TO : Engineer’s
Representative
Mr. Edmund Kwong
CONTRACT NO. 20/WSD/97
YUEN LONG WATER SUPPLY
MAINLAYING BETWEEN
YUEN LONG AND TAN KWAI
TSUEN
&Binnie@
CONTRACTOR’S SUBMISSION
Title of Submission: Method Statement for Construction of New Bus Bay at CH710
Submission Number
CSCE/(20/WSD/9TYCS/925
‘Specification Reference :
Drawing Reference
Description of Contents
‘We would submit herewith a method statement for construction of new bus-bay at CHA710 for your approval.
‘Remarks Ref : 4757/(20/WSD/97V/M25/110/
Distribution Date
Name [Aston | Comment [into
BBVHKL
FILE
Purpose of Submission
For Approval 2 For Information 0 For Record Purposes
Date response required by :-
FROM : Contractor's Agent
NAME : Chris Leung CHINA STATE CONSTRUCTION
SIGNATURE: <3 ENGINEERING CORPORATION
DATE : 12-6 - 2000
FORM CR-02
‘Originator : BryanSubmission Number: CSCE/(20/WSD/97)/CS/925
Method Statement for Construction of New Bus Bay at CHA710
Demolish and remove the existing u-channel concrete covers.
Demolish the existing 225 u-channel along bus-bay
Demolish the existing pavement, excavate the existing sub-base (150mm th.) and ground
soil to reach the formation level.
Construct new 225 u-channel as per RE’s sketch 4757/(20/WSD/97)/S/DR/524 (SNS13)
Laying of KI road kerb as per sketch no. 4757/€20/WSD/97)/S/DR/616B
‘Compact the formation ground and place granular sub-base (150*)
Pour concrete to rigid pavement with A393 steel mesh (250mm th.) and the verge (75mm)
Installation of stee! bollard and type 2 handrails,
Painting of road marking.