6. SAFETY
7. FINAL ACCEPTANCE APPROVAL………………………………………………………………………………………….
………………………………….………….. 29
STANDARD REFERENCES:
“IEC 62446: ON/OFF Grid connected photovoltaic systems – Minimum requirements for system
documentation, commissioning tests and inspection”
Base on IEC Standard, the following pre-commissioning checklist and test describe at the basic of
IEC 62446 Clause 4, where:
4.1 General establish minimum documentation to ensure Key system data is available
4.2 System data Information about system information, designer and installer
4.3 Wiring diagram Single line wiring diagram
4.4 Datasheets For all types of modules and inverters
4.5 Mechanical design information – Data sheet for array mounting system
4.6 Operation and maintenance information Correct operation, failure, shutdown, maintenance,
cleaning, warranty.
4.7 Test results and commissioning – Copies with results from verification tests”
PT. REJA ATON ENERGI as System Integrator and contractor for this project of the Grid Connected
of PV systems (GCPV) must prepare documents pre-commissioning checklist and submitted to user.
This activity shall be conducted by the competent persons as stated at the end of the checklist,
whilst adhering to the relevant laws and regulations.
During the pre-commissioning checks, the GCPV systems shall not be engaged to the grid. All
checks during pre-commissioning are done visually.
IEC Standard:
1. General Inspection (IEC 62446-4.1)
2. PV Module Mounting Structure & Civil foundation (IEC 62446-4.5)
3. DC Junction Box or Main Distribution Panel DC Box (IEC 62446-4.2)
4. Grounding Earth & Lightning Arrestor (IEC 62446-5.4.2)
5. PV Module (IEC 62446-4.4)
6. Inverter (IEC 62446-4.4)
7. AC Distribution Box or Main Distribution Panel AC Box (IEC 62446-5.4.1)
8. Cable identification and cable routing inspection (IEC 62446-5.4.2)
9. Weather monitoring station and monitoring system (IEC 62446-5.4.7)
10. Cable insulation test (IEC 62446-5.4.2)
11. String fuse continuity and string open circuit voltage test (IEC 62446-5.4.4)
12. String DC short circuit current test (IEC 62446-5.4.5)
13. Isolation device functional test (IEC 62446-5.4.6)
4.1 GENERAL INSPECTION
Table 4.1.1 General Inspection
Visual Inspection
Description Date of inspection
(Please tick in the box, if the job has been done satisfactorily)
Instructions This form shall be filled-up Inverter 1 and 2 {Checklist }
for each sub-
array connected to one
inverter
A. General
1 Check for necessary safety equipment is available at the site
2 Array frame correctly fixed and stable
3 Cable route entries tray and conduit are weather proof
4 PV module Ground Mounting Layout, Inverter Racking Layout, Cable Route
Layout as per approved layout drawing
5 SLD Layout, MDP DC and MDP AC Layout, Grid interconnection Layout as per
approved layout drawing
6 Equipment for testing, inspection and operation & maintenance
7 Protection device are connected as per approved drawing
8 All cables are selected for current carrying capacity
9 All cables are identified and connected as per approved drawing
10 Cables routed are in safe zone or protected against mechanical
damage
B. DC Voltage Section
1 All DC components are sized for rated operation at maximum
DC system voltage
2 All DC cables are mean for solar PV applications and as per design
document
3 PV string fuse or DC switch breaker are available in the MDP DC
box
4 Protection Device are available Such as Fuses, Surge arrester, DC
Switch
C. Protections against over voltage and electric shock
1 Surge protection devices or lightning arrestor are available
2 Frame correctly integrated associated with grounding system
installation
3 Live parts Insulated protected by barrier/enclosure, placed out of
reach
D. AC Voltage Section
1 MDP AC are lockable
2 Inverter protection setting as per local regulation
(Labeling & identification mark)
3 General labeling for circuits, protective devices switches &
terminals
4 MDP AC layout are placed at panel box
5 AC isolators are clearly labeled
COMMENT:
CHECKED BY: WHITNESES BY:
COMMENT
COMMENT
COMMENT
COMMENT
COMMENT
COMMENT
1 All cable routed areas on the air (by fixed & tentative support) and
ground
2 All power cable route & locations are as per drawing
3 All cables are properly tagged
4 All DC cables are meant for solar PV applications and as per design
document
5 Incoming/outgoing cables are properly connected as per approved
schematic diagram
Comments: Proceed to next checklist YES NO
(Please tick in the appropriate box
COMMENT
COMMENT
1 INV 1-1
(Inverter 1-MPPT 1)
2 INV 1-2
(Inverter 1-MPPT 2)
3 INV 2-1
(Inverter 2-MPPT 1)
4 INV 2-2
(Inverter 2-MPPT 2)
COMMENT:
Table 4.11 String fuse and String Open Circuit Voltage test
Format No Date of inspection:
Description References:
Inverter No
Comment:
-2
Solar irradiance should be at least 350 Wm when
performing this test.
Instructions:
SWITCH OFF / DISCONNECT the following:
- PV AC Main Switch (isolator)
- All AC switches
- All DC switches
- All DC fuses
COMMENT
COMMENT:
After completion of all visual inspections from the checklist, ATONERGI as System Integrator
must perform commissioning tests to ensure all inter-connections of the components are
satisfactory.
Conditions:
1. All tests must be done in sequence.
2. If a test fails, the next test shall not be performed.
3. Failure of any test nullifies the entire Testing and Commissioning.
4. The Weather Monitoring Station and PV Monitoring System shall be provided, installed
and maintained by ATONERGI for the entire duration of preventive maintenance in a year.
COMMENT
COMMENT
Table 5.3.1. Information about cable and wiring INV-1 and INV-2
Description Visual Inspection
(Please tick in the box, if the job has been done
satisfactorily. If not applicable, write ‘NA’ in the box)
Instruction: This form shall be filled-up for Inverter 1 and Inverter 2
each connection to one inverter
No. Item Details Unit Check
()
1 All exposed cables are free from
mechanical damage
2 All plugs, connectors and sockets are
fully engaged
3 Array MDP DC Box for outdoor should be
closed are weather proof
4 Marking/tagging of positive and
negative cables are properly done
5 PV string cable size mm2
6 PV Array cable size mm2
7 PV string fuse are in disconnected
position
8 PV string polarity connected correctly
9 Grounding cables are properly mm2
connected
10 PV DC Main Switches are connected
properly
11 All DC cables are for solar PV
applications
12 Overall wiring are labeled
COMMENT
COMMENT
COMMENT
COMMENT:
CHECKED BY: WHITNESES BY:
Check
No. Item Details ()
1
1 No. of reference cells/pyranometers pcs
1
2 No. of temperature sensors (ambient) pcs
1
3 No. of anemometers pcs
1
4 No. of temperature sensors (module) pcs
Modbus RTU
5 Communication protocol
COMMENT:
CHECKED BY: WHITNESES BY:
Format No :
Description References
-2
Solar irradiance should be at least 350 Wm when
performing this test.
COMMENT:
Contractor
Testing and
Commisioning
Officer
Reccomended
By
Accepted By