Professional Documents
Culture Documents
“ELECTRICAL DISTRIBUTION
WORKS FOR A CENTRAL
HOSPITAL”
I
إهدإء
مع ل
الى من شاركتنا هدإ ا ل...
II
Presented by:
III
TABLE OF CONTENTS
CH1. Introduction ................................................................................................... 1 - 5
1.1 Editorial .................................................................................................................. 2
1.2 Hospital design criteria ........................................................................................... 2
1.3 Project overview and layout ................................................................................... 3
1.4 Scope of work ......................................................................................................... 4
CH2. Lighting Design ........................................................................................... 6 - 20
2.1 Healthcare application ............................................................................................ 7
2.2 Luminaires classification ......................................................................................... 8
2.3 Factors to be considered in lighting design .......................................................... 15
2.4 Lighting calculations ............................................................................................. 15
2.5 Legend of lighting fixtures .................................................................................... 17
2.6 Branch circuit design ............................................................................................ 19
2.7 Project’s sample .................................................................................................... 19
CH3. Power Design ............................................................................................. 21 - 33
3.1 Electrical sockets.................................................................................................... 22
3.2 HVAC (heating, ventilation, and air conditioning) ............................................... 24
3.3 Elevators................................................................................................................. 27
3.4 Pumps .................................................................................................................... 30
CH4. Cable Sizing and Voltage Drop Calculations .......................................... 34 - 47
4.1 The factors affecting cable selection .................................................................... 35
4.2 Construction of cable ............................................................................................ 35
4.3 Cables classification .............................................................................................. 36
4.4 Cable routing types ............................................................................................... 38
4.5 Cable sizing ........................................................................................................... 38
4.6 Voltage drop calculations ..................................................................................... 44
CH5. Circuit Breaker and Short Circuit Calculations .................................... 48 - 62
5.1 Circuit Breakers ............................................................................................. 49 - 54
5.1.1 Why using circuit breaker ............................................................................ 49
5.1.2 Function of circuit breaker .......................................................................... 49
5.1.3 Types of circuit breaker ............................................................................... 49
5.1.4 Calculations of circuit breaker ratings ......................................................... 52
5.2 Distribution Board .......................................................................................... 55 - 57
5.2.1 Types of distribution boards ........................................................................ 56
5.3 Medium Voltage Switch Gear .............................................................................. 58
5.4 Short Circuit .................................................................................................... 59 - 62
5.4.1 Types of short circuit ................................................................................... 59
5.4.2 Short circuit calculations ............................................................................. 61
CH6. Power Factor Correction ......................................................................... 63 - 72
6.1 Power factor definition ......................................................................................... 64
6.2 Why to improve power factor ............................................................................... 65
6.3 How to improve power factor ............................................................................... 67
6.4 By using what equipment ...................................................................................... 68
IV
TABLE OF CONTENTS
6.5 Where to install power factor ................................................................................. 69
6.6 Power factor correction implementation .............................................................. 71
CH7. Electrical Power Supplies ........................................................................ 73 - 86
7.1 Ring Main Unit .............................................................................................. 74 - 75
7.2 Transformer .................................................................................................... 76 - 80
7.2.1 Types of transformers .................................................................................. 76
7.2.2 Equivalent circuit .......................................................................................... 78
7.3 Uninterruptable Power Supply........................................................................ 81 - 83
7.3.1 What is the UPS ............................................................................................ 81
7.3.2 UPS circuit diagram...................................................................................... 81
7.3.3 Types of UPS ............................................................................................... 82
7.4 Generator ......................................................................................................... 84 - 86
7.4.1 What is the generator ................................................................................... 84
7.4.2 A standby generator ..................................................................................... 84
7.4.3 Uses of standby generator ............................................................................ 85
CH8. Earthing System ......................................................................................... 87 - 95
8.1 What affects the ground resistance ....................................................................... 88
8.2 Ground system design ............................................................................................ 89
8.3 Earthing system classifications .............................................................................. 91
8.4 Project’s earthing system design and calculations................................................. 93
CH9. Fire Alarm System ................................................................................... 96 - 105
9.1 Objective of system ............................................................................................... 97
9.2 Main components of system ................................................................................. 97
9.3 Steps of design ...................................................................................................... 97
9.4 Precautions during design ................................................................................... 100
9.5 Automatic fire detector ....................................................................................... 100
9.6 Audible devices ................................................................................................... 102
CH10. Light Current ........................................................................................ 106 - 128
10.1 Telephone Network .................................................................................. 107 - 114
10.1.1 Major system elements ............................................................................ 108
10.1.2 Types of telephone cables ........................................................................ 108
10.1.3 Telephone network components .............................................................. 109
10.2 Data System .............................................................................................. 115 - 119
10.2.1 System components ................................................................................. 115
10.2.2 Design steps ............................................................................................. 115
10.3 Nurse Call System..................................................................................... 120 - 128
10.3.1 Patient room equipment .......................................................................... 121
10.3.2 Nurse station ........................................................................................... 126
Appendix ......................................................................................................................... 129
V
CHAPTER 1
INTRODUCTION
Chapter Contents:
1.1 Editorial.
1.2 Hospital design criteria.
1.3 Project overview and layout.
1.4 Scope of work.
VI
CHAPTER 1 INTRODUCTION
1. INTRODUCTION
1.1 Editorial
Electric power distribution is the final stage in the delivery of electric power, it carries
electricity from the transmission system to individual consumers. Distribution substations
connect to the transmission system and lower the transmission voltage to medium voltage
with the use of transformers.
Distribution transformers lower the voltage to the utilization voltage used by lighting,
industrial equipment or household appliances. Often several customers are supplied from
one transformer through secondary distribution lines.
The planning of electrical power distribution in buildings and infrastructure facilities is
subject to many transformations. The search for a dependable solution should fulfil those
usual requirements placed on cost optimization, efficiency, and time needs.
The initial project planning stages are of vital importance in. They determine the basic set-
up and guidelines for the project. Wrong assumptions and specifications may result in
system oversizing which may bring about unnecessary costs. Undersize may result in
overload and plant failures.
Critical non-medical processes: Patient data systems (Server rooms, Data Centre).
2
CHAPTER 1 INTRODUCTION
Every concept, every component requires an appropriate selection according to codes and
standards for healthcare guides.
ABO-TESHT Central Hospital, QENA: is one of the national project for the development
of 31 hospitals carried out by the ministry of health and population and under the management
of the national service project of the ministry of defense.
Main building and 7 service buildings on a land area of 11,517m2 with a total built-up
area of 13,949 m2 (7,599 m2 to be reconstructed and 6,350 m2 to refurbished). The main
building comprises the following:
3
CHAPTER 1 INTRODUCTION
5 upper floors: kidney dialysis center (24 units + 2 isolation rooms) outpatient clinics,
inpatient wards (36 beds + 4 isolation rooms), 4 operation rooms, ICU (5 beds + 2
isolation rooms), NICU (7 beds + 1 isolation room), obstetrics & gynecology unit (16
beds), CSSD, as well as staff accommodation and management area; and
Roof: equipment.
Project Layout
4
CHAPTER 1 INTRODUCTION
5
CHAPTER 2
LIGHTING DESIGN
Chapter Contents:
2.1 Healthcare application.
2.2 Luminaires classification.
2.3 Factors to be considered in lighting design.
2.4 Lighting calculations.
2.5 Legend of lighting fixtures.
2.6 Branch circuit design.
2.7 Project’s sample.
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2. LIGHTING DESIGN
Lighting design is one of the most important aspects considered by power engineers,
lighting designers, architects, landscape engineers and others involved in this process.
The main purposes of lighting are as follows:
Ensure the safety of the people.
Provide suitable lighting level to carry out the required visual task.
Help create appropriate visual environment.
The required levels are included in different codes e.g. CIBSE, IESNA...etc., and it differs
according to the extent of visual tasks that will be carried out.
