Toaz - Info Method Statement For Earthing Installationdocx PR
Toaz - Info Method Statement For Earthing Installationdocx PR
CONTENTS:
1. Scope of works
2. Project organization for Health & Safety Control
3. Health & Safety Risk and Control
4. Access / Egress
5. Lighting
6. Plant & Equipment
7. Personnel Training Certificate
8. Hazardous Materials & Substances
9. Waste Management
10. Special Control Measures
11. Appendixes
Appendixes
Appendix 1: Checklist for Earthing Installation
Appendix 2: Project Organization for Health & Safety control
Appendix 3: Risk Assessment
Appendix 4: Personnel Training Certificate
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993
1. Scope of Works
Scope of Activities
This scope defines the minimum standards to be adopted when installing Earthing in
surfaced concrete/brick wall according to construction co-ordination drawings. The
Electrical Earthing system shall be installed both vertically and horizontally along the
routes shown on the drawings, and shall form the network bonding all switchboards,
control panels, distribution boards, all exposed conductive parts and extraneous
conductive parts to the building’s main earth bar.
Site Procedure
Site mobilization shall be done with real time monitoring the conditions & progress of
builder works. Before commencement of the work, carry out examination of the
physical condition of the area. Photographs should be taken where necessary, prior
to commencement and during works.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993
Method Statement
I. Preparation stage
a. The principle components of a conventional structural lightning protection
system are
1. Down Conductors
2. Bonding
b. Specification allows the use of 'natural conductors' such as rebars and
structural steelwork, provided that they are electrically continuous and
adequately earthed.
c. Prior to install lightning protection system examine paths to ensure all
areas free of debris that may interfere with the installation.
d. Inventory all items immediately after unloading, using manufactures
packing list.
e. All the related material should be stored away from high traffic areas.
have been met, and that the earthing system is safe to connect.
f. A certificate of compliance is completed by a registered Licensed Electrical
Worker in accordance with regulations.
g. After Testing & Commissioning of Earthing Installations, Engineer-in-charge
shall check the complete works and complete the Inspection checklist for T&C
of earthing installation works. ( See annex. 1 )
h. Engineer-in-charge shall arrange and request for inspection with the Owner’s
representative M&E clerks of works (COW) using approved Main con
Request for Inspection (RIN) form. ( See annex.2 )
2. Preferred Materials
N.A
5. Access / Egress
Proper step ladders shall be provided for access and egress into Distribution board as
applicable.
6. Lighting
Adequate temporary/task lighting shall be provided if work to be carried at night or at dark
places.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993
*The above machinery & Equipment used quantity will be varied depending on site conditions
and production rate.
8. Waste management
The Rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.
ANNEX 1:
Inspection Checklist
for Earthing
Installation
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993
ANNEX 2 :
ANNEX 3:
Project Organisation
for Health & Safety
Control
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993
ANNEX 4:
Risk Assessment