBE
I. Introduction
This practice covers procedures for preparation, process of installation, Setting
parameter and Trouble shooting the DCI (Data Collection Instrument). Download DCI
is using KSHHU. Saving into file and making standard report or finding on the field.
II. Equipment
1. Fix Data Logger (DCI – Dx – ER/LPR – 01/04)
2. Transmitter (DCI – Tx – ER/LPR)
3. Portable Data Logger (KSHHU – ER/LPR)
4. Cable Communication and Connector
5. Electronics Tools set
III. Safety
1. Test and check should be done to all equipment before attempting to use in
field.
2. Provide a secure operation which requires minimum 2-trained operators.
3. Verify with Instrument Supervisor to determine where will be the most
appropriate and the closest location toward the Instrument Panel Complex
located.
4. Ask for an approved welder if you plan to mount DCI using Environment
Protection Box (EPB) structure to the existing or nearest location to Instrument
Panel Complex in Offshore.
5. Make sure that the users have complied all plant safety requirements and
environmental regulation procedures.
6. Also ensure that the user already has all of required safety equipments i.e.
protection outfit, safety helmet, safety glasses, safety gloves, ear plug, safety
shoes and breathing apparatus when toxic atmosphere exists.
IV. Operation
4.1 Preparation
1. Safety Procedure always ask for a person who will be in charged,
specifically as an Instrument, or Electrical, or Corrosion Engineer who will
take care your duty in the field during Installation DCI and other
accessories.
2. If you plan to protect the wiring between the Corrosion Probe and the DCI
or any related Instrumentation using Conduit for the first time or during your
field survey, always prepare Sketch Drawing or Draft on the notebook of
every length, position, and angle of direction. Make sure that the conduit
KS-MNL-ENG-01-02-Rev0 Page 15 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
3. During wiring process, do not cut any cable in a hazardous area if you are
not sure enough that the correct lengths of all cable for Instrumentation are
screened (armored) in overall length. So, you should not extent or make
any connection without Junction Box, except in Non Hazardous area.
Any extension or connection between two cables will result in unwanted
noise affecting the sensitivity of the signal and resulting in erroneous data
or malfunctioning of the monitoring system.
4. Always Test all of your Equipment before you move them to be installed on
the field. Prepare any tools required such as, spare ER/LPR probe,
extension probe, Probe Cable, Dummy Probe, Battery Pack etc.
5. Prepare Documentation and all Manual Book required in the field for having
Installation, setting parameter and Troubleshooting.
a. Using KSHHU-ER
1. Connect the DCI (Dx type) nine pin serial cable to the KSHHU
nine pin serial cable for hazard area (make sure that the battery
has been installed at DCI).
2. Turn on KSHHU and check the battery.
3. Press enter on standby menu display and select DCI setup
command from data logger setup display.
KS-MNL-ENG-01-02-Rev0 Page 16 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b. Using PC
1. Connect the DCI (Dx type) nine pin serial cables to the PC nine
pin serial cables in safety area (Make sure that your PC has
already installed KS-Corrosion Monitoring Software).
2. Open KS-CMS software application.
KS-MNL-ENG-01-02-Rev0 Page 17 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
4.4.1 PC Requirements
To run the Korosi Specindo Corrosion Monitoring Software (KS-CMS),
you need a PC that meets the following requirements:
Pentium® class processor
Windows® XP operating system
64 MB of RAM
20 MB of minimum available hard-disk space
lution
Mouse or pointing device recommended
Available 9-pin or 25-pin serial port (for instrument download)
CD-ROM drive for software installation (software available on 3.5"
diskettes by request)
KS-MNL-ENG-01-02-Rev0 Page 18 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
V. Mounting
DCI (Dx type) is mounted in field and equipped with Environment Protection Box
(EPB) to protect from environment disturbances such as sunlight, rain, wind or sea
breeze. Environment Protection Box (EPB) made from glass is filled with polyester,
for the application in harsh climates, Standard Enclosure NEMA 4X and IP66.
VI. Maintenance
KS-MNL-ENG-01-02-Rev0 Page 19 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
SECTION V
RETRIEVAL PROCEDURES
I. Introduction
This practice covers procedures for preparation, process of installation – removal
and safety consideration during retrieval corrosion coupon and probe.
