You are on page 1of 253

This is a reproduction of a library book that was digitized

by Google as part of an ongoing effort to preserve the


information in books and make it universally accessible.

https://books.google.com
8/5 : 150/5370-14
Asphalt Paving Ha... Govt. Publs. Dept.
Hot Mix Asphalt
U.S.Department
of Transportation
Federal Aviation Paving Handbook
Administration

AC : 150/5370-14 Advisory Circular

Date : 10/15/91

X
Advisory
U.S.Department
ofTransportation
Circular
Federal Aviation
Administration

Subject: HOT MIX ASPHALT PAVING HANDBOOK Date: 10/15/91 AC No: 150/5370-14
Initiated by: AAS-200 Change:

1. PURPOSE. This advisory circular (AC) provides In order to address this problem, the Transportation
guidance on asphalt paving operations including plant Research Board (TRB) developed an asphalt paving
operations, transportation of materials, surface prepara- handbook under the auspices of several Federal and in-
tion, laydown and compaction. dustry agencies. The handbook is aimed at governmen-
2. BACKGROUND . Agencies and contractors tal agency personnel and contractor employees in-
share common concerns about the problems of prop- volved in the construction of asphalt pavements. It
erly constructing asphalt pavements. Training is a concentrates on field practices at the asphalt plant
major problem in a decentralized industry such as as- during mix production and at the paving site during
phalt paving, where many procedures and contractors mix laydown and compaction. The handbook is includ-
operate on too small a scale to make long-term invest- ed in this AC as Appendix 1.
ments in personnel development; and, as a result, the
knowledge and field experience of field personnel is
not current.

Rayna Ticke
LEONARD E. MUDD
Director, Office of Airport Safety and Standards

EPOSIT

FEB 31992

INDIA
LIM
4

90

For sale by the U.S. Government Printing Office


Superintendent of Documents, Mail Stop: SSOP, Washington, DC 20402-9328
ISBN 0-16-036002-1
10/15/91 AC 150/5370-14

APPENDIX 1 - HOT MIX ASPHALT PAVING HANDBOOK


AC 150/5370-14
10/15/91
Appendix 1

PREFACE

Each year, more than $20 billion is spent in the United States to
construct asphalt pavements for highways and airports. Asphalt
paving contractors, public agencies, and the pavement research
community share concerns about the problems of properly construct-
ing these pavements. Pavement experts agree that highway and
airport agencies and their pavement contractors not only have
difficulty incorporating research findings into field practice , but also
have difficulty in consistently applying proven procedures from earlier
research experience . Training is a problem in such a decentralized
industry, where many producers and contractors operate on too small
a scale to make long-term investments in personnel development ; and ,
as a result, the knowledge and experience of field personnel is often
not up-to-date.

A working group of industry, government, and academic officials


assembled by the Transportation Research Board (TRB) * agreed
that a step towards addressing some of these problems would be the
development of an asphalt paving handbook, widely accepted by
major segments of the paving industry. Field manuals and handbooks
have been available from many agencies, but none has been adopted
by all major industry segments; and , as a result, personnel from
contractors and specifying agencies may be confused by conflicting
recommended practices. A single manual could reduce this confusion
and assist in the promulgation of good practice based on available
research and experience.

In 1988 , the TRB Executive Committee accepted the recommendation


for the preparation of such a handbook, and with financial support
from the American Association of State Highway and Transportation
Officials, the Federal Aviation Administration, the Federal Highway
Administration, the National Asphalt Pavement Association, and the
U.S. Army Corps of Engineers proceeded with its development. The
handbook is being technically approved and distributed as a general
guide for asphalt paving construction not only by its financial sponsors
but also by the American Public Works Association and the National
Association of County Engineers" . Each agency followed its
individual process and submitted the manuscript for review by its
technical experts.

iii
AC 150/5370-14
Appendix 1
10/15/91

To undertake this project, the National Research Council appointed


a study committee chaired by Jon A. Epps, Dean of the College of
Engineering, University of Nevada - Reno. The committee, with
members knowledgeable in the various aspects of asphalt pavement
construction practices and representing agencies, producers, and
contractors, commissioned James A. Scherocman to draft the
handbook under its direction . The final version incorporates changes
made in response to comments received from members of the
committee, approving organizations, and from other individuals
appointed to review the draft in accordance with the National
Research Council's report review guidelines.

This handbook covers the state of the art of asphalt paving operations
including plant operations, transportation of materials , surface
preparation, laydown, and compaction . It is aimed at the field
personnel who are responsible for these operations, both contractor
personnel who do the work and agency personnel who oversee and
inspect the work. It is hoped that the handbook will create a better
understanding of the processes involved and thereby result in
improved asphalt pavement construction.

The handbook is not intended to cover administration , contracting


procedures, site investigation, geometric design, structural design, or
mix design, although some general information is included concerning
contract administration and mix design. Therefore , in these areas
existing agency policies and procedures will have precedence .

The work was performed under the overall guidance of Thomas B.


Deen, Executive Director, and Robert E. Skinner, Jr., Director for
Special Projects. Herbert A. Pennock managed the project. Special
appreciation is expressed to Judith A. Klein for editing the handbook.

July 31, 1991

*The Transportation Research Board is a unit of the National Research Council,


which serves as an independent advisor to government on scientific and technical
questions of national importance . The Research Council, jointly administered by the
National Academy of Sciences, the National Academy of Engineering, and the
Institute of Medicine, brings the resources of the entire scientific and technical
community to bear on national problems through its volunteer advisory committees.

**This publication was approved as a Guide by the American Association of State


Highway and Transportation Officials Executive Committee on December 8 , 1990 .
This document is also being published as Federal Aviation Administration Advisory
Circular AC 150/5370-14 and as the U.S. Army Corps of Engineers publication
UN- 13 (CEMP-ET) .

iv
AC 150/5370-14
10/15/91
Appendix 1

TABLE OF CONTENTS

PART ONE

SECTION ONE BACKGROUND 1-1


Purpose and Organization of Handbook 1-1
Terminology 1-1
Workmanship 1-4

SECTION TWO PROJECT ORGANIZATION 1-5


Introduction 1-5
Project Documents 1-5
Preconstruction Conference 1-6
Ongoing Communication 1-6
Project Records 1-7
Safety 1-8

SECTION THREE MIX DESIGN AND THE JOB MIX FORMULA ……………. 1-10
Introduction 1-10
Material Properties 1-10
Mix Design Procedures 1-19
Laboratory- and Plant-Produced Mixes 1-20
Summary 1-23

PART TWO

SECTION ONE TYPES OF ASPHALT PLANTS 2-1


Introduction 2-1
Batch Plants 2-1
Continuous Mix Plants 2-4
Drum Mix Plants 2-4

SECTION TWO AGGREGATE STORAGE AND HANDLING 2-10


Introduction 2-10
Aggregate Stockpiles 2-10
Cold-feed Systems for New Aggregates 2-12
Cold-feed Systems for Reclaimed Asphalt Pavement 2-19
Addition of Hydrated Lime 2-21
Calibration 2-21
Summary of Aggregate Handling Operating Techniques 2-22

SECTION THREE ASPHALT CEMENT SUPPLY SYSTEM 2-24


Introduction 2-24
Storage Tanks 2-24
Pump and Meter System 2-25
Addition of Liquid Antistrip Materials 2-27
Calibration 2-27
Summary of Asphalt Cement Supply Operating Techniques 2-28

SECTION FOUR DRUM MIX PLANT 2-29


Introduction 2-29
Aggregate Entry 2-29
Burner System 2-29
AC 150/5370-14
Appendix 1
10/15/91

Contents (continued)

Heat-Transfer Process 2-31


Asphalt Cement Injection 2-36
Mineral Filler and Baghouse Fines Feed System 2-38
Reclaimed Material Recycling Systems 2-40
Production Rates 2-42
Plant Efficiency 2-44
Summary of Drum Mixer Operating Techniques 2-46

SECTION FIVE SURGE AND STORAGE SILOS .... 2-48


Introduction 2-48
Conveying Devices 2-48
Bin Geometry 2-48
Top of the Silo 2-49
Surge Versus Storage 2-51
The Cone, Loadout, and Segregation 2-53
Summary of Silo Operating Techniques 2-54

SECTION SIX EMISSION CONTROL 2-56


Introduction 2-56
Fines Carryout 2-56
Primary Dry Collector 2-56
Wet Collector 2-58
Baghouse 2-59
Fugitive Dust 2-61
Summary of Emission-Control Operating Techniques 2-62

SECTION SEVEN BATCH PLANT .... 2-63


Introduction 2-63
Aggregate Handling 2-63
Addition of Hydrated Lime 2-65
Asphalt Cement Supply System 2-65
Addition of Liquid Antistrip Additives 2-65
Aggregate Heating and Drying 2-65
Screening and Storage of Hot Aggregate 2-66
Weigh Hopper 2-70
Pugmill 2-70
Producing Recycled Mix 2-74
Loading the Truck or Silo 2-77
Emission-Control Equipment 2-77
Calibration 2-77
Summary of Plant Operating Techniques 2-78

BIBLIOGRAPHY 2-79

PART THREE

SECTION ONE MIX DELIVERY………


.. 3-1
Types of Trucks 3-1
Hauling Procedures 3-4
Summary of Mix Delivery Techniques 3-9
AC 150/5370-14
10/15/91
Appendix 1

Contents (continued)

SECTION TWO SURFACE PREPARATION 3-10


Introduction 3-10
Preparation of Existing Surface 3-10
Tack Coat 3-13
Surface Preparation Techniques 3-15

SECTION THREE MIX PLACEMENT …………. 3-17


Introduction 3-17
The Tractor Unit 3-17
The Screed Unit 3-25
Mix Placement Techniques 3-37

SECTION FOUR AUTOMATIC SCREED CONTROLS 3-40


Introduction 3-40
Automatic Screed Controls 3-41
Grade Control 3-43
Slope Control 3-48
Yield, Minimum Thickness, and Screed Controls 3-48
Automatic Screed-Control Operating Techniques 3-52

SECTION FIVE JOINT CONSTRUCTION 3-53


Introduction 3-53
Transverse Joints 3-53
Longitudinal Joints 3-64
Joint Construction Operating Techniques 3-69

SECTION SIX COMPACTION 3-70


Introduction 3-70
Definitions 3-70
Factors Affecting Compaction 3-70
Compaction Variables 3-81
Determination of the Rolling Pattern 3-86
Roller Operating Techniques 3-87

SECTION SEVEN EQUIPMENT AND MAT PROBLEMS .... 3-89


Introduction 3-89
Surface Waves 3-89
Tearing 3-91
Nonuniform Texture 3-92
Screed Marks 3-93
Screed Responsiveness 3-95
Surface Shadows 3-95
Precompaction Levels 3-96
Joint Problems 3-97
Checking 3-98
Shoving 3-100
Bleeding and Fat Spots 3-101
Roller Marks 3-103
Segregation 3-104
Other Pavement Problems 3-107

BIBLIOGRAPHY 3-108
:
AC 150/5370-14
10/15/91 Appendix 1

Part One

INTRODUCTION
AC 150/5370-14
10/15/91
Appendix 1

PART ONE

TABLE OF CONTENTS

SECTION ONE BACKGROUND .... • 1-1


PURPOSE AND ORGANIZATION OF HANDBOOK 1-1
TERMINOLOGY .. 1-1
Hot-Mix Asphalt 1-1
Dense-Graded Asphalt Concrete 1-2
Large-Stone Mixes 1-2
Sand Mix 1-3
Open-Graded Mixes 1-3
Open- Graded Asphalt-Treated Permeable Material 1-3
Gap-Graded Asphalt Mixes 1-3
WORKMANSHIP 1-4

1111
SECTION TWO PROJECT ORGANIZATION ... 1-5
INTRODUCTION 1-5
PROJECT DOCUMENTS 1-5
PRECONSTRUCTION CONFERENCE • 1-6
ONGOING COMMUNICATION 1-6
Formal Meetings 1-6
Informal Meetings 1-7
Communication Form 1-7
PROJECT RECORDS 1-7
Plant Reports 1-7
Pavement Reports 1-8
Daily Diary 1-8
SAFETY .. 1-8

SECTION THREE. MIX DESIGN AND THE JOB MIX FORMULA 1-10
INTRODUCTION 1-10
MATERIAL PROPERTIES 1-10
Properties of the Asphalt Cement 1-10
Asphalt Cement Grade 1-10
Temperature-Viscosity Characteristics 1-11
Laboratory Mix Design 1-11
Plant-Produced Mix 1-11
AC 150/5370-14
Appendix 1 10/15/91

Part One Contents (continued )

Properties of the Aggregates 1-12


Shape 1-12
Surface Texture 1-12
Maximum Particle Size 1-12
Absorption 1-12
Gradation 1-12
Voids in Mineral Aggregate 1-16
Percent Passing No. 200 (75-μm) Sieve 1-16
Gradation Passing the No. 200 (75-μm) Sieve 1-16
MIX DESIGN PROCEDURES 1-19
Marshall Method 1-19
Hveem Method 1-19
AAMAS Method 1-20
LABORATORY- AND PLANT-PRODUCED MIXES .... ... 1-20
Asphalt Cement 1-20
Aggregate 1-20
Mixing Process 1-22
Compaction 1-22
SUMMARY 1-23
AC 150/5370-14
10/15/91
Appendix 1

SECTION ONE
BACKGROUND

PURPOSE AND ORGANIZATION OF HANDBOOK The use of reclaimed asphalt pavement (RAP) in
The purpose of this Hot-Mix Asphalt Paving Hand- both drum and batch plants is described . Emphasis is
book is to describe the production and placement of placed on entry location and potential problems with
asphalt mixtures from a practical viewpoint . It is written normal plant operation when RAP is used in the mix.
for two different, yet similar, groups of individuals. The Part Three focuses on the laydown site, where the
first group includes the governmental agency personnel, delivery of the mix to the paver is discussed . Methods
consisting of people who carry such titles as resident presented include depositing the mix into the paver
engineer, county engineer, municipal engineer, project hopper directly from the truck, depositing the mix on
engineer, and plant or paving inspector. The second grade in a windrow, and using a windrow elevator or
group includes the contractor's employees. Individuals other device. The preparation of the existing pavement
who are part of this category carry titles such as project surface for placement of the mix is reviewed , with
superintendent, plant or paving superintendent, and emphasis on the application of a tack or prime coat. The
plant or paving foreman . The handbook concentrates on operation of the paver is reviewed in detail. The func-
field practices--at the asphalt plant during mix produc- tions of the primary parts of the tractor or drive unit
tion and at the paving site during mix laydown and (hopper, wings, slat conveyor, and augers) are analyzed .
compaction. The principle of the free-floating screed and the forces
Part One provides a brief review of project organiza- acting on the screed are examined . The use of automatic
tion, followed by the role of mix design relative to screed controls on the paver is also discussed .
mixture behavior during manufacture, paving, and This handbook reviews the construction techniques
compaction. The importance of quality control on the used to build transverse and longitudinal joints. It also
part of the contractor and quality assurance on the part looks at the compaction process: the importance of
of the governmental agency is considered, together with compaction, the equipment used to compact the mix,
the differences between method-type specifications and and the rolling techniques used to achieve the required
end-result-type specifications. degree of density in the mix. The final section of the
Part Two discusses the process of producing mix in handbook reviews some of the more common problems
an asphalt plant. The aggregate stockpiling techniques that may exist during and after the placement operation:
are discussed , along with the operation of the cold -feed surface waves, checking, shoving, tearing, nonuniform
bins. Handling of the asphalt cement and delivery of this surface texture, screed marks, and auger shadows.
material to the mixer is outlined . The handbook covers The format used in this handbook includes develop-
both drum and batch plants used for blending and ing an understanding of the processes being described
mixing of the asphalt cement and aggregate . and differentiating between proper and improper
The operation of a drum mix plant is analyzed , with construction methods. Recognition of a problem or
emphasis on the heat-transfer process that occurs inside potential problem, a description of the possible cause of
the drum and the methods used to blend the asphalt the problem, and a discussion of probable solutions are
cement with the aggregate, both inside and outside the important sections of the handbook. The handbook is
drum . The delivery of the mix from the drum to the written for those individuals actively involved in the
surge or storage silo is discussed, together with proce- construction of asphalt pavements.
dures to deposit mix in the silo and discharge the
material into the haul truck. The three different types of TERMINOLOGY
emission-control equipment used on plants are exam- Hot-Mix Asphalt
ined . The term hot-mix asphalt (HMA) is used generically
Components of batch plants are identified and to include many different types of mix that are produced
discussed. Emphasis is placed on operation of the screen at an elevated temperature in an asphalt plant . The
deck, hot bins, aggregate weigh hopper, asphalt cement category of HMA is divided into three different types of
weigh bucket, and pugmill . mixes, depending primarily on the gradation of the

Page 1-1
AC 150/5370-14
Appendix 1 10/15/91

HOT MIX ASPHALT


(HMA)

Dense Graded Open Graded Gap Graded

Asphalt Concrete Asphalt-Treated


Permeable Material

Large Stone

Sand Mix

Figure 1-1 . Types of HMA mixes.

aggregate used in the mix (Figure 1-1) . The three mix some changes in the mix production, placement, and
types are: (a) dense-graded, (b) open-graded, and (c) compaction operations may be needed for each mix type
gap-graded. Within the dense-graded category are three to produce a durable HMA mixture.
different types of HMA mixes: dense- or continuously
graded, large-stone mix, and sand mix. The open-graded Large-Stone Mixes
classification includes open-graded mixes and open- By definition, a large-stone HMA mix is one that
graded asphalt-treated permeable materials. contains some coarse aggregate that has a nominal size
greater than 1 in. In essence, this mix is still a dense-
Dense-Graded Asphalt Concrete graded material but has a greater percentage of larger
Dense-graded asphalt concrete consists of a uniform size coarse aggregate in the mix. The mix design cannot
or continuous aggregate grading with an asphalt cement be done using the standard 4-in. Marshall or Hveem
binder. It is also called asphaltic concrete or bituminous design molds. For the Marshall mix design method,
concrete . molds having a diameter of at least 6 in. should be used
The information provided in this handbook empha- to prepare the mixture samples. In addition, the amount
sizes the production, placement, and compaction of of compactive effort applied to the laboratory specimens
conventional asphalt concrete mixtures. All asphalt must be increased proportionately to achieve the proper
concrete mixes are, by definition , hot-mix asphalts. All air-void content in the specimens. The measured stability
HMAs, however, are not asphalt concrete (Figure 1-1) . and flow values for the 6-in. specimens will also be
The vast majority of the processes and procedures greater than for the standard 4 -in . specimens.
discussed in this handbook are applicable to the other For plant production of large-stone mixes, some
types of HMA mixes. Because of differences in the additional equipment wear may occur in the batch plant
gradation of aggregates used in mixes and the type and dryer and the drum mixer because of the use of the
amount of asphalt cement blended with the aggregate, larger aggregate . Further, additional wear may be experi-

