You are on page 1of 4

PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE AT KIZAD

REMAINING WORK SCHEDULE REV.00

Activity ID Activity Name Original Start Finish Total Float 2023


Duration Mar Apr May Jun Jul Aug Sep Oct Nov
16 17 18 19 20 21 22 23 24
PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE-PENDING WORK REV.00 86 01-Apr-23 26-Jun-23 0 26-Jun-23, PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE-PENDING WORK REV.00

KEY MILESTONE 0 01-Apr-23 01-Apr-23 0 01-Apr-23, KEY MILESTONE


KM-PEN-1000 Start Miletone for pending works 0 01-Apr-23 0 Start Miletone for pending works

CONSTRUCTION 46 01-Apr-23 05-Jun-23 2 05-Jun-23, CONSTRUCTION


CIVIL WORKS 46 01-Apr-23 05-Jun-23 0 05-Jun-23, CIVIL WORKS
GUARD ROOM 22 01-May-23 25-May-23 8 25-May-23, GUARD ROOM
GRD-CIV-1000 External wall painting works 5 20-May-23 25-May-23 8

GRD-CIV-1010 Internal wall Painting works 5 01-May-23 05-May-23 8

GRD-CIV-1020 Ceiling Painting works 4 06-May-23 10-May-23 8

GRD-CIV-1030 Floor Tile works 6 01-May-23 06-May-23 11

GRD-CIV-1040 Doors&window installation 3 11-May-23 13-May-23 8

PUMP ROOM 18 10-May-23 30-May-23 4 30-May-23, PUMP ROOM


PMPR-CIV-1000 External wall Painting works 5 25-May-23 30-May-23 4

PMPR-CIV-1010 Louver Door installation works 4 12-May-23 16-May-23 4

PMPR-CIV-1020 Grating cover installation works 2 10-May-23 11-May-23 4

SUBSTATION 5 25-May-23 30-May-23 4 30-May-23, SUBSTATION


SBT-CIV-1000 External wall Painting works 5 25-May-23 30-May-23 4

ADMIN BUILDING 46 01-Apr-23 05-Jun-23 0 05-Jun-23, ADMIN BUILDING


GROUND FLOOR 46 01-Apr-23 05-Jun-23 0 05-Jun-23, GROUND FLOOR
ADMO-CIV-GF-1000External ACP works 22 10-May-23 05-Jun-23 0

ADMO-CIV-GF-1010Tile installation works wall &Floor 16 01-Apr-23 01-May-23 0

ADMO-CIV-GF-1020Staircase Granite works 8 01-May-23 10-May-23 0

ADMO-CIV-GF-1030Staircase Handrail installation works 5 10-May-23 16-May-23 17

ADMO-CIV-GF-1040False Ceiling works 12 01-May-23 15-May-23 0

ADMO-CIV-GF-1050Gypsum/glass Wall Partition works 8 05-May-23 15-May-23 0

ADMO-CIV-GF-1060Ceiling Painting works 9 10-May-23 20-May-23 0

ADMO-CIV-GF-1070Internal Wall Painting works 33 01-Apr-23 20-May-23 13

ADMO-CIV-GF-1080Doors and windows installation works 9 10-May-23 20-May-23 13

FIRST FLOOR 46 01-Apr-23 05-Jun-23 0 05-Jun-23, FIRST FLOOR


ADMO-CIV-FF-1000External ACP works 22 10-May-23 05-Jun-23 0

ADMO-CIV-FF-1010Tile installation works floor 8 01-May-23 10-May-23 22

ADMO-CIV-FF-1020Ceiling Painting works 4 05-May-23 10-May-23 22

ADMO-CIV-FF-1030Internal Wall Painting works 11 19-Apr-23 05-May-23 26

ADMO-CIV-FF-1040Doors and windows installation works 5 15-May-23 20-May-23 13

ADMO-CIV-FF-1050Roof Water Proofing works 5 01-Apr-23 11-Apr-23 41

BLENDING PLANT 38 07-Apr-23 30-May-23 5 30-May-23, BLENDING PLANT


BNP-CIV-1000 Wall Sheet installation works 7 07-Apr-23 24-Apr-23 5

BNP-CIV-1010 External wall Painting works 9 15-May-23 25-May-23 5

BNP-CIV-1020 Internal wall Painting works 21 14-Apr-23 15-May-23 12

Critical Remaining Work Milestone Date Revision Checked Approved


Page 1 of 4
04-Apr-23 REMAINING WORK SCHEDULE REV.00 VJS
Actual Work Critical Milestone Data Date : 01-Apr-23
Remaining Work Summary TASK filter: All Activities
PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE AT KIZAD
REMAINING WORK SCHEDULE REV.00

