You are on page 1of 34

SCHEDULE H -

SUBSTATION

Page 1 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

The items and par culars in Schedule H are the Definite Items of the Plant switchgear or equipment
and its associated works in this Contract. The Schedule is divided into several parts, i.e.:

 Part 1: Plant Primary Equipment


 Part 2: Plant Secondary Equipment
 Part 3: Plant Telecontrol Equipment
NA Part 4: Telecommunica on
 Part 5: Power Cables
 Part 6: Civil Works
 Part 7: Common Works Items
 Part 8: Miscellaneous Items
NA Part 9: O/H Lines

The Parts indicated with  shall form part of the Schedule H or NA for ‘not applicable’.

The Schedule shall be read in conjunc on with the schedule of drawings and the Technical
Specifica ons indicated in the Condi on of Contracts. In case of contradic on, FIDIC Clause 1.5
(Priority of Documents) shall prevail. All related engineering and design works associated with the
project and schedules shall be included as part of the Items.

The Works shall include any work which is necessary to sa sfy the Employer’s Requirements,
Contractor s Proposal and Schedules, or is implied by the Contract, and all works which (although not
men oned in the Contract) are necessary for stability or for the comple on, or safe and proper
opera on, of the Works as per FIDIC Clause 4.1.

Items not specifically men oned in this Schedule but necessary to be included for the complete and
sa sfactory opera on of the system as specified by the Specifica ons (including special tools for
construc on, tes ng, opera on, and maintenance purposes of the equipment) shall be deemed to
be included in the Contract Price.

The Contractor is fully responsible to comply with the design requirements as specified in
Specifica ons and to ensure sa sfactory opera on and maintenance of the equipment installed or
rehabilitated under this Contract.

The Contractor shall provide Design Consultancy Services from Engineering consul ng firm with valid
registra on with BEM. The consultant shall be responsible for all design and supervision of civil and
structural (C&S), mechanical and electrical (M&E) and architectural and planner related to the
project. When required, the consultant prepare submission, and obtaining approval for Cer ficate of
Comple on and Compliance (CCC) and liaise with relevant authori es. The Contractor shall submit all
drawings for approval with Malaysia Professional Engineer with Prac sing Cer ficate (PEPC)
endorsement under the scope of work in this contract under the Registra on of Engineers Act and
Regula ons (Act 138 - Revised 1988), Part I, Clause 8. It required only Professional Engineers with
Prac sing Cer ficate (of the relevant discipline) registered with the Board of Engineers, Malaysia

Page 2 of 34
(BEM), may cer fy and submit plans, drawings, schemes, proposals, reports, designs or studies to
any person or authority in Malaysia. This requirement shall be strictly enforced without excep on.

The original equipment manufacturer (OEM) is required to supervise erec on works for all new
Circuit Breaker, Disconnector and Earth Switch at the respec ve substa on and to ensure compliance
to their standard erec on procedure and quality workmanship.

TNB Accepted Relay List enclosed in the tender document shall serve as reference for tendering
purposes only. The successful Tenderer shall supply relays based on the TNB Accepted Relay List
prevailing at the me of contract award and the models to be supplied shall be declared at the
contract kick-off mee ng.

The Schedule shall be read in conjunc on with HSE Requirement for Contractor indicated in the
Condi on of Contracts and shall be deemed to be included in the Contract Price.

Before commencement of the test of comple on, the Contractor shall provide four (4) sets of
approved and bound plant and ancillaries’ drawings, installa on, opera on and maintenance
manuals shall be submi ed to the Client.

Before the expiry of the Defect No fica on Period, the Contractor shall supply to the Client four (4)
bound hard copies and four (4) so copies of all as-built drawings, installa on, opera on and
maintenance manuals for each substa on in a form of AutoCAD for drawings and Portable Document
Format (PDF) format for manuals using thumb drive.

The prices for the individual items shall be entered in Schedule of Prices indicated in the Condi on of
Contracts. The offer is to be a fixed Lump Sump without quan es and not subject to
measurements. The amount quoted shall allow for compliance with the Condi on of Contracts,
Par cular Condi on to the Condi on of Contract (FIDIC Yellow Book Ed. 1999), Employer's
Requirement and Specifica on shall be deemed to include for all labour, materials, tools, equipment
and all relevant machineries for the proper execu on and comple on of all works and to the
sa sfac on of the Employer and relevant authori es.

The Contractor is fully responsible on successful coordina on, interfacing with overhead line and/or
underground cable and/or remote end (where applicable) contractor during design, construc on,
tes ng and commissioning of this scope of Works.

Page 3 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 1: PLANT PRIMARY EQUIPMENT

BILL OF QUANTITY

ITEM DESCRIPTION

No Item Quan ty
1 132-OHF 6
2 132-BC 1
3 132-BBVT 2
4 132-AL 5
5 LR Lump sump
6 ES Lump sump
7 ST2 Lump sump

132kV CONVENTIONAL SWITCHGEAR

Outdoor 132kV double busbar 3150A open terminal switchgear with fault ra ng,
as stated in the Contract, of 31.5kA for 3 seconds.

Minimum Specific Creepage Distance for outdoor equipment shall be 25 mm/kV.

ALL EQUIPMENT SHALL BE 3-PHASE UNLESS STATED OTHERWISE.

The equipment to be supplied and installed are generally as shown on drawings


(refer to tender drawings) and as detailed in the Specifica ons complete with
galvanized steel support structures, access ladders, pla orm, and walkways,
where relevant and necessary etc., to complete, comprising: -

132-OHF 132kV 1600A OVERHEAD LINE FEEDER BAY, EACH BAY IS EQUIPPED WITH: -

Quan ty Item
a 2 sets Busbar disconnectors
b 1 set Circuit breaker
c 1 set Current transformers
d 1 set Feeder disconnector with earth switch
e 1 set Capacitor voltage transformers
f 1 set Surge arresters
g 1 set i. Complete set of stranded aluminium conductors with
adequate ampacity for transfer busbars, circuit
connec on between all the equipment and to
busbars, including clamps, connectors, jumpers,
fi ngs, suspension, and tension insulator sets, to
complete.
ii. Rigid aluminium tubular conductors with adequate
ampacity for circuit connec ons between busbar

Page 4 of 34
disconnectors including clamps and connectors, to
complete. The Contractor shall submit all the rigid
aluminium tubular conductor’s calcula on but not
limited to current carrying capacity, sagging and
deflec on, short circuit current and short circuit force
calcula on.
h 1 nos Marshalling kiosk

132-BC 132kV 3150A BUS-COUPLER BAY, EACH BAY IS EQUIPPED WITH: -


Quan ty Item
a 2 sets Busbar disconnectors
b 1 set Circuit breaker
c 2 set Current transformers
d 1 set i. Complete set of stranded aluminium conductors
with adequate ampacity for transfer busbars,
circuit connec on between all the equipment and
to busbars, including clamps, connectors,
jumpers, fi ngs, suspension, and tension
insulator sets, to complete.
ii. Rigid aluminium tubular conductors with
adequate ampacity for circuit connec ons
between busbar disconnectors including clamps
and connectors, to complete. The Contractor shall
submit all the rigid aluminium tubular conductor’s
calcula on but not limited to current carrying
capacity, sagging and deflec on, short circuit
current and short circuit force calcula on.
e 1 nos Marshalling kiosk
132-BBVT 132kV 1600A BUSBAR VT BAY, EACH BAY IS EQUIPPED WITH: -

Quan ty Item
a 1 sets Busbar disconnectors
c 1 set Induc ve Voltage transformers
d 1 set i. Complete set of stranded aluminium conductors
with adequate ampacity for transfer busbars,
circuit connec on between all the equipment and
to busbars, including clamps, connectors,
jumpers, fi ngs, suspension, and tension
insulator sets, to complete.
ii. Rigid aluminium tubular conductors with
adequate ampacity for circuit connec ons
between busbar disconnectors including clamps
and connectors, to complete. The Contractor shall
submit all the rigid aluminium tubular conductor’s
calcula on but not limited to current carrying
capacity, sagging and deflec on, short circuit
current and short circuit force calcula on.
e 1 nos Marshalling kiosk

Page 5 of 34
132-AL 132kV 3150A TUBULAR ALUMINIUM BUSBARS, PER BUSBAR SECTION: -

Quan ty Item
a 2 sets Tubular aluminium busbars to complete (Main and Reserve
busbar)
b 1 set Post insulator(s) for moun ng of busbars, and all other
accessories including clamp, end caps and damper wire, etc.,
to complete

The Contractor shall submit all the rigid aluminium tubular conductor’s
calcula on but not limited to current carrying capacity, sagging and deflec on,
short circuit current and short circuit force calcula on.

