Professional Documents
Culture Documents
Abstract: The main objective of this research is to propose a methodology for configuration management
in COTECMAR in conjunction with the Integrated Logistic Support (ILS) describing the elements that
make up the ILS and its activities throughout the life cycle of the system in the framework of a naval
program, which is based on standards issued by different authors of both military and civilian nature, taking
into account the methodology of acquisition of military systems adopted by the Navy and COTECMAR.
Also, a proposal for the design of a computer tool for configuration management was developed. As a final
point, it was described how the ILS will evolve in COTECMAR considering the concept of shipyard 4.0
and how the development of the ILS will allow COTECMAR to be a world class shipyard.
Keywords: ILS, Configuration Management, Logistics Engineering, Shipyard 4.0, Industry 4.0, System
Engineering, Military Systems, NATO.
170
throughout the life cycle. Since configuration management is Exhaustive use of international standards
the element that allows establishing the database and initiating
a flow of information for the development of the other Reduction of the number of manufacturers and
elements and acts throughout the life cycle of the program as suppliers.
an articulating process for the other elements.
Configuration Management is then understood as the process
4 DESIGN OF THE CONFIGURATION that ensures the correct identification of the different
MANAGEMENT PROCESS IN THE CASE OF configurations of a product, the change control, the
COTECMAR. implementation record of changes for physical and functional
characteristics for a system, product, equipment, and
The process design, information from the main authors of this components. The effort of configuration management lies in
process in Naval Programs has been used. Figure 5 shows the the traceability of design decisions and modifications.
structure that corresponds to the phases of the process Configuration management is performed from the lowest level
requirement of the methodology established to be able to of the product breakdown. (AIA, ASD, 2016 )
approach the design of this process.
The process and PGC is composed of four main activities as
shown in the following Figure 6.
The process starts with configuration planning, which will be 4.1 Configuration identification phase
adjusted with the customer's policies for configuration Configuration identification is the activity performed to
management and ILS. The result of this planning stage will be establish levels or boundaries for independent management.
the Configuration Management Plan (CMP) document, which Configuration Identification establishes and maintains the set
will be updated throughout the life cycle and will have of documents and technical information describing a product
agreements such as level of detail of the information, control (baseline) for the control and recording of the configuration
points, monitoring teams, among others. status of a system and its configured elements (product,
The Configuration Management process has standardization as equipment, subsystem) throughout the life cycle.
a principle; this is identified in criteria such as: The configuration identification activity ensures that all
management and acquisition disciplines use a common set of
Same configuration in all vessels of the same class.
documentation as the basis for developing a new system,
Selection of equipment and components that have modifying an existing system, purchasing a product, and
already been installed on other vessels.
171
providing support for a system and its components. The proposed change or grant. This activity ensures that no change
configuration identification process includes: is implemented without consideration of its effects on the
baseline, including logistical impact, cost, schedule, build, or
Select Configuration Items at appropriate levels of alignment with the product mission.
the product structure to facilitate their
documentation, control, and support. Figure 8. Sets out the process for the configuration control
activity and then describes the inputs and outputs along with
Determine the types of configuration documentation an explanation of each sub-activity:
required for each Configuration Element to define its
performance, physical and functional attributes,
including internal and external interfaces.
172
Validation of the initial baseline configuration and
incorporation of approved changes to ensure that the
configuration meets the established performance and
requirements.
5 PROPOSED LIFE CYCLE SUPPORT PORTAL. Figure 12 shows the proposed main and secondary modules:
Nowadays it is unthinkable to perform an effective
management without the support of Information and
Communication Technologies (ICT), so the purpose of this
section is to propose a new application that should be
developed for ILS management and life cycle support.
The importance of the development of this tool is the
contribution it will make to the maintenance management for
a future line of ILS business and life cycle support, where
COTECMAR will provide services to military and civilian
customers more specifically to industrial plants taking Figure 12 Costs over the life cycle of a military system. Source:
Own elaboration.
advantage of the capacity in design, construction and
maintenance, on the other side, It is necessary to mention that In the future, COTECMAR and the ARC will have to develop
between 70 and 80% of the total costs of a vessel (NATO, jointly, which will be a data supervision and analysis center in
2001), are associated with the operation and maintenance of which its competitive advantage and rapid decision-making
the same as can be seen in Figure 11, the implementation of reside to optimize the maintenance tasks of an industry thanks
this portal would contribute to COTECMAR could assume a to the treatment of the generated data. But for this, first, it is
greater portion of the market for maintenance of ships in necessary to identify the fundamental unit, in a 4.0 system it is
industrial facilities. This information is based on the sales the data in a hyperconnected and automated system, the
prices of vessels built at COTECMAR. generation of data is the first link in the value chain.
