CENTER LINE METHOD OF TAKING
QUANTITIES

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 3


Contents

 Method of Details Estimate


 CENTER LINE METHOD OF TAKING QUANTITIES
 Example

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 4


CENTER LINE METHOD OF TAKING
QUANTITIES
• In this method sum – total length of center lines of walls, long and short
has to be found out.

• Find the total length of center lines of walls, of same type, long and
short wall having same type of foundation and footing.

• Then find the quantities by multiplying the total center length by


the respective breadth and the height.

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 5


CENTERLINEMETHODOFTAKING QUANTITIES

• In this method the length will remain the same


– Excavation in foundation
– For concrete in foundation
– For all footings
– For superstructure

• Slight differences will occur when there are cross walls or number of
junctions.

• This method is quick but requires special attention and consideration


at the junctions, meeting points of partitions or cross walls

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 6


Example 1 B
MEASUREMENT SHEET
Item
No. Description of Items No Length Breadth Height/Depth = Quantity Unit Remarks
1 Earthwork in excavation in foundation
2*(5.3+4.3)
1 19.2 m 0.9m 0.9m = 15.55 Length=
=19.2m
TOTAL = 15.55 m3
2 Concrete in foundation
Length same as for
5.18
1 19.2m 0.9m 0.3 = excavation
TOTAL = 5.18 m3
3 Brickwork in foundation and plinth
1st footing 1 19.2m 0.6m 0.3m = 3.46m3
2nd footing 1 19.2m 0.5m 0.3m = 2.88m3
Plinth wall 1 19.2m 0.4m 0.6m = 4.61m3

TOTAL = 10.95 m3
4 Brickwork in superstructure
1 19.2m 0.3m 3.5m = 20.16m3

TOTAL = 20.16 m3
Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 7
EXAMPLE 2

• The plan of superstructure wall of a single room building of 5m x 4m


and the cross-sections of the walls with foundation are given on the
next slides.
• Estimate the quantities of (using Individual wall method) :
1) Earthwork in excavation in foundation
2) Concrete in foundation
3) Brickwork in foundation and plinth
4) Brickwork in superstructure
Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 8
Room Plan

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 9


Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 10
Cross Section of Footing of Walls

Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 11


Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 12
Engr. Noman khan (SUIT Peshawar) nomi38899@gmail.com 13