LR LIGHTNING PROTECTION SYSTEM USING LIGHTNING RODS:

The lightning protec on system shall include various components including


lightning rods and eleva on rods, PVC insulated copper (for counters) and copper
tape down conductor, control junc on, earth termina on system and lightning
strike counter wherever appropriate for complete shielding of switchyard and
plant against direct lightning strikes.

The lightning protec on system study report shall be submi ed for approval.

Quan ty Item
a Lump sump Lightning rods
b Lump sump Lightning counter
c Lump sump Accessories and fi ngs

Complete descrip ons of the lightning rods system are as per TNB specifica on.

ES SUBSTATION EARTHING SYSTEM

Earthing system for the substa on and all equipment comprising complete set of
copper tapes, earth electrodes, test links, etc., and all connec ons to equipment
for all voltage levels supplied under this Contract including, where relevant but
not limited to steel-reinforce bonded to the perimeter fencing, interface
requirements with exis ng earthing system and earthing or lightning protec on
system of buildings, underground cables, and overhead lines. The soil resis vity,
earthing study report and calcula on shall be submi ed for approval.

Where reasonably prac cal, earthing conductors shall be embedded in concrete


for purpose of control against the .

Complete descrip ons of the earthing system are as per TNB specifica on.

ST2 STEEL STRUCTURES WITH TUBULAR TYPE GANTRY TOWER(S) FOR THE WHOLE
SUBSTATION: -

Page 6 of 34
One set of tubular type steel structures (for the en re outdoor switchyard,
including where relevant, structures for equipment support at the other side of
power cable end for hybrid cable-overhead connec on) for gantry towers,
gantries, tower or tower extension for earth wire or lightning rod, support for
main equipment and earth mast/lightning rod, etc., to complete.

Where the detailed design requires the use of gantries or support structures for
addi onal support of busbars or conductors, although not indicated in the
tender drawing, the structures (and the relevant insulators and fi ngs) are
deemed included.

Page 7 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 2: PLANT SECONDARY EQUIPMENT

132KV PROTECTION AND CONTROL

No Item Quan ty
1 132-OHF/DCP 6
2 132-OHF/DRP 6
3 132-BC/DCP 1
4 132-BC/DRP 1
5 132-BBP/DRP 1
6 132-WIP 1

SUBSTATION AUXILLARY SUPPLIES

No Item Quan ty
1 APC 1
2 OFC 1
3 LVAC 1
4 DC 1

Page 8 of 34
ITEM DESCRIPTION

SUBSTATION 132kV DIGITAL PROTECTION & CONTROL

132-OHF/DCP 132kV INDOOR DIGITAL REMOTE-CONTROL PANEL FOR OVERHEAD


LINE FEEDER BAY EQUIPPED WITH: -

a) Bay Controller Unit with IEC 61850


b) Managed Ethernet Switch
c) Digital Power Meter (DPM)
d) DC supervision relays
e) Mimic diagram with:
i. SELECT push bu on for Plant Item (circuit breaker and isolators),
ii. OPEN and CLOSE push bu on with indica ng lamp,
iii. Emergency OPEN CB push bu on, and
iv. Semaphore indica on for circuit breaker, isolators, and earthing
switch
f) Annunciator with 6-ways window and facili es for accept, cancel, and test.
g) Trip relays reset (illuminated type) and lamp test push-bu ons.
h) Front mounted AC 240V 13A supply socket
i) Glazed transparent acrylic window front cover door.
j) All necessary selector switches, push bu on switches, auxiliary relays,
bistable relays, contactors, MCB's, test terminal blocks, sliding link terminals
blocks with spring loaded type, drawing compartment, fibre op c
connectors, indica ng lamps, energy saving LED, an -condensa on heater,
earthing bar, trip links, etc., to complete.

132-OHF/DRP 132kV INDOOR DIGITAL PROTECTION RELAY PANEL FOR OVERHEAD


LINE FEEDER BAY EQUIPPED WITH: -

a) Current Differen al with IEC61850 protec on relays suitable for three


terminal uses (to be matched with remote end) with op cal fibre links,
interfacing with PCM Mul plexer via IEEE C37.94 protocol.
b) Backup Distance with IEC61850 protec on relay
c) Breaker Management with IEC61850 (CBM)
d) Trip circuit supervision for each trip coils
e) Electrically reset lockout master tripping relay.
f) Front mounted AC 240V 13A supply socket
g) Group isola on link for each main, backup protec on and CBM
h) Glazed transparent acrylic window front cover door.
i) All necessary selector switch, auxiliary relays, bistable relays,
contactors, MCB's, test terminal blocks, sliding link terminals blocks,
drawing compartment, fibre op c connectors, indica ng lamps,
energy saving LED, earthing bar, trip links, etc., to complete.

Note: The characteris c of propose Current Transformer as follows: -

Core 1: 900/450/1A Class 5P20, 30VA for Main Protec on


Core 2: 900/450/1A Class 5P20, 30VA for Backup Protec on
Core 3: 900/450/1A Class 0.5, 30VA, FS5 for Bay Controller and Instrumenta on

Page 9 of 34
Core 4: 3000/1A Class PX, Vk≥600V, Rct ≤12 Ohm and Im≤10mA at Vk/2 for
busbar protec on – Spare
Core 5: 3000/1A Class PX, Vk≥600V, Rct ≤12 Ohm and Im≤10mA at Vk/2 for
busbar protec on – Low Impedance

Note: The characteris cs of proposed Voltage Transformer as follows: -


Secondary Winding 1: Class 3P, 50VA for Protec on
Secondary Winding 2: Class 0.5, 50VA for Instrument and Control

The CT and VT calcula on shall be submi ed for approval.

132-BC/DCP 132KV INDOOR DIGITAL REMOTE-CONTROL PANEL FOR BUS COUPLER


FEEDER BAY EQUIPPED WITH: -

1. Bay Controller Unit with IEC 61850


2. Sta on Input & Output IED with IEC61850
3. Sta on Managed Ethernet Switch
4. Digital Power Meter (DPM) for Main busbar
5. Digital Power Meter (DPM) for Reserve busbar
6. DC supervision relays
7. Mimic diagram with:
i. SELECT push bu on for Plant Item (circuit breaker and isolators),
ii. OPEN and CLOSE push bu on with indica ng lamp,
iii. Emergency OPEN CB push bu on, and
iv. Semaphore indica on for circuit breaker, isolators, and earthing
switch
8. Annunciator with 6-ways window and facili es for accept, cancel, and test.
9. Trip relays reset (illuminated type) and lamp test push-bu ons.
10. Front mounted AC 240V 13A supply socket
11. Glazed transparent acrylic window front cover door.
12. All necessary selector switch, auxiliary relays, bistable relays, contactors,
MCB's, test terminal blocks, sliding link terminals blocks, drawing
compartment, fibre op c connectors, indica ng lamps, energy saving LED,
earthing bar, trip links, etc., to complete.

