Professional Documents
Culture Documents
Waste Management Procedure AquaChemie Version
Waste Management Procedure AquaChemie Version
3.6.2.1 Wastewater
Potential sources of wastewater are listed below in Table 3.7. Table 3.7:
Solid waste will be mainly from non-routine sources. Potential sources of solid
waste are listed below in Table 3.8 below.
4.1.1 General
4.1.4 Water
4.1.5 Land/Soil
Avoid sealant and glazing formulations which use lead as a drying agent.
Use lead-free paint and primers, varnish and wood staining systems.
Minimise the use of solvent-based paints or replace with water-
based materials.
Substances containing CFCs (chlorofluorocarbons) and HCFCs
(hydrofluorocarbons) shall not be used.
8. Construction employees shall be made aware that unauthorised disposal of
materials to the environment is unlawful and can result in serious penalties.
9. The contractor shall be responsible for arranging the timely collection of waste
material to prevent indiscriminate disposal of rubbish. Good housekeeping shall
be maintained at all times.
10. The contractor shall appoint an individual responsible for the regular inspection
of the site and site housekeeping.
11. All waste shall be disposed at approved waste disposal site of Dubai Municipality
through DM approved waste disposal contractors. Records of all waste disposal
shall be maintained.
As there are no ecological assets on site, no mitigation and or enhancement measures are
required and hence not recommended.
The proposed project is within an existing site which is fully developed as an industrial area.
Hence, construction of the project will not cause any adverse effects on the aesthetic value
of the area and hence no further recommendations are required.
An essential element of the IEE/EIA process is to develop measures to eliminate, offset or reduce
impacts to acceptable levels during construction and operation of projects. The integration of such
measures into project implementation and operation is supported by clearly defining the
environmental requirements within an environmental management plan (EMP).
The Environmental Management Plan (EMP) for the proposed project aims to mitigate the
potentially adverse impacts on the environment. It is also necessary that continued compliance with
existing environmental regulations is ensured.
An Environmental Management Plan (EMP) has been developed as part of the present IEE study
describing the environmental protection measures to be put in place. The EMP focuses on:
Objectives/targets
Mitigation measures to be applied in the field to minimize potential adverse impacts and achieve
objectives/targets
Management practices and responsibilities (procedural measures) and staff training
Environmental Organization
Environmental monitoring and audits
The environmental objectives and targets are environmental legislation that shall be
complied with. All applicable environmental standards and legislation are discussed in detail
in Section 1 of this report.
ACME believes in bringing together of good business management, innovation and safety
and environmental protection. Therefore ACME proactively has developed and EHS
Management System and is certified to ISO 14001: 2015 and OHSAS 18001: 2007.
A framework Construction Environmental Management Plan (CEMP) is developed for the on-
going and balance construction activities of the project.
The construction contractor shall prepare a CEMP based on the framework CEMP presented
in this report. The CEMP to be developed shall include as a minimum the following:
Introduction
Objectives of the CEMP
Structure of the CEMP
Overview of the project development
Details of the construction activities with statement of work methods
Tabulated list of identified environmental aspects and impacts.
Corrective actions/measures to control and manage the identified construction-related
impacts.
Monitoring methodology, list of environmental quality parameters, and the frequency
of sampling or scope of monitoring
Incident/Emergency Preparedness and Response
Data management and reporting
Statement of responsibilities, whether jointly or separately, of Contractors, Consultants,
and/or Project Owner.
Waste is an excess material resulting from any activity which is discharged as reject and
unwanted or any surplus material whether as a total useless matter or those that can be
rendered useful again by recycling, treatment or recovery thru a different process from
which it was originally produced.
Potential waste sources during construction phase of the proposed project are as follows:
Construction waste
Domestic sewage
Domestic refuse
Hazardous waste (e.g. waste paint cans)
Waste Minimization sets out the following hierarchy for waste management options:
waste avoidance/reduction
reuse, and recycling
waste treatment
waste disposal
Preference shall be given to waste avoidance or reduction, ahead of recycling and reuse.
Waste treatment and the least preferred alternative of waste disposal should be considered
only if the waste avoidance/reduction and reuse options are not feasible or possible.
Waste minimization during construction and commissioning phases of the project are
already discussed in Section 4.5.4 and 4.5.5 of this report. Additional waste minimization
measures are presented in Table 6.1 below.
All wastes shall be disposed only through authorized and licensed waste collection
companies.
Teamwork and commitment from construction staff, supported by strong management and
effective management systems, should enable sustainable and continuous performance
improvement. The construction contractor’s top managements' commitment shall include a
policy statement on waste minimization which shall be circulated and made known to all
staff. The statement shall include responsibilities of staff.
A useful starting point for a waste minimization program is to prepare a construction waste
management plan (WMP). The first step to preparing a WMP is a waste audit, which involves
identifying the sources, types and quantities of wastes generated during construction. The
waste audit should:
• identify all waste streams;
• establish how each waste stream is generated;
• quantify and characterize the waste streams
After the waste audit is completed, a waste assessment shall be conducted. This involves
identifying the options available to minimize each of the waste streams.
The WMP shall contain an implementation timetable and description of the method of
implementation, and the anticipated costs and environmental benefits.