The objective of this data analysis center will be to support
decisions regarding the maintenance of platform equipment
and systems of ships or civil facilities, which would allow
avoiding catastrophic failures and allowing greater efficiency
173
in maintenance, modifying the maintenance schedule COTECMAR and ARC must change the current maintenance
According to the condition, provide our Fleet with the highest model and implement an Integrated Logistic Support model in
operational availability, understanding the term availability as line with international regulations such as those of NATO, this
the operability of equipment and systems. Figure 13 shows the will allow ARC to make its ships interoperable with other
objectives graphically: navies, reduce the maintenance costs of its ships, optimize the
purchase of COTS equipment, develop dual technologies,
participate in international R&D&I projects (Riola &
Gonzáles, 2009), and increase its relationship with the
industrial technology base to optimize the life cycle of the
vessels.
The creation of data analysis centers should be promoted both
in the shipyard and in ARC, through the use of information and
communication technologies that allow maintenance
personnel to have data on the operation of the systems
deployed in real time. These data analysis centers should
become repositories of knowledge about the ships and systems
and will allow ARC to improve its ship maintenance plans
Figure 13 Synchronization virtual and real environment. Source: with consequent cost savings.
self-made
7 REFERENCES
The development of the ILS for the conceptualization of this
AIA, & ASD. (2016). The S-Series ILS especifications.
capacity is directly related to the elements called measurement
Brussels.
equipment and devices, maintenance plan and the availability
AIA, ASD. (2016). SX00i International guide for the use of
of installation and infrastructure to do so. And it will be able
the S-Series. Brussels.
to face with guarantees the development of an Integrated
Blanchard, B. (1991). System Engineering Magnagment.
Platform Control System (SICP) for Navy ships.
New York: Wiley & Sons.
This is how the implementation of technologies in the line of COTECMAR. (2019). Direcciónamiento Esrategico 2019-
work and development of the aforementioned capacity will 2034. Cartagena.
allow for an evolution of the ILS and being at the forefront Department of Defense EEUU. (1972). Integrated Logistics
with world-class shipyards. Support Implementation Guide for DoD Systems and
Equipment. Washington D.C: Government Printing
6 DISCUSSION AND CONCLUSIONS Office.
ILS is an internationally recognized and accepted Murcia , H., Paipa Sanabria , E., & Ruiz, M. (2019).
methodology for the application of technical, logistical and Importancia de la Metodologia de planeación por
support capabilities, with the objective of generating effective capacidades y del Soporte Logistico Integrado en
maintenance at the lowest possible cost for military Programas Navales de Alta complejidad en
applications and easily diversifiable to the civilian Colombia. Cartagena.
environment, since it allows an easy articulation with the NATO. (2001). ANEP-49 Ways to reduce costs of ships.
system requirements generated in the early phases of the life NATO. (2011). Guidance on integrated logistics support for
cycle. multinational armament programmes. North
Atlantic Treaty Organization.
The application of ILS and configuration management in the Riola, J., & Gonzáles, G. (2009). Los observatorios
framework of military acquisition projects requires a new tecnologicos. I+D+i de defensa: los observatorios
relationship model between COTECMAR and its customers, tecnologicos. 48 Congreso de Ingenieria Naval e
where contracts are established not only for repair but also for Industria Maritima. Vigo.
the management of the life cycle of the assets in the medium Vera Macias, S. D. (2019). Propuesta de un sistems de
and long term. The implementation of these contracts will gestión de activos físicos según norma ISO 55001:
generate industrial ecosystems that will allow the development 2014 en la extractora agrooleaginosas los Ríos
of Colombian suppliers for the optimization of quality and life Oleríos SA que aumente el ciclo de vida y valor de
cycle cost. los activos . (Bachelor's thesis, Quevedo: UTEQ).
174