II. Equipments
1. Retriever tools assembly
2. Service valve assembly
3. Mechanical tools set
4. Diverter hose assembly
III. Safety
a. Test and check should be done to all equipment before attempting to use in
field.
b. Safe operation requires minimum 2-trained operator.
c. Do not use this retrieval equipment unless you have been trained in its safe
operation.
d. Make sure you have complied with all plant safety requirements and
environmental regulations.
e. Identify the type media its pressure and temperature. Review material safety
data information on the media prior to operation.
f. Ensure you have all the required safety equipment and used, i.e.: protective
clothing, safety helmet, safety glasses, safety gloves, ear plug, safety shoes
and breathing apparatus when toxic atmosphere exists.
g. Any actions, which could vary system pressure such as surges, caused by
opening and closing of valves and chokes should be delayed until completion
of retrieval operations.
h. Insure you have enough clearance for safe operation; there must be sufficient
space available for head room as well as enough shoulder room to allow free
movement of the equipment as well as of the operator. Clearance beyond the
top of the access fitting body is required for installation and extension of the
retriever and service valve. The following recommendations should give
adequate clearance:
14-14‖ Stroke - 4.5 feet (1.5 meters)
18-18‖ Stroke - 6 feet (1.8 meters)
25-25‖ Stroke - 7 feet (2.1 meters)
34-34‖ Stroke - 8.5 feet (2.6 meters)
49-49‖ Stroke - 11 feet (3.4 meters)
For shoulder room above ground level requires 3 feet radius circle and below
ground level a minimum diameter of 4 feet is required with the fitting located off
to one side of the hole.
KS-MNL-ENG-01-02-Rev0 Page 20 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
IV. Operation
4.1 Preparation
Note: - Ensure by-pass service valve in ―OPEN‖ position.
c. Ensure bleed valve retriever and service valve in ―CLOSE‖
position.
a. Check condition of service valve.
Inspect the O-ring (18) at the hammer nut end for nicks, cuts and
abrading
b. Check condition of retriever.
Extend and collapse the retriever to ensure it‘s lubricated and operating
properly, check the condition of O-ring (25) at thread adapter.
c. Adjust the socket adapter assembly, for solid or hollow plug
assemblies the socket adapter should be set in the third and fifth holes
from the hex end.
d. Check pressure in pressure gauge in protective cover.
Note: If there‘s any indication pressure, release by opening bleed valve in protective
cover.
2. Remove the pipe plug ½” NPT. Use a crescent wrench to remove pipe
plug slightly counter clockwise.
Warning : If for any reason there’s pressure behind the plug, after
one or two minutes has not been bleed – off.
Loosen the steel pipe plug 1/8 turn more. If pressure
bleeds – off, remove the pipe plug; if it has not re – tighten
the plug and following the procedure of overshoot
adapter.
3. Connect the service valve to the fitting. Lift the service valve and place
it on the access fitting body. Turn the hammer nut (20) clockwise until the
service valve is securely seated. Tap the hammer nut (20) tight using a
brass hammer. The valve should be in ―OPEN‖ position.
KS-MNL-ENG-01-02-Rev0 Page 21 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
6. Connect the socket adapter pilot. Remove the locking clamp if installed.
Collapse or move the outer barrel (20) toward the access fitting body until
the socket adapter pilot (41) contacts the plug assembly. Do not allow the
socket adapter hex to engage the plug assembly hex. (A turning, sliding
motion – as opposed to a straight sliding motion. Turn the outer barrel
(20) clockwise to engage the socket adapter pilot (41) thread to the
female threads of the plug assembly.
7. Connect the socket adapter hex (37). Collapse the retriever outer barrel
(20) toward the access fitting body while turning slightly clockwise until
the socket adapter hex (37) slides over the plug assembly hex.
KS-MNL-ENG-01-02-Rev0 Page 22 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b) Pressure balance will begin after 4 to 5 turns of the outer barrel (20).
Pressurization should be signified by pressure gauge reading, hearing
the fluid enter the retriever or feeling the increase in friction as the
seals experience pressure load. When the retriever begins to de-
pressurize, stop turning the outer barrel (20) and wait for at least 5
minutes for the retriever and line pressure to be balance.
9. Retrieving the plug assembly from the access fitting body. When the
retriever has ―pressure – balanced‖ with the line, continue pushing on and
rotating counter - clockwise the barrel (20) for approximately 14 - 16 turns
to fully disengage the plug from the access fitting body. Ensure that the
socket adapter hex (37) and plug assembly hex remain engaged during
this operation.
