DATE: DECEMBER 1, 2023

TWO REGIS
ACTIVITIES: ISSUES: REMARKS:

ARCHITECTURAL:
1. INSPECTION OF HALLWAY CEILING BALANCE AREA AT
FRAME ELEVATION 1. ELEVATOR LOBBY
2. ACCESS HALLWAY TO POOL AREA
NOT INCLUDING FRAMING SYSTEM

FROM 80 POINTS
AT AREA 1 FROM PT 1-18 - NO
CORRECTION
AT AREA 2 FROM PT 19 - 58 - NO
CORRECTION
(NOT THAT BALANCE AREA AT ACTIVITY
TILE)
AT AREA 3 FROM PT 60-80
1. PT 77 AT 1562MM
2. PT 76 AT 1564MM
2. INITIAL TILES INSPECTION AT 2ND BALANCE AREAS 1. HOLLOW TILES - 4 TILES
FLR UNIT L 1. BALCONY AT BEDROOM AND 2. BALANCE INSTALLATION - 10 TILES
LIVING AREA 3. LIPPAGES - 4 TILES
2. COMMON TOILET AND BATH 4. WITH STAIN/ CLEAN - 1 TILE
3. KITCHEN AREA 5. DAMAGE TILES - 0
4. MASTER’S TOILET AND BATH 6. OFFSHADE - 0

NO GROUT APPLICATION YET


3. INSTALLATION OF TOILET AND 1. NO LINTEL BEAM AT TOP OF 1. LOCATION TO MAIN DOOR OPENING
BATH DOOR JAMB AT 2ND FLR UNIT A DOOR JAMB (CENTER) TO TOILET OPENING (CENTER)
1675MM
2. OPENING (HALF) - 330MM
3. OPENING (WHOLE) 660MM
4. ELEVATION AT 1000MM - 1115MM BOTH
SIDES
5. PLUMBNESS AT 600MM OFFSET - 559 TO
600MM
4. INSTALLATION OF TOILET AND 1. NO LINTEL BEAM AT TOP OF 1. LOCATION TO MAIN DOOR OPENING TO
BATH DOOR JAMB AT 2ND FLR UNIT U DOOR JAMB TOILET DOOR OPENING - 2575MM
2. OPENING (HALF) -330MM
3. OPENING (WHOLE) - 660MM
4. PLUMBNESS AT 600MM OFFSET - 599 TO
603MM
5. ELEVATION AT 1000MM - 1116MM AND
1115MM
5. INSTALLATION OF TOILET AND 1. FOR REINSPECTION DUE TO
BATH DOOR JAMB AT 2ND FLR UNIT R UNPLUMB SETTING