132-BC/DRP 132KV INDOOR DIGITAL PROTECTION RELAY PANEL FOR BUS


COUPLER FEEDER BAY EQUIPPED WITH: -

a) Backup Distance Protec on with IEC61850 relay for Main busbar


b) Backup Distance Protec on with IEC61850 relay for Reserve busbar
c) Breaker Management with IEC61850
d) Trip circuit supervision for each trip coils
e) Electrically reset lockout master tripping relays
f) Front mounted AC 240V 13A supply socket
g) Glazed transparent acrylic window front cover door.
h) Group isola on link on each backup protec on and CBM
i) All necessary selector switch, auxiliary relays, bistable relays, contactors,
MCB's, test terminal blocks, sliding link terminals blocks, drawing
compartment, fibre op c connectors, indica ng lamps, energy saving LED,
earthing bar, trip links, etc., to complete.

Page 10 of 34
Note: The characteris cs of propose Current Transformer on Main Busbar side
as follows: -

Core 1: 3000/1A Class 5P20, 30VA for Distance protec on


Core 2: 3000/1A Class PX, Vk≥600V, Rct ≤12 Ohm and Im≤10mA at Vk/2 for Low
Impedance Busbar Protec on

Note: The characteris cs of propose Current Transformer on Reserve Busbar side


as follows: -

Core 1: 3000/1A Class 0.5, 30VA, FS5 for Bay Controller and Instrumenta on
Core 2: 3000/1A Class 5P20, 30VA for Breaker Management (CBM) & Distance
protec on
Core 3: 3000/1A Class PX Vk≥600V, Rct ≤12 Ohm and Im≤10mA at Vk/2 for Low
Impedance Bubsar Protec on

Note: The characteris cs of propose Voltage Transformer on Main and Busbar as


follows: -
Secondary Winding 1: Class 3P, 50VA for Protec on
Secondary Winding 2: Class 0.5, 50VA for Instrument, Control & Sta on IOIED

The CT and VT calcula on shall be submi ed for approval.

132-BBP/DRP ONE (1) SET OF INDOOR DIGITAL LOW IMPEDANCE BUSBAR PROTECTION RELAY
PANEL FOR 132KV DOUBLE BUSBAR CONFIGURATION EQUIPPED WITH: -

a) Low Impedance Differen al Busbar Protec on system with IEC 61850 for all
132kV bays
b) For Bus Coupler bay acquisi on unit shall use Current Transformers on both
sides of the CB.
c) Group isola on link on each bay
d) Self-reset tripping relays for each bay (if require/necessary)
e) Protec on in service/out of service selector switches
f) Front mounted AC 240V 13A supply socket
g) Glazed transparent acrylic window front cover door for Central unit and Bay
acquisi on unit.
h) An -condensa on heater, On/Off switch, indica ng lamp and thermostat.
i) All necessary selector switch, auxiliary relays, bistable relays, contactors,
MCB's, test terminal blocks, sliding link terminals blocks, drawing
compartment, fibre op c connectors, indica ng lamps, energy saving LED,
earthing bar, trip links, etc., to complete.

132-WIP ONE (1) SET OF 132kV WAIS INTERFACE PANEL (WIP) EQUIPPED WITH: -

a) To install WAIS devices inclusive internal wiring (The WAIS devices will be
supplied, configured, tested & commissioned by the TNB. The Contractor
shall arrange the devices to be taken from Client designated office to site. All
cost transporta on, mobilise, demobilised, loading, unloading etc. shall be
under the Contractor)
b) All necessary interfacing circuit from WIP panel to control and relay panels:

Page 11 of 34
i. Current circuit and VT circuit from backup protec on CT core and
protec on VT winding
ii. 4-20mA current circuit of circuit breaker’s trip coil, closing coil and
motor (mul pair instrumenta on cable)
iii. Busbar voltage from protec on VT winding for Main and Reserve
busbar
c) Isola on trip link at WIP panel for all CB Opening circuit to control panels.
d) Coaxial cable with BNC connector from Sta on Time Server (STS) at SGW
panel to WIP panel. Daisy chain connec on if more than one (1) WIP panel
e) CAT5E cable with RJ45 connector and serial twisted pair (mul pair
instrumenta on cable) with DB9 connector from WAIS panel to WIP panel
f) WAIS Disable switch WIP panel.
g) Front mounted AC 240V 13A supply socket
h) Glazed transparent acrylic window front cover door.
i) All necessary selector switches, MCB’s, sliding link spring loaded terminals
blocks, drawing compartment, energy saving LED, earthing bar, etc., to
complete.

Note: Addi onal WIP panel is required if the total number of CBs are more than
15 CBs.

APC AUXILIARY POWER AND CONTROL CABLES

Interfacing cables between all equipment supplied under this Contract.


and supplied by others.

The Works to be inclusive of: -


a) Mul core, screened twisted pair and screened copper Ethernet (minimum
CAT 5E) cables for all primary and secondary equipment including the
telecontrol equipment, telecommunica on equipment, Ethernet Managed
Switch (ESM) etc. to complete.
b) The complete set of auxiliary power, mul core control cables including cable
trays, cable ladders, racks, cleats, supports, cable glands and all necessary
termina ons kits, etc. to complete.
c) All relevant schemes not limited to the following, e.g., voltage selec on,
synchronizing, busbar protec on, live transfer, interlocking, monitoring,
measurement, inter-tripping i.e., sending/receiving to remote end
substa ons etc., to complete.

All cables shall be direct buried (at switchyard subject to soil inves ga on result)
and/or laid on cable ladder/trays (inside control building. The cable ladder/trays
to match with exis ng size where applicable) as per TNB specifica on. Op cal
fiber cables outside of building shall be laid in HDPE pipe, while inside of building
shall be laid in flexible metal corrugated conduits.

For cable laying inside cable trench with the depth is equals or more than
600mm, cable trays shall be provided inclusive of supports for cable trays fixed in
concrete. Where cable tray is provided, minimum width of cable trench shall be
1000mm.

Page 12 of 34
OFC FIBRE OPTIC CABLES: -

Interfacing fiber op c cables including op cal fibre connectors, op cal fibre


junc on boxes, cable management guide, cable trays/casing, cable spare and all
necessary termina ons between all equipment supplied under this contract and
supplied by others including the following to complete: -

a) Backbone communica on for IEC 61850 Sta on Bus between Managed


Ethernet Switches.
b) Cabling between Managed Ethernet Switches and IEDs or Clients
c) Cabling from Line Protec on IEDs to Communica on Panel
d) Cable Management and Accessories.

Any cabling between buildings or panels with physical distance apart shall be laid
in the form of armoured cable.

Any cabling across adjacent panels shall be laid in the form of patch cord.

Cable Management and Accessories shall include bend radius and physical
protec on to ensure cables are properly handled, supported, and protected to
prevent any micro or macro bending or subjected to any poten al tensile load.

Cable Management shall also ensure proper design of cable rou ng paths and
easy cable access.

Green enclosed metal trunking, racks, cleats and supports are to be supplied
under this item.

Type of cable between IED to Communica on Panel shall be referred to the


product technical specifica on.