10. After the plug assembly is removed from the access fitting body, fully
extend the retriever outer barrel (20) with a twisting and sliding motion
until the plug assembly is withdrawn. If looks like hard to extend the outer
barrel (20) ―Open‖ the bleed valve (4) ¼ turns.
11. Install the locking clamp onto the inner barrel (22) if the fitting is
mounted in a position that would allow the retriever outer barrel (20) to
collapse of its own weight.
12. ”Close” the service valve using the service valve extensions handle (7)
(if required). The pressure in the retriever is now confined.
Bleed the pressure from the retriever by opening the retriever bleed valve
(4) one or two more turns for gas line. Watch the pressure gauge, a
gradual drop to zero should be indicated, at which point the retriever
should have bleed-off pressure completely. An optional diverter hose
assembly is recommended when bleeding-off retriever pressure, fluids
can be collected in a container and gasses can be diverted to a safe area
away from the operator.
14. Close the bleed valve (4) and disconnect the diverter hose
assembly. When the retriever is completely de-pressurized, disconnect
the diverter hose assembly and close the bleed valve (4).
KS-MNL-ENG-01-02-Rev0 Page 23 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
15. Tap loose the retriever hammer nut (7) using brass hammer and
unscrew fully.
16. Lift the retriever to remove it from the service valve. Do this carefully.
If the product media is a fluid, a certain amount will ooze at the
disconnect junction or from the retriever.
17. Remove the locking clamp. If it was installed on the inner barrel (22)
and collapse the retriever.
18. Check for plug assembly retrieval. At the socket adapter (37) ends of
the retriever, check to see that the plug assembly was removed. The plug
assembly can be unscrewed from the socket adapter pilot (41).
19. Check retriever operation. Stroke the retriever (extend and collapse) if it
seems difficult to operate or feels gritty; rinse the internal with a solvent
(kerosene or varsol). Grease the inner barrel (22) and stroke the retriever.
If it still difficult to operate, feels gritty or friction, strip the retriever before
further use is recommended.
KS-MNL-ENG-01-02-Rev0 Page 24 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
RETRIEVER KIT
PRESSURE GAUGE
BLEED VALVE
SERVICE VALVE
SOCKET ADAPTER
PIPE LINE
b. Unscrew and remove the corrosion coupon (7) from the coupon
holders (5). See next standard procedure for handling of coupon.
c. Slack off the anti-vibration set screw (8) using a hex key.
d. Remove the packing nut from the bottom of the solid plug (2) (left
hand thread). Replace any used primary packing (4) and O-ring (3).
e. Replace packing nut with the coupon holder (5) and tighten. Use no
more than one-quarter turn against the primary packing (4) seal.
KS-MNL-ENG-01-02-Rev0 Page 25 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
g. Assemble the new coupon (7) on the coupon holder (5), ensuring that
the coupon (7) are completely insulated from the mounting screw (6),
nuts and coupon holder (5) by utilizing the insulation and mounting
hardware set (6) provided.
h. Make a mark across the hex of the solid plug (2) to indicate the
orientation of the coupon (7). Fluid flow must be across each coupon
(7) – not against the face of the coupon (7) (this procedure not relevant
to flush type coupon).
Note : Coupon must not be handled with the bare hand, and
maximum cleanliness must be maintained until the coupons
are inserted into the pipe. The use of surgical or rubber glove
is recommended while handling coupons.
KS-MNL-ENG-01-02-Rev0 Page 26 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b. Remove hollow plug nut (5) from bottom of hollow plug (1) if has
been installed. Replace any used primary packing (2), probe packing,
and set screw (3&4).
c. Screw the probe insert into the bottom of the hollow plug (1), first
checking that a new square section probe packing seal is fitted. The
probe insert must be tightened down very firmly (left hand thread). Steps
3 & 4 also apply when hollow plug nut (5) is fitted in place of a probe.
e. Replace the plug (1) and probe (6) assembly in the fitting as
described below. For majority of probe there is no requirement to
orientate the probe in the fluid flow. Some special probes Duo and Sand
for example, require orientation – consult the installation instructions
provided with these items. Ensure removal of all traces of moisture within
KS-MNL-ENG-01-02-Rev0 Page 27 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
the hollow plug and six – pin electrical connector. If setting an extension
adapter, makes certain that the key way is properly located before
pushing the pins into the sockets.
Notice : Rotation after the pins are located into the sockets can
cause irreparable damage to the probe.