Page 1-2
AC 150/5370-14
10/15/91
Appendix 1

enced on the slat conveyor and the augers of the paver. (lose some of the asphalt cement film thickness around
Because of the large-size aggregate, the compactive the aggregate particles) while stored temporarily in a
effort applied to the mix must be monitored to prevent surge silo and during delivery to the paver by a haul
excessive fracture of the larger aggregate pieces during vehicle. The placement of an open-graded mix is usually
the compaction process. Vibratory rollers, pneumatic-tire conventional. The compactive effort needed with this
rollers, and static steel-wheel rollers can all be used . If type of mix is generally less than that needed for dense-
a vibratory roller is used , however, the applied force graded mixtures. Because the open-graded mix is
(amplitude) should be at the lowest level that achieves normally placed as a relatively thin surface course layer,
compaction without extending the number of passes and two or three passes over the mix with a static steel -wheel
the frequency of the vibration should be at the manufac- roller is all that is usually necessary to properly set this
turer's maximum rating for the amplitude selected . high air-void-content material. When used as a very thin
friction course, a single pass may be sufficient .
Sand Mix
Sand mix is an asphalt mix that is made without Open-Graded Asphalt-Treated Permeable Material
coarse aggregate . Typically, 100 percent of the aggregate An open-graded asphalt-treated permeable material
passes the 3/8-in. (9.5-mm) sieve and the majority of the is designed primarily to allow for the passage of a large
particles also pass the No. 4 (4.75-mm) sieve . The quantity of water through the mix as quickly as possible .
asphalt cement content of this HMA mix is higher than The purpose of this layer is to provide a drainage course
dense-graded mixes because of the large amount of within the pavement structure . The mix design consists
surface area of the fine aggregate. Unless manufactured of coarse aggregate particles with 0-4 percent passing
sand or an angular natural sand is used in the mix, the the No. 200 (75 µm) sieve. In addition, the size of the
stability of this type of mix is typically very low. coarse aggregate is usually about 1 in ., although mixtures
Sand mix can be produced in a batch plant or drum with maximum size between 2 and 2-1/2 in. have been
mix plant without any significant changes in the plant used . The asphalt cement content of the mix is very low,
operation. Transport and placement of the mix is also typically between 1.5 and 2 percent, because of the lack
standard. Under the compaction equipment, however, of surface area of the coarse aggregate.
sand mix may tend to shove and check under steel-wheel The production of the open-graded asphalt-treated
rollers, especially when constructed in relatively thick permeable material in a batch or drum plant is similar
layers (greater than 2 in .) . Vibratory rollers operated in to that of a dense-graded HMA material, except for the
low amplitude and pneumatic-tire rollers with low tire possibility of a drain-down of the binder if the mix is
contact pressure and high contact area are usually used produced at too high a temperature or if the mix is held
to compact a sand mix course . for a long period of time (more than an hour) in a surge
silo. Drainage of the asphalt-cement film from the
Open-Graded Mixes aggregate particles can also occur in the haul vehicle
An open-graded asphalt mixture is one that consists during transport to the paving site. Placement of the mix
primarily of coarse aggregate, a minimal amount of fine is in the normal manner through the paver. The mix,
aggregate, and asphalt cement binder. The main purpose when placed in thick (greater than 6 in .) lifts, can be
of this mixture is to provide a very open surface texture ; relatively unstable under compaction equipment . State
one that will allow water to drain into the mix and that DOTS ensure stability by requiring use of crushed
provides a significant amount of large aggregate (macro- aggregate, use of a stiff grade of asphalt cement, and
texture) for contact with a vehicle traveling over the control of temperatures before rolling. Typically only
pavement surface. two or three passes of a steel-wheel roller or a combina-
The mix design procedure for the open-graded mix tion of steel-wheel and pneumatic-tire rollers are
is different from that for a dense-graded HMA material necessary to properly compact the mix. In general, a
because of the lack of fines in the mix. Although film vibratory roller should not be used on an open-graded
thickness is greater for the same maximum size aggre- asphalt-treated permeable material.
gate size, the asphalt content is typically less . The
production of the open-graded mix in the plant is similar Gap-Graded Asphalt Mixes
to a dense-graded mix with one major exception. Open- A gap-graded asphalt mix is essentially the same as
graded mixes that contain excess asphalt cement or that an open-graded mix; however, the amount of fine
are heated to very high temperatures will tend to drain aggregate incorporated into the mix is usually greater

Page 1-3
AC 150/5370-14
Appendix 1
10/15/91

than the amount of fine aggregate used in the open- cesses, and procedures to be used to construct the
graded mix. The aggregate gradation in the middle-size asphalt pavement properly. On some jobs, however,
aggregate [that between the No. 4 (4.75 - mm) and the problems come from a lack of attention to the specifica-
No. 30 (600 -μm) or No. 40 (425-µm) sieves ] is missing tion requirements. For reasons of expediency (in order
or present only in small amounts. The production, to get the job done before the completion date, for
placement, and compaction of a gap-graded HMA mix example) shortcuts are taken that can reduce the quality
is similar to the processes used for an open-graded mix. of the mix being placed .
Draining of the binder from the aggregate during Marginal practices also have the potential to reduce
temporary storage and transport is normally not a major the service life of HMA. Many examples exist . Some-
problem because of the amount of fine aggregate used times weather forecasts for rain are ignored when a
in the mix. project is behind schedule or there is a rush to get the
job completed . When the rain comes and some truck-
WORKMANSHIP loads of mix are on the way from the plant to the paver,
Three major factors directly affect the ultimate the tendency is to shut the plant down but to lay the mix
performance of an HMA pavement: (a) the structural that is en route . Another example is when a roller
design of the pavement layers, (b) the mix design, and breaks down at the paving site but the compaction
(c) the workmanship or construction procedures used to process continues without a change in the production
produce, place, and compact the mix. The ultimate rate at the plant or a slowdown in the speed of the
durability of an asphalt mixture and pavement structure paver. In order to keep up, the remaining rollers merely
is directly dependent on the quality of the workmanship speed up to keep from falling too far behind the lay-
used to construct the project. The best set of specifica- down machine. Only after it is determined that the
tions, if not followed, will not assure a good, long-lasting broken roller may be out of service for several hours
pavement. The best mix design, if not duplicated in the and no replacement roller is available is it typically
plant, will not provide the desired life of the pavement decided to alter the production and placement process
under traffic . The most modern and sophisticated equip- to accommodate the reduced number of rollers. Prob-
ment, if operated improperly, will not produce a mixture lems such as these are encountered regularly at a
that withstands the effects of the environment and construction site . The manner in which they are resolved
applied loads, nor will it provide the desired ride quality. directly relates to the quality of the pavement being
Poor workmanship can be one of the more significant constructed.
factors responsible for premature distress of an asphalt This handbook does not directly address workman-
pavement. Most asphalt pavements do not fail uniformly ship but it is inherent in all of the discussions that
from one end of a job to the other end . Within the follow. Performing a task properly assures that the
length of a project, failure normally starts at one or asphalt concrete mix produced , placed , and compacted
more isolated locations and either remains localized or has a better chance of performing well under traffic.
spreads over a wider area. Ignorance of the correct procedures, or disregard for the
Many times, poor workmanship evolves from an specifications, typically will reduce the ultimate life of
ignorance of (a) the specifications, (b) proper construc- the HMA. Good specifications, mix design, and materi-
tion techniques, or (c) proper operation of equipment. als cannot overcome poor workmanship . The ultimate
On some projects, untrained or poorly trained personnel goal is to use both good specifications and good work-
produce, place, and compact mix without a complete manship to build a durable HMA pavement.
understanding of what is required : the materials, pro-

Page 1-4
AC 150/5370-14
10/15/91
Appendix 1

SECTION TWO
PROJECT ORGANIZATION

INTRODUCTION Materials (ASTM) are often listed in the specifications


The most essential part of project planning and and become part of the contract documents just as if the
organization is communication . The project documents whole text were written into those specifications . Addi-
are written instructions that describe in detail the tional documents, such as the Manual on Uniform Traffic
requirements. The preconstruction conference initiates Control Devices (MUTCD) and the Occupational Safety
verbal communication between the representatives ofthe and Health Administration (OSHA) regulations are also
agency and the contractor personnel. It sets the tone for treated in the same manner when referenced in the
both the working relationship and direct communications specifications.
during the execution of the project. Many of the material specifications and test methods
It is difficult, if not impossible, to produce high- that are written by AASHTO or ASTM for national use
quality work if open lines of communication do not exist are modified for use under local conditions . Governmen-
between the contractor's people and the agency's tal agencies often publish their own material specifica-
personnel. Likewise, safety on the job cannot be main- tions and test methods. These publications typically are
tained if communication between all parties is inade- referenced in the contract documents and become part
quate . of those documents. Inspection manuals or guidelines
are normally for use by the agency's representatives and
PROJECT DOCUMENTS usually are not part of the contract documents.
Project documents illustrate and describe work to be If there is a discrepancy between the instructions and
done under the contract . Specific definitions of these specifications in any of the contract documents, a
and other terms that apply directly to a project are definite hierarchy exists among the four major forms of
normally included in the first section of the governing documents. The order of priority, from the highest to
standard specifications . the lowest, for the contract documents is usually defined
• Plans: The drawings that show the location, as the special provisions, the plans, the special or supple-
character, dimensions, and details of the work to be mental specifications, and, finally, the standard specifica-
done. tions. The order of priority corresponds to the docu-
• Standard Specifications: The directions, provi- ment's specific applicability to a particular project or
sions, and requirements for performing the work illus- contract.
trated and described in the plans. The items in the The plans and specifications need to be accurate and
standard specifications relate to or illustrate the method complete, and they should leave little room for assump-
and manner of performing the work or describe the tions or for later reinterpretation. In addition, the plans
qualities and quantities of materials and labor to be and specifications need to define the responsibilities of
furnished under the contract. the representatives of the agency as well as the contrac-
• Special or Supplemental Specifications: Approved tor personnel . If method specifications are to be used,
additions and/or revisions to the standard specifications. the type and frequency of the inspection and testing
• Special Provisions: Additions or revisions to the procedures must be given explicitly. If quality assurance-
standard or supplemental specifications that are applica- quality control specifications are to be used , the require-
ble only to an individual project . ments for the contractor to monitor its own work and
A number ofother documents are often incorporated for the agency personnel to do the necessary acceptance
by reference into the standard specifications, supplemen- testing must be provided in detail. Accurate and com-
tal specifications, and special provisions. Material specifi- plete contract documents save many hours of later
cations and test procedures from the American Associa- discussion between the agency's representatives and the
tion of State Highway and Transportation Officials contractor. 1
(AASHTO) and the American Society for Testing and

Page 1-5
AC 150/5370-14
Appendix 1 10/15/91

PRECONSTRUCTION CONFERENCE ered, as well as procedures for retesting inadequate


A preconstruction conference is often held before materials. The details of the quality control program,
work commences on a project. During this meeting, the both on the part of the contractor and the agency,
overall tone is set for the job, preferably one of coopera- should be discussed so that everyone is aware of "who,
tion. It is generally the responsibility of the agency's what, why, when, and how."
representatives to outline the scope of the project and to One of the most important items to be discussed at
discuss the information provided in the contract docu- the preconstruction conference is job safety. Safety is
ments. In addition , it is also the responsibility of the not only a legal and financial responsibility of all the
agency personnel to discuss any unusual aspects of the people on the project but a moral responsibility as well.
job--items that are not routine construction practices. A This topic should include not only the safety of those
list of personnel who will be assigned to the project individuals working on the job (both contractor and
should be provided to the contractor . agency personnel) but also the safety of the traveling
The individuals representing the contractor should be public. Clear responsibility for maintenance of all traffic
familiar with the job and be able to speak with authority control devices such as signs, pavement markings, and
about what is to be accomplished . A progress schedule flagging should be delineated . The name of the person
for the job should be presented and discussed with the responsible for safety for the contractor should be
agency's personnel. Any questions about the information provided to the agency so that rapid and clear communi-
in the contract documents should be raised and clarifica- cations can be accomplished if safety problems occur.
tion requested, if necessary. A listing of key contractor All personnel involved in the project must be required
personnel who will be assigned to the project should be to comply with all safety standards applicable to the type
provided, with clear lines of authority established . of construction and asphalt paving work to be carried
The people in attendance at the preconstruction out.
conference should not assume that all of the other
individuals present understand fully and are in complete ONGOING COMMUNICATION
agreement with the proposed progress schedule. Agree- Communication cannot stop once the preconstruction
ment is needed on the methods to be employed to conference is concluded . The quality of the work com-
complete the project on schedule, with a minimum of pleted and the safety of those performing and inspecting
delays and change orders. Because continuity of the the construction are directly related to the quality of the
asphalt-paving operations is critical to providing a communication between the agency and the contractor.
quality pavement , the discussion between the agency and It is important that the individuals in daily charge of the
the contractor personnel should include such items as project for both the agency and the contractor meet
material sources, plant production rates, haul distances periodically, both on a formal and on an informal basis,
and routes, paving widths and speed, and the type and to discuss the progress and quality of the work done to
operation of the compaction equipment. If known, a list date and the schedule for future work.
of equipment that is to be used on the project should be
supplied by the contractor to the agency. Formal Meetings
The role of each person on the project, for both the The frequency of the formal meetings depends on
agency and the contractor, should be discussed and the scope and the size of the paving job. On a major
made clear. This requires that the supervisory personnel project, the "update" meetings should occur at least
define the tasks, authority, and responsibility of each of twice a week. Key personnel from both the agency and
the key individuals to be involved in the work. the contractor should be present . The discussion should
Sampling methods and frequencies should be dis- include such items as the quantity of work completed,
cussed . Test methods to be used should be reviewed to the test results obtained, and any problems that have
assure that all individuals understand the purpose of occurred. The meeting should also focus on what is yet
each test, the location and the personnel who are to to be accomplished : the schedule for the coming weeks .
conduct the test, the time frame for the return and Changes to be made in the progression of the work,
communication of the test results, and the procedures to including personnel changes, different equipment use
be used if failing test results are obtained . If not ade- and construction methods, and mix design information,
quately covered in the specifications, the use of dupli- should all be discussed . Problems that have occurred and
cate or split samples (one for testing by the contractor that are anticipated should be communicated to both
and one for testing by the agency) needs to be consid- parties and solutions explored .

Page 1-6
AC 150/5370-14
10/15/91
Appendix 1

If formal meetings are needed, they should be held PROJECT RECORDS


on a regularly scheduled basis, such as every Monday It is important that accurate and complete records be
morning at 8:00 a.m. at the project office. Everyone who kept for all construction projects. This is true for both
is supposed to attend the meeting should be there and the project engineer and staff and for the contractor's
be on time. The meeting should be conducted jointly by general superintendent, plant and paving superinten-
the agency and the contractor and should be used as a dents, and all foremen . Trying to reconstruct events at
forum for positive input to the job. A list of all individu- a later time without written notes and complete test data
als in attendance should be prepared , along with written is usually frustrating and often results in conflicting
minutes of the meeting. These minutes should be com- opinions as to exactly what happened . One procedure
pleted and distributed to all involved people as quickly should constantly be followed : if in doubt about whether
as possible. the information is important or beneficial, write it down.

Informal Meetings Plant Reports


Informal meetings should be held on a daily basis The results of all daily and periodic tests conducted
between the two individuals in charge of the job for the at the asphalt plant should be recorded . Although
agency and the contractor. Ideally, these meetings different forms may be used, both the project inspection
should occur at a regularly scheduled time, but can be personnel and the contractor employees should collect
held on the job site; at the asphalt plant or at the paver. essentially the same type of information . Further, the
The purpose of the informal meetings is twofold . First, contractor personnel should complete their own records,
the discussion should include what occurred the day even if not required to do so by the agency.
before, such as work completed, test results, and prob- Some of the data that should be shown on the form
lem areas. The topics should include what is going to include: (a) project number and location information,
happen in the next several days; an update on the (b) weather conditions, (c) source of materials used on
information exchanged at the last formal meeting. the project, (d) job-mix formula information, (e) aggre-
Asphalt paving projects, like many construction gate gradation and asphalt content test data, (f) mix test
projects, are not always built as originally scheduled . results, (g) the amount of each material (aggregate,
Changes occur because of material supply, equipment asphalt cement, and additives) used , (h) the number of
breakdown, contractor and subcontractor schedules, and tons of asphalt mix produced, and (i) location on pave-
weather conditions . When such changes do occur, it is ment where daily production was placed . Any additional
important that they be communicated between the information required by agency specifications, such as
contractor and the agency and between the agency and the moisture content of the individual aggregate stock-
the contractor . Communication is a two-way process . piles, should also be reported on the form.
The informal meetings on a daily basis provide a forum It is important to record the date, time, and location
for the exchange of such information . of all samples taken, and the name of the individual
taking the samples . If, for example, aggregate gradation
Communication Form is determined from samples taken at two different places
Communications should be oral and written. Much (from the cold-feed belt and from the extracted mix) ,
information can be communicated in oral form . Impor- the sampling location must be marked on the report.
tant information should be followed up in written form . Similarly, if asphalt content is normally determined by
In some cases, formal letters should be written by the nuclear gauge and occasionally checked by extraction,
contractor and by the agency when conditions on the the procedure used to measure the mix property should
project change substantially. Often a less formal note be recorded .
can be written to confirm the data that had already been Most forms should have a "Remarks" area. This
communicated orally. In addition , personnel for both the portion of the form should be used to indicate any
agency and the contractor should keep daily diaries of unusual occurrences or test results that took place
events that occur. If something happens that is impor- during the day. Failing test results should be highlighted
tant enough to remember later on, it is important on the form . Additional comments about the possible
enough to take the time to write it down immediately cause of the deficiency should be written under " Re-
after it happens so that the information is accurate and marks." Any corrective action or changes to the mix
complete. materials, plant-operating parameters, or test procedures
should be indicated . The results of those actions or

Page 1-7
AC 150/5370-14
Appendix 1
10/15/91

changes should also be indicated on the form. It should also be used to record the reasons for delays
in paving (e.g., because of an equipment breakdown or
Pavement Reports poor weather conditions) . The purpose of the daily
Information on what occurred on the pavement diary, then, is to save for possible later reference the
during the mix placement and compaction operations nonroutine events that happened during each paving
also must be recorded . Again, the data gathered may be day.
reported in a different style by the paving inspector and For the information in a diary to be accurate and
by the contractor's superintendent, but essentially the meaningful, the data must be recorded in the book
same information should be reported by both . This will shortly after the events occur . Ideally, the diary should
allow for more meaningful discussion later if deficiencies be updated at least twice a day: once near midday and
develop in the test results or in the performance of the again at the end of the day. If job conditions and
mix under traffic. schedules preclude making the midday entry, the events
Some of the data that should be shown on the of the day should always be written down upon comple-
paving-site form include: (a) project number and loca- tion of each day's activities . It is not practical to try to
tion, (b) weather conditions, (c) the type and number of recall and record what happened on Monday when it is
tons of each mix placed and the exact location of that the following Wednesday evening or the end of the
mix--layer number, thickness, lane, and station number, week.
(d) the type and make of equipment used by the con- The information contained in the diary must be
tractor, (e) the density results obtained, and (f) the detailed and complete. It should contain as much
smoothness results obtained . In addition, other data detailed information as possible . If a conversation is held
should be reported, such as the type, amount, and with other project personnel concerning project activity,
location of any tack coat material placed ; the location regardless of whether they are agency inspection person-
(both transversely and longitudinally--station number) of nel or contractor employees, the date and location of
any tests taken; and a running total of the tons of each the conversation should be recorded . The names and
mix laid on the project. titles of any people involved in the discussion should be
All samples taken must be marked properly to written down, as well as the topics reviewed. The
indicate the location from which the material was gath- outcome of each conversation, if it affects the progress
ered, the time and date of the sampling, the reason that or the results obtained from the mix manufacturing and
the sample was taken, what quantity of material the placement operations, must be stated . Who told whom
sample represents, and the name of the person who took to do what, and what was the reply? That is the type of
the sample. If a nuclear gauge is employed to determine information that should be included in the daily diary.
the relative density of the mix, any calibration proce- The importance of the information contained in each
dures used to check the reliability of the gauge should daily diary cannot be overemphasized . Many claims and
be referenced . lawsuits have been settled on the basis of information
The " Remarks " area on the pavement report form written in a diary. If one person involved in a dispute
should be used to report any unusual conditions or test can present information written in timely fashion in a
results that occur during the day. Failing test results diary and the other individual can only rely on memory
should be highlighted on the form and an explanation to reconstruct the important events, the writer usually
provided, if possible, as to both the cause of the defi- will have an advantage in the settlement of the disagree-
ciency and the steps taken to correct the problem . The ment. The information may also be useful for follow-up
result of the corrective action should also be given. research, determining reasons for premature failures,
etc.
Daily Diary
All project supervisors, both agency personnel and SAFETY
contractor employees, should keep a detailed daily diary. The old saying " Safety is Everyone's Business" is
This document should be used to record any changes certainly true on an HMA paving project . From the
that are made in the mode of operation of the asphalt contractor's superintendent, to the front-end loader
plant or the laydown and compaction equipment. It operator at the asphalt plant, to the truck driver, to the
should be the place to report any different or unusual raker behind the paver, every individual who works for
events that occur on the job. It can be used to document the contractor must be aware continuously of the need
other events, such as a listing of visitors to the project. to practice safe work habits. Likewise, every person who