Activity ID Activity Name Original Start Finish Total Float 2023


Duration Mar Apr May Jun Jul Aug Sep Oct Nov
16 17 18 19 20 21 22 23 24
BNP-CIV-1030 Floor Epoxy Coating works 23 24-Apr-23 20-May-23 13

BNP-CIV-1040 Rolling shutter installation 9 14-Apr-23 01-May-23 12

BNP-CIV-1050 Doors and windows installation works 9 11-May-23 22-May-23 12

BNP-CIV-1060 False ceiling works in storage 1& 4,corridors 8 01-May-23 10-May-23 18

BNP-CIV-1070 FRP Cover installation on Trench 4 25-May-23 30-May-23 5

EXTERNAL AREA 33 01-Apr-23 20-May-23 13 20-May-23, EXTERNAL AREA


U/G STORMWATER TANK 4 01-Apr-23 10-Apr-23 37 10-Apr-23, U/G STORMWATER TANK
UG-CIV-1000 GRP Lining works 4 01-Apr-23 10-Apr-23 37

OIL INTERCEPTOR 3 10-Apr-23 14-Apr-23 37 14-Apr-23, OIL INTERCEPTOR


OIL-INT-CIV-1000 GRP Lining works 3 10-Apr-23 14-Apr-23 37

OIL TANK 2 14-Apr-23 18-Apr-23 37 18-Apr-23, OIL TANK


OIL-TANK-CIV-1000GRP Lining works 2 14-Apr-23 18-Apr-23 37

ROAD AREA 24 01-Apr-23 10-May-23 13 10-May-23, ROAD AREA


RD-CIV-1000 Interlock Laying Works 24 01-Apr-23 10-May-23 13

WALKWAY 25 17-Apr-23 20-May-23 13 20-May-23, WALKWAY


WALKWAY-1000 Interlock Laying Works 25 17-Apr-23 20-May-23 13

MEP WORKS 41 01-Apr-23 30-May-23 7 30-May-23, MEP WORKS


GUARD ROOM 33 05-Apr-23 22-May-23 12 22-May-23, GUARD ROOM
GRD-MEP-1000 CCTV and data - all pending 2 20-May-23 22-May-23 11

GRD-MEP-1010 Fire alaram and fire fighting 4 14-Apr-23 25-Apr-23 36

GRD-MEP-1020 Incommer cable Installation 2 07-Apr-23 10-Apr-23 36

GRD-MEP-1030 Lighting arrestor conencting with earth Pit 3 05-Apr-23 10-Apr-23 36

GRD-MEP-1040 Ac Installation 3 14-Apr-23 24-Apr-23 36

SUBSTATION 8 05-Apr-23 24-Apr-23 36 24-Apr-23, SUBSTATION


SBT-MEP-1000 Wire installation for photosensor 3 05-Apr-23 10-Apr-23 36

SBT-MEP-1010 Electrical Meter cabinet fixing and Wire Pulling 3 14-Apr-23 24-Apr-23 36

SBT-MEP-1020 Capacitor bank cable pulling and termination 2 17-Apr-23 24-Apr-23 36

SBT-MEP-1030 DB-SS cable Pulling 3 11-Apr-23 15-Apr-23 38

SBT-MEP-1040 Lighting arrestor and pit Installation 3 05-Apr-23 10-Apr-23 38

ADMIN BUILDING 41 01-Apr-23 30-May-23 5 30-May-23, ADMIN BUILDING


ADMO-MEP-1000 External CCTV cable pulling and conduting 9 04-Apr-23 24-Apr-23 7

ADMO-MEP-1010 New Entrace camera reloction for Exit Light and Door Exit Light ( As per new drawing) 4 10-Apr-23 15-Apr-23 7

ADMO-MEP-1020 1st Floor IDF installation and cable pulling 4 10-Apr-23 15-Apr-23 7

ADMO-MEP-1030 Data point Pulling 4 10-Apr-23 15-Apr-23 7

ADMO-MEP-1040 Shaft Through Duct, Tray, Piping ( CCTV) Fire damper 4 10-Apr-23 15-Apr-23 7

ADMO-MEP-1050 Roof Plumbing works and final fixtures installationin admin block 6 10-Apr-23 24-Apr-23 17

ADMO-MEP-1060 Roof AC units installation 14 24-Apr-23 10-May-23 17

ADMO-MEP-1070 Roof electrical work(tray and conduit installation ,cable pulling & isolator installation) 6 19-Apr-23 29-Apr-23 7

ADMO-MEP-1080 SMDB AD Termination 3 19-Apr-23 26-Apr-23 10

Critical Remaining Work Milestone Date Revision Checked Approved


Page 2 of 4
04-Apr-23 REMAINING WORK SCHEDULE REV.00 VJS
Actual Work Critical Milestone Data Date : 01-Apr-23
Remaining Work Summary TASK filter: All Activities
PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE AT KIZAD
REMAINING WORK SCHEDULE REV.00