KS-MNL-ENG-01-02-Rev0 Page 28 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
e) Apply grease sparingly to the full length of the thread on the plug
(only for Solid Plug), primary packing and O-rings.
2. Connect the plug assembly to socket adapter pilot (41). Engage the
plug assembly female thread to the socket adapter pilot (41) male
threads. Screw on the plug assembly to the socket adapter (37). Push the
plug assembly to check that the hex will engage in the socket adapter
(37).
3. Fully extend the retriever and if required install the locking clamp on the
inner barrel (22) and tighten.
4. Connect the retriever to the service valve. First, examine the O-ring (2)
at the hammer nut (7) end of the retriever and replace if nicked, cut or
abraded. Lift the retriever and place it on the service valve, turn the
hammer nut (7) clockwise until the retriever is securely seated and
tightened in place on the service valve. Use the brass hammer to tap a
secure connection.
5. Ensure that the bleed valves are fully “CLOSED”. Even though the
locking clamp may have been installed.
7. Open the service valve ball (12) and close the by-pass valve (27).
8. Remove the locking clamp from the inner barrel (22) and begin
collapsing the retriever. Use a twisting and sliding motion, until the plug
assembly just barely contacts the access fitting body.
KS-MNL-ENG-01-02-Rev0 Page 29 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b) Pull back the retriever to ensure that the pilot (41) has attached, and
then re-engage the hex.
c) If cross threading does occur, remove the retriever and service valve
strictly observing all of the procedures as outline in chapter V. B.
Removing Process. Attach the access fitting body tap assembly. See
special procedure for retriever.
11. Bleed the retriever. If the operational diverter hose assembly is being
used, it should be connected at this time. Open the bleed valve screw one
or two turns to bleed-off the pressure.
12. Disengage the socket adapter from the plug assembly. Disconnect
the diverter hose assembly, if used. Pull back the outer barrel slightly to
disengage the socket adapter hex. While maintaining this disengagement,
unscrew the socket adapter pilot from the plug assembly by turning
counter-clockwise.
13. Retrievers bleed – off. Extend the retriever fully. Open the retriever
bleed (4) valve and drain the retriever product pressure and media
residue into a container until all pressure has been relieved.
14. Loosen the retriever hammer nut (7) and remove the retriever. Using
the brass hammer. Lift the retriever from the service valve. Do this
carefully if the product media is a fluid because a small amount of product
will also drain from the connection.
15. Loosen the service valve hammer nut (20) and remove the service
valve. Using the brass hammer. Lift the service valve from the access
fitting body. Do this carefully if the product media is a fluid because a
small amount of product will also drain from the connection.
Orientate the plug assembly if required. The index mark filed as
mentioned above must now be aligned to the product flow direction. Turn
the plug assembly hex clockwise until the mark aligns with the flow
direction.
KS-MNL-ENG-01-02-Rev0 Page 30 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
16. Install the stainless steel pipe plug for solid plug assemblies.
Liberally grease ½‖ stainless steel pipe plug and install securely.
17. Prior to installing the protective cover, thoroughly grease the ACME
threads on the access fitting body.
IMPORTANT: The following procedures assume that the service valve is still
installed on the access fitting body. It is in the closed position
and the plug assembly is absent from the access fitting body.
2. Connect the retriever. Extend the retriever fully. If the access fitting to
be serviced mounted on the top of line, install locking clamp on the
inner barrel (22) to prevent the retriever outer barrel (20) from
collapsing of its own weight. Lift the retriever and place it on the
service valve. Turn the hammer nut (7) clockwise until retriever is
securely seated tightened in place on the service valve. Use a brass
hammer to make up a secure connection.
3. Open the service valve by-pass (27) then open service valve ball (12).
4. Collapse the retriever, remove the locking clamp and with a twisting,
turning, sliding motion on the retriever outer barrel until the tool just
barely contacts the access fitting body.
KS-MNL-ENG-01-02-Rev0 Page 31 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
5. Turn the retriever outer barrel (20) two full turns counter – clockwise
while applying moderate pressure towards the access fitting. This will
help to allow the tap threads to align with the access fitting threads.
6. For thread tap cutting, slowly turn the retriever outer barrel (20)
clockwise, allowing the tool threads to engage the access fitting, 14 to
17 turns, occasionally turn the retriever outer barrel (20)
counterclockwise to help the tap threads to clear scale or chips from
the tool flutes.
