Minggu Ke 1 2 3 4 5

Cumulative cost 10,641,529 28,441,082 46,220,370 88,790,581 131,665,841


Presentase 1.13 3.02 4.91 9.43 13.98
6 7 8 9 10 11
155,486,785 233,365,098 290,208,368 344,997,067 424,036,174 467,795,399
16.51 24.77 30.81 36.62 45.01 49.66
12 13 14 15 16 17
522,719,677 558,087,680 581,268,538 599,290,314 627,753,305 666,560,050
55.49 59.24 61.70 63.62 66.64 70.76

Kurva S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Minggu Ke
18 19 20 21 22 23
706,285,473 759,620,776 823,648,255 858,061,996 873,796,056 887,769,521
74.97 80.64 87.43 91.09 92.76 94.24

Kurva S
100.00

90.00

80.00

70.00
presentase

60.00

50.00

40.00

30.00

20.00

10.00

0.00
3 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Minggu Ke
24 25 26 27 28 29
897,152,564 905,675,424 923,683,987 930,707,917 932,383,239 942,033,885
95.24 96.14 98.05 98.80 98.98 100.00