LVAC ONE (1) SET OF 415V LVAC EQUIPMENT COMPRISING: -

a) Two 400A 3-phase 4-wire moulded case circuit breakers MCCB for main
incoming supplies and one 400A MCCB for bus-sec on, all mechanically and
electrically interlocked
b) Two 150A MCCB for supplies to oil treatment plant for future use.
c) 4-phase segregated air insulated high conduc ng copper busbar.
d) MCCBs or MCBs of required numbers and ra ng for all substa on equipment
including transformers, building services, indoor control and relay panel,
ba ery charges, outdoor ligh ng etc. to complete.
e) All the necessary contactors, switches, terminal block, indica ng lamps,
Ammeters, Voltmeters, voltage indicators, monitoring relays, wiring, AC
transducer, termina on, labels, heaters, etc. to complete.
f) Facility for connec on to backup supply from a standby diesel generator set
in the event of main incoming supply fail.
g) Separate cable termina on box/
h) AC loading calcula on for all equipment including 20% spare load shall be
submi ed for approval.

Page 13 of 34
DC ONE (1) SET OF 110V NICKEL CADMIUM BATTERIES, DC CHARGERS AND
DISTRIBUTION SWITCHBOARDS (2x100% ba ery capacity, 2 x 100% charger) to
be installed in the substa on switch house in accordance with the requirements
of this Specifica on, comprising: -

a) Two banks of nickel cadmium ba eries shall be equal or more than 250Ah
each at the rated 5-hour rate of discharge (type C5) to meet the total
requirements of standing load (8 hours discharge period) and transient load
together with ba ery rack.
b) Two DC chargers with minimum float charge ra ng of 50A per charger and
fi ed with float and boost charge facili es suitable for the specified ba ery
capacity and standing load of all equipment, interlocking facili es, charger
control and alarm monitoring facili es.
c) Two double pole contactors or isolators for outgoing supplies from charger
to distribu on boards
d) Two sets main ba ery wall mounted switch fuse from chargers to ba ery
banks
e) Low Electrolyte Level Probe (LELP) detector with insulator at both ends to be
supplied and installed by Ba ery Manufacturer/ Ba ery Supplier
f) DC distribu on boards complete with instruments, lamps and switches with
segregated busbars, double pole MCBs/MCCBs minimum (20 nos – 16A, 35
nos – 32A, 5 nos – 63A) for all outgoing DC supply to all equipment of each
bay.
g) Definite spare including spare control and alarm cards, and maintenance
accessories as listed in the technical specifica ons.
h) All the necessary contactors, switches, sliding link terminal blocks, DC earth
fault relays, DC transducers, Ammeters, Voltmeters, wiring, blocking diode,
termina on, labels, heaters, etc. to complete.
i) Set of equipment earthing system including copper tape, copper bar,
electrodes, test links, connec ons from substa on earthing to equipment,
etc. to complete associated with this schedule.
j) DC ba ery sizing, DC charger sizing and DC loading calcula on for all
equipment including 20% spare load shall be submi ed for approval.

Page 14 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV KAMPUNG AWAH (KAWA)

PART 2: PLANT SECONDARY EQUIPMENT

132KV PROTECTION AND CONTROL

No Item Quan ty
1 132-OHF/CRPX 2
2 132-APCX 1

ITEM DESCRIPTION

KAMPUNG 132kV Protec on & Control


AWAH

132-OHF/CRPX MODIFICATION TO THE EXISTING 132KV INDOOR CONTROL & RELAY PANEL FOR
OVERHEAD LINE BAY EQUIPPED WITH: -

a) Current Differen al with IEC 61850 protec on relays suitable for two
terminal uses (to be matched with remote end) with op cal fibre links,
interfacing with PCM Mul plexer via IEEE C37.94 protocol.
b) Group isola on link for each protec on relays supply under this contract
c) Inter tripping relays complete with sending/receiving to remote end
substa ons.
d) Modifica on and upgrading of indica on/alarms/signal to exis ng
equipment such as annunciator, RTU-SIP, telecommunica on digital
equipment PCM MUX, etc. to complete.
e) All necessary switches, trip counters, intertrip send/receive relays, auxiliary
relays, contactors, MCB’s, test terminal blocks, sliding link spring loaded
terminals blocks, drawing compartment, op cal fibre cable, op cal fibre
connectors, indica ng lamps, energy saving LED, earthing bar, etc., to
complete.
f) To relocate exis ng relay and auxiliary components (where and if required)
to accommodate the installa on of new components at exis ng panel
including all necessary modifica ons to ensure the completeness and
successful opera on.
g) To add or modify wiring to ensure the completeness and successful
opera on of control and protec on schemes at the panels etc. to complete.
h) All necessary design and modifica on on the related exis ng equipment such
as Marshalling Kiosk/Local Control Panel, Control Relay Panel, Busbar
Protec on panel, etc. to complete
i) To update all labelling and exis ng drawings
j) To dismantle any exis ng relay/components/equipment inclusive of
packaging and handing over to TNB regional office.

Page 15 of 34
132-APCX AUXILIARY POWER AND CONTROL CABLES: -

Interfacing cables between all equipment supplied under this Contract, supplied
by others and exis ng equipment such as telecontrol equipment including from
RTU panel, SIP panel, control panels, relay panels, marshalling kiosk panel,
SDII/WAIS panel, AC & DC panels, telecommunica on panels, exis ng busbar
protec on, etc., to complete.

The Works to be inclusive of: -

a) Mul core, screened twisted pair, coaxial cable and screened cooper Ethernet
(minimum CAT 5E) cables for all secondary equipment including telecontrol
equipment, programmable transducer, Managed Ethernet Switch (ESM) etc.
to complete.
b) The complete set of auxiliary power, op cal fiber and mul core control
cables including cable trays, cable ladders, racks, cleats, supports, cable
glands and all necessary termina ons kits, etc.
c) All relevant schemes not limited to the following, e.g., voltage selec on,
synchronizing, busbar protec on, live transfer, interlocking, monitoring,
measurement, inter-tripping i.e. sending/receiving to remote end
substa ons etc., to complete.

All cables shall be direct buried (at switchyard subject to soil inves ga on result)
and/or laid on cable ladder/trays (inside control building. The cable ladder/trays
to match with exis ng size where applicable) as per TNB specifica on. Op cal
fiber cables outside of building shall be laid in HDPE pipe, while inside of building
shall be laid in flexible metal corrugated conduits.

For cable laying inside cable trench with the depth is equals or more than
600mm, cable trays shall be provided inclusive of supports for cable trays fixed in
concrete. Where cable tray is provided, minimum width of cable trench shall be
1000mm.

Page 16 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV MARAN (MRAN)

PART 2: PLANT SECONDARY EQUIPMENT

132KV PROTECTION AND CONTROL

No Item Quan ty
1 132-OHF/CRPX 1
2 132-APCX 1

ITEM DESCRIPTION

MARAN 132kV Protec on & Control

132-OHF/CRPX MODIFICATION TO THE EXISTING 132KV INDOOR CONTROL & RELAY PANEL FOR
OVERHEAD LINE BAY EQUIPPED WITH: -

a) Current Differen al with IEC 61850 protec on relays suitable for two
terminal uses (to be matched with remote end) with op cal fibre links,
interfacing with PCM Mul plexer via IEEE C37.94 protocol.
b) Group isola on link for each protec on relays supply under this contract
c) Inter tripping relays complete with sending/receiving to remote end
substa ons.
d) Modifica on and upgrading of indica on/alarms/signal to exis ng
equipment such as annunciator, RTU-SIP, telecommunica on digital
equipment PCM MUX, etc. to complete.
e) All necessary switches, trip counters, intertrip send/receive relays, auxiliary
relays, contactors, MCB’s, test terminal blocks, sliding link spring loaded
terminals blocks, drawing compartment, op cal fibre cable, op cal fibre
connectors, indica ng lamps, energy saving LED, earthing bar, etc., to
complete.
f) To relocate exis ng relay and auxiliary components (where and if required)
to accommodate the installa on of new components at exis ng panel
including all necessary modifica ons to ensure the completeness and
successful opera on.
g) To add or modify wiring to ensure the completeness and successful
opera on of control and protec on schemes at the panels etc. to complete.
h) All necessary design and modifica on on the related exis ng equipment such
as Marshalling Kiosk/Local Control Panel, Control Relay Panel, Busbar
Protec on panel, etc. to complete
i) To update all labelling and exis ng drawings
j) To dismantle any exis ng relay/components/equipment inclusive of
packaging and handing over to TNB regional office.