7
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2.2 Luminaire Classification
- Wall luminaires
- Pendant luminaires
8
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
4. Cheap and available every where.
5. Not harmful to environment.
• Disadvantages:
1. Draw large units of power as 90% of power is drawn in heat.
2. Even global warming is major concern.
- Gas discharge:
• Types:
1. High pressure sodium:
• Advantages:
1. Most efficient member of the HID light family, 7 times as efficient as incandescent
and over 2 times as efficient as mercury vapor.
2. Warm-up period is 3-4 minutes, which is somewhat less than that of a mercury
vapor or metal halide lamp.
3. Long lamp life -- 24,000 hours.
4. Excellent lumen maintenance.
5. Wide range of lamp types with wattages ranging from 35 to 1000 watts.
6. Most HPS lamps can operate in any position.
• Disadvantages:
1. The light produced is a golden white color, which may not be appropriate for
certain applications.
2. Requires a ballast.
3. Once started can take from five to ten minutes to reach full light output. They also
require at least a one minute cool-down to re-strike.
4. End of life is characterized by on-off-on cycling, and continued operation can
damage the lamp ballast if not replaced quickly.
9
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2. Low pressure sodium:
• Advantages:
1. Most energy efficient light source commercially available, with an efficacy of 100
to 185 lumens per watt.
2. Lamps have average life in the 14,000 to 18,000 hour range and have excellent
lumen maintenance (very little reduction in lumen output over life of lamp).
3. Most lamps will restart immediately after interruption of power supply, but require
some time to come up to full brightness.
4. Provides superior uniformity of light distribution over all HID lamps.
• Disadvantages:
1. These lamps have poor color rendering characteristics. It is almost impossible to
distinguish colors under an LPS lamp because light produced by this source is
monochromatic (a single color).
2. Most expensive lamp to install.
3. Run time to full light output is the longest (7 to 15 minutes).
4. Wattage will increase over the life of the lamp to maintain lumen output.
5. Requires special disposal considerations.
10
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
4. Require a maximum warm-up period of five to seven minutes before giving full
light output, depending on lamp type, ballast and ambient temperature. They can
be used only where this delay is acceptable.
5. Four to five minute cooling and restart time.
6. New outdoor installations are illegal under some state laws.
7. Lamps are quite voltage sensitive. Unless special ballasts are used, care must be
taken to keep the supply voltage within plus or minus 5% of the rated voltage.
8. Mercury lamp ballasts are noisy. Remote mounted ballasts may be an alternative.
4. Fluorescent:
• Advantages:
1. 4 to 5 times more efficient than incandescent lamp bulbs, and longer life (anywhere
from 10 to 20 times greater than incandescent).
2. Easy to maintain.
3. Available in a wide range of sizes and colors.
• Disadvantages
1. Most lamps are large in size and require costly metal fixture housings.
2. The ballasts in fluorescent fixtures can have an objectionable hum (some louder
than others).
3. Ballasts are given a noise rating. Low noise ballast are recommended for office
areas, louder and less expensive ballasts are used in industrial facilities.
4. Fluorescent lamps are temperature sensitive and may have difficulty starting at low
temperatures. Lumen output drops at low and high temperatures.
5. Special ballasts are required for low and high temperature applications.
5. Metal halide:
• Advantages:
1. Designed for general lighting applications.
2. Relatively long lamp life.
3. Interchangeable with mercury lamps in many applications.
11
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
4. Concentrated source is easily controlled by special fixtures.
5. Good color rendering characteristics.
6. Light output is a bright crisp white light.
7. Twice as efficient as mercury lamps and 6 times as efficient as incandescent.
• Disadvantages:
1. Short life compared to other HID lamps (6,000 to 20,000 hours depending on size
and manufacturer)
2. Different lamps have to be used for base-up versus base down burning
configurations.
3. Horizontal operation may severely reduce lamp life.
4. Require a ballast
5. Some lamp types require 2 to 5 minutes to warm-up before giving full light output
and 10 minutes to cool-down. Others have instant restart capability.
6. Color may vary from lamp to lamp (color shift.)
7. Many wattages require operation in enclosed fixtures due to the risk of lamp
breakage upon failure.
6. LED:
- Light Emitting Diode (LED) systems have made great strides in recent years. In
addition to being used in traffic lights.
- They are much more energy efficient and have longer lives than incandescent lamps.
12
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
- Because of their ability to start in cold temperatures, LED lighting has become the
light of choice for reach in refrigerator and freezer cases in grocery and convenience
stores
- Their long life is also a big benefit in reducing maintenance costs in these stores.
- In agricultural settings, LED lighting of a certain spectrum can promote chlorophyll
absorption, photosynthesis, and reduce fertilizer costs while lowering the lighting
costs by up to 40%.
13
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
LED lighting is the mainly type used in this project, as it offers unprecedented design
freedom in terms of color, dynamics, miniaturization, architectural integration and
energy efficiency opening up new possibilities in brand building and ambience
creation, for instance by dynamically changing the lighting, using various highlighting
and color effects.
14
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2.3 Factors to be considered in lighting design
Maintenance factor :
- It accounts for the reduction in light levels over time. A good lighting calculation
considers how much lighting the lighting fixture will produce years from operation
not on the first day of operation.
Factors that affects the maintenance factor :
- Lamp Lumen depreciation.
- Luminaire dirt depreciation.
- Room surface dirt depreciation.
Illuminance (LUX) :
- It is the average luminous flux per unit area.
Uniformity (Unit less) :
- Ratio between the minimum illuminance and the average illuminance for a certain
space (Emin/Emax).
Manual calculation:
- By using the following equation to estimate the number of the required luminaires to
achieve a suitable illuminance (lux):
𝐿𝑈𝑋 × 𝑎 × 𝑏
𝑁 =
𝐿𝑢𝑚𝑒𝑛 × 𝑈.𝐹 × 𝑀.𝐹 × 𝑛
Where,
N is the number of Luminaires.
n is the number of lamps per luminaire.
LUX is Lighting level, get from standard table (IEC, EC and NEC)
a is the room width.
b is the room length.
U.F is Utilization factor.
M.F is Maintenance factor.
15
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
Software lighting design:
Though the architectural & structural drawing is usually exported to the lighting design
software, carrying out the lighting design knowing the room’s dimensions is useful as
well. For example working on a project with no CAD drawing available. DIALux is one
of the most commonly used lighting design software.
Sample from the project: According to CIBSE or Egyptian code, the required Illuminance
level for pharmacy is 500 lux, and average lux is accepted (+ or -10%) of the required lux.
From the equation and by applying the appropriate factors we deduce the total number of
luminaires required to achieve the required lux is 9.
16
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2.5 Legend of lighting fixtures
17
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
18
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
2.6 Branch circuit design:
- According to EC the maximum power per branch circuit shouldn’t exceed 1000 watt
- In this project we use from 8 to 12 luminaires per branch circuit.
- The selected feeding wire is 3*2.5 mm2 Cu/PVC with 16 A circuit breaker, as
according to IEC standard that we can extend this branch circuit up to 62 m with
achieving of the allowable voltage drop and sensing of occurrence of short circuit
along this length, as shown in the following table:
19
CHAPTER 2 LIGHTING DESIGN
CHAPTER 1
- 10 luminaires per branch circuit.
- Panel schedule
20
CHAPTER 3
POWER DESIGN
Chapter Contents:
3.1 Electrical sockets.
3.2 HVAC
(heating, ventilation, and air conditioning).
3.3 Elevators.
3.4 Pumps.
21
CHAPTER 3 POWER DESIGN
CHAPTER 1
3. POWER DESIGN
At power design, we are committed to providing a quality product and excellent customer
service. While our growth is a part of our culture, business decisions are made based on long-
term relationships and commitment, not profit margins. Partnering with power design means
having a team member on board that seeks to create successful, innovative projects, delivered
on time and on budget.