Page 1-8
AC 150/5370-14
10/15/91
Appendix 1

works as a representative of the agency, from the project Another class of individuals who often suffer need-
engineer, to the inspector at the plant, to the ticket less injuries are people who have been around the plant
taker at the paver, must be aware of safe work habits. and the paving operations for many years and who are
Communication is one of the keys to a safe work "comfortable" being around the equipment. Sometimes
environment. Every individual should know what is these people perform their duties by rote . They typically
expected and know how to perform the assigned tasks. take short cuts because they have survived without injury
Proper training in the operation of a piece of machinery for many years. Safety should be as much a part of these
is essential for equipment operators, for example. Re- individuals' day as it is for the new people on the job.
training is necessary at frequent intervals because the Working around an asphalt plant is a potentially
longer a person continues to perform the same task, day hazardous occupation . Functioning equipment parts,
after day, the more likely he or she is to do things by high temperatures, noise, and moving delivery and haul
"remote control" and ignore surrounding events. Every- trucks all add to the possibility of an accident occurring.
one, regardless of title or job function, must be aware It is possible, if an individual is not trained to perform
continuously of the need for safe work practices. Occu- a particular function, for him or her to get burned by
pational Safety and Health Administration regulations hot asphalt mix, to be sprayed with hot asphalt cement,
must be known, understood, and followed by each to have a hand caught in a piece of machinery, or to be
person involved in the construction project . struck by a moving vehicle .
Safety talks are a good way to start the day for both Working around an asphalt paving site is also a
contractor and agency personnel. Several different potentially hazardous occupation. Individuals who are
organizations publish short, concise safety presentations working on the pavement around the paver (e.g., the
that can be completed in 2 or 3 min. People need to be ticket taker, truck dump person, the screed operator,
reminded that they are operating in a potentially danger- and the rakers) are susceptible to being hit by passing
ous environment, both at the plant and the laydown site. traffic. Further, these same people have the potential to
Daily talks are one way of accomplishing the task of be hurt by equipment being used in the paving opera-
continuously reminding them . Further, if an unsafe work tion. People can be injured by the haul trucks backing
practice is noticed, corrective action should be taken into or pulling away from the paver, as well as by
immediately, even if the paving operation has to be shut compaction equipment. In addition, all of the paving
down until the unsafe practice is changed . personnel have the possibility of being burned by the hot
The people most likely to be hurt on an asphalt asphalt mix.
paving project are those individuals who are new to this Constant care and vigilance is needed to prevent
type of work. Without adequate advance training, these accidents and injury. The Occupational Safety and
people do not fully understand all the differences Health Administration, the National Asphalt Pavement
between following safe work practices and taking foolish Association, state DOTS, and others have published
chances. Often new employees, working either for the manuals that deal with safety at the asphalt production
agency or for the contractor, want to show that they are plant and around a paving operation . These manuals
capable and can perform the tasks assigned to them. At should be made available to all plant and paving person-
times their enthusiasm to excel and to please other nel, both for the agency and for the contractor, and
people can overcome their awareness of proper safety should be required reading. Safety is everyone's business
practices. on a construction project.

Page 1-9
AC 150/5370-14
Appendix 1 10/15/91

SECTION THREE
MIX DESIGN AND THE JOB MIX FORMULA

INTRODUCTION asphalt mix for the project.


Hot-mix asphalt has two primary ingredients : binder This section discusses briefly the properties of the
and aggregate. The asphalt binder is usually asphalt asphalt cement and the aggregates used to produce an
cement, which is obtained from the refining of crude oil. asphalt mix. It also will review some of the differences
Asphalt cements are graded either by penetration or by that can exist between laboratory- and plant-produced
viscosity. The aggregate used typically is a combination mixes and differences between the job mix formula
of coarse and fine materials, with mineral filler as values and the plant test results .
needed . The aggregates are often available locally, either
from a pit or from a quarry. The mix design system MATERIAL PROPERTIES
determines the correct proportion of asphalt cement and Properties of the Asphalt Cement
aggregate needed to produce an asphalt mix that has the Asphalt Cement Grade
properties and the characteristics to withstand the effects The penetration of an asphalt cement is determined
of traffic and the environment for many years. at a temperature of 77°F. In general, the harder the
Mix design is performed in the laboratory generally asphalt cement (the lower its penetration) the stiffer the
using one of two methods. The more common mix mix made with the material. At a given temperature a
design method is the Marshall method . This procedure mix containing 60-70 penetration -grade asphalt cement
is followed by approximately 75 percent of the state typically will be stiffer and will require somewhat more
highway departments as well as the U.S. Department of compactive effort by the rollers to achieve the desired
Defense and the Federal Aviation Administration . The density than will a mix made using a 120-150 penetra-
second procedure is the Hveem method . This method is tion-grade asphalt cement . Thus the stiffer mix must
used by many public agencies in the western United either be placed at a higher temperature or a greater
States. compactive effort must be applied by the rollers to
Another mix design procedure is the asphalt- aggre- achieve a given degree of density.
gate mixture analysis system (AAMAS) recently pub- The viscosity of an asphalt cement is typically deter-
lished by the National Cooperative Highway Research mined at two different temperatures: 140°F and 275°F.
Program. In this method , the traditional empirical means A viscosity-graded material must fall within a range of
of determining HMA mixture strength (or stability) have values at the lower temperature and meet a minimum
been replaced by more rational test procedures. Mix viscosity requirement at the higher temperature . In
properties such as resilient modulus, indirect tensile general, a mix containing an AC-20 asphalt cement will
strength and strain at failure, and creep modulus values be stiffer, at a given temperature, than will an AC- 10
are determined to estimate the performance of the asphalt cement and require slightly more compactive
asphalt mix in the pavement under traffic. Test results effort to reach a certain level of density.
are used to home in on an optimal mix design that will For a particular asphalt cement prepared from a
produce pavements resistant to distresses such as fatigue given source of crude oil by a given refining method,
and thermal cracking, rutting, stripping, and age harden- there is a relationship between the penetration of the
ing. material and its viscosity. This relationship does not
On an asphalt paving project, the mix design can be hold , however, for different asphalt cements made from
developed by one of three different entities: by the different crude oils or by different refining processes.
governmental agency, by the contractor, or by a consul- Thus, an 85-100 grade asphalt cement might possibly
tant; depending on the requirements of the project meet the viscosity specifications for either an AC- 10 or
specifications. Regardless of who completes the labora- an AC-20 grade material. The same is true for a viscosi-
tory mix design phase of the job, the result of the mix ty-graded asphalt cement; an AC-20 material might have
design process is a job mix formula (JMF) . The JMF is a penetration as low as 40 or as high as 110, for exam-
to be followed by the contractor in manufacturing the ple.

Page 1-10
AC 150/5370-14
10/15/91
Appendix 1

Different asphalt cements ofthe same penetration or selected mixing temperature and compaction tempera-
viscosity grade may harden (decrease in penetration and ture for the mix are determined by the viscosity of the
increase in viscosity) to different degrees during the asphalt cement. The mixing temperature is selected as
mixing process in a drum or batch plant . A mix manu- the temperature at which the asphalt has a viscosity of
factured with an asphalt cement that does not harden 170 ±20 centistokes, and the compaction temperature is
much during the mixing process might be more tender chosen as the temperature at which the asphalt cement
under the compaction equipment, at a given tempera- has a viscosity of 280 ± 30 centistokes. The temperature
ture, than will a similar mix made with an asphalt at which each of these two viscosity values occurs is
cement that hardens to a greater degree in the batch determined by plotting the viscosities measured at both
plant pugmill or inside the drum mixer. 140°F and 275°F and interpolating the appropriate
temperature from the graph.
Temperature-Viscosity Characteristics Using the viscosity of the asphalt cement to deter-
The degree of change in viscosity of an asphalt mine the laboratory mixing and compaction tempera-
cement with a change in temperature is a very important tures provides binder materials that are of equal stiffness
characteristic. The temperature susceptibility of the even though those materials may have different degrees
asphalt cement is defined as the change in the flow of temperature susceptibility. This permits the mixing
properties of the material with a change in temperature. procedures in the laboratory to be standardized and a
An asphalt mix made with an asphalt cement that is particular level of air voids to be obtained in the mix
highly temperature susceptible typically will be more with a given compactive effort of the Marshall hammer.
tender and tend to move more under the breakdown For the Hveem laboratory mix design method, the
rollers than will a mix made with an asphalt cement of mixing temperature for the asphalt cement is determined
low temperature susceptibility. An asphalt cement that by the grade of the material. A range of temperatures,
has a flatter slope on a viscosity-temperature chart than for both the asphalt cement and the aggregate, is given,
another asphalt cement is less temperature susceptible. depending on the penetration or the viscosity grade of
Two asphalt cements of the same penetration grade thus the binder material. For compaction of the Hveem
can have considerably different characteristics at elevat- specimens, a standard temperature of 230°F is used,
ed temperatures. Although similar in consistency at regardless of the grade of the asphalt cement used .
77°F , two 85-100 penetration asphalt cements may have
different flow properties at 275°F. Similarly, two asphalt Plant-Produced Mix
cements that have the same viscosity at 140°F can also The grade of asphalt cement used will influence, to
have significantly different viscosities at 275°F. some degree, the mixing temperature selected . In
Thus, during the mixing and compaction process, two general, the lower the penetration or the higher the
binder materials of either the same penetration grade or viscosity of the binder material, the higher the tempera-
the same viscosity grade can contribute to different ture to which the asphalt cement should be heated in
stiffness characteristics in the mix and may influence the order to pump the material properly (normally about
degree of tenderness of the mix and the compactive 300°F) . The temperature susceptibility of the asphalt
effort needed to obtain a predetermined level of density. cement is not a factor in the production of the mix.
The asphalt cement that is more temperature suscep- The temperature susceptibility of the asphalt cement
tible--has the steeper slope (higher ratio of change in may, however, be a factor during the compaction
viscosity for a change in temperature)--will have a process. In general, a mix containing a highly tempera-
greater effect on the properties of the mix. The true ture-susceptible asphalt cement will stiffen more quickly
effect of the asphalt cement properties on the cohesive- with a change in temperature than will a mix made with
ness of the mix, however, depends on and is interrelated an asphalt cement of lower temperature susceptibility.
with many other properties of the mix, including the This means that the compactive effort applied to the mix
characteristics of the aggregate, the concentration of by the rollers might need to be altered to achieve the
coarse aggregate, and the amount of laboratory compac- same degree of density. In addition , the mix containing
tion used to determine the asphalt cement content and the more temperature - susceptible asphalt cement might
the field compaction requirement. initially be somewhat more tender and tend to check and
shove more under the rollers. The degree of tenderness,
Laboratory Mix Design however, is also greatly affected by other mix character-
For the Marshall laboratory mix design process, the istics besides the properties of the binder material.

Page 1-11
AC 150/5370-14
Appendix 1 10/15/91

A change in the source of asphalt cement used on a particle, the greater will be its tendency to be tender
project, even though it is from the same supplier, can under the compactive effort of the rollers. A mix con-
affect the properties of the mix, particularly during the taining an aggregate that has a rough surface texture,
compaction process . It is possible that a mix that can be similar to the particle with an angular shape, will
densified properly with one amount of compactive effort generally require more compactive effort to densify to a
from the rollers might become more tender (or more given air void content.
stiff), requiring a different degree of compactive effort,
if the properties of the asphalt cement changed because Maximum Particle Size
of a change in the asphalt cement source . Aggregate having different maximum particle sizes
Project personnel are not normally notified by the can have different degrees of workability. Typically the
supplier when a change in the source of the asphalt larger the maximum size of aggregate in a mix in
cement is made . If the specifications call for the use of relation to the layer thickness and the greater the
an AC-20 viscosity- graded asphalt cement, an AC- 20 will amount of large aggregate in the mix, the more difficult
be delivered . The properties of one AC-20, however, can it is to compact the mix. Further, if the nominal maxi-
be very different from the properties of another AC-20 mum aggregate size exceeds one-half of the compacted
asphalt cement. It is good practice, therefore, for the thickness of the pavement layer, the texture of the mix
contractor to request that the asphalt cement supplier can be affected and the degree of density obtained in
provide a temperature -viscosity graph for each load of the mix by the compaction equipment may be reduced.
material delivered to the plant. These graphs should be Although a relatively minor factor for most mixes in
reviewed as each load of asphalt cement is unloaded . If comparison with the other aggregate properties, the
the temperature-viscosity characteristics of the binder maximum particle size can be a significant factor in the
material have changed significantly, adjustments may properties of the asphalt concrete mix when large-stone
need to be made in the plant-mixing and mix-compac- (greater than 1 -in . nominal maximum size ) mix is being
tion processes . produced. This is particularly true in regard to density,
and a field compaction test strip may be necessary to
Properties of the Aggregates determine the degree of density that can be achieved in
Various properties of the aggregate will have various the large-stone mix.
effects on the properties of the final asphalt mix. The
aggregate properties of interest include shape, surface Absorption
texture, particle size, absorption, gradation, voids, and The amount of asphalt cement that is absorbed by
percent and gradation of material passing the No. 200 the aggregate also may have a major effect on the
(75 μm) sieve . properties of the asphalt mixture . If the aggregate
particles have high asphalt absorption, the asphalt
Shape content in the mix must be increased to compensate for
The shape of the individual aggregate particles the binder material that is drawn into the pores of the
affects the properties of the mix. Aggregate that is aggregate and is unavailable as part of the film thickness
rounded is more easily displaced by an applied load. around those particles. If that asphalt content correction
Aggregate that is angular (usually produced by crushing) is not made, the mix can be dry and stiff. The amount of
will have a greater degree of interlock when a load is compactive effort needed to achieve density in the mix
applied and will be more resistant to displacement by would have to be increased and the mix would have a
that load. Crushed aggregate mixes may require a tendency to ravel under traffic .
greater compactive effort to obtain the required level of
density than mixes containing rounded gravel . In addi- Gradation
tion, the amount of surface area for each aggregate is, The maximum size of an aggregate gradation is the
in part, a function of its shape . An aggregate that has a smallest sieve through which the entire amount ( 100
greater surface area will require a greater amount of percent) of the aggregate is required to pass . The
asphalt cement to obtain a given film thickness around nominal maximum size of an aggregate is the smallest
the aggregate particles. sieve through which the entire amount ( 100 percent) of
the aggregate is permitted to pass. For example, if 100
Surface Texture percent of an aggregate passes the 1 -in . ( 25-mm) sieve
The smoother the surface texture of an aggregate and 90 to 100 percent of the same aggregate may pass

Page 1-12
AC 150/5370-14
10/15/91
Appendix 1

the 3/4-in. ( 19- mm) sieve, the maximum size of that 100 percent passing the 3/4-in . (19- mm) sieve and 99
aggregate would be 1 in. and the nominal maximum size percent passing the 1 /2-in . ( 12.5- mm) sieve would have
would be 3/4 in . the same theoretical maximum density line as a mix that
The gradation of the coarse and fine aggregate has has 100 percent passing the 3/4- in . sieve and only 88
a great effect on the properties of all HMA mixtures. percent passing the 1/2-in. sieve . The properties of two
The potential effects can be evaluated using 0.45 power mixes made with aggregates of these two gradations,
gradation paper . This graph paper, which was developed however, could be considerably different. For this
by the Federal Highway Administration in 1962 for reason, a modification is normally made in the starting
asphalt concrete mixes, is shown in Figure 1-2. Using location for the maximum density line . As shown in
this graph, an estimate of the densest grading of the Figure 1-2 , the modified maximum density line is drawn
combined coarse and fine aggregate, on a percent from the sieve on which some aggregate is first retained .
passing basis, will plot as a straight line, as shown in this In the example shown , if the amount of material passing
figure. As illustrated , if 100 percent of the aggregate in the 3/4-in. sieve was 100 percent and the amount of
a particular asphalt concrete mix passes the 3/4- in . aggregate passing the 1/2- in . sieve was 99 percent, the
(19-mm) sieve, the estimated densest gradation of latter value would serve as one end for the modified
aggregates for that mix would lie on the line that maximum density line . If only 88 percent of the aggre-
extends from that point at the upper-right portion of the gate passed the 1/2- in. sieve , that value would be em-
graph to the zero point at the lower-left corner of the ployed as the starting point for the modified maximum
graph. This line is called the maximum density line. density line.
The maximum density line can be used to estimate Also as originally developed, the aggregate gradation
several properties of the asphalt concrete mix before the that has the maximum density will generally contain a
asphalt cement is added to the aggregate in the actual high amount of material passing the No. 200 (75-μm)
laboratory mix design process. In this regard, it provides sieve when plotted on the 0.45 power paper. In Figure
some guidelines for the voids in mineral aggregate 1-2 this value is approximately 8 percent . This amount is
(VMA) content of the mix. In general, an aggregate higher than the amount of fine aggregate normally
gradation that is close to the maximum density line, permitted to pass the No. 200 sieve ; most mixes contain
particularly below the No. 4 sieve, will have a lower from 2 percent to 7 percent passing that sieve. For this
VMA content than will the gradation of the same reason, use of the graph paper may be further modified
aggregate that is farther away from the maximum density to use the actual amount of aggregate passing the No.
line--either above or below the line . 200 sieve as the other end point for the maximum
Many factors besides gradation have an effect on the density line instead of the zero point on the graph . This
VMA content of the mix. In particular, the shape of the line is called the gradation reference line and is illustrat-
aggregate as well as the surface texture of the aggregate ed in Figure 1-3.
will cause the aggregate to have a different VMA The gradation reference line is drawn on the upper
content even though several different aggregates may right from the sieve on which any aggregate is first
have the same gradation when plotted on 0.45 power retained--has a percent passing that is less than 100
gradation paper. A mix that contains angular aggregate percent. The line is drawn through the percent passing
compared to rounded aggregate will typically have a the No. 200 (75-μm) sieve that is actually in the mix. In
higher VMA content. Further, a mix that contains Figure 1-3, the amount of aggregate passing the No. 200
aggregate with a rough surface texture will usually have sieve is assumed to be 3 percent . Using these two points,
a higher VMA content than will a mix that contains as shown in Figure 1-3, provides the maximum density
smooth textured aggregate, for the same gradation . In line for the actual mix being manufactured.
addition, the properties of the fine aggregate generally In Figure 1-3 two different gradation reference lines
have a greater effect on the VMA content of the mix are shown. The first line is for a mix with 100 percent
than do the properties of the coarse aggregate . Thus the passing the 3/4-in. ( 19 -mm) sieve, 99 percent passing the
0.45 power gradation paper maximum density line 1/2-in. (12.5 -mm) sieve, and 3 percent passing the No.
should be used only as a guide in determining a starting 200 (75-μm) sieve . The second is for a mix with 100
point for the actual laboratory mix design process . percent passing the 3/4-in . ( 19-mm) sieve , 88 percent
Use of the sieve with 100 percent passing as the passing the 1/2- in . ( 12.5 - mm ) sieve, and 3 percent
origin for the maximum density line can lead to the use passing the No. 200 (75 -µm) sieve . Both of these mixes
of an improper line . As shown in Figure 1-2 , a mix with would have the same maximum density line ( as shown in

Page 1-13
Appendix 1
AC 150/5370-14

CHART
GRADATION
REPRESENTS
SCALE
HORIZONTAL
THE
TO
RAISED
SIZES
.SIEVE
POWER
0.45
"S IMPLIFIED
INDICATED
PRACTICE
BYIZES
100 100

90 " 2 90
1/
ng
s"si2
80 / 80
pa 1 g
% in
99 ss
pa
70 x % 70
88

60 ne 60
Li
t y
n si

Page 1-14
50 De
m um "
3/4 "
1 "
1¼ "
1/2
xi SIEVES NO
Ma . .NO L
TOTA TOTAL
40 RETAINED .RET % %
PASSING ON WT
. % PASSINWT
.G % PASSING