132-APCX AUXILIARY POWER AND CONTROL CABLES: -

Interfacing cables between all equipment supplied under this Contract, supplied
by others and exis ng equipment such as telecontrol equipment including from

Page 17 of 34
RTU panel, SIP panel, control panels, relay panels, marshalling kiosk panel,
SDII/WAIS panel, AC & DC panels, telecommunica on panels, exis ng busbar
protec on, etc., to complete.

The Works to be inclusive of: -

d) Mul core, screened twisted pair, coaxial cable and screened cooper Ethernet
(minimum CAT 5E) cables for all secondary equipment including telecontrol
equipment, programmable transducer, Managed Ethernet Switch (ESM) etc.
to complete.
e) The complete set of auxiliary power, op cal fiber and mul core control
cables including cable trays, cable ladders, racks, cleats, supports, cable
glands and all necessary termina ons kits, etc.
f) All relevant schemes not limited to the following, e.g., voltage selec on,
synchronizing, busbar protec on, live transfer, interlocking, monitoring,
measurement, inter-tripping i.e. sending/receiving to remote end
substa ons etc., to complete.

All cables shall be direct buried (at switchyard subject to soil inves ga on result)
and/or laid on cable ladder/trays (inside control building. The cable ladder/trays
to match with exis ng size where applicable) as per TNB specifica on. Op cal
fiber cables outside of building shall be laid in HDPE pipe, while inside of building
shall be laid in flexible metal corrugated conduits.

For cable laying inside cable trench with the depth is equals or more than
600mm, cable trays shall be provided inclusive of supports for cable trays fixed in
concrete. Where cable tray is provided, minimum width of cable trench shall be
1000mm.

Page 18 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV FS07 TNB SWITCHING STATION (FS07)

PART 2: PLANT SECONDARY EQUIPMENT

132KV PROTECTION AND CONTROL

No Item Quan ty
1 132-OHF/CRPX 1
2 132-APCX 1

ITEM DESCRIPTION

FS07 TNB 132kV Protec on & Control

132-OHF/CRPX MODIFICATION TO THE EXISTING 132KV INDOOR CONTROL & RELAY PANEL FOR
OVERHEAD LINE BAY EQUIPPED WITH: -

k) Current Differen al with IEC 61850 protec on relays suitable for two
terminal uses (to be matched with remote end) with op cal fibre links,
interfacing with PCM Mul plexer via IEEE C37.94 protocol.
l) Group isola on link for each protec on relays supply under this contract
m) Inter tripping relays complete with sending/receiving to remote end
substa ons.
n) Modifica on and upgrading of indica on/alarms/signal to exis ng
equipment such as annunciator, RTU-SIP, telecommunica on digital
equipment PCM MUX, etc. to complete.
o) All necessary switches, trip counters, intertrip send/receive relays, auxiliary
relays, contactors, MCB’s, test terminal blocks, sliding link spring loaded
terminals blocks, drawing compartment, op cal fibre cable, op cal fibre
connectors, indica ng lamps, energy saving LED, earthing bar, etc., to
complete.
p) To relocate exis ng relay and auxiliary components (where and if required)
to accommodate the installa on of new components at exis ng panel
including all necessary modifica ons to ensure the completeness and
successful opera on.
q) To add or modify wiring to ensure the completeness and successful
opera on of control and protec on schemes at the panels etc. to complete.
r) All necessary design and modifica on on the related exis ng equipment such
as Marshalling Kiosk/Local Control Panel, Control Relay Panel, Busbar
Protec on panel, etc. to complete
s) To update all labelling and exis ng drawings
t) To dismantle any exis ng relay/components/equipment inclusive of
packaging and handing over to TNB regional office.

132-APCX AUXILIARY POWER AND CONTROL CABLES: -

Interfacing cables between all equipment supplied under this Contract, supplied
by others and exis ng equipment such as telecontrol equipment including from

Page 19 of 34
RTU panel, SIP panel, control panels, relay panels, marshalling kiosk panel,
SDII/WAIS panel, AC & DC panels, telecommunica on panels, exis ng busbar
protec on, etc., to complete.

The Works to be inclusive of: -

g) Mul core, screened twisted pair, coaxial cable and screened cooper Ethernet
(minimum CAT 5E) cables for all secondary equipment including telecontrol
equipment, programmable transducer, Managed Ethernet Switch (ESM) etc.
to complete.
h) The complete set of auxiliary power, op cal fiber and mul core control
cables including cable trays, cable ladders, racks, cleats, supports, cable
glands and all necessary termina ons kits, etc.
i) All relevant schemes not limited to the following, e.g., voltage selec on,
synchronizing, busbar protec on, live transfer, interlocking, monitoring,
measurement, inter-tripping i.e. sending/receiving to remote end
substa ons etc., to complete.

All cables shall be direct buried (at switchyard subject to soil inves ga on result)
and/or laid on cable ladder/trays (inside control building. The cable ladder/trays
to match with exis ng size where applicable) as per TNB specifica on. Op cal
fiber cables outside of building shall be laid in HDPE pipe, while inside of building
shall be laid in flexible metal corrugated conduits.

For cable laying inside cable trench with the depth is equals or more than
600mm, cable trays shall be provided inclusive of supports for cable trays fixed in
concrete. Where cable tray is provided, minimum width of cable trench shall be
1000mm.

Page 20 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 3: PLANT TELECONTROL EQUIPMENT

TELECONTROL SYSTEM FOR GRID

No. Item Quan ty


1 GRID – HMI 1
2 GRID – SGW 1
3 GRID – WAIS 1
4 GRID – INTEG 1

The Telecontrol scope of work for this Contract includes provision of facili es for supervisory control
and monitoring of all 132kV in this substa on and in accordance with the signal list as specified in
Grid Substa on Signalling Requirements (GTS-GSE-SSR) unless stated otherwise.

All related interfacing cables to refer to Part 2: Plant Secondary Equipment – APC & OFC.

ITEM DESCRIPTION
GRID – HMI HUMAN MACHINE INTERFACE (HMI)

Supply, install, configure, tes ng and commissioning of:-

a) One (1) nos. of HMI complete with Processor, monitors (2 nos), keyboard,
mouse, Opera ng system, and HMI applica ons.
b) One (1) no. Operator’s desk console complete with steel cabinet to house
HMI, MCBs, AC sockets, surge arrestor for DC input and other accessories as
required.
c) Complete set of tools and so ware necessary to engineer, configure and
maintain the HMI, inclusive all relevant so ware licensing/product
key/installer /dongle required for successful re-installa on in the event of
hard disk crash.

to facilitate Control and monitoring of all equipment in this substa on, via
IEC61850 protocol on TCP/IP Ethernet transport.

GRID – SGW SCADA Gateway (SGW)

Supply, install, configure, tes ng and commissioning of:-

a) One (1) nos. of SCADA Gateway (SGW) complete with two (2) nos. of
Ethernet RJ-45 with IEC60870-5-104 protocol on TCP/IP Ethernet transport
complete with surge protectors and port mirroring facility.
b) One (1) nos. Sta on Time Server (STS) using SNTP complete with GPS
receiver, antenna and surge protector.
c) One (1) nos. Client Managed Ethernet Switch (ESM) to interface with the
132kV substa on ring and other related equipment’s.
d) One complete set of panel(s), type floor standing to house all the above
devices complete with ancillary components such as individual MCB for DC

Page 21 of 34
input of each device, AC sockets, surge arrestor for DC, earthing etc. to
complete.
e) Complete set of tools and so ware necessary to engineer, configure and
maintain SGW, STS and ESM inclusive all relevant so ware licensing/product
key/installer /dongle required for successful reinstalla on.