Every device in the building need sockets and switching method to control it.
22
CHAPTER 3 POWER DESIGN
CHAPTER 1
we use in BHU (NORMAL SOCKET –EMEREGENCY SOCKET –UPS SOCKET)
2. Duplex socket
This electrical outlet is single phase up to 10A or 16A 250VA, used for light home load
and have different shapes as shown below
3. Power Socket
This electrical outlet is single phase up to 32A.
More than 2000VA.
Used for detected load.
23
CHAPTER 3 POWER DESIGN
CHAPTER 1
4. Three phase industrial socket
These socket used for industrial application – and have rating up to 152A
Room application
Room furniture
Each 3 meters put a single or duplex socket
For kitchen, there must be at least one power socket
HVAC stands for heating, ventilation, and air conditioning. In computing and especially in
enterprise data centers, HVAC systems control the ambient environment (temperature,
humidity, air flow, and air filtering) and must be planned for and operated along with other
data center components such as computing hardware, cabling, data storage, fire protection,
physical security systems and power. The selection of an HVAC contractor is an important
step in planning a data center.
Almost all physical hardware devices come with environmental requirements that include
acceptable temperature and humidity ranges. Environmental requirements are usually
described in a product specifications document or in a physical planning guide.
24
CHAPTER 3 POWER DESIGN
CHAPTER 1
A separate space, called a plenum, is often allocated to house and allow air circulation for
HVAC and communication cabling, typically in the space between the structural ceiling and a
drop-down ceiling or under a raised floor.
TYBES OF HVAC:
1. Chilled Water System
Chilled water systems work much the same way as direct expansion systems work. The
exception is they use water in the coil rather than refrigerant. Technically speaking, water can
be classified as a refrigerant. Chilled Water systems can be rather complex and many chilled
water systems are found in commercial and industrial applications. There are some chilled
water systems used in residential applications.
25
CHAPTER 3 POWER DESIGN
CHAPTER 1
Chillers range in size from smaller than 5 tons all the way up to several hundred tons. Chillers
can be found in residential applications, commercial buildings, and industrial process
applications.
The water is then transferred to a cooling tower where the heat in this water is removed to the
atmosphere. Once the heat is removed from the water it is pumped back to the chiller barrel to
absorb more heat from the refrigerant. Some chillers do not have a condenser barrel to remove
the heat. The refrigerant is pumped into a condenser coil where a fan blows across the coil and
removes the heat. These chillers are cheaper to purchase upfront but not as efficient to run as
those with the condenser barrels. The upfront costs are less but the energy costs are more over
the long run. One bonus to an air cooled chiller is that it does not require a cooling tower and
therefore the maintenance costs associated with maintaining a cooling tower.
26
CHAPTER 3 POWER DESIGN
CHAPTER 1
The AHU is used to control the following parameters of the space:
Temperature.
Humidity.
Air Movement.
Air Cleanliness.
- We use disconnector switch for maintenance.
3.3 ELEVATORS
An elevator (or lift in the Commonwealth excluding Canada) is a type of vertical transport
equipment that efficiently moves people or goods between floors (levels, decks) of a building,
vessel or other structures. Elevators are generally powered by electric motors that either drive
traction cables or counterweight systems like a hoist, or pump hydraulic fluid to raise a
cylindrical piston like a jack.
Elevator Types:
1. According to hoist mechanism:
Elevators will be classified according to hoist mechanism to 4 main types as follows:
Hydraulic Elevators.
Traction Elevators.
Climbing elevator.
Pneumatic Elevators.
27
CHAPTER 3 POWER DESIGN
CHAPTER 1
High-Rise buildings (12 + stories)
Buildings up to about 12+ stories typically use Gear-Less Traction Elevators.
Hospital Elevators.
Residential /Domestic Elevators.
Agricultural Elevators.
Industrial Elevators.
Commercial Elevators.
Parking buildings Elevators.
‘Hospital elevator ’
28
CHAPTER 3 POWER DESIGN
CHAPTER 1
Hospital Elevators:
Hospital Bed Elevators
Hospital bed elevators generally transport patients who are not well enough to sit up even in a
wheelchair. One of the features of bed elevators should be its ability to transport the patient
has smoothly as possible with minimal amount of bumping and jostling. Many contemporary
bed elevators are manufactured to consume extremely low amounts of power and to be durable
with a number of safety features built-in. Hospital bed elevators generally draw very little
power so that should there be a power outage they are still operational off the hospital's backup
power supply. Most often there will be a rear and a front entry to the elevator cabin.
They usually are smaller than bed elevators. This particular type of elevator is usually
hydraulic or traction based depending on the location of the machine room. They are
specifically manufactured to be low-noise bed elevators that smoothly transport patients,
doctors, nurses and hospital staff between floors, allowing them the utmost in comfort.
Because hospital bed elevators are only used for transporting patients and hospital staff they
arrived at their location quite quickly, eliminating lengthy waits. Many of these bed elevators
are key operated so as to prohibit use by the general public.
Elevator Design:
STEP1: Elevator speed is selected according to the number of building floors, In this project
the hospital has six floors, so the speed is between 1 to 1.5 (m/s).
STEP2: Motor power calculations is determined with known elevator weight and speed.
In our project, we design weight of cabin to be 1000 kg and speed 1 m/s, so from curve the
power is 10 kW.
29
CHAPTER 3 POWER DESIGN
CHAPTER 1
3.4 PUMPS
A Booster Pump
Is a machine which will increase the pressure of a fluid. They may be used with liquids
or gases, but the construction details will vary depending on the fluid. A gas booster is similar
to a gas compressor, but generally a simpler mechanism which often has only a single stage of
compression, and is used to increase pressure of a gas already above ambient pressure. Two-
stage boosters are also made. Boosters may be used for increasing gas pressure, transferring
high pressure gas, charging gas cylinders and scavenging.
On new construction and retrofit projects, water pressure booster pumps are used to
provide adequate water pressure to upper floors of high rise buildings. The need for a water
pressure booster pump can also arise after the installation of a backflow prevention device
(BFP), which is currently mandated in many municipalities [where?] to protect the public
water supplies from contaminants within a building entering the public water supply. The use
of BFPs began after The Clean Water Act was passed. These devices can cause a loss of 12
PSI, and can cause flush meters on upper floors not to work properly. After pipes have been
30
CHAPTER 3 POWER DESIGN
CHAPTER 1
in service for an extended period, scale can build up on the inside surfaces which will cause a
pressure drop when the water flows.
A Fire Pump
A part of a fire sprinkler system's water supply and powered by electric, diesel or steam.
The pump intake is either connected to the public underground water supply piping, or a static
water source (e.g., tank, reservoir, lake). The pump provides water flow at a higher pressure
to the sprinkler system risers and hose standpipes. A fire pump is tested and listed for its use
specifically for fire service by a third-party testing and listing agency, such as UL or FM
Global. The main code that governs fire pump installations in North America is the National
Fire Protection Association's NFPA 20 Standard for the Installation of Stationary Fire Pumps
for Fire Protection.
Fire pumps function either by an electric motor or a diesel engine, or, occasionally a
steam turbine. If the local building code requires power independent of the local electric power
grid, a pump using an electric motor may utilize, when connected via a listed transfer switch,
the installation of an emergency generator.
The fire pump starts when the pressure in the fire sprinkler system drops below a threshold.
The sprinkler system pressure drops significantly when one or more fire sprinklers are exposed
to heat above their design temperature, and opens, releasing water. Alternately, other fire hoses
reels or other firefighting connections are opened, causing a pressure drop in the firefighting
main.
Fire pumps are needed when the local municipal water system cannot provide sufficient
pressure to meet the hydraulic design requirements of the fire sprinkler system. This usually
occurs if the building is very tall, such as in high-rise buildings, or in systems that require a
relatively high terminal pressure at the fire sprinkler in order to provide a large volume of
water, such as in storage warehouses. Fire pumps are also needed if fire protection water
supply is provided from a ground level water storage tank.