PERCENT PASSING
30

20

10

50
No.
100
200 30 16 "
3/8 1/2

O
B

06
40
80
No. 20 10 "
¼4
SIEVE
SIZES
GAS
Figure
1-2
P. ossible
maximum
density
lines
using
FHWA
0.45
gradation
paper
.power
10/15/91
10/15/91

GRADATION
CHART
HORIZONTAL
. IMPLIFIED
POWER
0.45
THE
TO
RAISED
SIZES
SIEVE
REPRESENTS
SCALE
"S
PRACTICE
BY
INDICATED
IZES
100 100

90 90

ne
80 Li 80
", 2 ) 0 ce
r en
1/ 20 e
.g ef
70 sNion R 70
s g on ne

70
70

pa s in ti Li
a
%9 as a,d
" ce
(9 p% Gr /2 ) 00 r en
60 3 1 2 e 60
.g ef
Nion R
s n
s g io
pa s in at

Page 1-15
50 % s ad
8( 8 pa Gr 3/4
" "

% "

3
SIEVES .NO .NO AL
TOT TOTAL
40 % %
WT
.
PASSINGON RETAINED .RET PASSING
WT
. % PASSING
%

PERCENT PASSING
30

20

10

50
100
200
No. 30 16 "
3/8 "
1/2

91
80
No. 40
20 10 "
1/4
SIEVE
SIZES
Appendix 1
AC 150/5370-14

.line
refere
G nce
. radati
1-3
Figure on
AC 150/5370-14
Appendix 1 10/15/91

Figure 1-2). They have different gradation reference level in the laboratory when made and compacted in
lines, however, because of the amount of material steel molds . That same mix, however, may be difficult to
retained on the largest sieve . compact to the required air void content on the pave-
Blends of aggregate that are finely graded are more ment; it normally will be tender and may check and
workable and easier to compact than are blends of shove under the compaction equipment.
material that are coarsely graded . As shown in Figure 1- The 0.45 power graph paper can be used to evaluate
4, when plotted on the 0.45 power gradation paper the the potential for problems with the mix during the
finer blend of aggregate (Gradation A) will fall above placement and compaction operations. During the
the gradation reference line--to the fine side of the line, production of the mix, the results from the extraction
with greater percentages of material passing each test should also be plotted . Gradations that resemble
particular sieve than for a coarsely graded combination Gradations A or B in Figure 1-4 typically should pro-
of aggregate. Coarse graded aggregates (Gradation B) duce durable mixtures that can be placed and rolled
are normally more difficult to compact, but may result without major problems. Gradations that look like
in more rut-resistant pavement layers. Gradations Cor D in Figure 1-5, however, may produce
asphalt concrete mixes that are tender and check or
Voids in Mineral Aggregate shove during the compaction operation.
The voids in mineral aggregate (VMA) of a mix can
be defined as the volume of intergranular void space Percent Passing No. 200 (75-μm) Sieve
between the aggregate particles of a compacted paving The amount of material passing the No. 200 (75 -µm)
mixture that includes the air voids and the effective sieve can have a variable effect on the ability to densify
asphalt content, expressed as a percent of the total a particular blend of coarse and fine aggregate. As the
volume of the sample. This room within the aggregate amount of aggregate passing the No. 200 sieve increases,
gradation is at a minimum for a combination of coarse the workability of the blend of aggregate increases, up
and fine aggregate that has a gradation that is close to to a certain point. Beyond that level, as the amount of
the gradation reference line (Gradation C in Figure 1-5). fine aggregate that passes the No. 200 sieve increases,
A mix with a low VMA content will become very sensi- the stiffness of the mix normally will increase .
tive to total fluids content: asphalt cement content plus Initially, the incorporation of some aggregate passing
any moisture in the mix . During placement and compac- the No. 200 (75-μm) sieve fills the voids in the total
tion, the mix will tend to check and shove . Under traffic, aggregate gradation and makes the blend more continu-
the mix will tend to rut and bleed if the asphalt content ously graded . This tends to decrease the voids in mineral
is high and will tend to ravel if the asphalt content is aggregate content ofthe material combination and make
low. the blend of aggregate more workable . If an excess of
An aggregate gradation that crosses the gradation aggregate passing the No. 200 sieve is present, this
reference line, particularly in the fine aggregate portion additional fine material pushes the other aggregate
of the gradation (Gradation D in Figure 1-5) , will also particles apart, decreasing the contact between the
have a tendency to have low VMA contents. Aggregate coarser aggregate particles and altering the compact-
blends that have a pronounced hump in the grading ability of the aggregate blend . For most asphalt concrete
curve usually will be more tender than are mixes that mixes, the amount of aggregate passing the No. 200
are more continuously graded , either above or below the sieve should typically be in the range of 3 to 6 percent.
gradation reference line. The hump occurs because a
large amount of fine aggregate passes one sieve , such as Gradation Passing the No. 200 (75-µm) Sieve
the No. 30 (600 -μm ) sieve , and is retained on the next Not only does the amount of aggregate passing the
sieve, the No. 50 (300 µm) . The hump also typically No. 200 (75 -μm) sieve have an effect on workability, the
takes place, using a different series of sieves, between gradation of that material can have a dramatic effect on
the No. 40 (425-μm) and the No. 80 ( 180-μm) sieves. the tenderness of the blend of aggregate. Ifthe majority
The effect of the hump on the compactive effort ofthe aggregate that passes the No. 200 sieve is relative-
needed to obtain density depends on the severity of the ly coarse (larger than about 40 µm) , most of this materi-
hump; the more pronounced the hump, the lower the al will fill the voids in the coarse aggregate, decreasing
VMA, and generally the more tender the mix. A mix the void content of the aggregate blend and altering the
with a hump in the fine aggregate portion of the total optimal asphalt content in the mix. If, however, the
grading curve may easily achieve the desired density material passing the No. 200 sieve is ultra-fine (a signifi-

Page 1-16
10/15/91

GRADATION
CHART
S
'THE 00
PRACTICE
IMPLIFIED
POWER
0.45
REPRESENTS
."SIEVE
TO
RAISED
SIZES
HORIZONTAL
SCALE SIZES
BYA
INDICATED
100 100

90 90

80 80

70 70
) e
n
f(i ne
A Li
60 n e 60
io nc

09
t e
a da fer

Page 1-17
Gr Re

)
e
50 n

rs
io 3/4 1 14
" "
12

a
t
da
ra SIEVES .NO .NO AL
TOT TOTAL

B (co
G
40 D % %

on
. RET
. PASSING
. % PASSING
PASSING ON RETAINEWT % WT

a ti

PERCENT PASSING
ad
Gr
30

20

10

50
100
200
No.
30 16 "
3/8 "
1/2

96
No.
80 40 20 10 "
14
SIZES
SIEVE
Appendix 1
AC 150/5370-14

mixes
coarse
.and
Cfine
of
omparison
1-4
Figure
Appendix 1
AC 150/5370-14

GRADATION
CHART
HORIZONTAL
. IMPLIFIED
POWER
0.45
THE
TO
RAISED
SIZES
SIEVE
REPRESENTS
SCALE
"S
PRACTICE
BY
INDICATED
IZES
100 100

90 90

80 80
D
on
a ti
ad 70
Gr

70
60 ne 60
Li
n ce
re

Page 1-18
50 e
ef

C
R "3/4 1 14
" "

n
on

io
i SIEVES NO
. .
NO

t
at TOTAL TOTAL

da
d % %

a
40 a RET
.

IIIII:
Gr PASSING
% PASSING

Gr
.
WT
PASSING ON RETAINED % .
WT

PERCENT PASSING
30

30
20

10

100
200
No. 50 30 16 3/8 1/2
No.
80 40 20 10 1/4
"
SIEVE
SIZES

values
.VMA
low
with
gradations
A. ggregate
1-5
Figure
10/15/91
AC 150/5370-14
10/15/91
Appendix 1

cant portion of the aggregate smaller than 20 µm, with in the mineral aggregate, and the unit weight of the
some material as fine as 2 to 5 µm in size) , this material material.
can act to extend the volume of the asphalt cement and The "optimum " asphalt cement content of the mix is
can become part of the asphalt cement film around the determined from a family of plots based on mix proper-
aggregate particles . ties measured at different asphalt contents. Unit weight,
It is sometimes useful to conduct a hydrometer stability, flow, air void content, and voids in mineral
analysis to determine the gradation of the filler material aggregate content are plotted against asphalt content.
that passes the No. 200 (75 -μm) sieve . That gradation The "optimum " asphalt cement content is usually calcu-
affects the workability of the total blend of aggregate lated as the average asphalt content at the point of
just as gradation of the aggregate retained above this maximum unit weight, maximum stability, and at an air
sieve does. The actual effect depends, however, on the void content of 4 percent. In addition , the flow value
proportion of the material that is relatively coarse must be between certain limits and the voids in mineral
compared with the portion of the material that passes aggregate content must be above a minimum value . In
the No. 200 sieve that is ultra-fine (smaller than 20 µm) . some cases, the "optimum" asphalt cement content is
The finer the filler material, the greater the effect on selected based only on the amount needed to achieve 4
the workability of the total aggregate blend . This grada- percent air voids in the mix, and the other mix proper-
tion of the aggregate passing the No. 200 sieve is ties are checked at that asphalt cement content to see if
particularly important if a baghouse is used on the plant they comply with the specification requirements.
and the collected fines are returned to the plant for re- The optimum asphalt content is a function of the
incorporation into the mix. amount of compactive effort used to densify the mix.
Typically, two different compactive efforts (50 blows per
MIX DESIGN PROCEDURES side and 75 blows per side) are used in the laboratory to
To produce an asphalt mix design, asphalt cement simulate the amount of compaction that will take place
and aggregate are blended together in the laboratory. under both the compaction equipment at the time of
The characteristics of each component, the relative construction and under traffic with time. The higher
proportion of these two materials, and the air void compactive effort (75 blows) will result in a lower
content of the compacted mix determine the physical optimum asphalt content in the mix for any given aggre-
properties of the mix. Two common, but empirical, gate gradation.
methods of mix design are in use: the Marshall method Use of the Marshall method to determine the job
and the Hveem method . Both methods have the same mix formula for mix production does not mean that the
purpose: to determine the " optimum" asphalt cement mix produced will perform satisfactorily during place-
content for a particular combination of aggregate . ment and compaction or long-term under traffic . Mixes
Details on these two methods can be found in the that have high Marshall stability values may still shove
Asphalt Institute Manual MS-2. under the rollers and/or undergo permanent deforma-
tion (rutting) when subjected to heavy loads. Mixes that
Marshall Method have adequate VMA, however, normally perform
The Marshall method of mix design, which is limited significantly better than mixes made with the same
to mixtures containing aggregates that have a maximum aggregate and asphalt cement but that are low in VMA
size of 1 in. or less, uses three test procedures to deter- content.
mine the properties of the mix: a determination of the
bulk specific gravity, measurement of Marshall stability Hveem Method
and flow, and analysis of specimen density and voids The Hveem mix design method uses a series of tests
content. The stability value gives a measure of the load to determine "optimum" asphalt cement content . Those
under which the specimen fails, and the flow value test procedures include use of the centrifuge kerosene
provides a measurement of the deformation of the equivalent test to determine an approximate asphalt
specimen at failure. Mixes that have low stability and content, preparation of test specimens at a range of
high flow values are too plastic and tend to distort (rut asphalt contents both below and above the approximate
and shove) easily under load . Mixes that have very high optimum asphalt content, a stability test to evaluate the
stability and very low flow values are brittle and may resistance to deformation, and a swell test (rarely run)
crack readily. A density and voids analysis is conducted to determine the effect of water on the volume change
to determine the air void content, the amount of voids and permeability of the specimen .

Page 1-19
AC 150/5370-14
Appendix 1
10/15/91

The Hveem stability test measures the lateral pres- that may take place in the laboratory, however, is quite
sure that results from the application of a vertical load. variable .
The higher the Hveem stability, the more resistant the Asphalt cement is normally produced in a refinery by
mix is to distortion. The amount of air voids in the mix a steam distillation/vacuum process . The light products
is determined from both the measured bulk specific in a barrel of crude oil are driven off at various temper-
gravity of the mix and the maximum specific gravity of atures, leaving behind a soft residue . Some of the light
the mix, which is calculated from the specific gravity of products can remain in the asphalt cement, however,
the asphalt cement and the specific gravity of the depending on the type of refining procedure used and
aggregate in the mix. An appropriate allowance is made the type of crude oil processed . If a single-stage refinery
for the amount of asphalt cement absorbed by the is operated , a considerable amount of the lighter prod-
aggregate. ucts (light ends) can remain in the asphalt cement.
Compliance of the job mix formula with the Hveem
mix design criteria does not guarantee that the mix will Aggregate
not be tender during the construction process or that it In the laboratory, gradation of the aggregate to be
will be durable over time and traffic. The Hveem incorporated into the mix can be determined by conduct-
method is used primarily to pick an asphalt content for ing either a dry-sieve or a wet-sieve analysis. If the
the mix in order to fit inside a range of mix properties. aggregate is clean, the difference between the two test
results will be minimal. If the aggregate is dirty and has
AAMAS Method a great amount of fine material clinging to the coarse
The asphalt -aggregate mixture analysis system aggregate particles, there may be a considerable differ-
method of mix design, recently published by the Nation- ence between the dry and wet gradations. For this
al Cooperative Highway Research Program, should reason, the aggregate gradation used in the laboratory
provide mixtures that are better able to perform under should represent the actual gradation of the aggregate
traffic. The resilient modulus value, indirect tensile to be used in the mix at the plant.
strength, and creep modulus value are more related to In the field, the materials are incorporated into the
the distress mechanisms that affect the durability of an mix as received from the aggregate supplier. If there is
asphalt pavement: fatigue, permanent deformation, a considerable amount of fines clinging to the coarser
moisture damage, disintegration, and low-temperature material, those fines are put into the cold-feed bin with
cracking. the coarser material and delivered to the dryer or drum
mixer . This change in gradation does not normally exist
LABORATORY- AND PLANT- PRODUCED MIXES in the laboratory, particularly if a washed aggregate
Differences may exist between the properties of an gradation is used in the mix design . Thus, a difference in
asphalt mix designed in the laboratory and the " same" aggregate gradation, from lab to field, can exist.
job mix formula produced in a batch or drum mix plant . As the aggregate passes through a batch plant dryer
It is important to look at those differences and under- or drum mixer, its gradation is usually changed to some
stand how and why the test properties or characteristics degree . The amount of the change ( an increase in the
conducted on mix produced in a plant might vary amount of fines in the mix) is a function of many vari-
significantly from the results predicted from tests ables but is primarily related to the hardness of the
conducted on laboratory-produced material. aggregate. As the abrasion resistance of the aggregate
decreases, the amount of fines generated inside the
Asphalt Cement dryer or the drum normally increases . For a hard ,
In an asphalt cement storage tank, the binder is held durable aggregate, the amount passing the No. 200
in bulk and usually is circulated continuously by a pump. (75-μm) sieve may increase no more than 0.2 percent
The amount of aging and hardening that occurs during when processed. If a soft aggregate is used , the amount
storage is minimal. In the lab, the asphalt cement can be of the aggregate passing the No. 200 sieve may increase
heated in an oven for various periods of time . It usually by as much as 1 or 2 percent.
is handled in small quantities in containers that are open All materials will vary in gradation from the average
to the air. Although some hardening does occur during value for the percent passing each sieve. This is recog-
this laboratory mixing process, the degree of hardening nized by assigning allowable tolerance values, about that
is generally less than that which occurs during mix average value, to each sieve size . Thus, the aggregate in
production at the asphalt plant . The degree of hardening the cold-feed bins can be expected to fall within a range

Page 1-20
AC 150/5370-14
10/15/91
Appendix 1

of gradations instead of on an exact gradation. In the mix design procedure. Thus the type of emission - control
laboratory, however, the aggregate is sieved into differ- equipment used on the batch or drum plant can signifi-
ent fractions and then recombined to an exact gradation cantly affect the properties of the asphalt mixture . The
curve . The degree of precision in the lab is significantly amount of fines can change the filler/asphalt ratio and
greater than what occurs at an asphalt batch or drum thus also change the stiffness of the resulting asphalt
mix plant . mix. The change in the type and amount of fines nor-
The aggregate used to make laboratory samples is mally is not taken into account in the laboratory mix
completely dry; there is essentially no moisture in the design procedure.
material. For aggregate heated in a batch plant dryer, it Baghouses operate at different efficiencies, depend-
is possible to reduce the moisture content to about 0.1 ing on the pressure drop between the dirty and clean
percent, by weight of the aggregate, but in most cases side of the filter bags. If the bags are clean and the
the moisture content in the aggregate will range up to pressure drop is small, the fines-laden exhaust gases will
0.5 percent, depending on the amount of moisture in the pass through the fabric filter and some of the very fine
incoming aggregate, the production rate of the dryer, particles will go out the plant stack. As the bags become
and the aggregate discharge temperature. Rarely will the more heavily coated with material and as the pressure
aggregate discharged from a typical dryer be completely drop increases, more of the fines are captured on the
without some retained moisture . For aggregate pro- coating already on the bags. Thus, as the loading on the
cessed through a drum mix plant, the moisture content bags is increased, the baghouse actually becomes more
in the mix at discharge typically is less than 1.0 percent efficient and a greater volume of fines as well as a finer
but can be higher, depending on the same variables as gradation of material is returned to the mix in either a
for the batch plant. Although there should be no more batch or drum mix plant. The change in the amount of
than 0.5 percent moisture retained in the plant- produced fines captured and sent back to the plant can be sub-
mix, differences will exist in the amount of moisture stantial.
between the lab- and plant-produced mix. If the plant is equipped with only a dry collector
In the lab oven, the aggregate is uniformly heated (knockout box or cyclone), most of the fines returned to
throughout, and the coarse and fine portions of the the mix will be larger than the No. 80 or No. 100
aggregate will both be at approximately the same (180-μm or 150-μm) sieve . With the use of a fabric filter,
temperature. In the plant dryer or drum mixer, the particles as small as 5-μm size (smaller than the asphalt
coarse aggregate usually is heated to a lower tempera- cement film thickness on the aggregate) can be reincor-
ture than is the fine aggregate and there is often a porated into the mix. These ultra-fine particles, which do
distinct temperature differential between the two not exist separately during the laboratory mix design
fractions of aggregate . In a batch plant, the temperature procedure, can act like extra asphalt cement, causing the
is generally equalized during pugmill mixing. In a drum mixture to look greasy and become tender. Thus, a
mix plant, however, a heat balance is not always ob- stable mix in the lab can be soft and tender in the field
tained unless the material is held in the surge silo for a if the baghouse is returning ultra-fine aggregate particles
period of time. back into the plant. For any plant equipped with a fabric
If a wet scrubber is used on either a batch or drum filter, not only the quantity of the baghouse fines needs
mix plant, any fines captured are carried out of the dryer to be known, but also the gradation of those fines
or drum mixer and wasted . These fines are no longer should be determined .
part of the aggregate gradation . If a baghouse is used as If RAP is incorporated into the mix, this material is
the emission-control device on either type of plant, some normally mixed in the laboratory until it is thoroughly
or all of the collected fines can be returned to the mix. heated and blended with the new aggregate. In the
If the fines from the baghouse are wasted , a slightly plant, however, the amount of mixing and heat transfer
different aggregate gradation will exist in the mix, similar that occurs from the new aggregate to the reclaimed
to that which occurs when the plant is equipped with a material is a function of many variables, such as the
wet-scrubber system. If all of the baghouse fines are amount of RAP in the mix, the point of introduction of
returned to the mix, the gradation of the aggregate still the RAP, the temperature of the new aggregate, and the
may be different from the gradation of the aggregate amount of mixing time available . In addition, the
tested in the laboratory because the baghouse will collect reclaimed material may add a significant amount of fines
ultra-fine aggregate particles not normally separated [percent passing the No. 200 (75 -μm) sieve ] to the mix.
from the other aggregate particles during the laboratory Finally, both Marshall and Hveem mix design proce-