GRID – WAIS ONE (1) INDOOR WIDE AREA INTELLIGENT SYSTEM (WAIS) PANEL EQUIPPED
WITH:

a) Supply and install of One (1) Indoor WAIS panel to be located close to SGW
panel complete with design, installa on and wiring of Enterprise Gateway
(Enterprise Gateway will be supplied, configured, tested & commissioned by
the TNB. The Contractor shall arrange the devices to be taken from Client
designated office to site. All cost transporta on, mobilise, demobilised,
loading, unloading etc. shall be under the Contractor)
b) Supply and install one (1) nos. of Client Managed Ethernet Switch (ESM) to
interface with WAIS devices. (Client Managed Ethernet Switch (ESM) will be
supplied, configured, tested & commissioned by the TNB. The Contractor
shall arrange the devices to be taken from Client designated office to site. All
cost transporta on, mobilise, demobilised, loading, unloading etc. shall be
under the Contractor)
c) The scope of work including all interfacing to IEC61850 sta on bus,
Telecommunica on, DCDB, LVAC, etc., to complete.
d) Supply, install, tes ng and commissioning communica on cable (CAT5E) from
WAIS panel to WIP panel, ESM at SGW panel and Telecommunica on panel.
e) Front mounted AC 240V 13A supply socket
f) Glazed transparent acrylic window front cover door.
g) All necessary MCB’s, sliding link spring loaded terminals blocks, drawing
compartment, energy saving LED, earthing bar, etc., to complete.

GRID – INTEG SYSTEM ENGINEERING AND INTEGRATION

To engineer and integrate all IEC 61850 equipment and devices supplied under
this contract and supplied by others to ensure successful implementa on and
opera on of the Digital Substa on.

Page 22 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV KAMPUNG AWAH (KAWA)

PART 3: PLANT TELECONTROL EQUIPMENT

TELECONTROL SYSTEM FOR GRID

No. Item Quan ty


1 GRID – RTUX 2
2 GRID – SDIIX 1
3 GRID – SIPX 1

The Telecontrol scope of work for this Contract includes provision of facili es for supervisory control
and monitoring of exis ng 2 x 132kV Overhead Lines bays in this substa on, and in accordance with
the signal list as specified in Grid Substa on Signalling Requirements (GTS-GSE-SSR) unless stated
otherwise.

For this item, the scope of work only involves related interfacing cables that shall be covered in Part
2: Plant Secondary Equipment – APCX.

ITEM DESCRIPTION
GRID-RTUX EXPANSION AND RECONFIGURATION OF THE EXISTING REMOTE TERMINAL UNIT
(RTU)

Complete set of RTU input and output modules at the exis ng telecontrol system
with all required hardware and so ware to complete, but not limited to new
panel, sub-racks, etc. for the RTU to func on. For supervisory control, the
interfacing scheme shall be the same as in the exis ng Plant.

GRID-SDIIX EXPANSION OF THE EXISTING SDII/WAIS PANEL EQUIPPED WITH:

a) Client Managed Ethernet Switch (ESM) for Modbus TCP

GRID-SIPX EXPANSION OF EXISTING SUPERVISORY INTERFACE PANEL (SIP)

Expand and modify the exis ng SIP(s) as necessary. It shall include supply and
install, as a minimum, all component/equipment required but not limited to new
panel, terminal blocks, labels, wiring, connectors, and other accessories as
necessary.

Page 23 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV MARAN (MRAN)

PART 3: PLANT TELECONTROL EQUIPMENT

TELECONTROL SYSTEM FOR GRID

No. Item Quan ty


1 GRID – RTUX 1
2 GRID – SDIIX 1
3 GRID – SIPX 1

The Telecontrol scope of work for this Contract includes provision of facili es for supervisory control
and monitoring of exis ng 1 x 132kV Overhead Lines bays in this substa on, and in accordance with
the signal list as specified in Grid Substa on Signalling Requirements (GTS-GSE-SSR) unless stated
otherwise.

For this item, the scope of work only involves related interfacing cables that shall be covered in Part
2: Plant Secondary Equipment – APCX.

ITEM DESCRIPTION
GRID-RTUX EXPANSION AND RECONFIGURATION OF THE EXISTING REMOTE TERMINAL UNIT
(RTU)

Complete set of RTU input and output modules at the exis ng telecontrol system
with all required hardware and so ware to complete, but not limited to new
panel, sub-racks, etc. for the RTU to func on. For supervisory control, the
interfacing scheme shall be the same as in the exis ng Plant.

GRID-SDIIX EXPANSION OF THE EXISTING SDII/WAIS PANEL EQUIPPED WITH:

a) Client Managed Ethernet Switch (ESM) for Modbus TCP

GRID-SIPX EXPANSION OF EXISTING SUPERVISORY INTERFACE PANEL (SIP)

Expand and modify the exis ng SIP(s) as necessary. It shall include supply and
install, as a minimum, all component/equipment required but not limited to new
panel, terminal blocks, labels, wiring, connectors, and other accessories as
necessary.

Page 24 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV FS07 TNB SWITCHING STATION (FS07)

PART 3: PLANT TELECONTROL EQUIPMENT

TELECONTROL SYSTEM FOR GRID

No. Item Quan ty


1 GRID – RTUX 1
2 GRID – SDIIX 1
3 GRID – SIPX 1

The Telecontrol scope of work for this Contract includes provision of facili es for supervisory control
and monitoring of exis ng 1 x 132kV Overhead Lines bays in this substa on, and in accordance with
the signal list as specified in Grid Substa on Signalling Requirements (GTS-GSE-SSR) unless stated
otherwise.

For this item, the scope of work only involves related interfacing cables that shall be covered in Part
2: Plant Secondary Equipment – APCX.

ITEM DESCRIPTION
GRID-RTUX EXPANSION AND RECONFIGURATION OF THE EXISTING REMOTE TERMINAL UNIT
(RTU)

Complete set of RTU input and output modules at the exis ng telecontrol system
with all required hardware and so ware to complete, but not limited to new
panel, sub-racks, etc. for the RTU to func on. For supervisory control, the
interfacing scheme shall be the same as in the exis ng Plant.

GRID-SDIIX EXPANSION OF THE EXISTING SDII/WAIS PANEL EQUIPPED WITH:

a) Client Managed Ethernet Switch (ESM) for Modbus TCP

GRID-SIPX EXPANSION OF EXISTING SUPERVISORY INTERFACE PANEL (SIP)

Expand and modify the exis ng SIP(s) as necessary. It shall include supply and
install, as a minimum, all component/equipment required but not limited to new
panel, terminal blocks, labels, wiring, connectors, and other accessories as
necessary.

Page 25 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 5: POWER CABLES

This Bill of Quan ty shall be read in conjunc on with Technical Specifica ons and Tender Drawings.
All related engineering, design, supply, and erec on works associated with the project and schedules
shall be included as part of the Items. Items not specifically men oned in this Bill of Quan ty but
necessary to be included for the complete and sa sfactory opera on of the system as specified by
the Specifica ons (including special tools for construc on, tes ng, opera on, and maintenance
purposes of the equipment) shall be deemed to be included in the Contract Price.

The prices for the individual items shall be entered in Schedule of Price.