31
CHAPTER 3 POWER DESIGN
CHAPTER 1
Types of pumps used for fire service include: horizontal split case, vertical split case, vertical
inline, vertical turbine, and end suction.
A Jockey Pump:
Is a small pump connected to a fire sprinkler system and is intended to maintain pressure
in a fire protection piping system to an artificially high level so that the operation of a single
fire sprinkler will cause a pressure drop which will be sensed by the fire pump automatic
controller, causing the fire pump to start. The jockey pump is essentially a portion of the fire
pump's control system. A jockey pump is sized for a flow less than the flow to one sprinkler
in order to ensure a system pressure drop. Jockey pumps are typically small multistage
centrifugal pumps, and do not have to be listed or certified for fire system application. The
control equipment for jockey pumps may however carry approvals. Jockey pumps should be
sized for 3% of the flow of the main fire pump and to provide 10psi more pressure than the
main fire pump (As per Code IS 15105: 2002).
𝑊 × 𝑄 × 𝐻 × 0.746
𝑃=
75 × 𝐸
Where,
E is efficiency ≅ 60%.
Q is Rate (m3/s).
32
CHAPTER 3 POWER DESIGN
CHAPTER 1
-in our project at Q = 20 L/s = .02 m3/s, to boost 2 bar = 20 m head, so the required power of
the pump will be 7.5 kW.
LIST OF LOADS:
- MEDICAL EQUIPMENTS:
• Three X-rays devices (20 KW & 80 KW & 120 KW).
• Water treatment hemodialysis machine 20 KW.
• Medical air compressor 20 KW.
- HVAC :
• Chillers each 480 KW.
• Chilled water pumps each 19 KW.
• 12 AHU each with average power 40 KW.
33
CHAPTER 4
Chapter Contents:
4.1 The factors affecting cable selection.
4.2 Construction of cable.
4.3 Cables classification.
4.4 Cable routing types.
4.5 Cable sizing.
4.6 Voltage drop calculations.
34
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
An electrical cable is an assembly of one or more wires running side by side or bundled, which
is used to carry electric current.
Cables refer to feeders which feed electric panels or 3-ph loads but Wires for branch circuits
to 1-ph small loads.
35
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
(5) Metallic sheath or Tap shield
CU or AL with 0.1 mm width, it is used for the protection of cable from humidity and
mechanical stresses & for earthing of cable so, it must withstand the short circuit
current.
(6) Filler or Assembly
Polypropylene to fill spaces between cores to make the round form of cable.
(7) Inner jacket
PVC bedding, only in case of armoured cables.
(8) Armouring
Steel tape or wire tape, it is used for protection of cable against mechanical stresses.
(9) Outer jacket (Sheath)
PVC, it protects the cable and its metallic parts from corrosion.
Mainly used in the design of lighting and small power branch circuits, as these dedicated loads
draw small currents.
XLPE (Thermo-Setting)
• Higher cost.
• Max. operating temp. = 90 °C.
36
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
• Max. short circuit temp. = 250 °C.
• Rigid.
Mainly used in the feeders between main distribution panels and submain panels, as at the
same cross section area XLPE insulated cables carry current more than PVC insulated cables.
4) According to Armouring
Armoured
• STA (Steel Tape Armouring).
• STA.
• SWA.
37
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
4.4 Cable Routing Types:
1) Free in air
• Cables are installed on cable trays or cable ladders.
2) Laid in ground
• Directly buried in ground.
• Buried in ground inside conduit.
• Buried in ground inside duct bank.
3) In conduits
• Inside wall.
Carry the permanent full load current, and normal short-time over currents.
Doesn’t cause voltage drops likely to result in an inferior performance of certain loads.
Protect the cabling and busbars for all levels of overcurrent, up to and including short-
circuit currents
Ensure protection of persons against indirect contact hazards, particularly in TN- and
IT- earthed systems, where the length of circuits may limit the magnitude of short-circuit
currents, thereby delaying automatic disconnection (it may be remembered that TT-
earthed installations are necessarily protected at the origin by a RCD, generally rated at
300 mA).
The cross-sectional areas of conductors are determined by the general method described
in this Chapter. Apart from this method some national standards may prescribe a
minimum cross-sectional area to be observed for reasons of mechanical endurance.
38
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
Particular loads require that the cable supplying them be oversized, and that the
protection of the circuit be likewise modified.
• The maximum load current (IB) corresponds to the rated KVA of the load
according to the following equation:
𝑆 × 103
𝐼𝐵 =
√3 𝑉
Where,
39
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
4. Taking account of correction factors for different environment conditions.
The cable rating must be greater than the breaker current to allow the breaker to sense
the fault and take action before damage occurs. But, there are some derating factors due
to the surrounding conditions affecting the cable sizing which must be taken into
account.
40
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
• Soil thermal resistivity.
• Grouping factor.
* In order to take the previous environmental or special conditions of installation into account,
correction factors have been introduced.
The current carrying of cables is determined using the max. load current IB divided by different
correction factors, k1, k2,...
𝐼𝐶 ≅ 𝐼𝐵 × 1.5
Where,
41
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
5. Determination of cross-sectional areas using tables giving the current carrying
capability.
From the ELSEWEDY CABLES catalogue, the corresponding cross-sectional area of
cable for the determined cable current is chosen, as in the following figure:
42
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
A sample on the cable current calculation and cable sizing used in this project.
-Calculations:
43
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
4.6 VOLTAGE DROP CALCULATIONS
The impedance of circuit conductors is low but not negligible: when carrying load current
there is a voltage drop between the origin of the circuit and the load terminals. The correct
operation of a load (a motor, lighting circuit, etc.) depends on the voltage at its terminals
being maintained at a value close to its rated value.
It is necessary therefore to determine the circuit conductors such that at full-load current, the
load terminal voltage is maintained within the limits required for correct performance.
This section deals with determining voltage drop, in order to check that:
44
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
In this project the allowable voltage drop doesn’t exceed 2.5%, according to the following
equation:
𝑚𝑣 × 𝐼𝐵 × 𝐿
𝑉. 𝐷 =
1000 × 𝑛
Where,
45
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
NOTE:
For more accurate voltage drop calculations, we used ETAP load flow and voltage drop
software:
ETAP Load Flow software performs power flow analysis and voltage drop
calculations with accurate and reliable results.
The Load Flow software module calculates bus voltages, branch power factors, currents, and
power flows throughout the electrical system.
Built-in features like automatic equipment evaluation, alerts and warnings summary, load flow
result analyzer, and intelligent graphics make it a very efficient electrical power flow analysis
tool.
46
CHAPTER 4 CABLE SIZING AND VOLTAGE DROP CALCULATION
CHAPTER 1
A sample of the ETAP calculation used in this project:
47
CHAPTER 5
Chapter Contents:
5.1 Circuit Breakers
5.1.1 Why using circuit breaker.
5.1.2 Function of circuit breaker.
5.1.3 Types of circuit breaker.
5.1.4 Calculations of circuit breaker ratings.
5.2 Distribution Board.
5.2.1 Types of distribution boards.
5.3 Medium Voltage Switch Gear.
5.4 Short Circuit.
5.4.1 Types of short circuit.
5.4.2 Short circuit calculations.
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
Circuit breakers are the central part of air-insulated (AIS) and gas-insulated (GIS) switchgear.
High-voltage circuit breakers are mechanical switching devices which connect and break
current circuits (operating currents and fault currents) and carry the nominal current in closed
position.
• ACT by tripping the circuit breaker in a time frame necessary to prevent damage to itself and
the associated Load cables.
49
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
Based on location
1. Indoor (GIS)
2. Outdoor (AIS)
50
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
- Current rating: 10, 15, 20, 25, 30, 35, 40, 45, 50, 55, 60A, for NEC code.
