Professional Documents
Culture Documents
Project Construction
Project Construction
CIEG 486-010
Construction Methods & Management
CIEG 486-010
Construction Management
Construction Management
• Contractual arrangement
• Construction management personnel can
represent owner or contractor
• CM manages the basic resources of
construction
Basic Resources
• workforce • material
• subcontractors • information
• equipment • time
• construction • money
plant
Construction Methods & Management
CIEG 486-010
Project Management
• Optimize the three attributes of: quality, cost,
and time
• Principle objective of a construction manager
is to complete each project on time and within
budget, while maintaining acceptable levels
of safety and risk
Construction Methods & Management
CIEG 486-010
Traditional Design-Bid-Build
Construction phase
Suspended Steel
Trusses/Framing
West Approach
East Approach
Main Cables
Bridge Deck
Anchorages
West Piers
East Piers
Test Piles
Lighting
Towers
Construction Methods & Management
CIEG 486-010
Contract Types
• Traditional vs. alternative
• Classification by method of award and
method of pricing
• Model contracts have been developed
by AIA, AGC, CEC, DBIA, CMAA, and
Engineers Joint Contract Documents
Committee (EJCDC)
Construction Methods & Management
CIEG 486-010
Contract Types
Method of Award
1. Competitive bidding
– formally advertised public work
– selective invitation for private work
– awarding of contracts by:
• Lowest responsible bid or
• Best value i.e.: technical score price or
price + time(ft), and other variations
Construction Methods & Management
CIEG 486-010
Contract Types
Method of Award
2. Negotiated contracts
– Generally private work
– Benefits include flexibility of pricing arrangement
– Often used on projects of large size and great
complexity
– Owner may value expertise and integrity of a
particular contractor and can award contract without
competition that may otherwise exclude that
contractor from the work
Construction Methods & Management
CIEG 486-010
Method of Pricing
Fixed-price
1. Lump sum
– Traditional, single fixed price
– Predetermined price that includes profit,
overhead, and all other costs
– Greatest risk to contractor resulting in a
higher markup (the greater the risk, the
higher required rate of return )
– Most common contract form
Construction Methods & Management
CIEG 486-010
Method of Pricing
Fixed-price
2. Unit-price contract
– Prices of specified units of work are fixed or
predetermined
– Actual cost to the owner will vary with actual
quantities placed
– Best used when details and general character
of the work are known, but quantities are
subject to variation
– Risk of unbalanced bids
Construction Methods & Management
CIEG 486-010
Method of Pricing
Cost-plus
• Contractor agrees to perform the work for a fixed
or variable fee covering profit and home office
costs (general overhead)
• Field costs are reimbursable at actual cost
• Used when:
– nature of the work or physical conditions are
unpredictable
– scope is unknown or difficult to define
Construction Methods & Management
CIEG 486-010
Method of Pricing
Cost-plus
• All cost-plus contracts depend on cooperation
among A/E, owner, and contractor
• Record keeping and timely evaluation are
extremely critical
• Detail record of labor hours and salaries,
material and equipment must be maintained
• Good application for professional CM services
Construction Methods & Management
CIEG 486-010
Construction Contracts
• Prequalification of bidders
– Evidence of satisfactory previous experience
– Financial stability
– Advanced or specialized prequalification may be
required as dictated by the magnitude and nature
of the work
– Bid bonds are often required
Construction Methods & Management
CIEG 486-010
Construction Contracts
……bidders are required to:
– examine all portions of the contract documents
– examine the physical conditions of the site
– determine legal requirements affecting the work
– complete these investigations prior to bidding
Construction Methods & Management
CIEG 486-010
Construction Contracts
……contract documents should:
– Include a hierarchy to determine which
documents govern in case of conflict, i.e.:
DelDOT’s hierarchy
– Not contain ambiguous language
– Not contain exculpatory clauses
Construction Contracts -- General Conditions
• Contractor’s warranties • Inspection of materials
• Defective drawings • Inspection of field work
• Approval of contractor’s • Authority of the Eng’r.
plans and equipment • Duties of the inspector
• Approval of shop drawings • Permits and licenses
other submittals • Labor considerations
• Guarantee by the • Work done by the owner
Contractor
• Lines and grades
• Conduct of the work
• Order and discipline
• Defective work
• Performance
• Relations with other
contractors and • Final inspection &
subcontractors acceptance
Construction Contracts -- General Conditions
• Federal, state, and local • Retainage
government regulations • Bonding and insurance
• Employment (EOE rules) • Guarantee of equipment
• Emergencies • Borings
• Minimum wage rate • Spare parts
• Domestic vs.foreign
materials and labor
• Construction reports
• Payrolls and bills of material
• Cooperation among
contractors
• Patents
Risk Allocations -- General Conditions
Specifications
• Standard, supplemental, and special
provisions
• two types of specifications:
– method specification dictates equipment
and procedures
– performance spec specifies only the
desired end result or product
– should include hierarchy
Construction Methods & Management
CIEG 486-010
Hierarchy
Governing ranking of contract components in
case of a discrepancy (DelDOT)
• General Notices
• Special Provisions
• Plans
• Supplemental Specifications
• Standard Construction Details
• Standard Specifications
Construction Methods & Management
CIEG 486-010
Shop Drawings
– structural steel details & erection plan
– erection procedures (safety)
– PS/PC concrete items
– shoring & underpinning details
– jacking plans and calculations
– scaffolding and falsework
– concrete formwork design and details
– construction sequencing diagrams
Construction Methods & Management
CIEG 486-010
Shop Drawings
– cofferdam design & details
– dewatering procedure
– stream diversions
– pipe and ductwork fabrication details
– reinforcing steel bending diagrams and bar lists
– structural timber elements
– ornamental iron or steel
– maintenance of traffic plans (alternates)
Construction Methods & Management
CIEG 486-010
Change Orders
– a written order issued by the owner to the
contractor for a change to the contract within
the scope of work
– change orders are written for:
• extra work
• increasing or decreasing the contract quantities
• alterations
– change orders state the basis and amount of
payment and time extensions
Construction Methods & Management
CIEG 486-010
Contracts
• Liquidated damages
• Incentive/Disincentive (bonus/penalty)
• Acceleration
– Increase crew levels, crew size
– Add shifts and/or extend work hours
• CPM schedule is an extremely valuable tool in
analyzing delay claims
Construction Methods & Management
CIEG 486-010
Types of Claims
– delay or disruption claim
– extra work claim
– acceleration
– impossibility-of-performance claim
– defective design claim (error or omission)
– interference claim
– superior knowledge claim
Construction Methods & Management
CIEG 486-010
Dispute Resolution
• Early settlement between parties
• Alternative depute resolution (ADR)
– negotiation – arbitration (1 or 3 members)
– mediation – neutral advisors
– Dispute Review Board (DRB)
• 3 or more odd number of board members selected
evenly by both sides
• Litigation
– sometimes unavoidable; usually undesirable; but
sometimes best method
Construction Methods & Management
CIEG 486-010
Credits
• Credits – reimbursement from contractor to
owner for work eliminated (lump sum
contract or item)
• Credit may also be given when specified
performance criteria is not met
Construction Methods & Management
CIEG 486-010
Claims Avoidance
• producing comprehensive, accurate, contract
documents
• constructibility review
• clear understanding of contract requirements prior to
bidding
• having good administrative procedures in place
• open and honest communication
• timely troubleshooting
Construction Methods & Management
CIEG 486-010
Claims Avoidance
• Claims avoidance begins in the pre-
construction phase
AyIf
Level of Influence on Cost
0%