POWER CABLES IN SUBSTATION

The following items and par culars are the Definite Items of the cable in this
Tender. All related design, supply and installa on works associated with the
project and schedules shall be included as part of the Items. Items not
specifically men oned in this Schedule but necessary to be included for the
complete and sa sfactory opera on of the system as specified by the
Specifica ons (including special tools for construc on, tes ng, opera on, and
maintenance purposes of the equipment) are deemed to be included in the
Contract Price.

The contractor shall submit complete documenta ons and drawings showing
detailed and true to scale dimensioned cross-sec ons of the power cables, cable
join ng and termina ng accessories.

415/LVAC LOW VOLTAGE CABLE FOR LVAC: -

Quan ty Item
a Lump sump 415V Low Voltage cables 4 core 240mm2 Al XLPE/PVC/
SWA/PVC+FR+AT

a) From generator set to LVAC board at 132kV substa on


building, complete with termina ons at both ends.
b) From compact-type substa on to LVAC board at 132kV
substa on building, complete with termina ons at
both ends.

Refer to Specifica ons Sec on 3: Auxiliary Power, Control


And Instrumenta on Cable GTS-GSE-APCI.

CABLE INSTALLATION WORKS

The cables shall be laid in a combina on of the following erec on methods: -


a) Cable trench.

Page 26 of 34
b) Buried direct in ground with pipe on concrete pla orm on pile (subject to soil
inves ga on result).
c) Concrete encased pipes under substa on road.
d) Cable cellar with trays, ladders, and supports.
e) Cable cellar on the floor with supports.
f) Cable sha with trays, ladders, and supports.

The installa on described in the erec on methods above shall include: -


a) u lity mapping and trial holes,
b) supply of all material and workmanship as per TNB requirement,
c) excava on, trenching, hacking, and coring,
d) encased with grade 20 concrete under substa on road,
e) cable trench crossing and other cable crossings, where applicable.
f) complete fill with si ed sand in cable trench,
g) sand for direct buried,
h) concrete cable protec ve slabs,
i) reinstatement of exis ng surfaces,
j) cable route marking,
k) labelling for all types of cables laid at both ends,
l) cable ladders/trays,
m) cable clamps and supports,
n) cable cleats,
o) steel works,
p) applica on of fire-retardant paint for all exposed power cables,
q) fire block mortar at cable entrance, etc., to complete as per contract
specifica on.

All join ng and termina on works shall be carried out by Cer fied Cable Jointers
approved by TNB. The jointers shall have valid competency cer ficates issued by
the joint and termina on manufacturer for the relevant voltage level and
par cular model offered for installa on.

Page 27 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 7: COMMON WORKS ITEMS

BILL OF QUANTITY

ITEM DESCRIPTION

No Item Quan ty
1 CPTN Lump sump
2 INSR Lump sump
3 CIDB Lump sump
4 SHO/SSS Lump sump
5 PSAFE Lump sump
6 DTRAIN Lump sump
7 TEST Lump sump
8 OTHERS Lump sump

Common works for the relevant scope of works:

CPTN ELECTRICAL SERVICES/COMPETENT ENGINEERS/CONTRACTOR QUALIFIED


PERSON

Electrical Services and Competent engineer(s) associated with the project and
the Schedules inclusive of the works involving extension to a "live" substa on or
working in the vicinity of "live" equipment. The permit to work (PTW) shall only
be issued to the named competent person(s).

Successful Contractor shall submit the name(s) of person(s) holding Cer ficates
of Competence issued under the Electricity Regula on 1994 who shall be
responsible for installing, tes ng, and commissioning of electrical installa on,
sta ng the type of Cer ficate of Competency and Limita on.

Electrical Services and Competent engineer(s) may delegate the PTW to the
contactor's supervisor that has a valid Contractor Qualified Person (CQP),
training cer ficate from ILSAS. The validity of the cer ficate shall be in relevant
to his/her current employment with the main contractor. It will be invalid once
the supervisor change employment to other company which requires
recer fica on.

INSR PROJECT INSURANCE

Project Insurance associated with the project and the Schedules inclusive of
Erec on All Risk/ Contractor All Risk and Workmen Compensa on Insurance.

The Project Insurance shall also provide coverage for free issued plants and
material and dismantled equipment, if any

Page 28 of 34
CIDB CIDB

Registra on with Construc on Industry Development Board Malaysia CIDB


associated with the project and the Schedules, including CIDB Green card
registra on for all workmen working in the substa on.

SHO/SSS PROJECT SAFETY REQUIREMENT SHALL BE AS FOLLOWS:

a) To appoint a full me Safety and Health Officer (SHO) registered with


Department of Occupa onal Safety and Health (DOSH) at project site for the
whole dura on of the contract. SHO is compulsory for all type of project
irrespec ve of contract value. The nomina on criteria for the SHO are as
follow:
i. At least 2 years’ experience as SHO in construc on work
internally/externally OR 2 years’ experience as SSS in TNB projects + 1
year as SHO externally.
ii. Compulsory to have a valid cer ficate for First Aid & NTSP.
iii. No fatali es for the past 2 years.

b) To appoint Site Safety Supervisor (SSS) registered with Department of


Occupa onal Safety and Health (DOSH) at project site as s pulated in sub
regula on (1), Regula on 25 – Site Safety Supervisor, Building Opera ons
and Work of Engineering Construc on (BOWEC) Regula on 1986, Factories
Machinery Act (FMA) 1967 (Act 139) and sub clause 9.5 – Site Safety
Supervisor, TNB HSE Requirement for Contractor, for the whole dura on of
the contract at project site. The nomina on criteria for the SSS are as follow:
i. At least 2 years’ experience as SSS in construc on work
internally/externally.
ii. Compulsory to have a valid cer ficate for First Aid & NTSP.
iii. No fatali es for the past 2 years.

Notes: Ensure compliance to HSE Requirement for the contractors. SHO and
SSS are compulsory to a end induc on/ awareness course of WAH,
Scaffolding and Li ing Supervisor conducted by TNB HSE.

PSAFE The payment for this PSAFE item will be based according to the Schedule of
Payment as stated in the General Requirement under Item 22.0 (Project Safety
Requirement – sub clause 22.2). The contractor shall fill up the Schedule of Price
for PSAFE item in BQ according to the table of the contract cost for PSAFE as
follows:

PROJECT DESCRIPTION PROPOSED PSAFE AMOUNT


PROJECT ABOVE 50MIL Min Capping: RM500,000.00
(0.5% from tenderer contract cost)
PROJECT BELOW 50MIL Min Capping: RM300,000.00
(1% from tenderer contract cost)

Page 29 of 34
All workers under this scope of works in the Contract (Work Permit/Skill &
Unskilled) shall have valid NTSP (NIOSH TNB Safety Passport) throughout the
contract dura on un l the issuance of Taking Over Cer ficate (TOC).

DTRAIN DIGITAL SUBSTATION TRAINING

1. Two (2) training sessions in modules concept (Client personnel in a single


session) with the facili es provided by the Contractor or OEM.

2. Two (2) training sessions for Operator training (Client personnel in a single
session) with any addi onal facili es provided by the Contractor or OEM at
site.