- Advantages of MCB compared to fuse:
It automatically switches off the electrical circuit during abnormal condition of the network
means in over load condition as well as faulty condition. The fuse does not sense but Miniature
Circuit Breaker does it in more reliable way. MCB is much more sensitive to over current than
fuse.
51
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
For interrupting arc it creates an arc voltage in excess of the supply voltage. Arc voltage is
defined as the minimum voltage required maintaining the arc, its types:
After conducting load and diversity factor calculations, now we consider C.B capacity
calculations which are as follows:
𝑆 (𝑡𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑)
𝐼𝐶.𝐵 = × 1.25
380√3
Circuit breaker standard:
52
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
53
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
Back‐up protection:
In cases where the available short‐circuit current level exceeds the short‐circuit rating of the
downstream breaker a current‐limiting upstream breaker can be used to ensure proper
protection of the installation.
The take‐over current of the upstream breaker, i.e. the current at which the upstream breaker
starts to trip must not be larger than of the downstream breaker in order for that back‐up
protection providing breaker to ensure protection for all possible short‐circuit currents.
While back‐up protection enhances the protection level of the downstream breakers it can also
compromise selectivity since the upstream breaker is permitted to open and disconnect its
complete downstream installation.
54
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
- Safety.
- Flexibility.
- Reliability.
55
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
The NEC state that lighting circuit has a connection to the neutral of the panel board and has
over current protection of 30 amperes or less in one or more circuit. Maximum rating for one
circuit of light is 2000 VA which connected to the board by a feeder of 1.5mm^2 cross section
area. Number of light distribution board in each zone depends on the quantity of lighting use.
Aboard which considered as assembly of switch fuses for large motors and equipment
protected by a miniature circuit breaker of rated above 15 ampere.
Aboard which contain important & critical loads to ensure continuity of power supplied even
if the main source interrupted. Emergency Distribution board feed from diesel generator or
another feeder through (ATS) for important loads, also we can use UPS for very important
loads.
56
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
57
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
We have 4 transformers so MVSG is required to transfer the power from RMU to the
transformers.
It consists of two section and bus coupler and riser.
The Bus Coupler is 2 out of 3 (2/3) and is used to connect two bus bars incase if one of
the incoming was out of service to insure power sustainability to the loads.
58
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
The current in an electrical circuit flows the easiest way and if two points in a circuit with
different potentials are connected with low electrical impedance the current is taking a
shortcut between the two points.
The short-circuit current must be calculated at each level in the installation in view of
determining the characteristics of the equipment required to withstand or break the fault
current
Fault currents cause equipment damage due to both thermal & mechanical processes.
The single line-to-ground fault, the most common type, is caused by lightning or by conductors
making contact with grounded structures.
59
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
It might seem logical to declare a Line-Line fault as a 2-phase Fault objects because the fault
involves two phases.
However, it is simply a 1-phase fault connected between two phases of the same bus.
60
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
Etap
61
CHAPTER 5 CIRCUIT BREAKER AND SHORT CIRCUIT CALCULATIONS
62
CHAPTER 6
POWER FACTOR
CORRECTION
Chapter Contents:
6.1 Power factor definition.
6.2 Why to improve power factor.
6.3 How to improve power factor.
6.4 By using what equipment.
26
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
The Power Factor is an indicator of the quality of design and management of an electrical
installation. It relies on two very basic notions: active and apparent power.
The active power P (kW) is the real power transmitted to loads such as motors, lamps,
heaters, and computers. The electrical active power is transformed into mechanical power,
heat or light.
The apparent power S (kVA) is the product: VRMS X IRMS. The apparent power is the
basis for electrical equipment rating.
The Power Factor λ is the ratio of the active power P (kW) to the apparent power S(kVA):
λ = P(kW)/S(kVA)
In order to perform this conversion, magnetic fields have to be established in the machines.
The magnetic field is created by the circulation of current in coils, which are mainly
inductive.
It should be noted that while reactive current does not draw power from the system, it does
cause power losses in transmission and distribution systems by heating the conductors.
64
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
For these two reasons (transmission power losses and voltage drop), the Network Operators
work for reducing the amount of reactive (inductive) current as much as possible.
2. Technical/economic optimization:
65
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
A high power factor allows the optimization of the components of an installation.
Overrating of certain equipment can be avoided, but to achieve the best results, the
correction should be affected as close to the individual inductive items as possible.
66
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
If a bank of shunt capacitors is added to the load, its (capacitive) reactive current will
take the same path through the power system as that of the load reactive current. Since,
67
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
this capacitive current Ic (which leads the system voltage by 90 degrees) is in direct
phase opposition to the load reactive current (IL). The two components flowing through
the same path will cancel each other, such that if the capacitor bank is sufficiently large
and Ic = IL, there will be no reactive current flow in the system upstream of the
capacitors.
68
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
installation where the active-power and/or reactive-power variations are relatively large,
for example:
At the busbars of a general power distribution board.
8 At the terminals of a heavily-loaded feeder cable.
69
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
2. Compensation by sector:
Capacitor banks are connected to busbars of each local distribution board.
A significant part of the installation benefits from this arrangement, notably the feeder
cables from the main distribution board to each of the local distribution boards at which
the compensation measures are applied.
Advantages
- Reduces the tariff penalties for excessive consumption of kvars
- Reduces the apparent power kVA demand,
- The size of the cables supplying the local distribution boards may be reduced, or will
have additional capacity for possible load increases
- Losses in the same cables will be reduced
Comments
- Reactive current still flows in all cables downstream of the local distribution boards
- For the above reason, the sizing of these cables, and the power losses in them, are
not improved by compensation by sector.
70
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
6.6 Power factor correction implementation:
With total demand load of 1680 KW with power factor equals 0.8 at each main
distribution board.
We need to compensate the power factor to 0.92
From the following table we need 0.321 KVAR for each KW
So we need 0.321*1680 = 540 KVAR in steps
Capacitor bank and Circuit breaker sizing:
71
CHAPTER 6 POWER FACTOR CORRECTION
CHAPTER 1
According to Schneider Electric installation guide:
72
CHAPTER 7
ELECTRICAL POWER
SUPPLIES
Chapter Contents:
7.1 Ring Main Unit.
7.2 Transformer.
7.2.1 Types of transformers.
7.2.2 Equivalent circuit.
7.3 Uninterruptable Power Supply.
7.3.1 What is the UPS.
7.3.2 UPS circuit diagram.
7.3.3 Types of UPS.
7.4 Generator.
7.4.1 What is the generator.
7.4.2 A standby generator.
7.4.3 Uses of standby generator.
CHAPTER 7 ELECTRICAL POWER SUPPLIES
In electrical power distribution system, a Ring Main Unit is a factory assembled, metal
enclosed set of switchgear used at the load connection point of a ring – type distribution
network.
It include in one unit two switches that can connect the load to either or both main conductor,
and a fusible switch or circuit breaker and switch that feed a distribution transformer, the metal
enclosed unit connects to the transformer either through a bus throat of a standardized
dimension, or else through cable and is usually installed outdoors.
This type of switchgear used for Medium – voltage power distribution from 7200 volts to
36000 volts.
Types of RMU:
Ring main units can be characterized by their type of insulation, air, oil or gas. The switch
used to isolate the transformer can be a fusible switch, or may be a circuit breaker using
vacuum or gas-insulated interrupters. The unit may also include protective relays to operate
the circuit breaker on a fault.
74
CHAPTER 7 ELECTRICAL POWER SUPPLIES
Function of RMU:
1. Connect the Substation with each other.
2. Connect the distributer transformer to medium voltage network.
3. Connect many transformers which rated less than 5 MVA.
Earthing Switch:
Used to discharge the charges are trapped on the RMU.