7. Retrieve the tool. Turn the retriever outer barrel (20) counter
clockwise for about 14 to 17 turns until the tool threads are
disengaged from the internal threads access fitting.
10. Close the retriever bleed valve (4). Remove the diverter hose
assembly.
11. Close the service valve ball (12) and the service valve bleed screw
(22).
12. Bleed and remove the retriever. Open the retriever bleed valve (4)
and allow pressure to bleed off completely. Using the brass hammer,
tap loose and fully unscrew the retriever hammer nut. Lift the retriever
from the service valve.
13. Remove the tap. Unscrew the tap from the socket adapter pilot (41).
KS-MNL-ENG-01-02-Rev0 Page 32 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
2. Connect the retriever. Extend the retriever fully. If the access fitting to
be serviced mounted on the top of line, install locking clamp on the
inner barrel (22). Lift the retriever and place it on the service valve.
Turn the hammer nut (7) clockwise until retriever is securely seated
tightened. Use a brass hammer to make up a secure connection.
3. Open the service valve by-pass (27) then open service valve ball (12).
4. Collapse the retriever, remove the locking clamp and with a twisting,
turning, sliding motion on the retriever outer barrel until the tool just
barely contacts the access fitting body.
5. Brush the threads. Continue the twisting, turning, sliding motion of the
brush, in a clockwise direction, until it bottom.
8. Close the service valve ball (12) and the service valve by-pass (27).
9. Bleed and remove the retriever. Open the retriever bleed valve (4)
and allow pressure to bleed off completely. Using the brass hammer,
tap loose and fully unscrew the retriever hammer nut (7). Lift the
retriever from the service valve.
10. Remove the thread brush service assembly. Unscrew the tool from
the socket adapter pilot (41).
KS-MNL-ENG-01-02-Rev0 Page 33 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b) Place hammer nut (20) end of the surge tube assembly on the
service valve. Turn the hammer nut (20) clockwise until the surge
tube assembly is securely seated.
KS-MNL-ENG-01-02-Rev0 Page 34 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
1. Attach the pipe plug adapter to the square head of the pipe plug and
tighten the L-key head set screw.
2. Install the service valve onto the access fitting body. Turn the hammer
nut (20) service valve clockwise until it securely seated. Tap the
hammer nut (20) tight using brass hammer.
3. Install the retriever and engage the socket adapter pilot (41) to pipe
plug adapter in the same manner as previously described in section
C. no 6 – 7.
KS-MNL-ENG-01-02-Rev0 Page 35 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
b) Install the clamp into the inner barrel (22) if the fitting is mounted
in a position to allow the retriever outer barrel (20) to collapse on
its own weight.
7. Close the equalizing valve (27) at service valve and service valve ball
(12).
a) The service valve extension handle (7) (features a slotted and
engages the roll pin of the equalizing valve stem for easy opening
and closing.
b) Close the service ball (12) using the service valve extension
handle (7).
10. Loosen the retriever hammer nut (7) by using brass hammer.
11. Lift the retriever from the service valve.
12. Collapse the retriever to expose the socket adapter (37), the attached
pipe plug adapter, and the pipe plug.
13. Remove the adapter and the pipe plug from the socket adapter pilot
(41).
14. Reinstall the retriever on the service valve then pressure balances the
retriever by opening the equalizing valve (27).
2. Loosing the retriever hammer nut (7) from the service valve by using
brass hammer until fully unscrew.
a) The inner barrel (22) can turn easily, not locked to service valve.
The outer barrel (20) and inner barrel (22) will move together.
KS-MNL-ENG-01-02-Rev0 Page 36 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
7. Retriever can not be used for next retrieving. It must be service with
disassembly. Bring the retriever to workshop for maintenance.
KS-MNL-ENG-01-02-Rev0 Page 37 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
V. Maintenance
5.1 Retriever
The maintenance interval required by either the TKS retriever will vary
depending upon the service to which it is subjected. Certain fluids will wash out
all lubricant from the retriever after one retrieval; others will deposit debris in
the retriever making operation difficult.
If the retriever has been in use and it is anticipated not being used for a period
longer than one day, it should be completely disassembled, cleaned and
lubricated. Also, if in a days operation (because of adverse retrieval
environment conditions) the retriever becomes difficult to operate, feels gritty
and does not stroke or turn easily, it should first be cleaned and lubricating
without disassembly does not relieve the difficulties in the retriever operation, it
should be completely disassembled, cleaned and lubricated as indicated in
either Part 8.3 or 8.4 of this Section.
