Professional Documents
Culture Documents
Construction Management 508 PDF Free
Construction Management 508 PDF Free
promote the successful execution of capital projects for owners. These projects can be highly
complex. Few owners maintain the staff resources necessary to pay close, continuing attention to
Construction Project Management is the overall planning, co-ordination and control of a project
functionally and financially viable project that will be completed on time within authorized cost
and to the required quality standards. Project management is the process by which a project is
management that applies to the construction sector (3rd Forum ”International Construction
The Construction Management Association of America (CMAA) says the 120 most common
- Cost Management
- Time Management
- Quality Management
- Contract Administration
- Safety Management
- CM Professional Practice
CM Professional Practice which includes specific activities like defining the responsibilities and
management structure of the project management team, organizing and leading by implementing
project controls, defining roles and responsibilities and developing communication protocols,
and identifying elements of project design and construction likely to give rise to disputes and
claims.
services applied to construction projects and programs through the planning, design, construction
and post construction phases for the purpose of achieving project objectives including the
A professional CM can augment the owner's staff with pre-planning, design, construction,
engineering and management expertise that can assure the best possible project outcome no
"Agency" CM is a professional service that can be applied to all delivery systems where the CM
acts as the owner's principal agent in the management of a construction project or program,
where the CM is responsible to the owner for managing the planning, design, construction and
post construction phases, or portions thereof. The CM represents the interests of the project in its
dealings with other construction professionals, and with other private and public entities.
Project scheduling
Comprehensive management of every stage of the project, beginning with the original concept
and project definition, yields the greatest possible benefit to owners from Construction
Management.
deliver the project within a Guaranteed Maximum Price (GMP). The construction manager acts
as consultant to the owner in the development and design phases, but as the equivalent of a
general contractor during the construction phase. When a construction manager is bound to a
GMP, the most fundamental character of the relationship is changed. In addition to acting in the
MEETINGS
PURPOSE
Various meetings are held on a regular basis to provide a platform for those parties involved in
the delivery of the project to come together to discuss those items, issues, processes, procedures,
etc. that are required to complete the project, as required by contract. These platforms will also
provide a vehicle to identify and track the responsibility of those parties involved with specific
issues, and the status and progress of various items and issues. Some of the typical project
coordination meetings, change order negotiation meetings, Request for Equitable Adjustment
(REA) resolution meetings, Notice of Non-Compliance (NNC) and Job Memorandum (JM)
resolution meetings are commonly used for problem prevention and resolution. The purpose of
RESPONSIBILITIES
Construction Manager (CM): The CM, or designee, is primarily responsible for meeting
distribution, and follow up on issues that require action by the various participants of the
attending all required meetings, ensuring that the appropriate subcontractor, supplier, vendor, etc.
is notified of required attendance (as necessary), and preparation and distribution of Contractor
PROCEDURE
Pre-Construction Meeting
The Pre-Construction Meeting provides the project participants with a basic project orientation
of the roles, responsibilities, processes and procedures, and frontend priorities for the project.
The lines of communication and the project required processes and procedures for items such as
requirements, submittals, RFI’s, and change orders should be addressed in this meeting.
The Pre-Construction Meeting should be held within 15 working days after issuance of the
Notice to Proceed. The attendees may include the following individuals or organization
representatives:
1. Owner/Client Representative
8. Principal Construction Inspector, the Lead Inspector, and a representative from BCA’s
9. City Scheduler
11. Utility representative (DWP, natural gas company, telephone company, etc.)
12. Other City agencies (Sanitation, DOT, Police, Fire, Building and Safety, etc.)
13. Other government agencies that have a direct influence on the execution of the project
The CM prepares the meeting Agenda. After preparation of the Agenda, written notification of
the meeting is distributed to required and requested attendees. The status of the attendee, either
required or requested, should be indicated on the notification. The notice should also include a
copy of the Agenda, and the time, place and date of the meeting. Preparation for the meeting
should include a sign-in sheet, and any required handouts and notes for the meeting. Meeting
The Weekly Construction Progress Meetings are held to discuss general project status, specific
1. CM
2. PE (as required)
3. Lead Inspector
5. Owner/Client Representative
The meeting Agenda is prepare and distributed at the meeting. The CM presides over the
2. Job Memos and outstanding Non-Compliances Issued. The CM should establish a timeline for
3. Record Drawings.
4. Change Orders (CO). The CM should establish the responsible party and a time limit for
5. Submittals. The CM should establish priorities for processing all unapproved submittals.
6. Requests for Information (RFI) and Plan Clarifications (PCs). The CM should establish time
7. Construction Schedule.
outstanding item.
10. New Business. The CM should establish the responsible party and a time limit for each
outstanding item.
The Monthly Schedule Update Meetings are held to review and discuss required monthly
submittals, such as progress payments, schedules and trade staffing levels. In addition, some of
the issues and topics discussed in the Weekly Construction Progress Meetings may also be
addressed in these meetings, if necessary. CM staff and the Contractor may elect not to have a
monthly meeting, if the issues to be addressed in the monthly meeting are covered and addressed
The attendees and procedures are the same as the Weekly Construction Progress Meeting noted
above.
Partnering meetings are utilized to follow up on action items established during formal
partnering sessions (see Procedure 15.1). During these meetings, PM level and Sponsor level
2. Project schedule.
3. Partnering strategy.
4. Outstanding issues.
The CM Team Meeting is utilized to monitor progress and identify issues hindering construction
of a specific project. The attendees shall include the City’s CM Team only (PM, CM, PE,
Support Staff). During these meetings, the CM Team reviews and discusses the progress of the
project, including schedule variances and problem areas; responsibilities are assigned and
timeframes established for resolution of identified issues. The responsible parties report back in
subsequent meetings on progress being made toward resolution of previously identified issues,
and reports any additional issues identified. Meeting minutes (if required) are processed.
The CM Staff Meeting is utilized to provide staff training and ensure uniformity in managing all
of the construction projects within a Program or Division. The attendees shall include the CMs,
estimator(s) and scheduler(s). During these meetings, the CM staff should discuss:
2. Current issues affecting the contracting community and understand how they may impact