75
CHAPTER 7 ELECTRICAL POWER SUPPLIES
7.2 Transformer
A transformer is a static electrical device that transfers electrical energy between two or
more circuits through electromagnetic induction. A varying current in one coil of the
transformer produces a varying magnetic field, which in turn induces a varying electromotive
force (emf) or "voltage" in a second coil. Power can be transferred between the two coils,
without a metallic connection between the two circuits. Faraday's law of induction discovered
in 1831 described this effect. Transformers are used to increase or decrease the alternating
voltages in electric power applications.
Since the invention of the first constant-potential transformer in 1885, transformers have
become essential for the transmission, distribution, and utilization of alternating current
electrical energy. A wide range of transformer designs is encountered in electronic and electric
power applications. Transformers range in size from RF transformers less than a cubic
centimeter in volume to units interconnecting the power grid weighing hundreds of tons.
Although they all share the basic characteristic transformer principles, they are customized in
construction or electrical properties for certain installation requirements or circuit conditions.
76
CHAPTER 7 ELECTRICAL POWER SUPPLIES
Autotransformer: Transformer in which part of the winding is common to both primary and
secondary circuits, leading to increased efficiency, smaller size, and a higher degree of voltage
regulation.
Phase angle regulating transformer: A specialized transformer used to control the flow of
real power on three-phase electricity transmission networks.
Scott-T transformer: Transformer used for phase transformation from three-phase to two-
phase and vice versa.
Poly phase transformer: Any transformer with more than one phase.
Output transformer: Transformer used to match the output of a valve amplifier to its load.
77
CHAPTER 7 ELECTRICAL POWER SUPPLIES
Winding joule losses and leakage reactance are represented by the following series loop
impedances of the model:
Core loss and reactance is represented by the following shunt leg impedances of the model:
Core losses are caused mostly by hysteresis and eddy current effects in the core and are
proportional to the square of the core flux for operation at a given frequency. The finite
78
CHAPTER 7 ELECTRICAL POWER SUPPLIES
permeability core requires a magnetizing current IM to maintain mutual flux in the core.
Magnetizing current is in phase with the flux, the relationship between the two is non-linear
due to saturation effects. However, all impedances of the equivalent circuit shown are by
definition linear and such non-linearity effects are not typically reflected in transformer
equivalent circuits. With sinusoidal supply, core flux lags the induced EMF by 90°. With
open-circuited secondary winding, magnetizing branch current I0 equals transformer no-load
current.
The resulting model, though sometimes termed exact equivalent circuit based
on linearity assumptions, retains a number of approximations. Analysis may be simplified by
assuming that magnetizing branch impedance is relatively high and relocating the branch to
the left of the primary impedances. This introduces error but allows combination of primary
and referred secondary resistances and reactance by simple summation as two series
impedances.
Transformer equivalent circuit impedance and transformer ratio parameters can be derived
from the following tests: open-circuit test, short-circuit test, winding resistance test, and
transformer ratio test.
79
CHAPTER 7 ELECTRICAL POWER SUPPLIES
In our project
80
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
• Required for critical loads (in places that can’t live without Electricity not even for only one
second) like:
(Operations room, labs, data centers, Dialysis rooms, fire alarm control panels)
81
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
7.3.3 Types of UPS:
Three types of UPS are mainly used:
1. On-line UPS:
The Online UPS consist of a rectifier, battery and inverter in-line with AC mains and load.
The AC power supplied to the Online UPS is fed first to the rectifier circuit, then it will convert
it into DC power. Then, this DC power is used to charge the battery, and this DC power is
supplied to the inverter circuit, and then it is supplied to load. There is transfer switch, but that
will always be in ON position. Thus, at every instant of time, the power delivered to the load
will be from the combination of rectifier and inverter circuit. The main advantage of using
Online UPS is that no switching is required between the main power line path and battery
backup path in case of power outage and In Online UPS the inverter is always in ON condition,
thus the power delivered to the load will be available at every instant of time.
2. Off-line UPS:
The Offline UPS directly supply the AC power to the device connected to the load. In case of
power failure, the offline UPS changes the position of the transfer switch. And it connects the
load to the battery backup path.
The battery of the offline Ups gets charged during the availability of AC power. In that
condition, the AC power is directly supplied to the load circuit, and at the same time the battery
of the offline ups gets charged with the help of rectifier circuit.
82
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
In case of power outage, the charged battery is used to supply DC power to the inverter which
in turn converts the DC power into AC and supply it to the load terminal.
3. Hybrid UPS:
The Standby-Ferro UPS was once the dominant form of UPS. This design depends on a special
saturating transformer that has three windings (power connections). The primary power path
is from AC input through a transfer switch, through the transformer, and to the output.
In the case of a power failure, the transfer switch is opened, and the inverter picks up the
output load. In the Standby-Ferro design, the inverter is in the standby mode, and is energized
when the input power fails and the transfer switch is opened.
83
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
7.4 Generator
7.4.1 What is the Generator?
Generator is a device that converts motive power (mechanical energy) into electrical power
for use in an external circuit. Sources of mechanical energy include steam turbines, gas
turbines, water turbines, internal combustion engines and hand cranks.
is a back-up electrical system that operates automatically within seconds of a utility outage
when an automatic transfer switch senses the power loss, commands the generator to start and
then transfers the electrical load to the generator. The standby generator begins supplying
power to the circuits. After utility power returns, the automatic transfer switch transfers the
electrical load back to the utility and signals the standby generator to shut off. It then returns
to standby mode where it awaits the next outage, a standby generator runs weekly self-tests.
Most units run on diesel, natural gas or liquid propane gas.
84
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
7.4.3 Uses of the Standby Generator:
A standby generator is required for feeding emergency loads like:
(Elevators, Water pumps, Chillers, Fire pumps, Exhaust fans, X-ray equipment, Medical
gas equipment).
In our project
We use two diesel standby generators of rating 1125 KVA, 50 Hz, 400/230 V, the diagram of
generator from the single line diagram is shown below.
85
CHAPTER 7 ELEECTRICAL POWER SUPPLIES
CHAPTER 1
If both backup power supply devices bring same benefits, you may wonder which one is better.
Should you buy Ups or the generator. To help you decide whether to buy UPS or the generator,
we will go over few major differences between the two backup power supply systems.
For starters, uninterruptible power supply works like a battery backup power supply. It
converts the electrical AC (alternating current) into DC (direct current), stores the energy
which is used to backup power supply when the power shuts off. Put in plain English,
uninterruptible power supply charges when the power is on and uses stored energy to support
electronic devices the instant the power is out. However, even though uninterruptible power
supply system delivers instant backup power supply, it does not last long. Other beneficial
features of the uninterruptible power supply are:
On the other hand, the generator provides hours of backup power supply, but has slower start
up time. It needs about 10 or more seconds to start up which is more than enough to lose data
you’ve been working on. Also, backup power supply depends on the size of the generator.
Unlike uninterruptible power supply, the generator:
86
CHAPTER 8
EARTHING SYSTEM
Chapter Contents:
8.1 What affects the ground resistance.
8.2 Ground system design.
8.3 Earthing system classifications.
8.4 Project’s earthing system design.
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
8. EARTHING SYSTEM
The earthing system is the total set of measures used to connect an electrically conductive
part to earth. The earthing system is an essential part of power networks at both high- and
low-voltage levels.
First, the NEC code (1987, 250-83-3) requires a minimum ground electrode length of 2.5
meters (8.0 feet) to be in contact with soil.
But, there are three variables that affect the ground resistance of a ground system:
88
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
8.2 Ground system design:
Simple grounding systems consist of a single ground electrode driven into the ground. The
use of a single ground electrode is the most common form of grounding and can be found
outside your home or place of business. Complex grounding systems consist of multiple
ground rods, connected, mesh or grid networks, ground plates, and ground loops. These
systems are typically installed at power generating substations, central offices, and cell
tower sites Complex networks dramatically increase the amount of contact with the
surrounding earth and lower ground resistances.
