01-Pending Work Schedule.02
01-Pending Work Schedule.02
SBT-MEP-1010 Electrical Meter cabinet fixing and Wire Pulling 3 14-Apr-23 24-Apr-23 36
ADMO-MEP-1010 New Entrace camera reloction for Exit Light and Door Exit Light ( As per new drawing) 4 10-Apr-23 15-Apr-23 7
ADMO-MEP-1020 1st Floor IDF installation and cable pulling 4 10-Apr-23 15-Apr-23 7
ADMO-MEP-1040 Shaft Through Duct, Tray, Piping ( CCTV) Fire damper 4 10-Apr-23 15-Apr-23 7
ADMO-MEP-1050 Roof Plumbing works and final fixtures installationin admin block 6 10-Apr-23 24-Apr-23 17
ADMO-MEP-1070 Roof electrical work(tray and conduit installation ,cable pulling & isolator installation) 6 19-Apr-23 29-Apr-23 7
PRODUCTION BLOCK AND TANK FARM 38 01-Apr-23 26-May-23 9 26-May-23, PRODUCTION BLOCK AND TANK FARM
PROD-BLOCK-MEP-1000
isolator Instalation 9 15-May-23 25-May-23 9
PROD-BLOCK-MEP-1010
Final fixtures installation of water supply 2 19-Apr-23 25-Apr-23 9
PROD-BLOCK-MEP-1020
Cable pulling for RO unit and Air compressor Supply cable 9 03-Apr-23 19-Apr-23 9
PROD-BLOCK-MEP-1030
compressor piping 4 05-May-23 10-May-23 9
PROD-BLOCK-MEP-1040
Camera point cable pulling 4 10-May-23 15-May-23 9
PROD-BLOCK-MEP-1050
SMDB 1 Installation & Termination 4 05-May-23 10-May-23 13
PROD-BLOCK-MEP-1060
Earth Pit Instllation 4 25-Apr-23 29-Apr-23 15
PROD-BLOCK-MEP-1070
isolator fixing 8 14-Apr-23 29-Apr-23 13
PROD-BLOCK-MEP-1080
SMDB-2 Fixing & cablet termination 4 05-May-23 10-May-23 13
PROD-BLOCK-MEP-1090
Duct Pipe installation 4 05-May-23 10-May-23 13
PROD-BLOCK-MEP-1100
Light & Switch Fixing 38 01-Apr-23 26-May-23 9
PROD-BLOCK-MEP-1110
Plumbing works and final fixtures installation 6 29-Apr-23 06-May-23 9
PROD-BLOCK-MEP-1120
Equipment Earthing 9 10-May-23 20-May-23 13
PROD-BLOCK-MEP-1130
Tray Installation for isolator & cable pulling 4 25-Apr-23 29-Apr-23 9
PROD-BLOCK-MEP-1140
DB - WELD -trunking Installation 4 25-Apr-23 29-Apr-23 31
PROD-BLOCK-MEP-1150
Welding DB Installation 3 06-May-23 10-May-23 9
PROD-BLOCK-MEP-1160
Exhaust Fan Installation 26 14-Apr-23 20-May-23 13
PROD-BLOCK-MEP-1170
CCTV installation 26 14-Apr-23 20-May-23 13
PMPR-MEP-1020 diesel pump Exhaust installation and fire water pipe installation (PRV Line) 2 15-Apr-23 19-Apr-23 31
BLENDING PLANT - STORAGE AREAS 37 10-Apr-23 30-May-23 7 30-May-23, BLENDING PLANT - STORAGE AREAS
BNP-MEP-1000 Installation of high bay Lights 3 15-Apr-23 24-Apr-23 15
BNP-MEP-1050 Fire Hose cabinets and interfacing units inatallation 2 15-Apr-23 24-Apr-23 35
BNP-MEP-1060 duble flap ventilators and mechanical ventilation fans installation 37 10-Apr-23 30-May-23 5
BNP-MEP-1070 All Electrical sockets ,isolators and Plumbing final fixtures installation 2 19-Apr-23 25-Apr-23 35