KS-MNL-ENG-01-02-Rev0 Page 38 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
1. Extend the retriever until the socket adapter is withdrawn into the inner
barrel by approximately ½ inch. Place the retriever head end down on a
clean surface.
2. Add solvent. Pour approximately one pint (1/2 liter) of solvent into the
retriever inner barrel.
4. Extend the retriever slowly. The solvent while in the process of cleaning
and flushing will remove all lubricant or at least emulsify sufficiently to
make extension of the retriever difficult.
5. Turn the retriever end-for-end. With the retriever head end up, let the
solvent drain out.
KS-MNL-ENG-01-02-Rev0 Page 39 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
8. Pour SAE 30 weight motor oil into the retriever inner barrel (about four
ounces – 100 grams).
10. Stroke the retriever. Extend and collapse the retriever until the oil and
grease have been adequately filmed on all working surfaces.
11. Test the retriever operation. If the retriever still has a gritty feel and
sound after the stroking procedure indicated above, it must be
disassembled for thorough cleaning and lubricating.
2. Loosen and remove the mandrel rod stop nut (15). Remove the flat
washer (14).
3. Loosen and remove the four 3/8‖ Allen head screws (1) retaining the
retriever head, using a 5/16‖ Allen wrench.
4. Remove the retriever head (10) and the mandrel rod stop washer (11).
5. Withdraw the mandrel rod (12) from the inner barrel end (22).
7. Remove the hammer nut Ext. heavy duty ring (13). Lift the last turn of
the hammer nut retaining lock ring up (13) and out the groove; work
around the ring until the entire ring comes out of its groove in the thread
adapter (8).
KS-MNL-ENG-01-02-Rev0 Page 40 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
8. Loosen and remove the two ¼‖ Allen head screws (26) which retain the
thread adapter (8) by using a 1/8‖ Allen wrench.
9. Remove the thread adapter (8) from the inner barrel (22) by unscrewing
one from the other. Spanner holes are provided in the head end of the
inner barrel (22) and in the sides of the thread adapter (8) to
accommodate the spanner wrench. Remove the hammer nut (7) and
Ext. heavy duty ring (13).
10. Slide seal installation tool over threads of inner barrel (22). If tool is not
available, wrap threads with Teflon tape to protect the outer seal (18)
KOROSI SPECINDO from damage.
11. Loosen and remove the four 3/8‖ Allen head cap screws (1) to remove
the seal stop collar (9).
12. Carefully remove the seal (18) assembly by sliding them over the
protected threads of the inner barrel (22).
13. Stand the retriever in a vertical position with the inner barrel (22) thread
end downward. Push down on the outer barrel (20) until the inner barrel
head end is exposed.
14. Pull the inner barrel (22) out of the outer barrel (20).
15. Remove the seals from the inner barrel (22). It will be necessary to first
remove the four ¼‖ socket head cap screws (19) in the head of the
inner barrel (22). Remove the cap (24) and seal assembly (17) by
carefully prying on side, then the other (23 & 16) with a small slotted
screwdriver.
16. Remove the retriever bleed valve assembly (4) or (33) from the outer
barrel (20). The bleed assembly (4) or (33) can be removed by
unscrewing it from the valve body. The seals on the bleed valve can
also be removed for servicing.
KS-MNL-ENG-01-02-Rev0 Page 41 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
1. Clean the outer barrel (20) inside surface using a cleaning solvent.
Wipe the bore thoroughly clean and inspect it for damage.
2. Replace the o-ring, back-up rings and seals each time the retriever is
reassembled.
3. Apply grease to about four inches of the bore of the outer barrel (20).
The grease will be filmed thorough out the inside of the retriever when it
is fully assembled and later stroked.
4. Clean the inner barrel (22) using solvent. If the unplate areas of the
inner barrel (22) have been scratched or scored, polish the area with
fine emery cloth. Minor scratches in the chrome can be dressed with
fine crocus cloth. Examine the inner barrel (22) threads and repair as
necessary.
5. Lubricate mandrel seal (16). Press mandrel seal (16) (cup facing
outward) into inner barrel (22) using care not to kink, crimp or roll the
seal. Install seal retainer (23) into inner barrel (22).
Lubricate and install inner seal (17) press inner seal (17) (cup facing
outward) into inner barrel (22), using cares not to damage the seal (17).