Soil resistivity:
Soil Resistivity is most necessary when determining the design of the grounding system for
new installations (green field applications) to meet your ground resistance requirements.
Ideally, you would find a location with the lowest possible resistance. But as we discussed
before, poor soil conditions can be overcome with more elaborate grounding systems. The soil
composition, moisture content, and temperature all impact the soil resistivity. Soil is rarely
homogenous and the resistivity of the soil will vary geographically and at different soil depths.
Moisture content changes season ally, varies according to the nature of the sublayers of earth,
and the depth of the permanent water table. Since soil and water are generally more stable at
deeper strata, it is recommended that the ground rods be placed as deep as possible into the
earth, at the water table if possible. Also, ground rods should be installed where there is a
89
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
stable temperature, i.e. below the frost line. For a grounding system to be effective, it should
be designed to withstand the worst possible conditions.
90
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
8.3 Earthing system classifications:
TT system.
TN-S system.
TN-C-S system
TN-C system
IT system
TT systems:
This arrangement covers installations not provided with an earth terminal by the Electricity
Supply Company. Thus it is the method employed by most (usually rural) installations fed by
an overhead supply. Neutral and earth (protective) conductors must be kept quite separate
throughout the installation, with the final earth terminal connected to an earth electrode by
means of an earthing conductor.
TN-S system:
This is probably the most usual earthing system in the world, with the Electricity
Supply Company providing an earth terminal at the incoming mains position. This earth
terminal is connected by the supply protective conductor (PE) back to the star point (neutral)
of the secondary winding of the supply transformer, which is also connected at that point
to an earth electrode. The earth conductor usually takes the form of the armour and
sheath (if applicable) of the underground supply cable.
91
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
TN-C-S system:
In this system, the installation is TN-S, with separate neutral and protective Conductors. The
supply, however, uses a common conductor for both the neutral and the earth .This
combined and neutral system is sometimes called the 'protective and neutral conductor' (PEN)
the “combined neutral and earth” conductor (CNE). The system, which is shown In Fig is
most usually protective multiple earth (PME) system.
TN-C system:
This installation is unusual, because combined neutral and earth wiring is used in both the
supply and within the installation itself. Where used, the installation will usually be the earthed
concentric system, which can only be installed under the special conditions (mostly used in
France).
92
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
IT system:
The installation arrangements in the IT system are the same for those of the TT system
. However, the supply earthing is totally different. The IT system can have an unearthed
supply, or one which is not solidly earthed but is connected to earth through a current
limiting impedance. IT system is shown in Fig:
IT system
93
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
94
CHAPTER 8 EARTHING SYSTEM
CHAPTER 1
95
CHAPTER 9
Chapter Contents:
9.1 Objective of system.
9.2 Main components of system.
9.3 Steps of design.
9.4 Precautions during design.
9.5 Automatic fire detector.
9.6 Audible devices.
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
97
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
2. Distribution of detectors to cover total area of project and other elements as
Manual Switch, alarm bell, flasher, control panel.
3. Drawing network and dividing the project to more zones.
Control panel
1. Conventional type:
A fire alarm system is often a natural option for small systems or budget constraints
because it’s cheaper.
How to work
During occurring fire the control panel receives a signal from the detectors
or calling point as there is a fire as a result the control panel send signal to alarm
system (sound or light) to make fire alarm.
The conventional detectors usually connect to the control panel through the circuits
to protect a particular region.
2. Addressable type
It's used in many places such as hotels and administrative building.
How to work
- The digital fire alarm system wraps through a wire around the building with
each detector having its own address.
- This system may contain one or more rings depending on the size of the system
and design requirements.
- Its control panel reports each detector separately.
- Each detector has a unique address on the control panel, making it able to
display the signal at the specified location.
It’s clear that this help to quickly determine the location of the accident and that is why the
fire system entitled digital is the natural choice of large buildings and system that requires
more complexities.
98
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
Control module
The unit is installed on the alarms and this unit is installed on the speakers so that
these speakers are given in the motherboard and convert it to addressable.
Isolation module
Used in case of separation of detectors in case of short circuits.
Usually put 20 unit in new reagents provide each reagent with this unit.
Repeater
- Put in wide places, the fire board is placed in the villa and placed repeater in the security
room.
99
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
- According to Egyptian code, if the ceilings are higher than 3m above the floor, the
interior distance of the reagents should be reduced
100
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
4. Ionization
5. Thermal (heat)
6. Duct.
101
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
Light obscuration type
In a projected Beam Detector, alarms are generated by diffusing the projected light beam by a
specified percentage of obscuration. Total beam blockage generally results in a trouble signal.
Wire the receiver unit as a 4-wire detector (separate power and sensing connections to the
control panel.
Chimes: Soft-toned appliances used where loud noises could be disruptive to other operations.
Generally used where qualified personnel are continuously in attendance.
Sirens: Extremely loud devices generally limited in use to outdoor or heavy industrial areas.
Speakers: Audible devices used in conjunction with voice evacuation messages. Life-Safety
speakers are not generally associated with Muzak systems.
102
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
Intelligent System
- Always an Addressable System.
- Processes detailed, analog data from detectors about smoke levels.
- Can provide sensitivity data for each detector.
- Employs Drift Compensation (self-calibration) in its detectors.
Note that in this application, two detectors are not required because all areas within the room
are within 21 feet of the detector.
103
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
Heat Detector Spacing
104
CHAPTER 9 FIRE ALARM SYSTEM
CHAPTER 1
A sample from our project:
105
CHAPTER 1
CHAPTER 10
LIGHT CURRENT
TELEPHONE, DATA AND NURSE CALL
SYSTEM
Chapter Contents:
10.1 Telephone Network.
10.1.1 Major system elements.
10.1.2 Types of telephone cables.
10.1.3 Telephone network components.
10.2 Data System.
10.2.1 System components.
10.2.2 Design steps.
10.3 Nurse Call System.
10.3.1 Patient room equipment.
10.3.2 Nurse station.
CHAPTER 10 LIGHT CURRENT
These are used exclusively for internal inter communication without exchange
and the telephone station are connected directly together via lines In many building, it
is necessary to have a system of calling staff which are on duty in staff room to link
with other rooms in the building. This can be found for example; in hotels, hospitals and
old people homes. All such systems can be arranged electrically and form part of the
electrical services in a building.
Some buildings have an internal telephone system switch which may consist of
extensions to the public telephone or may be an entirely separate installation. Here again
the essential matter for the electrical service designer is to be agree the outlet positions
with his customer and to arrange for them to be linked to each other by (conduit or
trunking).
Trunking
Can be a useful alternative to conduit when the system is complex one needing many
cables with a large number of junctions. Telephone cables do not have a protective
sheathing and therefore need the mechanical protection of conduit trunking.
An internal telephone installation which independent of the public telephones must
receive power from somewhere, all telephone work on low voltage and this is
provided either by a battery or by an electric power pack.
A battery:-
Needs to be kept charged by a battery charger to be supplied by main power. A power
pack usually contains its own transformer but this must then be fed from the mains.
107
CHAPTER 10 LIGHT CURRENT
In whichever way the telephone works, main power has to be provided somewhere,
usually at the central exchanger of the system the power required is very small and
can be supplied from a socket outlet or fused spur unit on the nearest convenient
general purpose.
The first element is a telephone instrument itself, or any other form of apparatus that
is attached to the telephone line.
The second element is involved with the various techniques used to signal and
control the operation of the vast communication network. The communication
network itself involves the switching equipment that connects communication circuits
formed by a variety of transmission media.
The last two elements are transmission and switching.
Telephone wire and cable has generally been grouped into three categories:
Fiber.
Copper.
Hybrid (composed).
108
CHAPTER 10 LIGHT CURRENT
PABX stands for “private automatic branch exchanger”. It’s a telephone exchange that
serves a particular business or office, as opposed to one that a common carrier or telephone
company operates for many businesses or for the general public.
