Professional Documents
Culture Documents
I keep being puzzled by ONE essential fact that is consistently ignored by Project
personnel:
The duration of a Project is directly linked to how soon you place the purchase
orders for the Equipment ﴾all Equipment, not just the Long Lead Items﴿
Case study 1: On a particular 3 year EPC, no orders were placed before a year ﴾bids
did not fit into the budget﴿. The Contractor kept telling the Client that they will be
on‐time. The Client was unable to challenge this. They would if they had read "The
Oil & Gas Engineering Guide".
Presentation:
https://www.slideshare.net/hbaron/the‐oil‐gas‐engineering‐guide‐2nd‐edition
Please quote BAR2017 for a 25% discount when ordering from the publisher website
﴾link below﴿.
459 · 53 Comments
Like Reply
Simon C. 5y
In terms of percentage of total project capex the welded secondary steelwork needed to
support all the piping and electrical services is a relatively small factor, however the
manufacturing and surface treatment lead‐times, plus often under‐estimated re‐working
delays and costs, are critical : using up‐to‐date and quality/performance certified modular
screw assembly support systems, now capable of load bearing into the multi‐ton area, and
which are adjustable on‐site avoiding costly dismount, or worse scrap‐and‐redo, can greatly
improve ROI and time‐to‐project‐completion, even more so if built into the 3D engineering
model and supply chain specifications up‐front in Feed and Detail design phases.
Like Reply
I have to agree that the need for vendor data is often forgotten, or at best an afterthought. I
always include the delivery of vendor data in my schedules to make sure this requirement is
communicated to all stakeholders. Without this in the schedule, you are setting yourself up
for failure from the beginning.
Like Reply
Giorgio Monti 5y
very true
Like Reply
Tushar Zope 5y
Days are gone! Most customers start construction immediately after concept design is frozen.
Alan Kernaghan 5y
Stewart OBrien
Like Reply
Like Reply
Blas Azucenas 5y
FEED....
Like Reply
Bashir Mirza 5y
That is why smart clients conclude large equipment ordering prior to the LS EPC award. The
cost savings accrued from contractor "buy outs" are soon lost in the sea of delays in the
design and construction of steel and piping. Engineers love fine tuning, and project managers
must make engineering move forward when the plant can be run safely and is operable.
Like Reply
Explore topics
Workplace
Job Search
Careers
Interviewing
Internships
Employee Benefits
See All
© 2023 About
Language