You are on page 1of 3

1 EARTHWORKS

A. STRUCTURAL EXCAVATION
NOTE: ALLOWANCE OF 0.5 METERS FOR WORKERS
Column Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
F1C1 1.6 1.6 1.65 4.224 16 67.584
F2C1 1.4 1.4 1.65 3.234 22 71.148
TOTAL = 138.732 m3
Footing Tie Beam
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
FTB-1 4.3 0.85 0.7 2.559 16 40.936
1.6 0.85 0.7 0.952 5 4.760
1.375 0.85 0.7 0.818 2 1.636
4.1 0.85 0.7 2.440 2 4.879
3.275 0.85 0.7 1.949 4 7.795
3.3 0.85 0.7 1.964 6 11.781
3.375 0.85 0.7 2.008 2 4.016
TOTAL = 75.803 m3

Wall Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
WF-1 3.075 1 0.7 2.153 1 2.153
1.875 1 0.7 1.313 5 6.563
1.375 1 0.7 0.963 2 1.925
5.6 1 0.7 3.920 2 7.840
6.1 1 0.7 4.270 1 4.270
23.95 1 0.7 16.765 2 33.530
3 1 0.7 2.100 10 21.000
TOTAL = 77.280 m3

TOTAL VOL. OF EXCAVATION = 291.815 m3


B. GRAVEL BASE COARSE

Column Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
F1C1 1 1 0.15 0.15 16 2.4
F2C1 0.8 0.8 0.15 0.096 22 2.112
TOTAL = 4.512 m3

Footing Tie Beam


Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
FTB-1 5.8 0.25 0.1 0.145 16 2.320
3 0.25 0.1 0.075 5 0.375
5.6 0.25 0.1 0.140 2 0.280
4.775 0.25 0.1 0.119 2 0.239
4.8 0.25 0.1 0.120 3 0.360
4.8 0.25 0.1 0.120 6 0.720
4.5 0.25 0.1 0.113 2 0.225
2.775 0.25 0.1 0.069 2 0.139
TOTAL = 4.658 m3
TOTAL LENGTH= 186.300 m3

Wall Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
WF-1 90.2 0.4 0.1 3.608 1 3.608
TOTAL = 3.608 m3
TOTAL LENGTH= 90.2 m3

Flooring
Dimension (m) Volume Qty Total Volume
Designation
L W H (cu. m) (pcs) (cu. m)
A-1 5.35 14.35 0.1 7.67725 1 7.67725
A-2 23.95 14.35 0.1 34.36825 1 34.36825
A-3 4.25 8.3 0.1 3.5275 1 3.5275
TOTAL = 45.573 m3

TOTAL VOL. OF GRAVEL BASE = 58.351 m3


C. EMBEDDED CONCRETE
Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
F1 1 1 0.25 0.25 16 4
F2 0.8 0.8 0.25 0.16 22 3.52
TOTAL = 7.52 m3
Column
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
C1 0.25 0.25 2.5 0.15625 38 5.9375
TOTAL = 5.9375 m3
Footing Tie Beam
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
FTB-1 186.300 0.25 0.4 18.63 1 18.63
TOTAL = 18.63 m3
Wall Footing
Dimension (m) Volume Qty Total Volume
Designation
L W H (m3) (pcs) (m3)
WF-1 90.2 0.4 0.25 9.02 1 9.02
TOTAL = 9.02 m3
TOTAL VOL. OF EMBEDED CONCRETE = 41.108 m3

D. BACKFILL AND COMPACTION


Total Excavation = 291.815 m3
Total Embedded Concrete = 41.108 m3
Total Gravel Base = 58.351 m3
TOTAL = 192.357 m3

E. HAULING AND DISPOSAL OF EXCESS SOIL


Total Excavation = 291.815 m3
Gravel Base Above Ground = 45.573 m3
Backfill = 192.357 m3
TOTAL = 53.885 m3
F. SOIL POISONING
Dimension (m) Area
Designation
L W (m2)
A-1 5.6 14.6 81.76
A-2 28.45 14.6 415.37
TOTAL = 497.13 m2
G. POLYETHYLENE SHEET
Dimension (m) Area
Designation
L W (m2)
A-1 5.6 14.6 81.76
A-2 23.95 14.6 349.67
A-3 4.50 8.55 38.48
TOTAL = 469.91 m2

You might also like