Page 1-21
AC 150/5370-14
Appendix 1 10/15/91

dures are limited to 1 -in.-maximum-size aggregate . For the pavement before compaction may be sent in loose
larger-size aggregate that is often used in base course condition to a district or central laboratory for future
layers, modifications to the aggregate gradation or testing. The amount of hardening that occurs in the
sample size must be made . This causes differences in the ›inder material depends on the time between the manu-
properties of the mixes produced in the laboratory facture and testing, as well as on the storage conditions
compared with plant-manufactured mix. For mixes (temperature and the availability of oxygen). The
containing 1.5 in. maximum aggregate, a 6- in . mold process of reheating the sample, including the time and
should be used . A method is being developed to use 6- temperature of heating and any remixing of the sample
in. specimens in lieu of the standard 4-in. specimens. if compaction is not completed in the field , also can
have a significant effect on the measured properties of
Mixing Process the mix. Thus, the laboratory handling process can affect
As the mix time increases in a batch plant pugmill, the differences found between plant- and laboratory-
the degree of aging of the asphalt binder also increases. prepared samples.
For relatively short wet mix times (28 to 35 sec) , the
average asphalt cement will decrease 30 to 45 percent in Compaction
penetration. For longer wet mix times (up to 45 sec) , the Several methods, including Marshall hammer,
penetration of the asphalt cement may be up to 60 California kneading compactor, and gyratory shear
percent less than the original value . Higher mixing compactor, are commonly available to compact asphalt
temperatures increase the degree of hardening of the concrete specimens in the laboratory. The purpose of
asphalt cement. Thus, the mix produced in a batch plant any lab compaction process is to simulate, as closely as
pugmill can be much stiffer than the same material possible, the degree of density produced in the field by
produced in the laboratory with essentially unaged the rollers and the density of the mix after some time
asphalt cement unless the laboratory binder material is under traffic . This simulation includes such factors as air
continually reheated . void content, aggregate particle orientation, and void
The amount of hardening of the asphalt cement that distribution . Intra-laboratory and inter-laboratory test
occurs in a drum mix plant may be less, more, or the results have indicated that the degree of compaction
same as that in the pugmill of a batch plant . The degree obtained in the lab can be highly variable .
of hardening is quite variable and is a function of the The compaction process in the laboratory is very
thickness of the asphalt cement film around the aggre- quick, usually completed within 2 or 3 min . This is in
gate particles, as well as many other factors . Less direct contrast to actual roller operations in the field ,
hardening generally occurs during the coating process as which use an infinite variety of roller combinations,
the moisture content of the incoming new and reclaimed roller passes, and roller patterns and in which final
aggregate increases, as the volume of aggregate in the density levels might not be attained until 30 min or
drum increases, as the mix discharge temperature longer after the mix is placed by the paver. Also, during
decreases, and as the production rate of the plant the laboratory compaction process, the mixture tempera-
increases. ture is relatively constant . On the pavement, the temper-
The laboratory mixing process is accomplished by ature of the material is continually decreasing with time.
hand or by machine, with the time necessary to blend In the lab, the compaction effort is usually applied
the asphalt cement and aggregate together dependent on before the mix temperature drops to 240°F (Marshall)
the efficiency of the mixing process. Usually several or 220°F (Hveem) . In the field, the mix may cool to
minutes are required to obtain complete coating of the 175°F or less before the compaction process is complet-
aggregate. During this period, the asphalt cement is ed .

exposed to the air and some hardening takes place . The In the lab, the asphalt mix is compacted against a
degree of hardening is a function of the aggregate solid foundation, whereas in the field a wide variety of
temperature and the mixing time . The change in asphalt base types and stiffnesses are encountered . An asphalt
cement properties will not be the same as the change mix can be placed as part of a newly constructed pave-
that will occur during mix production in a batch or drum ment as the first layer on top of a soft subgrade soil or
mix plant. Thus, the stiffness of a mix produced in the as the surface course on a full-depth asphalt concrete
laboratory will probably be less than that of a plant- pavement structure . The material can be used as an
manufactured mixture . overlay on a distressed asphalt pavement or as resurfac-
Asphalt mix samples obtained from the plant or from ing on a portland cement concrete (PCC) pavement.

Page 1-22
AC 150/5370-14
10/15/91 Appendix 1

The ability to obtain a particular level of density in an desired properties of the mix should be checked and
asphalt mixture depends in part on the rigidity of the verified on the plant-produced, laboratory-compacted
base being laid over and on the type of compaction asphalt mixture. Daily tests should be run to determine
equipment used. The differences between some pave- the characteristics of the mix actually being manufac-
ment base conditions and laboratory base conditions can tured (mix verification). All of the mix values should be
be significant. A test section will establish the compac- within the range required by the mix design process. If
tive effort necessary to obtain specified density in the the test results on the plant-produced mix indicate
asphalt mix. compliance with the job mix formula requirements, the
plant should continue to operate. If one or more of the
SUMMARY mix properties is outside the desired range, an investiga-
The objective of any mix testing on plant-produced tion should be made quickly to determine the cause and
asphalt mixtures is to compare the test results to the the extent of the deficiency. In most cases, however, the
laboratory job mix formula. The attempt is made to plant should not be shut down nor drastic changes made
make the plant-produced mix equal the laboratory job in the mix design on the basis of only one set of test
mix formula. This is most often difficult to accomplish results. In addition, if major differences in gradation
because of all the variables that exist at the plant--from exist between the aggregate used in the laboratory mix
the type of plant used to the operating conditions at design process and the aggregate used in the plant, the
each particular plant. Major differences between labora- job mix formula should be adjusted and/or the mix
tory and plant mixes often exist in the gradation of the design should be rerun.
aggregates, the degree of hardening of the asphalt Problems that develop in the batch or drum mix
cement, and the addition of fine aggregate from the plant and on the pavement during the laydown and
emission-control equipment, to focus on only a few of compaction process are discussed in the section on mat
multiple factors. In addition, compaction conditions are problems in Part Three. Many of these problems, such
considerably different between the laboratory and the as checking and shoving, can be related to deficiencies
mix under the various rollers in the field . in the mix design used to create the job mix formula and
The job mix formula produced in the laboratory, to differences between the JMF mix properties and the
therefore, should be treated only as an initial mix design, properties of the mix actually produced in the plant.
used primarily to pick an asphalt cement content. The

Page 1-23
AC 150/5370-14
10/15/91
Appendix 1

Part Two

ASPHALT PLANTS
AC 150/5370-14
10/15/91
Appendix 1

PART TWO

TABLE OF CONTENTS

ZZZZ
SECTION ONE TYPES OF ASPHALT PLANTS

Z
INTRODUCTION •
BATCH PLANTS 2-1
CONTINUOUS MIX PLANTS • 2-4
DRUM MIX PLANTS 2-4
Parallel-Flow Drum Mixer 2-4
Counter Flow Drum Mixer 2-6

SECTION TWO AGGREGATE STORAGE AND HANDLING 2-10


INTRODUCTION 2-10
AGGREGATE STOCKPILES 2-10
COLD-FEED SYSTEMS FOR NEW AGGREGATES 2-12
Cold-Feed Bins and Feed Conveyors 2-13
Gathering Conveyor 2-15
Scalping Screens and Devices 2-15
Charging Conveyor 2-18
Batch Plants 2-18
Drum Mix Plants 2-18
Individual-Bin Weigh Bridges 2-19
COLD-FEED SYSTEMS FOR RECLAIMED ASPHALT PAVEMENT 2-19
Single-Feed Drum Mix Plants 2-21
Split-Feed Drum Mix Plants 2-21
ADDITION OF HYDRATED LIME • 2-21
CALIBRATION ... 2-21
SUMMARY OF AGGREGATE HANDLING OPERATING TECHNIQUES 2-22

SECTION THREE ASPHALT CEMENT SUPPLY SYSTEM ... 2-24


INTRODUCTION • 2-24
STORAGE TANKS 2-24
PUMP AND METER SYSTEM 2-25
Batch Plants 2-25
Drom Mix Plants 2-25
Asphalt Cement Delivery 2-25
Temperature Compensation 2-27
ADDITION OF LIQUID ANTISTRIP MATERIALS 2-27
CALIBRATION 2-27
SUMMARY OF ASPHALT CEMENT SUPPLY OPERATING TECHNIQUES 2-28
AC 150/5370-14
Appendix 1 10/15/91

Part Two Contents (continued)

SECTION FOUR DRUM MIX PLANT ... 2-29


INTRODUCTION 2-29
AGGREGATE ENTRY 2-29
BURNER SYSTEM ... 2-29
Fuel 2-29
Burners 2-30
HEAT-TRANSFER PROCESS 2-31
Temperatures Inside the Drum 2-31
Flight Design 2-32
Increasing the Veil of Aggregate 2-34
Heat Transfer 2-36
ASPHALT CEMENT INJECTION ..... 2-36
MINERAL FILLER AND BAGHOUSE FINES FEED SYSTEM 2-38
Mineral Filler 2-38
Baghouse Fines 2-39
RECLAIMED MATERIAL RECYCLING SYSTEMS ... 2-40
Single-Feed 2-40
Split-Feed 2-40
PRODUCTION RATES ... 2-42
PLANT EFFICIENCY 2-44
Mix and Stack Temperatures 2-44
Mix Discharge Monitoring 2-45 -
SUMMARY OF DRUM MIXER OPERATING TECHNIQUES 2-46

SECTION FIVE SURGE AND STORAGE SILOS 2-48


INTRODUCTION 2-48
CONVEYING DEVICES 2-48
BIN GEOMETRY 2-48
TOP OF THE SILO 2-49
Mix Delivery 2-49
Batcher 2-50
Rotating Spreader Chute 2-51
SURGE VERSUS STORAGE 2-51
Insulation and Heat 2-51
Storage 2-52
THE CONE, LOADOUT, AND SEGREGATION ... 2-53
Silo Cone 2-53
Loading and Segregation 2-53
Loading Hopper 2-54
SUMMARY OF SILO OPERATING TECHNIQUES .... ... 2-54

SECTION SIX EMISSION CONTROL .. 2-56


INTRODUCTION 2-56
FINES CARRYOUT 2-56
PRIMARY DRY COLLECTOR 2-56
WET COLLECTOR • 2-58
BAGHOUSE .. 2-59
FUGITIVE DUST 2-61
SUMMARY OF EMISSION-CONTROL OPERATING TECHNIQUES 2-62
AC 150/5370-14
10/15/91
Appendix 1

Part Two Contents (continued)

SECTION SEVEN BATCH PLANT • 2-63


INTRODUCTION 2-63
AGGREGATE HANDLING • 2-63
Aggregate Stockpiles 2-63
Cold-Feed Systems for New Aggregates 2-64
Cold-Feed Systems for RAP 2-64
ADDITION OF HYDRATED LIME 2-65

ASPHALT CEMENT SUPPLY SYSTEM .... • 2-65


Storage Tanks 2-65
Pump System 2-65
ADDITION OF LIQUID ANTISTRIP ADDITIVES …….. 2-65
AGGREGATE HEATING AND DRYING 2-65
SCREENING AND STORAGE OF HOT AGGREGATE 2-66
Hot Elevator 2-66
New Aggregate 2-66
Reclaimed Material 2-66
Screen Deck 2-68
Hot Bins 2-69
New Aggregate 2-69
RAP 2-69
WEIGH HOPPER • 2-70
New Aggregate 2-70
Reclaimed Material 2-70
PUGMILL 2-70
Capacity 2-70
Mixing Time 2-71
Dry Mix Time 2-71
Wet Mix Time 2-71
Total Mix Time 2-73
PRODUCING RECYCLED MIX 2-74
Recycling Variables 2-74
Moisture Content 2-75
Mix Discharge Temperature 2-75
Amount of Reclaimed Material 2-75
Dryer Operation 2-75
Visible Emissions 2-75
LOADING THE TRUCK OR SILO 2-77
EMISSION- CONTROL EQUIPMENT · • • 2-77
CALIBRATION ... 2-77
SUMMARY OF PLANT OPERATING TECHNIQUES 2-78

BIBLIOGRAPHY ... ... 2-79


AC 150/5370-14
10/15/91
Appendix 1

SECTION ONE
TYPES OF ASPHALT PLANTS

INTRODUCTION The aggregate used in the mix is removed from


The purpose of a hot-mix asphalt plant is to blend stockpiles and placed in individual cold-feed bins. Each
together aggregate and asphalt cement to produce a hot, different size aggregate is proportioned out of its bin by
homogeneous asphalt paving mixture. The aggregate the size of the opening of the gate at the bottom of each
used can be a single material, such as a crusher run bin or by use of a variable-speed belt feeder. Generally,
aggregate or a pit run material, or it can be a combina- belt feeders beneath each bin deposit each aggregate on
tion of coarse and fine aggregates, with or without a gathering conveyor located under all of the cold-feed
mineral filler. The binder material used is normally bins. The gathering conveyor transports the combined
asphalt cement but can also be an asphalt emulsion or aggregate to the charging conveyor, which carries it up
one of a variety of modified materials. Various additives, to the aggregate dryer.
including liquid and powdered materials, can also be The dryer operates on a counter flow basis. The
incorporated into the mixture. aggregate is introduced into the dryer at the upper end
There are two basic types of plants currently in use and moves down the drum both by the drum rotation
in the United States: batch plants and continuous mix (gravity flow) and by the flight configuration inside the
plants. Within the continuous mix plant category, there rotating dryer. The burner is located at the lower end of
are two different types of facilities: the older continuous the dryer, and the exhaust gases from the combustion
mix plant and the modern drum mix plant. Within the and drying process move toward the upper end of the
drum mix plant category, both parallel flow and counter dryer, against the flow (counter to the flow) of the
flow plants are operated . Each plant type fulfills the aggregate. As the aggregate is tumbled through the
same ultimate purpose, but the operation and flow of exhaust gases, the material is heated and dried . Moisture
the materials through the plant is different. The asphalt is removed and carried out of the dryer as part of the
mixture, however, should be essentially similar regardless exhaust gas stream. The hot, dry aggregate is discharged
of the type of plant used to manufacture it. from the dryer at the lower end .
A brief description of the flow of materials and the The hot aggregate is transported to the top of the
operation of batch plants, continuous mix plants, and plant mixing tower by a bucket elevator. Upon discharge
drum mix plants is provided in this chapter . A more from the elevator, the aggregate normally passes through
detailed discussion of drum mix and batch plants follows. a set of vibrating screens . The finest aggregate material
The equipment and procedures common to both types goes directly through all the screens into the No. 1 hot
of plants (aggregate stockpiling and cold-feed systems, bin. The coarser aggregate particles are caught by the
asphalt cement supply system, surge silos, and emission- different size screens and deposited into one of the
control equipment) are described jointly. The operations other hot bins. The separation of aggregate in each of
of the parallel-flow drum mixer as well as the batch the hot bins depends on the size of the openings in the
plant counter flow dryer and mixing tower are discussed screen that is used in the screen deck and the gradation
in separate sections . The old-style continuous mix plants of the aggregate in the cold-feed bins.
are not covered in a separate section , because very few The aggregate is held in the hot bins until it is
of them are still in operation. discharged from a gate at the bottom of each bin into a
weigh hopper. The correct proportion of each aggregate
BATCH PLANTS is determined by weight. If reclaimed material is used in
The major components of a batch plant are the cold- the mix, it typically is entered into the weigh hopper as
feed system, asphalt cement supply system, aggregate an additional aggregate .
dryer, mixing tower, and emission-control system. The At the same time that the aggregate is being propor-
plant tower consists of several elements: hot elevator, tioned and weighed, the asphalt cement is pumped from
screen deck, hot bins, weigh hopper, asphalt cement its storage tank to a separate weigh bucket located on
weigh bucket, and pugmill . These components are shown the tower just above the pugmill. The proper amount of
in Figures 2-1 and 2-2. material is weighed into the heated bucket and held

Page 2-1
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-1 . Typical batch plants (Barber-Greene).

until it is needed in the pugmill . the asphalt cement material . The total time in the
The aggregate in the weigh hopper is emptied into a pugmill, made up of dry-mix time and wet-mix time, can
twin shaft pugmill, and the different aggregate fractions be as short as 28 sec, in most cases.
are mixed together. After this brief dry-mix time, the When mixing is complete, the gates on the bottom of
asphalt cement from the weigh bucket is discharged into the pugmill are opened and the mix is discharged into
the pugmill and the wet-mix time begins. The mixing the haul vehicle or into a conveying device that carries
time for the blending of the asphalt cement with the the mix to a silo and eventually into the truck. For most
aggregate should be no more than that needed to com- batch plants, the time needed to open the pugmill gates
pletely coat the aggregate particles with a thin film of and discharge the mix is approximately 7 sec. Thus, the

Page 2-2
AC 150/5370-14
10/15/91
Appendix 1

Fourteen Major Parts


1. Cold bins 9. Hot bins
2. Cold feed gate 8
10. Weigh box
3. Cold elevator
11. Mixing unit -- or pugmill
4. Dryer 12. Mineral filler storage 1
6
5. Dust collector 13. Hot asphalt cement storage 9
6. Exhaust stack 14. Asphalt weigh bucket
7. Hot elevator
www
8. Screening unit
10

11 14

1 3 5
4

CO 12 13
www.2

Figure 2-2. Batch plant components (Asphalt Institute).

total mixing time for a batch would be about 35 sec remove particulate matter from the exhaust gases that
(dry-mix time + wet-mix time + mix discharge) in most flow out of the dryer and send clean air to the atmosph-
cases. ere through the stack.
The plant is equipped with emission-control devices, If RAP is incorporated into the mix, the material is
both primary and secondary collection systems . Either a placed in a separate cold-feed bin from which it is
wet-scrubber system or a dry- fabric filter system (bag- delivered to the plant . It can be added to the new aggre-
house) can be used as the secondary collection system to gate in one of three locations: the bottom of the hot.

Figure 2-3. Continuous- mix plant (J. Scherocman).

Page 2-3
AC 150/5370-14
Appendix 1 10/15/91

elevator, the hot bins, or the weigh hopper, with the last cement, measured by volume instead of weight, is mixed
location being the one most commonly used. Heat continuously with the aggregate as the two materials are
transfer between the superheated new aggregate and the moved toward the discharge end of the pugmill by the
reclaimed material begins as soon as the two materials mixing paddles. Mixing time can be increased or de-
come in contact and continues during the mixing process creased by changing the retention or dwell time of the
in the pugmill . aggregates in the pugmill, usually by altering the setting
of the pugmill discharge end gate or by reversing one or
CONTINUOUS MIX PLANTS more sets of paddles.
An old-style continuous mix plant is shown in Figures Because the mixing is a continuous process, a small-
2-3 and 2-4 . The components of this type of plant capacity, temporary holding hopper is provided at the
include the cold-feed system, asphalt cement supply discharge end of the mixer to store the material until it
system , aggregate dryer, hot-bucket elevator, screen unit, can be delivered into a haul truck. For emission-control
hot bins, mixing unit and holding hopper, and emission- purposes, the plant is equipped with a primary dry
control system . collector and a secondary wet collector or a baghouse.
The cold-feed bins are similar to those used on a If a recycled mix is being produced, the RAP materi-
batch plant, and typically a constant-speed feeder belt is al is placed in a separate cold-feed bin and transported
located under each bin. Material is proportioned from to the pugmill by a charging conveyor . This material is
each bin by the size of the discharge gate opening and added proportionately, by volume, to the new aggregate
deposited on the gathering conveyor. The aggregate is that has been superheated in the dryer. The heat
transferred to a charging conveyor for delivery to the transfer and mixing of the two materials is accomplished
dryer. Inside the dryer the moisture in the combined as they move through the pugmill.
aggregate is removed as the material is heated from
ambient temperature to the desired mixing temperature . DRUM MIX PLANTS
The dried and heated aggregate is then carried up an Parallel-Flow Drum Mixer
inclined bucket elevator to the screen deck, where it is The parallel-flow drum mix plant, shown in Figures
divided into various sizes and temporarily held in small 2-5, 2-6, and 2-7, is a form of the old-style continuous
hot bins. mix plant. It consists of five major components: the cold-
The aggregate is continuously removed from the bins, feed system, asphalt cement supply system, drum mixer,
proportioned according to the desired gradation in the surge silo, and emission-control equipment .
mix, and transported to the pugmill. The asphalt cement The cold-feed bins are used to proportion the
is kept in a storage tank and then pumped to the mixing material to the plant . Variable-speed feeder belts are
tower, where it is sprayed on the aggregate. The asphalt used under each bin. The amount of each aggregate

C E
B
Α D
ད་
F H
I

G
K

PRQS T
0
N

L M

A Cold aggregate storage and feed; B Dryer; C Dust collector; D Gradation control unit; E Mixer; F Grizzly; G Fan; H Vibrating screen;
I Transfer pump; J Pugmill ; K Pugmill jacket; L Belt feeder; M Reciprocating feeder; N Flights; O Collected fines; P Gates; Q Mineral
filler feed; R Aggregate sample point; S Metering pump; T Discharge Hopper
Figure 2-4. Continuous- mix plant components (Asphalt Institute).

