Height diff with Arch

detail. TBC ?

Any hardcore/
crusher run to
provide?

Column location
at GL A2/1-9. no
beam on top.
TBC ?

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

4000mm ht

2200mm ht

1800mm ht

2700mm ht

Size pile cap diff with schedule of


pilecap & layout. TBC ?
Ramp to follow Arch layout Ramp to follow Arch layout
drwg. To be topping up to Arch Trenches from GL 1 to drwg. To be topping up to
RC grd slab? Struc Typical 6 & 10 to 15 but Struc from RC grd slab? Struc Typical
Ramp not suitable? TBC ? GL 1-7 & 9-15. TBC ? Ramp not suitable? TBC ?

Ramp to follow Arch layout


drwg. To be topping up to
RC grd slab? Struc Typical
Ramp not suitable? TBC ?

MSMT SCALE
15.16MM : 3M
Struc design as
per latest Arch
desgn

Column location
at GL A2/1-9. no
beam on top.
TBC ?
Column Column
end at level 1B
TBC ?

Column location
at GL A2/1-9. no
beam on top.
TBC ?

Column Column
end at level 1B
TBC ?