3. The training requirements are as follow:

a) The training syllabus shall cover but not limited to the following topics: -

i. Func onal descrip on and architecture


ii. Opera on and maintenance
iii. Engineering, configura on, and parameteriza on
iv. Installa on of so ware, driver etc
v. Trouble shoo ng and correc ve maintenance.
vi. Logic programming
vii. Clone HDD and backup database
viii. Na ve So ware

b) The training program is to be submi ed to the Client one month before


training is schedule to start. The training program shall contain, as a
minimum: -

i. Training Schedule
ii. Course Objec ve
iii. Course Syllabus guideline will be provided by the OEM. Client to review
iv. Course Instructor – Name and Qualifica on
v. Minimum pre-requisite for par cipants
vi. One set of Course Notes and Documents, including the so copy of
vii. training materials
viii. Training setup system

c) Training documenta on (So copy & Hardcopy) shall be provided which


consists of the subject ma er presented during the training, any reference
documents, worked examples, drawing and any other material to facilitate
understanding of the subject ma er. The documenta on shall be provided as
hard copies binded properly in files.

d) All instructors or course facilitators are qualified and cer fied


trainers/instructors who have been specifically trained by the manufacturer
as well as have the necessary experience to conduct the training specified.
The Contractor shall furnish documentary evidence to show that the
instructors have the necessary qualifica on and experience. The Client has

Page 30 of 34
the right to reject any proposed instructors that is determined to not have
the necessary qualifica on or experience to conduct the training.

e) For hands-on training, each par cipant shall have access to their own
individual worksta on.

TEST Site tes ng and commissioning of all equipment relevant to the scope of work of
this project.

The scope of this works includes but is not limited to site tes ng for pre-
commissioning, commissioning and post-commissioning of equipment associated
with these Schedules and interfacing equipment where necessary, as well as
provision of all test equipment and accessories required, including all remote
end substa ons tes ng, coordina on within all overhead lines and/or
underground cables and/or remote end (where applicable) contractor for
successful comple on of the Contract as stated in SAT and relevant documents of
contracts.

OTHERS OTHER REQUIREMENT WHICH NOT SPECIFIED

Any other items not described or included in the foregoing but required or
implied in the drawings, specifica on, requirement of all relevant Authori es and
in order to have a complete system in accordance to an engineering prac se.

Contractor to submit and to specify the detail proposal.

Page 31 of 34
SCHEDULE H: BILL OF QUANTITIES

PLANT NAME: PMU 132kV SWITCHING STATION (SWS08) - AIS

PART 8: MISCELLANEOUS ITEMS

BILL OF QUANTITY

ITEM DESCRIPTION

No Item Quan ty
1 GENSET 1
2 ACAUX 1
3 DISM Lump sump
4 TPORT Lump sump
5 4WD Lump sump

The following items and par culars are the Miscellaneous Items of the
switchgear in this Contract.

GENSET EMERGENCY GENERATOR SET EQUIPPED WITH: -

Quan ty Item
a 1 no Minimum of 140kW Diesel generator set complete with all
accessories, Automa c Mains Failure (AMF) board, exhaust
silencer, alternator, acous c door, intake and discharge
silencer, vibrator moun ng, ba ery, to be u lized during
loss of normal LV AC auxiliary supply.

Diesel generator set sizing calcula on shall be submi ed


for approval.

Refer to Specifica ons Standby Diesel Engine Driven


Generators and Accessories 3-phase 415/240V 50Hz.

The Contractor shall liaison with local Department of


Environmental (DOE) for submission and approval. The
propose complete Diesel generator set shall have at least
five (5) years track records successfully in installa on,
tes ng, commissioning and opera on in TNB site.

Refer to Specifica ons Sec on 3: Auxiliary Power, Control


And Instrumenta on Cable GTS-GSE-APCI.

The installa on of the generator set shall comply to Akta Kuali Alam Sekeliling
1974.

Page 32 of 34
ACAUX AC AUXILIARY SUPPLY SYSTEM EQUIPPED WITH: -

Quan ty Item
a 1 no MV/LV compact-type substa on and all its founda on and
ancillaries, including all the necessary medium voltage
cables, joints, termina ons, 3 RMUs (for 2 incomers and a
transformer), a minimum 500kVA 11/0.433kV local
transformer, distribu on board, etc., to complete, as
required by TNB Distribu on, to be connected to the
switching sta on.

Tenderer to offer MV/LV compact-type substa on that is


already listed in Distribu on Network pre-approved list
(Sijil Guna Pakai).

b Lump sump All the necessary LV cable joints, termina on, and
accessories, etc., to complete, to connect the LV output of
the MV/LV compact substa on to the LVAC panel of the
switching sta on, including the LV Metering Panel, LV
Meters, Current Transformers, etc. to complete, for
connec on of the LV supply system.

The system shall be integrated with the generator set system for automa c start
up and load transfer of substa on AC auxiliary supply from the switching sta on
LVAC board to generator set.

Tenderer to appoint a Consultant Engineer for the electric supply (11kV and
0.433kV TNBD Supply) applica on to TNB and is responsible for the overall
applica on process, as per the supply applica on according to available guideline
in Electricity Supply Handbook Applica on (ESAH) for the electricity supply
connec on to the sta on.

All deposits, bank guarantees, insurances, processing fees, penal es, and other
costs, etc., where required, (refundable and non-refundable) are deemed to be
included and under the responsibility of the Contractor.

DISM DISMANTLING, PACKING AND STORAGE OF ALL EXISTING 132KV EQUIPMENT


THAT ARE TO BE REPLACED/SCRAPPED, INCLUDING:

Equipment to be dismantled are:


a) All exis ng secondary relays/components/equipments/panels related to this
project. All dismantled relays/component/ equipments/panels shall be
properly protected against physical and electronic sta c damage during
dismantling and storage with proper packaging and labelling.
b) All other related mul core & auxiliary cable, earthing, steel structures,
conductors including clamps, connectors, jumpers, line droppers, fi ngs,
etc. to complete and to be weighed accordingly.
c) All dismantled equipment is to be packed and marked suitably as to
avoid damage.

Page 33 of 34
All dismantled items, inclusive of any schedule waste must be packed and stored
in a proper manner to avoid any hazardous material leakage or spillage to
environment as per requirement Jabatan Alam Sekitar, Malaysia.

TPORT All dismantled items in DISM are to be transported and stored at a designated
loca on as instructed by the Employer.

4WD VEHICLE DETAIL DESCRIPTION AS FOLLOWS:

The Contractor shall provide new one 4WD pick-up for off-road use (to be
approved by the Client before purchase; TOYOTA HILUX/FORD RANGER Latest
and Full Specifica on model) of right-hand drive, 4-door pick-up, 5-seater,
minimum of 2.8 litre turbo diesel engine, auto transmission, air condi oned,
with motorised winch and kangaroo bar throughout the contract dura on un l
the issuance of Taking Over Cer ficate (TOC). The vehicle shall comply with all
the relevant Road Transport Department Law and Regula on of Malaysia. The
pick-up shall be handed over within three months a er Commencement Date.

The vehicle provided shall be maintained by the Contractor in efficient working


condi on, and any defec ve parts or tyres replaced. The Contractor shall provide
a PETRONAS fuel card with a value of RM 1,000.00 per month up to the end of
the Defect No fica on Period. The Contractor shall ensure that all
documenta on in rela on to vehicle is updated and valid in accordance to
exis ng laws and regula ons of Malaysia. In addi on, full comprehensive
insurance cover must be provided for the vehicle and driver for unlimited Third-
Party claims at all mes.

The Contractor shall make available the use of vehicle at all mes during the
Contract Period which shall include the dura on the Contract Period which shall
include the dura on of the Defect No fica on Period or any extension thereof.

The Contractor shall solely bear all costs in rela on to the schedule maintenance
and/or servicing of the vehicle as well as all replacement of parts whether due to
wear and tear and/or damage up to the end of the Defect No fica on Period.

In the event that maintenance, servicing and/or repair of the vehicle exceeds
twenty-four (24) hours. A one-to-one replacement of the vehicle is to be
immediately made available to the Employer.

The Contractor shall dispose of the vehicle to the Employer at the nominal rate
of RM 1.00 at the Time for Comple on.

Page 34 of 34

You might also like