Page 2-4
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-5 . Typical drum mix plant (Barber-Greene).

drawn from each bin can thus be controlled by both the gravity and by the flight configuration inside the drum.
size of the gate opening and the speed of the belt feeder As it travels, the aggregate is heated and the moisture
to provide accurate delivery of the coarse and fine removed . A dense veil of aggregate is built up near the
material. The aggregate on each feeder belt is deposited midpoint of the drum length to assist in the heat-trans-
onto a gathering conveyor that runs beneath all of the fer process .
cold-feed bins. The combined material is normally If RAP is added to the new aggregates, it can enter
passed through a scalping screen and transferred to a the drum in one of two locations: it can be combined
charging conveyor for transport to the drum mixer. with the new aggregate at the burner end of the drum
The charging conveyor is equipped with two devices (the single-feed method, which is very seldom used ), but
that are used to determine the weight of the aggregate most often is deposited from its own cold-feed bin and
being delivered to the plant : A weigh bridge under the gathering/charging conveyor into an inlet located at the
conveyor belt measures the weight of the aggregate center of the drum length (split-feed system) . In the
passing over it at an instant of time, and a sensor is used latter process, the reclaimed material is protected from
to determine the speed of the belt. These two values are the high-temperature exhaust gases by the veil of new
used to compute the wet weight of aggregate, in tons per aggregate upstream of its entry point.
hour, entering the drum mixer. The plant computer, with The new aggregate and reclaimed material, if used,
the amount of moisture in the aggregate provided as an move into the rear half of the drum. The asphalt cement
input value, converts the wet weight to dry weight to is pulled from the storage tank by a pump, fed through
control the amount of asphalt cement needed in the mix. a meter where the proper volume of asphalt cement is
The conventional drum mixer is a parallel-flow determined, and then through a pipe into the rear of the
system ; the exhaust gases and the aggregate move in the drum . The asphalt cement is injected onto the aggregate .
same direction. The burner is located at the upper end Coating of the aggregate occurs as the materials are
(aggregate inlet end) of the drum. The aggregate enters tumbled together and moved to the discharge end of the
the drum either from a charging chute above the burner drum . Mineral filler and/or baghouse fines are also
or on a slinger conveyor under the burner. The aggre- added into the back of the drum, either just before, or
gate is moved down the drum by a combination of in conjunction with, the addition of the asphalt cement.

Page 2-5
AC 150/5370-14
Appendix 1 10/15/91

Hot-Mix Conveyor
Automatic
Weighing System Mix
Surge
Cold Feed Conveyor Silo

Cold Feed Bins Dust Control


Drum Mixer Collector Van

Asphalt
Storage Tank चि Asphalt Pump

Figure 2-6. Drum mix plant components (Asphalt Institute).

The asphalt mix is deposited into a conveying device emissions from the plant . The uncoated aggregate, which
(a drag slat conveyor, belt conveyor, or bucket elevator) is heated and dried inside the parallel-flow drum, is
for transport to a surge silo. The silo converts the discharged into a single- or dual-shaft mixing chamber,
continuous flow of mix into a batch flow for discharge where it is sprayed with asphalt cement. The blending of
into the haul vehicle. the asphalt cement and the aggregate takes place as the
In general, the same type of emission-control equip- materials move from one end of the mixing unit to the
ment is used on the drum mix plant as on the batch other. When mixing is complete, the material is deliv-
plant. A primary dry collector and either a wet-scrubber ered to the device used to transport it to the silo. Figure
system or a baghouse secondary collector can be used. 2-8 is an illustration of the " coater" type of drum mix
If a wet-scrubber system is used, the collected fines plant.
cannot be recycled back into the mix and are wasted. If
the baghouse is used, the collected fines can be returned Counter Flow Drum Mixer
in whole or in part to the mixing drum or they can be A recent development in continuous mix plant design
wasted. is the counter flow drum mix plant. The development of
In the late 1980s, a number of variations to the this plant type is an effort to improve the heat-transfer
conventional drum mix plant were introduced to the hot- process inside the drum and to reduce plant emissions.
mix asphalt-paving industry. One of these plant types is As shown in Figure 2-9, the aggregate enters the
the "coater" plant. For this type of drum mixer (which is drum from the upper end, whereas the burner is located
really a type of continuous mix plant instead of a drum near the lower end of the drum, similar to its position
mixer), the asphalt cement injection pipe has been on a batch plant dryer. The aggregate moves down the
removed from the drum. This modification removes the drum against the flow of the exhaust gases--in a counter
asphalt cement from exposure to the high-temperature flow direction. No asphalt cement is introduced into the
exhaust gases and reduces both hydrocarbon and visible aggregate within the main portion of the drum. An

Exhaust
@

Virgin
Aggregate

Liquid
Asphalt

Hot
Mix
Figure 2-7. Parallel-flow drum mix plant (Astec) .

Page 2-6
AC 150/5370-14
10/15/91
Appendix 1

Recycle Asphalt
Product

Exhaust

Virgin
Aggregate

Liquid
Asphalt

Figure 2-8. Drum mix coater cutaway (Astec) .

extension to the drum is used , as shown in Figure 2-10, overheating the new aggregate in the upper end of the
to provide for the mixing of the heated and dried counter flow dryer and blending the two materials
aggregate with the asphalt cement. This mixing takes together in the lower portion of the drum, between the
place behind (downstream of) the dryer in a separate burner and the discharge end of the mixing unit.
mixing chamber or zone, out of contact with the exhaust In some counter flow drum mix plants, the mixing
gases from the burner. section is placed on the outside of (around) the primary
If RAP is used in the asphalt mix produced in a drum , as seen in Figures 2-11 and 2-12. The asphalt
counter flow drum mix plant, it is introduced into the cement in this double barrel plant is introduced into the
drum downstream of the burner. Thus the RAP does aggregate after the aggregate is discharged from the
not come in contact with the high-temperature exhaust inner drum into the outer drum . The blending of the
gases from the burner and visual hydrocarbon emissions two materials occurs as the aggregate and asphalt
are not generated. The reclaimed material is heated by cement are conveyed back uphill in the outer drum by

Exhaust
Recycle Asphalt
Product

Virgin
Aggregate
Air

Liquid
Asphalt
Hot
Mix

Figure 2-9. Counter flow drum mixer components (Astec) .

Page 2-7
AC 150/5370-14
Appendix 1 10/15/91

HOT OR

Figure 2-10. Counter flow drum mixer (Gencor) .

e
doubl berel

AST

Figure 2-11 . Double barrel plant (Astec).

Page 2-8
AC 150/5370-14
10/15/91
Appendix 1

a set of mixing paddles attached to the inner drum. The and thus reduces the possibility of the generation of blue
inner drum rotates, whereas the outer drum is station- smoke during the recycling process.
ary. Because the number of "coater" parallel-flow drum
As in the normal counter flow drum mixer, the RAP mix plants and counter flow drum mix plants in use is
material in the double barrel process enters the drum limited , and because their operation is essentially similar
between the inside and outside dryer drums, away from to that of a drum mixer and a dryer, no further discus-
the exhaust gases from the burner. This keeps the RAP sion of the operation of these types of continuous mix
from contact with the high-temperature exhaust gases plants will be undertaken in this manual.

Liquid Asphalt
Recycle Asphalt
Product Exhaust

00
0 000
000

00 Virgin
000
100 Aggregate

Hot
Mix

Figure 2-12. Double barrel drum mixer (Astec) .

Page 2-9
AC 150/5370-14
Appendix 1
10/15/91

SECTION TWO
AGGREGATE STORAGE AND HANDLING

INTRODUCTION do, however, and care must be taken with this operation
The information discussed in this section concerns to prevent the segregation problem from becoming
the stockpiling and the handling of both new aggregate worse.
and RAP material for use in any asphalt plant. This Aggregate should be stockpiled on a clean, dry,
section discusses proper stockpiling techniques, both for stable surface and should not be allowed to become
placement of the aggregate in the stockpile and for contaminated with foreign materials such as dust, mud,
removal of the aggregate from the stockpile . Care must or grass. Fugitive dust in the aggregate stockpile area
be taken to minimize possible segregation of the aggre- should be controlled so that the dust does not coat the
gate, both coarse and fine, during the stockpiling and surface of the aggregates and does not alter the grada-
handling process . tion of the material in each stockpile . The stockpiles
This section also contains a review of the discharge should be constructed to be free draining to ensure that
of the aggregate from the cold-feed bins onto the the moisture content of the aggregate is as low as
individual bin feeder conveyor belts, as well as the possible . Paved stockpile pads have been used to
passage of the aggregate onto the gathering conveyor facilitate drainage and provide a solid working platform.
and the delivery of the aggregate, sometimes through a Excess moisture in the aggregates, particularly in the
scalping screen, to the charging conveyor and finally to fine aggregates (sand) , increases the cost of drying the
the batch plant dryer or to the drum mixer . There is aggregates and reduces the production capacity of the
also a discussion, in the section on drum mix plant plant. The moisture content of each aggregate size
operations, of the use of a weigh bridge system on the should be determined at least twice a day and the
charging conveyor to determine the amount of aggregate average moisture content of all the aggregates entered
being fed into the drum . into the plant computer system .
This section reviews delivery of RAP from its cold- In order to reduce the amount of moisture that
feed bin to the batch or drum mix plant. It points out accumulates in the aggregate, especially from rain, it is
that the charging conveyor can deposit the reclaimed often cost-effective to cover the aggregate stockpiles.
material into three locations on a batch plant and two This cover typically is in the form of a roof or a shed.
locations on a drum mix plant. There is an examination Sometimes only the fine aggregate (sand) stockpile is
of calibration of the cold-feed system , with information covered because the fine aggregate usually has a higher
provided on the proper methods to use to check the rate moisture content than the coarser aggregate .
of aggregate delivery from the individual cold -feed bins The stockpiles of the various aggregate sizes should
and over the weigh bridge system. be kept separated --by physical barriers, if necessary-- at
all times. The cold-feed bins and feeders are calibrated
AGGREGATE STOCKPILES to provide a specific amount of each different size
Quality control of hot-mix asphalt, regardless of aggregate from each bin. If the various materials are
whether a batch or drum mix plant is used to manufac- blended in the stockpiles, a combination of sizes will
ture the mix, begins with the stockpiles of aggregate that occur in each cold -feed bin . This blending of the
are to be processed through the plant and incorporated aggregate will cause variations in the gradation of the
into the mix. The aggregate should be stored on a clean HMA produced by a drum mix plant and can cause
surface, with the different sizes of coarse and fine aggre- problems with unbalanced hot bins in a batch plant.
gate kept separated . Care should be exercised both Segregation of the stockpiled aggregate is a major
during the stockpiling process and during the removal concern. Many aggregate problems are caused by
process to minimize segregation of the aggregate in each mishandling of the aggregate during stockpiling and
pile. If segregation of a particular size of coarse or fine loadout operations. Whenever possible , aggregate
aggregate does occur, an effort should be made to blend should be stockpiled by individual size fractions. A well-
the segregated materials together before the aggregate graded or continuously graded material can easily
is delivered into the cold-feed bins. This is difficult to segregate if mishandled . Aggregate of larger size, par-

Page 2-10
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-15. Truck dump stockpile (Asphalt Institute).


Proper operation of the front-end loader used to
load haul trucks or charge the cold-feed bins of the
asphalt plant will also reduce the aggregate segregation
Figure 2-13. Segregated stockpile (Asphalt Institute).
and gradation variation problems. As shown in Figure
2-16, a stockpile of continuously graded aggregate will
ticularly when combined with smaller sizes of stone, has be segregated when produced by a stacker. The outside
a tendency to roll down the face of a stockpile and edge of the stockpile will be coarse, and the aggregate
collect at the bottom, as shown in Figure 2-13. below and slightly behind the head pulley will be fine .
Prevention of segregation begins with the construc- Significant changes in gradation can result from burrow-
tion of the stockpile. As illustrated in Figure 2-14, ing straight through the stockpile . The loader operator
stockpiles should be constructed in horizontal or gently should remove the aggregate in a direction perpendicu-
sloping layers. If trucks are used to carry the incoming lar to the aggregate flow and should work the entire face
aggregate to the plant site, each load should be dumped of the stockpile. This practice will minimize aggregate
gradation changes in the mix produced by the asphalt
plant.
The loader operator should be careful when cleaning
the edges of the stockpile so that yard material is not
pushed or dumped into the stockpile, contaminating the
stockpile. When loading out of a stockpile, the loader
operator should make sure that the loader bucket is in
the stockpile and not in the yardstone .
When loading from a stockpile built in layers, the
loader operator should try to get each bucket load by
entering the lower layer at the approximate midpoint of
that layer and scooping up through the overlying layer.
This results in half the aggregate being from each layer.
Figure 2-14. Layered stockpile (Asphalt Institute) . This procedure also reblends the aggregate, which , in
turn, reduces segregation . Removal of aggregate from
in a single pile as seen in Figure 2-15 . Any construction a stockpile should be planned so that a minimum
procedure that results in the aggregate being pushed or amount of aggregate is disturbed with each bucket load.
dumped over the side of the stockpile should be avoid- This is accomplished by rolling the bucket up, instead of
ed, because these practices may result in segregation . pulling or scooping the bucket up through the stockpile.
Trucks and loaders should be kept off of the stockpiles, Removal of aggregate from the bottom of a large
because they cause aggregate breakage, fines generation, stockpile of aggregate will result in the coarse aggregate
and contamination of the stockpile . rolling down the face of the pile and gathering at the
Aggregate coming off of the end of a stacking bottom and will increase the average moisture content
conveyor or radial stacker can be segregated by the of the aggregate .
wind. Aggregate being stockpiled by a stacker can also Besides working the face of the stockpile, the loader
be broken by the fall from the stacker. Segregation and operator should practice good stockpile management .
breakage can be minimized by use of a rock ladder. A good practice is to rotate stockpiles so that the first

Page 2-11
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-16. Conveyor delivery of aggregate (J. Scherocman) .

material put into the stockpile is removed first. Areas a problem because the RAP pieces will usually break
of the stockpile that are segregated should be reblended down inside the drum mixer or in the batch plant
by the loader operator at the stockpile. The operator pugmill during the heating, drying, and mixing process.
should definitely not feed one or two loads of coarse If a significant amount of large chunks of RAP (pieces
aggregate and then one or two loads of fine aggregate greater than 2 in. in size) are fed into the plant at one
into the cold-feed bins in an attempt to blend the time, however, those chunks may not be properly heated
aggregate . This type of procedure will cause significant and mixed with the new aggregates and asphalt cement.
problems in meeting the required aggregate gradation in Thus, care should be taken to assure that the RAP
the mix, no matter what type of plant is used to produce material that is fed into the plant is as consistent in
the mix. The best approach to minimizing segregation, gradation, from coarse to fine, as possible. It is often
however, is to use proper stockpiling techniques in the necessary to screen out and then crush the largest pieces
first place, instead of relying on the loader operator to of RAP to assure proper heat transfer and mixing of the
attempt to blend segregated materials adequately. reclaimed and new aggregates inside the drum mixer.
Generally, RAP should be stockpiled using the same
techniques described for new aggregate. In hotter COLD- FEED SYSTEMS FOR NEW AGGREGATES
climates, however, it may be desirable to limit the height The cold-feed systems on an HMA batch and drum
of the RAP stockpile in order to reduce the tendency mix plant are typically similar. Each consists of cold-feed
for the material to consolidate and bind back together bins, feeder conveyors, a gathering conveyor, and a
under its own weight. Typical maximum RAP stockpile charging conveyor. On most drum mix plants and on a
heights are in the range of 10 to 12 ft for mixtures few batch plants, a scalping screen is included in the
having relatively high asphalt contents. system at some point. If RAP is also being fed into the
Separation of the larger particles from the smaller plant to produce a recycled mix, an additional cold-feed
RAP pieces will typically occur more readily than with bin or bins, feeder conveyor and/or gathering conveyor,
new aggregate because the reclaimed material will scalping screen, and charging conveyor are necessary to
usually contain a greater variety of particle sizes than handle the extra material.
will individual new aggregate sizes. Normally this is not

Page 2-12
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-17. Cold -feed bin with dividers between bins (Barber-Greene) .

Cold-Feed Bins and Feed Conveyors bulkheads are used between the bins, aggregates that
The flow of aggregates through a plant begins at the should be in one bin can combine with the aggregates of
cold-feed bins, as seen in Figure 2-17 . The plant is a different size in the adjacent bin . This commingling of
equipped with multiple bins to handle the different sizes aggregate sizes can significantly alter the gradation of
of new aggregates used in the mix. Most cold-feed bins the mix being produced, particularly in a drum mix
are rectangular in shape, have sloping sides, and have a plant , where no screens are used to resize the aggregate

Bin Opening. Bin Opening


Configuration Configuration

Effective Area Effective Area

Dead Area

Figure 2-18. Cold-feed bin with rectangular opening Figure 2-19. Cold -feed bins with trapezoidal opening
(Astec). (Astec) .

rectangular (Figure 2-18) or trapezoidal (Figure 2-19) after it is dried . If bulkheads are not in place between
opening at the bottom. A bulkhead or divider should be the cold-feed bins and mixing of the different size
used between each cold -feed bin, as shown in Figure aggregates is a problem, these devices should be in-
2-17, to prevent overflow of the aggregate from one bin stalled. Care should be taken not to pile aggregate
into an adjacent bin. As seen in Figure 2-20, if no higher than the top of the bulkheads .

Page 2-13
AC 150/5370-14
Appendix 1
10/15/91

Figure 2-20. Overfilling cold-feed bins (J. Scherocman).

Each cold-feed bin is equipped with a gate to control individual conveyor is then set to determine the exact
the size of the discharge opening on the bin and a amount of each material withdrawn from the bin. If
conveyor belt to draw aggregate out of each bin at a small changes are needed in the amount of material to
controlled rate. On some plants, the speed of the be delivered from one bin, the speed of the feeder
conveyor belt under the bin is not variable. The amount conveyor can be increased or decreased to accommodate
of aggregate that is withdrawn from the bin is deter- the change. Theoretically, it is possible to withdraw
mined by the setting of the gate opening. The degree of aggregate from the bin using the full range of the belt
control exercised over the amount of aggregate with- speed, from 1 to 100 percent of the maximum belt
drawn from each bin is thus governed by the number of speed. In practice, only 20 to 80 percent of the maxi-
gate settings on each feeder gate . The size of the gate mum belt speed (ideally, 50 percent) should be used
opening is set by raising or lowering the gate by a hand when determining the size of the bin gate opening. This
or electric- powered crank or wheel, or by unbolting, will allow the plant operator some leeway to vary the
moving, and rebolting a sliding plate on one end of the production rate of the plant for changes in operating
bin. conditions without having to change the setting of the
Most cold-feed bins are equipped with variable-speed gate opening.
belt feed conveyors under each bin, as shown in Figure If a large change is needed in the feed rate for a
2-21 . The gate opening for each bin is set to deliver a particular size of aggregate, however, the gate opening
relative amount of aggregate in proportion to the at the discharge end of the bin needs to be adjusted .
amount of each aggregate needed in the mix; the more The speed setting of each belt feeder is displayed on the
of a particular aggregate required, the larger the open- operator's console in the plant control trailer and is
ing of the bin discharge gate. The speed of each typical shown as a percentage of the maximum belt

Figure 2-21 . Cold -feed bin belt feeder (NAPA).