109
CHAPTER 10 LIGHT CURRENT
In Telephony, a Main Distribution Frame (MDF or Main Frame) is a signal distribution frame
for connecting equipment (inside plant) to cables and subscriber carrier equipment (outside
plant).
The MDF is a termination point within the local Telephone exchange where exchange
equipment and terminations of local loops are connected by jumper wires at the MDF.
All copper pairs supplying services through user telephone lines are terminated at the
MDF and distributed through the MDF to equipment within the local Exchange.
110
CHAPTER 10 LIGHT CURRENT
Like other distribution frames the MDF provides flexibility in assigning facilities, at
lower cost and higher capacity than a patch panel.
Distribution frames are essential to the delivery of telecommunications services. They
provide a scalable means by which services can be delivered to individual subscribers
without requiring major cabling installations or changes.
In addition, by serving as a termination point for all copper pairs going to subscriber
locations, they are an ideal location for test access into the last mile, allowing service
providers to monitor and manage their entire physical copper infrastructure. Finally,
distribution frames often serve as a demarcation point between different carriers'
domains. As a result, they provide a simple means by which multiple service providers
can work together in a deregulated environment while maintaining independent network
infrastructures.
111
CHAPTER 10 LIGHT CURRENT
- SYSTIMAX 110-type hardware: is used for the Main Distribution Frame (MDF).
- 110-type hardware is available in two basic types: the 110A and 110P. The 110A
requires less wall space than the 110P. The 110P includes horizontal and vertical cable
troughs for managing cross-connect cables. The system is connected to the MDF with
the supplied B25A male to female 25-pair cables. The cables are provided in 10-foot (3
m) and 15-foot (4.5 m) lengths.
112
CHAPTER 10 LIGHT CURRENT
TTC stands for “Telephone Terminal Cabinet”. Telephone cabinet is used in telephone
networks of large buildings like hotels, companies, organizations, etc. as a termination of
outlets for connection of telephone sets.
One is used for connections of wall mounted type telephones & the other for connection of
desk type & fax type.
113
CHAPTER 10 LIGHT CURRENT
- Generally inside terminal room are preferred. This allows for access to power for
telephone equipment. With engineering approval wall Cabinets are acceptable for
buildings less than 20,000 square feet with external mounted SRP power cabinets.
- If power is provided in an inside terminal room Saddleback will collocate with them.
Sun West Engineering, Inc. MPOP-09604808 cabinet is the only one approved by
Saddleback Communications engineering. Other cabinets may be used but must be
approved prior to installation.
- An area 8’ in front of the cabinet must be kept clear for technician access.
- One isolated 20 Amp breaker circuit is extended to plywood backboard inside the
cabinet is to be provided.
- One #6 insulated copper wire terminated at the main power service panel ground bus
bar at one end and the other end terminated on a suitable buss bar located on the left
side of the cabinet near the splice compartment is to be provided.
- All access handles to accommodate a padlock.
- A maximum on four three foot radius 90 degree bends are allowed in each pulling
section.
Telephone socket
- It is a metallic box imbedded inside the wall arid inside it parts for connection of two
lines.
114
CHAPTER 10 LIGHT CURRENT
115
CHAPTER 10 LIGHT CURRENT
A patch cord (usually a 7 meter cable) is used to connect the output between the computer and
the number of cables used is equal to the required number of outputs.
Based on the cable used in Cat6 example, a Cat6 socket jump will be used
A keyboard that connects the switch between the computer and its features is numbered and
thus help you to arrange the cables from the switch to the computer and when a problem can
find the cable of the device to repair. If the cables are connected directly to the devices of the
switch we will find a forest of cables unorganized so we use the patch panel
It is selected according to the number of exits. For example, the second stage has 73 outputs
and accordingly a panel will be selected contains 48 ports.
116
CHAPTER 10 LIGHT CURRENT
Connectors:
After fixing the number of patch panel and is often empty, it is filled with connectors.
Patch cord:
The patch panel is connected to the switch (the switches are determined by the network
engineer and are not described during the design) by patch cord 1 m.
117
CHAPTER 10 LIGHT CURRENT
Cable Organizer:
In order to maintain the regulation of the cables during the conduction within the conductor, a
regulator is used for the passage of the wires and uses 1 for each patch panel.
The cable is connected by a normal data cable cat6, unless the distance between the drips is
more than 110 meters. The fiber cable is connected to the same cable as the normal data cable.
It is used in long distances. It is more expensive than ordinary cable and has its own
components. Use special patch panel and special components.
It is the structure in which the contents are installed or by cab and are characterized by cab
width & height
The RAC 42U is often used for the main building track and 18: 22U for the sub-rigs in the
rotors according to the number of appliances used.
118
CHAPTER 10 LIGHT CURRENT
Registered Jack is the meaning of the acronym RJ which is the acronym that cable connectors
usually start with. Two of the most common jacks are the RJ45 and RJ11, each with their own
specific purpose. The main difference between these two is in where they are actually used.
RJ45 jacks are used in networking, where you connect computers or other network elements
to each other. RJ11 is the cable connector that is being used in telephone sets.
119
CHAPTER 10 LIGHT CURRENT
120
CHAPTER 10 LIGHT CURRENT
1. Patient Stations.
2. Call Devices.
A device located on the wall behind the patient bed that allows patients or staff to
summon help. It is typically activated by a call cord or pillow speaker. It normally has
a call assurance lamp, which lights when a call is placed, and a reset switch for canceling
121
CHAPTER 10 LIGHT CURRENT
Call Cords:
- Cord sets are directly interchangeable to meet varying requirements.
- All call cord sets are approved and listed under UL1069 standards.
- All switches are totally enclosed for complete protection.
122
CHAPTER 10 LIGHT CURRENT
- Pressure pad cord set is available for elderly patients and others unable to use
their hands.
- The oxygen pressure pad cord set is safe for use in oxygen tents.
- The Dummy Plug deactivates stations when Pillow Speakers are removed.
123
CHAPTER 10 LIGHT CURRENT
- Room lamp:
A visual annunciator, mounted on the wall (or ceiling) outside a room that indicates calling
activities and the presence of staff members. It may have a single bulb or several bulbs of
different colors to indicate the types of calls and staff members. Also referred to as a dome
light.
124
CHAPTER 10 LIGHT CURRENT
- Room controller:
The components needed to process and distribute signals among nurse and patient stations and
other peripheral devices.
125
CHAPTER 10 LIGHT CURRENT
126
CHAPTER 10 LIGHT CURRENT
- Call and status identification with indication for zones, rooms, beds, normal calls,
bathroom / WC emergency calls, plug release calls, diagnostic calls, doctor calls,
call on hold, Presence I and II, failure, further calls .
- Free selectable zone interconnection.
- Call answering.
- Multiple calls and presence signals are indicated in parallel.
- Functions are activated via touch screen.
- Menu navigation and free assignment of buttons (alphanumeric display).
Equipped with:
1. 1 call push-button –red –with LED orientation / reassurance lamp.
2. 1 doctor call lamp -blue -with LED reassurance lamp.
3. 2 presence push-buttons –green and yellow –with LED reminder lamp.
4. 1 sound generator for call transfer.
5. 1 illuminated LCD with touch-sensitive surface.
Staff station:
- A station typically used by the staff to place calls to the nurse control station. It
is typically located in staff areas but can also be located in areas used by
ambulatory patients.
Duty station:
- A station that uses tones and lamps to annunciate calls by their type or priority. It
is normally installed in a location where nurses tend to be when they are not at
the nurse control station or in patient rooms (e.g., clean linens, soiled linens, and
nurses’ lounge).
127
CHAPTER 10 LIGHT CURRENT
128
APPENDIX
LOAD ESTIMATIOM
PANEL SCHEDULES
131
132
133
134
REFERENCES
REFERENCES
136
PLANS