Install the cap end (24) into inner barrel (22), insert the four ¼‖ socket
head cap screws (19) through the end cap screw holes and torque to 80
in. lbs.
6. Apply grease to the inside and outside surfaces of the inner barrel (22).
Wrap the thread on the inner barrel with PTFE tape and apply grease in
outside of inner barrel (22) thread.
KS-MNL-ENG-01-02-Rev0 Page 42 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
7. Stand the outer barrel (20) vertically with the bleed valve (4) assembly,
end down. Place the inner barrel (22) thread end first, into the outer
barrel (20). Hold the inner barrel (22) within the outer barrel (20) and
turn the barrels end-for-end. Place a rag under the inner barrel (22)
head end, and push down on the outer barrel (20) until the barrels are
in place.
8. Lubricate outer seal (18) work the seal carefully over the thread (cup
facing thread) until it lies in the thread relief groove of the inner barrel
(22). Install the seal stop collar (9) using the four 3/8‖ Allen head cap
screw (1). DO NOT tighten the screw fully at this time; allow the seal
stop collar (9) to have slight play.
9. Grease and install the o-ring (2) on the thread adapter (8). Install the
back-up ring (3) behind the o-ring (2) and on the same side as the
threads.
10. Install the hammer nut (7) and the ext. heavy duty ring (13) onto the
adapter thread (8).
11. Using the wood clamp, secure the inner barrel (22) and screw on thread
adapter (8) with ‗C‘ pin spanner. Install and tighten the two ¼‖ Allen
head set screw (26) with a 1/8‖ Allen wrench and torque to 70 in. lbs.
12. Install the ext. heavy duty ring (13) onto the thread adapter (8) by
feeding the leading edge into the groove and then working around the
ring.
13. Clean the mandrel rod (12) with solvent. Examine the mandrel rod (12)
for damage. Apply grease liberally to the entire length of the mandrel
rod (12), including the chamfer at the threaded end.
14. Pull the thread adapter (8) until the inner barrel (22) is withdrawn from
the outer barrel (20) and has approximately two inches exposed. Insert
the mandrel rod (12) threaded end first into the inner barrel (22). Gently
push the mandrel rod (12) through the seal.
15. Lay the retriever on its side. Continue pushing the mandrel rod (12) until
the threaded end is exposed from the outer barrel (20) end
KS-MNL-ENG-01-02-Rev0 Page 43 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
approximately one inch. Place the mandrel stop washer (11) onto the
exposed threaded end of the mandrel rod (12).
16. Place the retriever head (10) onto the mandrel rod (12), install the
washer (14) and the stop nut (15).
17. Install the four 3/8‖ Allen head cap screws (1) through the retriever head
screw (10) holes and into the outer barrel (20) screw holes. Torque the
cap screws (1) with a 5/16‖ Allen wrench to 45 ft. lb.
18. Tighten the mandrel rod stop nut (15) with a socket to 110 ft. lb.
19. Torque the four 3/8‖ Allen head cap screws (1) that were initially
installed as indicated in item steps 8 to retain the retriever seal stop
collar (9) to 45 ft. lbs.
21. Position the key in the mandrel rod (12) and reassembly and install the
socket adapter assembly (37) if it was removed. Position the two 5/16‖
cap screws (43) in the third and fifth holes from the socket adapter pilot
end (37) for normal service.
22. Stroke the retriever to ensure it slides easily and does not bind. If the
retriever does bind, loosen the eight 3/8‖ cap screws (1), four at the
head (10) end and four at the seal stop collar (9) end. Stroke the
retriever. Retighten all eight cap screws (1) to 45 ft. lb.; the retriever
should now stroke freely.
KS-MNL-ENG-01-02-Rev0 Page 44 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
* The valve should be rinsed with diesel fuel after each day‘s service in these
environments.
1. Loosen and remove cap screw (4) on handle (5) service valve. Remove
handle (5) from stem (3), remove plate position stop (25).
2. Place the service valve upside down (it will be better if placed in a vice
to secure it when removing interior parts from service valve. If this is
done, wooden block should be used to protect the body from marks
caused by vice jaws).
KS-MNL-ENG-01-02-Rev0 Page 45 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
3. Loosen and remove the four Allen cap screw 7/16‖ (23) by using a 5/16‖
Allen wrench. Loosen and remove the two cap screw ½‖ (24) by using a
3/8‖ Allen wrench. Remove the bonnet (2) from service valve body (1).