Activity ID Activity Name Original Start Finish Total Float 2023


Duration Mar Apr May Jun Jul Aug Sep Oct Nov
16 17 18 19 20 21 22 23 24
ADMO-MEP-1090 All Earth and Lightning work installation in downside connection and looping with pit 9 29-Apr-23 10-May-23 7

ADMO-MEP-1100 Duct work in admin block 7 01-Apr-23 15-Apr-23 5

ADMO-MEP-1110 Water heater installation 3 15-Apr-23 24-Apr-23 5

ADMO-MEP-1120 Sprinklers instalation 3 15-Apr-23 24-Apr-23 5

ADMO-MEP-1130 smoke detector 6 05-May-23 12-May-23 7

ADMO-MEP-1140 lights,Sockets and switch installation 12 01-May-23 15-May-23 5

ADMO-MEP-1150 data point final installation 4 10-May-23 15-May-23 7

ADMO-MEP-1160 isolator installation 9 15-May-23 25-May-23 7

ADMO-MEP-1170 plumbing final fixtures 14 01-May-23 17-May-23 5

ADMO-MEP-1180 Fire alarm and Firefighting interfacing 11 17-May-23 30-May-23 5

PRODUCTION BLOCK AND TANK FARM 38 01-Apr-23 26-May-23 9 26-May-23, PRODUCTION BLOCK AND TANK FARM
PROD-BLOCK-MEP-1000
isolator Instalation 9 15-May-23 25-May-23 9

PROD-BLOCK-MEP-1010
Final fixtures installation of water supply 2 19-Apr-23 25-Apr-23 9

PROD-BLOCK-MEP-1020
Cable pulling for RO unit and Air compressor Supply cable 9 03-Apr-23 19-Apr-23 9

PROD-BLOCK-MEP-1030
compressor piping 4 05-May-23 10-May-23 9

PROD-BLOCK-MEP-1040
Camera point cable pulling 4 10-May-23 15-May-23 9

PROD-BLOCK-MEP-1050
SMDB 1 Installation & Termination 4 05-May-23 10-May-23 13

PROD-BLOCK-MEP-1060
Earth Pit Instllation 4 25-Apr-23 29-Apr-23 15

PROD-BLOCK-MEP-1070
isolator fixing 8 14-Apr-23 29-Apr-23 13

PROD-BLOCK-MEP-1080
SMDB-2 Fixing & cablet termination 4 05-May-23 10-May-23 13

PROD-BLOCK-MEP-1090
Duct Pipe installation 4 05-May-23 10-May-23 13

PROD-BLOCK-MEP-1100
Light & Switch Fixing 38 01-Apr-23 26-May-23 9

PROD-BLOCK-MEP-1110
Plumbing works and final fixtures installation 6 29-Apr-23 06-May-23 9

PROD-BLOCK-MEP-1120
Equipment Earthing 9 10-May-23 20-May-23 13

PROD-BLOCK-MEP-1130
Tray Installation for isolator & cable pulling 4 25-Apr-23 29-Apr-23 9

PROD-BLOCK-MEP-1140
DB - WELD -trunking Installation 4 25-Apr-23 29-Apr-23 31

PROD-BLOCK-MEP-1150
Welding DB Installation 3 06-May-23 10-May-23 9

PROD-BLOCK-MEP-1160
Exhaust Fan Installation 26 14-Apr-23 20-May-23 13

PROD-BLOCK-MEP-1170
CCTV installation 26 14-Apr-23 20-May-23 13

Corridoor 13 01-May-23 15-May-23 17 15-May-23, Corridoor


PROBLCK-COR-MEP-1000
Light point and Switch Installation 13 01-May-23 15-May-23 17

PUMP ROOM 11 10-Apr-23 29-Apr-23 31 29-Apr-23, PUMP ROOM


PMPR-MEP-1000 Tray installation and cable pulling 4 10-Apr-23 15-Apr-23 31

PMPR-MEP-1010 pipe installation for water supply networks 2 15-Apr-23 19-Apr-23 31

PMPR-MEP-1020 diesel pump Exhaust installation and fire water pipe installation (PRV Line) 2 15-Apr-23 19-Apr-23 31

PMPR-MEP-1030 exhaust fan 3 15-Apr-23 25-Apr-23 31

Critical Remaining Work Milestone Date Revision Checked Approved


Page 3 of 4
04-Apr-23 REMAINING WORK SCHEDULE REV.00 VJS
Actual Work Critical Milestone Data Date : 01-Apr-23
Remaining Work Summary TASK filter: All Activities
PROPOSED MANUFACTURING PLANT FOR AQUACHEMIE AT KIZAD
REMAINING WORK SCHEDULE REV.00