The waste minimization program shall be periodically reviewed to ensure the WMP is being
adhered to, and to identify any new waste minimization opportunities. The waste
minimization program should be an integral part of the contractor’s approach to
environmental management.
ACME through their project consultant and or construction contractor shall ensure that
during construction phase the EMP is communicated to the relevant sub-contractors (if any),
to enable sub-contractors to incorporate the EMP’s requirements into their daily operations
and management plans.
The contractors shall take steps to comply with all environmental mitigation measures and
standards mentioned in this IEE report and that stipulated by Trakhees and DM. The overall
responsibilities of the contractor’s team are presented below in table 6.2.
The responsibilities of the Project consultant’s site supervisor are presented below in Table
6.3.
The basic aim of the EMP is to maintain the levels of pollutants within stipulated limits and
to comply with the regulatory standards. It is necessary that the construction contractor
complies with all relevant environmental regulatory standards stipulated by Trakhees EHS.
All wastes to be disposed outside the JAFZA shall meet Trakhees and DM standards and
regulations.
Measures to mitigate adverse environmental impacts during operation phase are discussed
in detail in Section 4.7 and the same shall be implemented.
Potential waste sources during operation phase of the proposed project are:
Blender washing
Boiler and cooling tower blowdown
RO reject
Laboratory waste
Accidental spills and leaks from storage tanks, drum filling, etc.
Domestic sewage
Waste/damaged drums/IBCs, waste pallets, waste raw material bags, and cartons
Domestic refuse
Waste generation may be reduced by simple actions presented in Table 6.4 below.
Teamwork and commitment from terminal staff, supported by strong management and
effective management systems, should enable sustainable and continuous performance
improvement. ACME top managements' commitment shall include: a policy statement on
waste minimization to be circulated and known by all staff and each responsibility, the plans
and the progress of the program, and in return to everybody's initiation is giving recognition
as appropriate to staff involved.
A useful starting point for a waste minimization program is to prepare a waste management
plan (WMP). The WMP can be prepared by ACME management. The first step to preparing a
WMP is a waste audit, which involves identifying the sources, types and quantities of wastes
generated from the project. The waste audit should:
The WMP shall contain an implementation timetable and description of the method of
implementation, and the anticipated costs and environmental benefits.
The waste minimization program shall be periodically reviewed to ensure the WMP is being
adhered to, and to identify any new waste minimization opportunities. The waste
minimization program should be an integral part of the company’s approach to
environmental management: it should be a key element when an environmental
management system is established.
A number of measures for waste minimization are already discussed in section 4.7.4 and
4.7.5 of this report.
ACME shall ensure that during operation the EMP is implemented and it is communicated to
all relevant employees.
ACME shall delegate a management representative as an EHS officer for the proper
implementation of EMP during operation phase. The responsibilities of ACME and EHS
delegate are presented in Table 6.5.
EHS procedures shall be established to implement mitigation measures. These shall include
procedures relating to the following presented in Table 6.6 below.
Table 6.6: Project EHS Procedures
Sr. No. Particulars
1. Access to project regulations, e.g. personnel identification, permitted/restricted
areas, EHS regulations, safety procedures and emergency information.
2. Reporting and investigation of incidents, review of accidents, near misses, etc.
3. Work permit system for maintenance works.
4. Personal Protective Equipment, type, numbers available, location, contact
persons for collecting, etc.
5. Housekeeping, working areas waste management, etc.
6. Waste storage and disposal
7. EHS performance reporting
8. Environmental specifications
9. EHS management of contractor personnel
10. Management of change
11. Emergency planning
6.3.7 Maintenance
Standard Operating Procedures (SOPs) and Standard Maintenance Procedures (SMPs) shall
be developed for the project. The SOPs, and SMPs, in conjunction with appropriate training,
will contribute to the mitigation of EHS impacts.
Waste audits shall be carried out annually (can be carried out internally) to assess the EHS
status of the project.
Waste audit shall be carried out as per Trakhees EHS Guideline No. ID EN-038 “Guidelines for
Conducting Waste Audit” in PCFC.
6.3.9 Training
Training to be provided to staff during operation phase are presented in Table 6.7 below.
The basic aim of the EMP is to maintain the levels of pollutants within stipulated limits and
to comply with the regulatory standards. It is necessary that ACME comply with all relevant
environmental regulatory standards stipulated by Trakhees.
Trakhees operate a system of prior approval of a process and no operation can begin until
the completed facility has been inspected and the authority is satisfied that it meets their
requirement and is fit for use when an Operation Fitness Certificate is issued.
All wastes to be disposed outside the JAFZA shall meet Trakhees and DM standards and
regulations.
A summary matrix of the framework environmental management plan for operation phase
is presented in Appendix-8 which indicates the potential impacts and the applicable
mitigation measures.
The top management of ACME shall be responsible for providing all the necessary funding
and administrative support to the EHS staff and the EMP; and be ultimately responsible for
carrying out this project with total commitment to environmental matters.
The HSE coordinator shall be responsible for coordinating all the HSE aspects of the project
which include:
All staff shall be made aware of all existing Trakhees, DM, and federal Environment, Health
and Safety laws and regulations.