Remove back up ring (8), seal stem (9), thrust ring (10) and o-ring (11)
from stem. Care must be taken in removing the seal stem (9) and o-ring
(11).
4. Loosen and remove the four Allen cap screw 5/8‖ (19) at the hammer
nut end (20) by using a ½‖ Allen wrench.
5. Remove hammer nut (20), retainer (16), carrier seat (13), valve ball (12)
(care must be taken in handling of ball) and carrier seat (13).
7. Loosen and remove pipe plug (21) from service valve body (1).
1. Clean all parts. A recommended cleaning solution for all metal parts is a
mixture of 5 gallons (20 liters) of diesel fuel, ½ pints (250 ml) of
standard motor oil and two tablespoons of methanol. A soft brush such
as a test tube cleaning brush may be used to remove any deposits.
2. Lubricate inside service valve body (1), lubricate carrier seat (13) and
install ring seat seal (15) into carrier seat (13), install o-ring (14) into
carrier seat (13).
NOTE: That there are two seat seal rings and carriers; and, that they are
interchangeable. There is only one carrier seal and it is to be
installed on to the carrier going into the ACME threaded end of the
service valve). If the seat seals are not being replaced, install the
better of the two seat seals in the ACME threaded end of the
service valve. Grease the face of the seat seal.
3. Place valve body (1) upside down (in a vice if possible using a wooden
blocks) then replace carrier seat assembly (13) into service valve body
(1) with o-ring (14) contact inside service valve body (1).
KS-MNL-ENG-01-02-Rev0 Page 46 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
4. Lubricate the valve ball (12) and install the better side in the ACME
threaded end of the valve body (1). Ensure that‘s the groove side on
valve ball (12) facing the stem (3). Then repeat item steps 3, install
carrier seat assembly into service valve body (1) with ring seat seal (15)
facing the valve ball (12).
5. Lubricate the retainer (16) (both side) then assembly o-ring (17 & 18).
Install retainer assembly (16) into service valve body (1). Install hammer
nut assembly (20) into service valve body (1) screw with the four 5/8‖
(19) Allen cap screw by using a ½‖ Allen wrench. DO NOT tighten them
securely at this stage.
6. Partially assembly the bonnet (2) by installing the back-up ring (8) and
stem seal (9) in the bonnet (2). Install the thrust washer and stem in the
bonnet. Position the bonnet-to-valve body ‗O‘ ring in the valve body (1)
stem recess.
7. Install the thrust ring (10) and stem (3) in the bonnet (2). Position the
bonnet-to-valve body is o- ring in the valve body (1) stem recess.
Carefully position the bonnet onto the valve body, ensuring that the
thrust washer is eased into position concentric with the ‗O‘ ring. Stager
torque the four 7/16‖ Allen head cap screws to 30 ft.lbs. And the two ½‖
Allen head cap screws retaining the bonnet to the valve body to 50
ft.lbs. Use a 5/16‖ and 3/8‖ Allen wrench, respectively.
8. Carefully position the bonnet (2) onto the valve body (1), ensuring that
the thrust ring (10) is eased into position concentric with the o- ring (11)
and ensure that the stem (3) inserted into valve ball groove. Stager
torque the four 7/16‖ Allen head cap screws (23) to 30 ft.lbs. And the
two ½‖ Allen head cap screws (24) retaining the bonnet (2) to the valve
body (1) to 50 ft.lbs. Use a 5/16‖ and 3/8‖ Allen wrench, respectively.
9. Install the plate position stop (25) over the top of the stem (3) and
position the valve ball handle (5) onto the square head of the stem (3).
Ensure that handle (5) positioning points away from the hammer nut
end (20) when the valve ball (12) is in the open position. Tighten the
cap screw (4).
10. Stager torque the four 5/8 ― Allen head cap screws (19) that were
initially installed as indicated in item steps 5 to 130ft. lbs, to retain the
hammer nut assembly (20) and retainer (16).
KS-MNL-ENG-01-02-Rev0 Page 47 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
KS-MNL-ENG-01-02-Rev0 Page 48 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
KS-MNL-ENG-01-02-Rev0 Page 49 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
KS-MNL-ENG-01-02-Rev0 Page 49 of 51
IOM 2‖ System Corrosion Monitoring KOROSI SPECINDO
KS-MNL-ENG-01-02-Rev0 Page 49 of 51