Activity ID Activity Name Original Start Finish Total Float 2023


Duration Mar Apr May Jun Jul Aug Sep Oct Nov
16 17 18 19 20 21 22 23 24
PMPR-MEP-1040 final fixtures(lights and isolators) 6 19-Apr-23 29-Apr-23 31

BLENDING PLANT - STORAGE AREAS 37 10-Apr-23 30-May-23 7 30-May-23, BLENDING PLANT - STORAGE AREAS
BNP-MEP-1000 Installation of high bay Lights 3 15-Apr-23 24-Apr-23 15

BNP-MEP-1010 installation of UPS 5 15-May-23 20-May-23 15

BNP-MEP-1020 Installation of beam detectors 4 10-Apr-23 15-Apr-23 5

BNP-MEP-1030 installation of IDF and CCTV 2 15-Apr-23 24-Apr-23 35

BNP-MEP-1040 SMDB- MIX installation and cable pulling 3 15-May-23 18-May-23 15

BNP-MEP-1050 Fire Hose cabinets and interfacing units inatallation 2 15-Apr-23 24-Apr-23 35

BNP-MEP-1060 duble flap ventilators and mechanical ventilation fans installation 37 10-Apr-23 30-May-23 5

BNP-MEP-1070 All Electrical sockets ,isolators and Plumbing final fixtures installation 2 19-Apr-23 25-Apr-23 35

EXTERNAL AREA 25 07-Apr-23 15-May-23 18 15-May-23, EXTERNAL AREA


EXT-MEP-1000 Oil interceptor 3 15-Apr-23 24-Apr-23 18

EXT-MEP-1010 Eterenal Pole Lights 4 10-May-23 15-May-23 18

EXT-MEP-1020 External pole camara 4 10-May-23 15-May-23 18

EXT-MEP-1030 Panelinstalltion& piping for storm water network 3 15-Apr-23 24-Apr-23 36

EXT-MEP-1040 lightning arrester installation - dropping - Looping 2 07-Apr-23 11-Apr-23 41

TESTING AND COMMISSION 35 22-May-23 26-Jun-23 0 26-Jun-23, TESTING AND COMMISSION


BCC-1000 Consrtuction Finish 0 05-Jun-23 0 Consrtuction Finish

BCC-1010 Project Completion 0 26-Jun-23 0 Project Completion

T&C-MEP 10 22-May-23 05-Jun-23 15 05-Jun-23, T&C-MEP


T&C-1000 Electrical Testing and commissioning 7 25-May-23 05-Jun-23 0

T&C-1010 Water supply Testing and commissioning 7 25-May-23 05-Jun-23 0

T&C-1020 Fire Alarm & Fire Fighting system 7 25-May-23 05-Jun-23 0

T&C-1030 HVAC testing and commissioning 7 25-May-23 05-Jun-23 0

T&C-1040 CCTV system 5 22-May-23 29-May-23 20

AUTORITY INSPECTION 51 12-Apr-23 26-Jun-23 0 26-Jun-23, AUTORITY INSPECTION


ADDC- ELECTRICAL 15 05-Jun-23 26-Jun-23 0 26-Jun-23, ADDC- ELECTRICAL
AUCA-MEP-1000 STAGE 01:INTIAL INSPECTION ADDC 9 05-Jun-23 16-Jun-23 0

AUCA-MEP-1010 STAGE 02:FINAL INSPECTION ADDC 6 16-Jun-23 26-Jun-23 0

ADDC- WATER SUPPLY 15 05-Jun-23 26-Jun-23 0 26-Jun-23, ADDC- WATER SUPPLY


AUCA-MEP-1020 STAGE 01:INTIAL INSPECTION ADDC 9 05-Jun-23 16-Jun-23 0

AUCA-MEP-1030 STAGE 02:FINAL INSPECTION ADDC 6 16-Jun-23 26-Jun-23 0

CIVIL DEFENCE 15 05-Jun-23 26-Jun-23 0 26-Jun-23, CIVIL DEFENCE


AUCA-MEP-1040 STAGE 01:INTIAL INSPECTION ADCD 9 05-Jun-23 16-Jun-23 0

AUCA-MEP-1050 STAGE 02:FINAL INSPECTION ADCD 6 16-Jun-23 26-Jun-23 0

TELEPHONE 7 12-Apr-23 25-Apr-23 44 25-Apr-23, TELEPHONE


AUCA-MEP-1060 STAGE 01: FINAL INSPECTION 7 12-Apr-23 25-Apr-23 44

Critical Remaining Work Milestone Date Revision Checked Approved


Page 4 of 4
04-Apr-23 REMAINING WORK SCHEDULE REV.00 VJS
Actual Work Critical Milestone Data Date : 01-Apr-23
Remaining Work Summary TASK filter: All Activities