Page 2-14
AC 150/5370-14
10/15/91
Appendix 1

O O

Figure 2-22. Discharge from cold-feed conveyor to gathering conveyor (J. Scherocman).

speed. If the feeder belt under a given cold-feed bin is Gathering Conveyor
operating at a level less than 20 percent or more than 80 As shown in Figure 2-22, aggregate deposited from
percent, the gate setting may need to be changed to each belt feeder is dropped onto a gathering conveyor
allow the belt to operate closer to the center of its speed that collects the aggregate discharged from each of the
range for the selected production rate. bins. The speed of the gathering conveyor, which is
The speed setting for each individual belt feeder is located beneath all of the individual feed conveyors, is
adjusted independently to allow the proper amount of constant. The amount of aggregate deposited on this
aggregate to be pulled from each particular bin. Once conveyor is a function of the size of the gate opening
determined, the speed of all the belt feeds is synchro- and the speed of the feeder conveyor under each cold-
nized so that a change in the speed of one belt feeder is feed bin.
proportional to the change in the speed of all the other To reduce the amount of buildup that may occur on
belt feeders. Thus, if the production of the plant is this conveyor, particularly when the various aggregates
increased from 250 to 350 tons per hour, a change in the are wet, the coarser aggregates should be placed on the
master control setting causes a corresponding propor- belt first. The sand, which typically has the higher
tional change in the speed of all the feeder belt convey- moisture content, if placed on the conveyor belt first,
ors. can stick to the belt and may need to be continually
Each cold-feed bin and its companion feed conveyor removed. This may affect the gradation of the aggregate
should be equipped with a "no flow" device that will in the mix .
alert the operator when no aggregate is coming out of
the cold-feed bin. If the bin is empty or if the aggregate Scalping Screens and Devices
has bridged over the discharge opening in the bin and On drum mix plants it is desirable to insert a scalping
no material is being discharged onto the gathering screen into the cold-feed system to prevent oversize
conveyor, the " no flow" sensor (typically a limit switch) material from entering the mixer. Scalping can some-
indicates the condition by sounding an audible alarm or times be accomplished successfully by placement of a
automatically shutting down the plant after a preset screen over the top of the cold-feed bins. In many
time. cases, however, this screen is only a grizzly-type device

Page 2-15
AC 150/5370-14
Appendix 1
10/15/91

SARBER-GREENE

Figure 2-23. Scalping screen (Barber-Greene).

with large openings. Because of the large volume of the smallest screen (the bottom screen if a double- deck
aggregate that is delivered at one time from the front- screen is being used) is typically slightly bigger than the
end loader to a cold-feed bin, a screen that has small maximum size aggregate used in the mix.
openings cannot properly handle the flow of aggregate Scalping devices can be tailored to the needs of each
from the loader bucket to the bin. Thus, scalping individual plant . Typically only a single-deck scalping
screens employed on top of the cold-feed bins are screen is used. Some plants employ a two-deck scalping
normally used only for the larger size coarse aggregate screen, which controls two different top -size aggregates
and for reclaimed material. without changing the screen (Figure 2-24) . If both
A scalping screen is most often placed somewhere screens are being used, a flop gate at the lower end of
between the end of the gathering conveyor and the the second screen is used to redirect the aggregate
drum to remove deleterious materials such as tree roots, caught on the bottom screen to the charging conveyor.
vegetable matter, and clay lumps, as well as oversize The flop gate can be operated either manually or
aggregate (Figure 2-23) . It is not normally necessary to automatically. The openings in the screen can be either
pass quarry-processed aggregates through a scalping square or slotted . The advantage of the use of the
screen, although it is always good practice to do so to slotted screen is that a smaller screen area can be used
prevent any extraneous oversize material from entering to handle a given volume of material.
the drum and the mix. A scalping screen should be used Some scalping screens are equipped with a bypass
as part of the cold-feed system on a batch plant if the chute . This allows the aggregates on the gathering
screens have been removed from the mixing tower or if conveyor to be deposited directly on the charging
The size of the openings in
the screens are bypassed . conveyor without passing through the screen. This

Page 2-16
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-24. Double-deck scalper (Astec) .

procedure is sometimes used when quarry-processed screen and onto the gathering conveyor. Oversized
aggregate or aggregate free of any deleterious material pieces are rolled down the screen into a reject chute
is fed to the plant. that deposits the aggregates in a pile for subsequent
Instead of a scalping screen at the end of the gather- disposal. Because the size of these individual-bin
ing conveyor, one make of cold-feed bins includes a scalping screens is quite small, if they become blinded or
small scalping screen under each cold-feed bin, which is clogged, the proper amount of aggregate will not pass
illustrated in Figure 2-25. The aggregate from a particu- through the screen onto the charging conveyor. Thus
lar bin falls off the belt feeder and onto the scalping the operation of such scalping screens should be moni-
screen. Properly sized material passes through the tored on a regular basis.

C
CHATTANOOGATE
AS , TENNESSEE USA

Figure 2-25. Individual scalping screen under each bin (Astec) .

Page 2-17
AC 150/5370-14
Appendix 1
10/15/91

Figure 2-26. Charging conveyor with weigh bridge system (J. Scherocman).

Charging Conveyor constant speed that is independent of the other con-


Batch Plants veyors. The weigh bridge itself is located near the
The combined coarse and fine aggregates are dis- midpoint of the charging conveyor.
charged from the gathering conveyor onto the charging A weigh idler, as seen in Figure 2-27, is the heart of
conveyor for transport to the drum. For a batch plant, the weigh bridge system. This idler is different from the
this conveyor delivers the aggregate to the inclined chute fixed idlers on the conveyor frame. It is free to move
at the upper end of the dryer. The charging conveyor is WINDSHIELDS LOAD CELL
a simple belt that operates at a constant speed but BELT GUIDES WEIGH IDLER
FOR CONSTANT
carries a variable amount of aggregate, depending on the ALIGNMENT
volume of aggregate delivered from the cold-feed bins.
The conveyor should normally be equipped with a device
(scraper blade or brush) to clean off the belt as it
revolves.

GRAVITY TAKE UP
Drum Mix Plants FOR CONSTANT BELT
TENSION AND SCALE
For a parallel-flow drum mix plant, the charging ACCURACY
conveyor carries the aggregate to a charging chute above
the burner on the drum or to a slinger conveyor under
the burner. From one of these two entry points, the BELT SPEED SENSOR
aggregates are introduced into the mixing drum . For Figure 2-27. Weigh bridge idler and gravity take up
this type of plant, the charging conveyor contains a (Barber-Greene).
weigh bridge system (shown in Figure 2-26) that mea- and is attached to a load cell. As the aggregates pass
sures the amount of aggregate, in tons per hour, being over the weigh idler, the weight of the material is
fed to the drum mixer. The weigh bridge, or belt scale , recorded as an electrical signal in the computer control
determines the weight of aggregate passing over the system . The weight value by itself is meaningless,
weigh idler. The charging conveyor operates at a however, because it covers only an instant of time. Thus

Page 2-18
AC 150/5370-14
10/15/91
Appendix 1

the charging conveyor is also equipped with a belt speed Individual-Bin Weigh Bridges
sensor, as shown in this same figure . This device , On a few plants, the individual cold-feed bins may be
usually located on the belt takeup pulley, is a tachome- equipped with weigh bridge systems located on the
ter, which, coupled with the diameter of the pulley, individual-belt feeder conveyor. For this type of setup,
measures the actual speed of the conveyor belt. the conveyor belt under each individual cold-feed bin
To obtain an accurate belt speed reading, it is essen- must be longer than belt feeders without the weigh
tial that the charging conveyor belt be tight around the bridge . Usually a plant with individual cold -feed weigh
gravity takeup pulley, as shown in Figure 2-27. Any bridges will not have a weigh bridge installed on the last
slippage of the belt over the speed sensor will result in feeder conveyor closest to the drum mixer. Another
an erroneous reading and an incorrect wet aggregate standard weigh bridge is installed on the charging
weight input value to the drum mixer. Some conveyors conveyor. This latter system provides data on the
are equipped with an air-actuated takeup system that is combined weight of all the aggregates, the same as the
located on the tail shaft pulley and operates in a manner weigh bridge system on most drum mix plants.
similar to the gravity takeup system. Its purpose is to The plant computer and controls are able to display
keep the belt tight and eliminate the potential problem the amount of aggregates pulled from each cold-feed
of inaccurate belt speed sensor readings. bin. The amount of material delivered from the bins
The information from the weigh idler on the belt equipped with individual weigh bridges is read directly,
scale and from the belt speed sensor is combined to after the amount of moisture in each aggregate fraction
determine the actual weight of aggregate, in terms of is deducted . The weight of aggregate discharged from
tons per hour. This value is the wet weight of the the last bin is determined by subtracting (by use of the
aggregate and includes the moisture in the aggregate. computer) the amount of aggregate weighed by the
The wet weight of this material is converted to dry individual feeders from the total aggregate weight
weight by the plant computer in order to add the proper measured by the weigh bridge located on the charging
amount of asphalt cement to the mix, using a manual conveyor, adjusted for moisture content .
input of the average moisture content in the combined
coarse and fine aggregates. COLD-FEED SYSTEMS FOR RECLAIMED ASPHALT
The moisture content of each of the aggregates being PAVEMENT
fed into the plant should be checked regularly and the The cold-feed system for handling RAP is essentially
average amount of moisture in the incoming aggregate the same as the conventional cold-feed system for new
determined . The determination should be made when- aggregates . On most plants, as shown in Figure 2-28,
ever the moisture content of the aggregate stockpiles has this is done through the use of a separate cold -feed bin.
·
changed, such as after a rain, or a minimum of twice a The bin (or bins) is similar to the cold -feed bins used for
day. This frequency can be reduced to a minimum of new aggregates except that all four sides of the RAP
once a day during periods of consistent dry weather feed bins are usually much steeper. The steeper sides
conditions. allow the asphalt-coated aggregates to be discharged
If the aggregates being carried on the belt are rela- from the bins more easily. This is particularly important
tively dry, all the aggregates that pass over the weigh in hot weather, when the RAP can become sticky. The
bridge will enter the drum. If the moisture content of steeper sides reduce the tendency of the reclaimed
the aggregate is high, however, some of the fine aggre- material to bridge the opening at the bottom of the bin.
gate may stick to the charging conveyor belt. This If a separate cold-feed bin arrangement is used for
"extra" material will not be fed into the drum, but will the reclaimed material, there is normally a variable-
remain on the belt. If not removed by a scraper, the speed belt conveyor under each bin . The bins are also
additional material will continually be detected by the provided with a gate that can be set at various openings.
weigh bridge and the plant computer will calculate a The RAP, typically delivered to the bin by front-end
greater weight of aggregate entering the drum than is loader, is discharged onto the feeder conveyor. If only
actually occurring. This will cause the computer to one cold-feed bin is used, the RAP on the feeder
signal the asphalt pump to deliver additional asphalt conveyor is transferred to a charging conveyor. If more
cement to the plant to compensate for the additional than one cold-feed bin is employed, the feeder conveyor
aggregate. Thus the belt scraper or brush should be in under each bin delivers the RAP to a gathering convey-
place, continually cleaning the charging conveyor belt as or and then to the charging conveyor. The RAP then
it carries aggregates to the mixing drum. should be passed through a scalping screen to remove

Page 2-19
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-28. RAP bin (J. Scherocman).

any oversized pieces of asphalt mixture or deleterious delivered to the boot (bottom) of the hot elevator, to
material. An alternative setup is to place a scalping one of the hot bins at the top of the plant, or to the
screen or fixed-bar grizzly over the cold-feed bin itself weigh hopper. If the reclaimed material is being trans-
and thus remove any oversize and foreign material ported to a drum mix plant, the charging conveyor will
before it enters the bin. Another alternative setup is to be equipped with a weigh bridge system that measures
place a small crusher in the system between the cold- the weight of the material passing over it as well as the
feed bin and the charging conveyor to reduce the size of speed of the belt itself. This weight, in tons per hour,
any oversize RAP pieces. includes the moisture in the RAP. The average mois-
After exiting the scalping screen, the RAP is dropped ture content value is manually input into the plant
onto the inclined conveyor for transport to the plant. If controls and the dry weight of the RAP calculated by
it is being carried to a batch plant, the material can be the plant computer. The information determined from

Figure 2-29. RAP & virgin feed bins (J. Scherocman).

Page 2-20
AC 150/5370-14
10/15/91
Appendix 1

the weigh bridge system on the RAP charging conveyor direction, as illustrated in Figure 2-30 . The gathering
is combined with the data from the new aggregate weigh conveyor under the feeder belts for the new aggregate
bridge system to determine the plant input tonnage. carries this material to a charging conveyor moving to
the burner end of the drum mix plant. The gathering
Single-Feed Drum Mix Plants conveyor under the feeder belts for the reclaimed
A very limited number of drum mix plants have only aggregate transports the RAP to a separate charging
one set of cold-feed bins. Some of the bins are used to conveyor that carries the RAP to an inlet location near
hold the new aggregates and the other bins are used to the midpoint of the mixing drum length.
handle the RAP, as shown in Figure 2-29. For one type Regardless of what cold -feed bin system is used for
of plant, the new and reclaimed aggregates are both fed the RAP, a weigh bridge and speed sensor are employed
at the same time into the burner end of the drum mix to measure the amount of reclaimed material moving up
plant. In this case, the RAP is handled exactly like the the charging conveyor and into the drum. Although
new aggregates . It can be deposited underneath or on using the same cold-feed bin system to handle both new
top ofthe new aggregates, depending on which cold-feed and reclaimed asphalt pavement saves the cost of a
bins are selected to hold the asphalt-coated aggregates. separate cold-feed bin or bins for the RAP, the chance
The reclaimed material is often deposited on top of the of bridging the opening at the bottom of the bin increas-
new aggregate so that it can be exposed to a water spray es because of the shallower angle of the sides of the
(used to reduce potential emission problems) when conventional cold-feed bins.
traveling up the charging conveyor .
ADDITION OF HYDRATED LIME
Split-Feed Drum Mix Plants In order to reduce the occurrence of moisture dam-
Most parallel-flow drum mix plants are equipped age, hydrated lime is sometimes added to the mix at a
with a split-feed system to handle the RAP. Typically, rate of 1 to 2 percent by weight of aggregate. This
a separate cold-feed bin and conveyor system is used to material may be added in one of two different forms: as
feed this material into the drum mixer through a rotary a dry powder or as a slurry. If it is used as a slurry, it is
center inlet. On some plants, however, a separate cold- typically proportioned as one part hydrated lime to three
parts water. The lime can be added by mixing it with
the aggregate on the cold-feed belt or by introducing it
Feeding Four Virgin Materials into the rear of the drum similar to a conventional
mineral filler. When the hydrated lime is added in dry
form to the aggregate, the specifications usually require
that the moisture content of the combined coarse and
fine aggregate be at least 3 percent to assure that the
Feeding Three Virgin & One Recycle lime is adequately attached to the aggregate particles as
the aggregate enters the drum mixer. The addition of
lime as a mineral filler is discussed in Section Four.
The dry lime or slurry is added to the aggregate as it
moves along the gathering conveyor or up the charging
Feeding Two Virgin & Two Recycle conveyor. The lime is normally placed on top of the
aggregate and then is mixed with the aggregate using
one of several different methods. That mixing may take
place when the aggregate passes through the scalping
screen, through a set of plows or mixing paddles on the
belt, or in an in-line pugmill placed in the cold -feed
Figure 2-30. Feeding virgin and reclaimed aggregate
(Astec). system between the gathering conveyor and the charging
conveyor.
feed bin is not used for the reclaimed material. In this
case, the material is placed in one or more of the CALIBRATION
conventional cold-feed bins. The gathering conveyor The rate of aggregate flow from a cold-feed bin
under the bin or bins is modified, however, by dividing should be determined to ensure that the proper propor-
it into two different belts, each moving in a different tion of each aggregate is delivered from the bin to the

Page 2-21
AC 150/5370-14
Appendix 1 10/15/91

plant to obtain the proper gradation for the mix. The drawn from the cold-feed bin and delivered , usually by
method used to calibrate the cold -feed bins depends on means of a diverter chute on the charging conveyor , into
the type of plant being used and on the type of feed the truck. After a set period of time, the flow of the
conveyor under each bin. aggregate is stopped and the truck is weighed to deter-
Each cold-feed bin should be calibrated at a flow mine the amount of aggregate delivered . For cold- feed
volume that will be within the range of material that will bins equipped with only a constant-speed feeder belt, the
be delivered from the bin during mix production . weighing process is accomplished for a variety of gate
Ideally, the bin should be checked at rates that are opening settings. For cold-feed bins that are equipped
approximately equal to 20 percent, 50 percent, and 80 with variable -speed feeder belts, the calibration process
percent of the estimated operational flow rate . is repeated at different gate opening settings as well as
If a cold-feed bin is equipped with a constant-speed at at least three different belt speeds per gate opening.
feeder belt, the only way to change the amount of On a drum mix plant, the weigh bridge must also be
aggregate delivered from the bin is to vary the size of calibrated . This is accomplished by running aggregate
the gate opening. In this case, the size of the gate over the weigh idler for a given period of time. Instead
opening at which the calibration procedure is conducted of being delivered to the drum mixer, the aggregate is
depends on the proportion of aggregate to be drawn out diverted into an empty, tared truck. After the selected
of the bin. If, according to the mix design information, time period has passed, the aggregate flow is terminated
25 percent of the total amount of the aggregate needed and the amount of aggregate in the truck is measured by
in the asphalt mix should come out of one bin, that bin weighing the truck. The weight determined is compared
should be calibrated at the gate opening size that will with the weight of aggregate calculated by the plant
typically provide that rate of flow. In addition, the computer system . To be correct, the two weights should
calibration procedure should be completed at both the be within the tolerance band set by the particular
next larger and the next smaller gate setting to allow for government agency and typically within 1.0 percent of
small changes in production rate. If significant changes each other (assuming that the weigh bridge is accurate
in production rate are anticipated, the cold-feed bins to 0.5 percent and that the truck scale is also accurate to
should be calibrated at whatever gate openings are 0.5 percent).
needed to provide the proper amount of that size For many drum mix plants, the weigh bridge should
aggregate to the plant . be calibrated at a production rate that is near the esti-
Many cold-feed bins on batch plants and the vast mated normal production rate for the plant. If the
majority of the cold-feed bins on drum mix plants are drum mixer is going to run at 90 percent of capacity, the
equipped with a variable-speed feeder belt in addition to calibration of the weigh bridge should be completed at
a means to change the size of the gate opening under three production rates: 70 , 85, and 100 percent of
the bin. The gate opening on the cold-feed bin should capacity. This calibration, however, will probably not be
be set at a level to deliver the proper amount of aggre- correct if the plant is run at a much lower capacity, such
gate at the desired plant production rate. In addition , as 60 percent. In this case, the calibration procedure
the bin should also be calibrated at three different should be repeated at the lower production rate (brack-
feeder belt speeds: 20 percent, 50 percent, and 80 eting the estimated rate with one rate above and one
percent of the range of speed of the feeder belt. The rate below the most probable production level) .
best operating conditions for the cold-feed bin would be Because of the differences in the operating proce-
to provide the proper amount of aggregate from the dures of different makes and models of cold-feed bins
preset gate opening with the feeder belt operating at 50 and asphalt plants, it is difficult to generalize the exact
percent of its maximum speed. This would permit the calibration procedure that should be used . The calibra-
plant operator some latitude to increase or decrease the tion instructions provided with the plant should be
production rate of the plant without having to change followed .
the setting of the gate opening at the bottom of the
cold-feed bins. SUMMARY OF AGGREGATE HANDLING OPERAT-
The calibration of each cold - feed bin is accomplished ING TECHNIQUES
by drawing aggregate out of a bin for a specific period Several key items should be monitored when viewing
of time and determining the weight of the aggregate the handling of new and reclaimed aggregates, both in
delivered in that time interval. In most cases, a truck's the stockpiles and when being fed into a batch or drum
empty (tare) weight is determined . Aggregate is with- mix plant. They are:

Page 2-22
AC 150/5370-14
10/15/91
Appendix 1

• The stockpiles should be built on a clean, dry, and plant operator when inadequate aggregate is being
stable foundation. Positive drainage for each pile should delivered from a cold-feed bin.
be provided. Aggregate of different sizes should be • Ifthe plant is equipped with variable-speed feeder
stockpiled separately from one another. conveyors, those conveyors should be run at a speed that
• The moisture content of each aggregate should be is between 20 percent and 80 percent of the maximum
determined at least twice each day, and more often if belt speed . Ideally, the speed of the feeder conveyor
moisture conditions change. The average moisture should be in the middle of the speed range to allow for
content of the incoming aggregate to the plant dryer or small increases and decreases in plant production
drum mixer should be inputted into the plant control capacity without the necessity of changing the cold-feed
system in order to permit proper setting of the burner bin gate-opening settings. The feeder conveyor should
controls, to calculate the dry weight of the incoming be calibrated at the speed at which it will typically run.
aggregate, and to determine the plant production rate. • A scalping screen should be placed in the cold-
To reduce the moisture content of the aggregate in the feed charging system of a drum mix plant or a batch
stockpiles, covering of the aggregate piles--particularly plant operated without screens to remove any oversize
the fine aggregate--with a roof should be considered . and deleterious material from the aggregates.
• Stockpiles should be built in horizontal or gently • For drum mix plants, the weigh bridge should be
sloping layers. Any stockpiling procedure that results in checked to see if the weigh idler is free to move and
aggregate being pushed or dumped over the side of a that the conveyor belt is tight around the gravity takeup
stockpile should be avoided in order to prevent segrega- pulley to assure an accurate belt speed sensor reading.
tion. Travel on stockpiles by trucks and front-end • The cold-feed bin(s) used for RAP should have
loaders should be minimized to prevent aggregate steep sides to prevent the material from bridging the
breakage and the generation of fines. gate opening at the bottom of the bin.
⚫ The front-end loader should work the full face of • The reclaimed aggregate feed system, both on a
the stockpile, removing the aggregate in a direction batch and on a drum mix plant, should include a scalp-
perpendicular to the flow of the aggregate into the ing screen over the cold-feed bin or at some other point
stockpile . The front-end loader operator should go in the material flow process .
straight into the stockpile, roll the bucket up, and then • Cold-feed bins should be calibrated . For bins
back out instead of scooping up through the stockpile. equipped with constant-speed feeder belts, the flow of
This will minimize segregation caused by the larger-size aggregate from the bins should be determined at three
aggregate rolling down the face of the stockpile . The different gate opening settings : one at the plant produc-
front-end loader operator is the key in providing a tion rate, one greater than the estimated rate , and one
consistent proportion of material to the plant and in lower than the estimated production rate.
minimizing segregation. • For cold-feed bins equipped with variable-speed
• Ifthe coarser aggregate stockpiles are segregated , feeder belts, the bins should be calibrated at three
the loader operator should not place one bucketful of different gate openings as well as at three different belt
coarse material and then a bucketful of finer material in speeds. The belt speeds should be approximately 20
the cold-feed bin. The segregated materials should be percent, 50 percent, and 80 percent of the range of the
blended by the loader (or by other means) before the possible belt speeds .
material is introduced into the cold-feed bins. • The weigh bridge on the charging conveyor of a
• Cold-feed bins that are kept relatively full of drum mix plant must also be calibrated . This should be
aggregate should be separated by a bulkhead between accomplished by collecting and weighing the amount of
each bin at the top of the bins so that aggregate that is aggregate that passes over the weigh bridge in a set
supposed to be in one bin cannot overflow into an amount of time and comparing that weight with the
adjacent bin. weight determined by the plant computer system. For
• The discharge end of the feeder conveyor should the weigh bridge to be calibrated properly, the two
be equipped with a "no flow" device to indicate to the weights should be within 1.0 percent of each other.

Page 2-23
AC 150/5370-14
Appendix 1 10/15/91

SECTION THREE
ASPHALT CEMENT SUPPLY SYSTEM

INTRODUCTION A lesser-used style of asphalt cement storage tank is


This section discusses the asphalt cement supply the "direct fired" tank. In this system, the asphalt cement
system, which consists of two major parts. The first is heated by direct heat exchange from the combustion
includes one or more storage tanks to store the asphalt source through a series of heat tubes to the asphalt
cement until it is needed by the mixing plant. The cement. Care needs to be used with this type of tank to
second is a pump and meter system used to draw asphalt prevent overheating of the asphalt cement immediately
cement from the storage tank in proportion to the adjacent to the heat tubes.
amount of aggregate being delivered to the batch plant All storage tanks should be completely insulated and
pugmill or drum mixer. heated, and all the lines for both asphalt cement and
heating oil should be insulated to prevent loss of heat .
STORAGE TANKS Both the line used to fill the tank from the asphalt
All asphalt cement storage tanks, as shown in Figure cement transport truck or rail car and the discharge line
2-31 , must be heated to properly maintain the correct from the tank to the plant should be located near the
temperature of the asphalt cement to assure that its bottom of the tank. The return line from the pump
viscosity is low enough so that it can be pumped and
mixed with the heated and dried aggregate. Most asphalt
cement storage tanks are heated with a hot oil system
and are equipped with a small heater to heat and main-
tain the temperature of the heating oil . The hot oil is
circulated through a series of coils inside the asphalt
cement storage tank, as shown in Figure 2-32, and the
heat is then transferred from the oil, through the coils ,
to the asphalt cement . This heat-transfer process reduces
the viscosity of the asphalt cement, causing it to flow
upward and circulate , and causing new, lower-tempera-
ture asphalt cement to come in contact with the heating
coils. Thus, the hot oil system, through a set of thermo-
couples and solenoid valves, maintains the proper
temperature of the asphalt cement, generally in the
range of 300°F to 350°F, depending on the grade and
type of asphalt cement being used .
Figure 2-32. Finned hot-oil tubes (Heatec).

KSATEC

HEATED

Figure 2-31 . Asphalt cement storage tank (Heatec).

Page 2-24
AC 150/5370-14
10/15/91
Appendix 1

should be located so that the asphalt cement enters the PUMP AND METER SYSTEM
tank at a level beneath the surface level of the asphalt Batch Plants
cement stored in the tank and does not fall through the For batch plants, two different systems typically exist
air. This will reduce the oxidation of the asphalt cement to transfer asphalt cement from the storage tank to the
during the circulation process. weigh bucket near the pugmill . The type of system
If the HMA plant is equipped with more than one depends on the location of the return line: whether one
asphalt cement storage tank, the capability should exist or two asphalt cement lines are present from the pump
to pump material from one tank to another. It is impor- to the weigh bucket.
tant that the plant operator know from which tank In the single-line process, as shown in Figure 2-33,
material is being pulled, especially if more than one two lines extend from the storage tank to the pump , but
grade or type of asphalt cement is being stored in only one line extends from the pump to the weigh
different tanks. bucket. The pump is a constant-volume, constant-speed
All asphalt cement storage tanks contain a "heel" of unit that runs continuously. Asphalt cement is always
material at the bottom of the tank. This asphalt cement, being pulled from the storage tank through the pump
located beneath the heating coils, usually does not and circulated back to the tank. When asphalt cement
circulate efficiently. The volume of material in the "heel" is needed in the weigh bucket, a valve on the end of the
depends on the type and style of the storage tank, the line at the top of the weigh bucket opens and material
location of the heating coils, and the amount of time is discharged into that bucket. When the proper amount
since the tank was last cleaned . It is recognized, howev- of asphalt cement is in the bucket, determined by weight
er, that some asphalt cement will typically remain in the (not volume), that valve is shut and a pressure relief
bottom of an "empty" tank. It is possible, therefore, that valve at the pump is opened. The asphalt cement then
placing asphalt cement of one type or grade into a tank passes through the pump but is recirculated back to the
that previously contained a different type or grade can storage tank, in the second line, instead of being sent to
cause an alteration of the properties of the asphalt the plant . A variation of this system allows the asphalt
cement to the point at which it no longer meets specifi- cement to circulate through the pump itself instead of
cations. being returned back to the storage tank.
The capacity of an asphalt cement storage tank can In the dual-line process, one line is used to deliver
be calculated from its diameter and length measure- asphalt cement to the weigh bucket and the second line
ments. The amount of material in the tank can be is used to return the "excess" asphalt cement back to the
determined using a tank "stick." The stick measures the storage tank. The asphalt cement passes through the
distance from the top of the dome or the top of the tank pump to a three-way valve at the bucket. When asphalt
down to the level of the asphalt cement in the tank (the cement is needed in the weigh bucket, the valve opens
point at which the tank stick just touches the top of the and the material is discharged into the bucket. When
material) . This distance is noted and the capacity of the the preselected weight is reached, the valve closes and
asphalt cement remaining in the tank below this level is the asphalt cement is recirculated in the second line
determined from the tank manufacturer's calibration back to the storage tank.
chart. Because the amount of asphalt cement used in most
When asphalt cement is delivered from a transport batch plants is measured by weight, no correction is
vehicle into a storage tank, it is very important to ensure needed for the temperature of the asphalt cement . On
either that the tank is clean or that it already contains a few old batch plants, however, the amount of asphalt
the same type of material as is being pumped into the cement delivered is determined by volume. In this case,
tank. If the tank is empty at the time the new material the amount of asphalt cement delivered to the pugmill
is being added, the tank should be checked to ensure must be corrected, based on both the temperature and
that no water has accumulated in the bottom. If asphalt the specific gravity of the asphalt cement. This can be
cement is loaded on top of an asphalt emulsion or on accomplished using the procedure given in ASTM
top of a layer of water in the tank, violent foaming of Specification D 4311 .
the asphalt cement will occur, creating a very severe
safety problem. Care should be taken to assure that all Drum Mix Plants
valves are in the proper position to prevent pressure Asphalt Cement Delivery
from building up in the lines and causing an explosion For most drum mix plants, three different systems
and possibly severe burns . exist to pull the asphalt cement from the storage tank,

Page 2-25
AC 150/5370-14
Appendix 1 10/15/91

C
A TE
PE

Figure 2-33. AC single-line circulating system (Heatec) .

meter it, and pump it to the plant . Those three pro- the asphalt cement to be recirculated back to the tank
cesses include: (a) a constant-volume pump with a when it is not needed by the plant.
variable-speed motor, (b) a constant-volume pump with The third system consists of a constant-volume pump
a constant-speed motor with a metering valve, and (c) a driven by a constant-speed motor. In this setup, the
variable-volume pump with a constant-speed motor. same volume of asphalt cement is pulled from the
The use of a particular pump and meter system is storage tank at all times. A proportioning valve is
dependent on the make, model, and date of manufacture placed in the line between the pump and the asphalt
of the plant and on the choice made by the individual cement meter. The position of the valve determines the
plant owner. volume of material sent through the meter. The propor-
For the system that uses a variable-volume pump
REGISTER
driven by a constant-speed motor, the amount of asphalt
cement pulled from the storage tank is controlled by -PULSER
VARIABLE VOLUME
changing the volume of asphalt cement being pumped . POSITIVE DISPLACEMENT SPRAY/CIRCULATE
PUMP VALVE
The volume needed at the pump is determined by the
METER
plant computer in proportion to the amount of aggre-
gate being fed into the plant. As the amount of aggre-
gate entering the drum mixer increases, the volume of
asphalt cement pulled through the pump also increases.
When the plant is not using asphalt cement, the material
continually passes through the pump and meter and PUMP
ADJUSTER
through a three-way valve that is set to circulate the
asphalt cement to the storage tank instead of to the -Interlocked to aggregate flow
-Feed back loop control for constant
plant. This process is shown in Figure 2-34.
monitoring.
A second system incorporates a fixed-displacement
(constant -volume) pump driven by a variable-speed Figure 2-34. Schematic asphalt pump system (Bar-
motor. The quantity of asphalt cement delivered to the ber-Greene) .

meter is varied by changing the speed of the variable- tioning valve sends some of the asphalt cement through
speed motor. The amount of material sent to the plant the meter and the rest back through the recirculating
is also dependent on the aggregate feed rate. A three- line to the storage tank. The system also has a valve
way valve in the system downstream of the meter allows downstream of the meter that allows the asphalt cement

Page 2-26
AC 150/5370-14
10/15/91
Appendix 1

sent through the meter to be recirculated to the tank. aggregates, and reclaimed aggregates, if used) and the
This valve is used during the warm-up period for the asphalt cement weight provides the production rate for
meter and during the calibration process. Again, the the drum mixer, in tons of HMA per hour. The asphalt
position of the proportioning valve is determined by the pump system is time delayed so that the asphalt cement
aggregate feed rate into the drum mixer, both of which increase or decrease reaches the drum at the same time
are controlled by the plant computer. that the increased or decreased material flow reaches
that point in the drum.
Temperature Compensation
Asphalt cement expands when heated. Thus the ADDITION OF LIQUID ANTISTRIP MATERIALS
volume of asphalt cement at 325°F will be somewhat Liquid antistrip additives are typically added to the
greater than its volume at 275°F. This latter volume will asphalt cement to improve the adhesion of the binder
be more than the volume at 60°F, which is the standard material to the surface of the aggregate . The additives
temperature for determining the volume of asphalt can be placed in the asphalt cement at several different
cement using conversion charts that are based on the locations. The additive can be in-line blended with the
specific gravity of the asphalt cement. If the specific asphalt cement as that material is pumped out of the
gravity of the asphalt cement and its temperature are tank truck or tank car and into the tank. The additive
known, the volume measured at the elevated tempera- can also be added to the asphalt cement in the tank,
ture can easily be converted to the "standard" volume at
60°F using the procedure given in ASTM Specification
D 4311.
The volume of asphalt cement moving through the
meter changes with temperature. Some meters are set
to measure the temperature of the asphalt cement
moving through the system and send that information
together with the volume data to the plant computer.
The specific gravity of the asphalt cement is set manually
on the controls. The computer then calculates the
volume of asphalt cement being fed into the plant at the
standard temperature of 60°F and converts that amount
to a weight that is displayed on the plant console.
On some meters, a temperature-compensating device,
as shown in Figure 2-35, is installed directly on the
meter stand itself. As the temperature of the asphalt
cement changes, the meter senses the change and, based
on the specific gravity of the asphalt cement, calculates
the volume of asphalt cement, at 60°F, passing through
the meter. This corrected volume (and corresponding
Figure 2-35. Temperature- compensating meter (Bar-
weight) is then sent to the plant console for display.
ber-Greene).
Regardless ofthe system employed, the asphalt pump
system must be capable of changing the volume of
asphalt cement sent through the meter in direct re- with the two different materials circulated together for

sponse to the demand of the aggregate supply. The a period of time before the treated asphalt cement is
response of the pump system must be directly related to sent to the drum mixer. The most common method,
the change in the amount of material measured by the however is to add the liquid antistrip material to the
aggregate weigh bridge system. In addition, the volume asphalt cement, using an in-line blender, as the binder
of asphalt cement measured at any given temperature material is pumped from the storage tank to the rear of
the drum mix plant.
must be converted to the volume of asphalt cement at
60°F. At this standard reference temperature, the
weight ofthe asphalt cement can be determined in terms CALIBRATION

of tons of material per hour, the same as for the aggre- The pump and meter system on the batch or drum
gate feed rate. The total of the aggregate input (new mix plant needs to be calibrated to assure that the

Page 2-27
AC 150/5370-14
Appendix 1 10/15/91

proper amount of asphalt cement is being delivered to kept at a constant temperature, normally between 300°F
the mix. For a batch plant operation, the amount of and 350°F. The tank should be properly insulated . All
asphalt cement needed is measured by weight (although hot oil lines should be insulated and the asphalt cement
a few older batch plants measure the asphalt cement by lines jacketed and insulated.
volume) by placing the asphalt cement in the plant • The asphalt cement fill line, discharge line, and
weigh bucket. For a drum mix plant, the amount of recirculation line should all enter the tank so that the
asphalt cement is measured by volume as it is pumped asphalt cement added or removed from the tank is
through a meter into the rear of the drum. charged or discharged below the surface of the material
For a drum mixer, the amount of asphalt cement is in the tank .
calibrated by pumping the material into an empty con- • The volume of asphalt cement in the tank must
tainer, the tare weight of which is known . Most often, be converted to a standard volume at 60°F when a tank
an asphalt distributor truck is used for this purpose. stick check is made of the amount of material in the
The actual weight of the material delivered to the tank.
container is determined . The weight of the material that • The amount of asphalt cement used in a batch
the metering system indicates has been delivered is then plant is measured by weight so that no volume correc-
determined by multiplying the corrected volume deliv- tion for temperature is needed .
ered from the meter totalizer by the specific gravity of • A correction for temperature must be made for
the asphalt cement . With some systems, this calculation the volume of asphalt cement passing through the
is done automatically. The actual weight is compared asphalt cement meter on a drum mix plant if the meter
with the metering system-calculated weight. The values is not equipped with an automatic temperature-compen-
should be within the required tolerance band (typically sating device. The correction is based both on the
1.0 percent) for the asphalt cement supply system to be actual temperature of the asphalt cement and its specific
in proper calibration. gravity at 60°F.
• The asphalt cement supply system should be cali-
SUMMARY OF ASPHALT CEMENT SUPPLY OPER- brated by weighing the amount of material delivered in
ATING TECHNIQUES a known amount of time. The "corrected" amount is
The asphalt cement supply system, composed of the determined in conjunction with the knowledge of both
storage tank and the pump/meter system, should be the temperature and the specific gravity of the asphalt
checked as follows: cement.
• The asphalt cement in the storage tank should be

Page 2-28
AC 150/5370-14
10/15/91
Appendix 1

SECTION FOUR
DRUM MIX PLANT

INTRODUCTION leakage air, (c) percent casing (shell) loss, (d) fan gas
This section is concerned with the processing of the temperature, (e) percent moisture removed from the
aggregate and the asphalt cement inside the parallel-flow aggregate, (f) mix discharge temperature, (g) use of
drum mixer. It reviews the methods used to introduce No. 2 fuel oil, and (h) the specific heat of the aggregate.
the aggregate into the drum. The operation of the The maximum output for the burner under these
burner is discussed, along with the three-step heating, conditions can be found on the rating plate attached to
drying, and heating process that occurs as the aggregate each burner. The actual operating conditions for the
moves down the drum. The importance of the veil of burner may be different from the conditions used to rate
aggregate across the whole cross section of the drum is the burner, however.
stressed. The methods for introducing the asphalt
cement into the drum and onto the aggregates are
considered, as well as the systems used to deliver both
mineral filler and/or baghouse fines into the drum.
The addition of RAP into the drum, primarily by use
of a split-feed system for the new aggregate and the
RAP, is discussed . Information is provided on the
factors that affect the production rate of the plant .
Finally, the relationship between the mix discharge
temperature and the exhaust gas temperature as it exits
the drum is analyzed in order to determine the efficiency
of the heat-transfer process inside the drum mixer.

AGGREGATE ENTRY
One of the two ways to introduce new aggregate
from the charging conveyor is by means of a charging
chute located above the burner. The aggregate is
delivered into a sloped chute and slides by gravity into
the drum. The chute, shown in Figure 2-36, is angled to
push the aggregate away from direct contact with the
Figure 2-36. New aggregate feed through charging
burner flame and toward the rear of the drum.
chute (Cedarapids).
The aggregate can also be deposited on a slinger
conveyor belt that is located beneath the burner, as
illustrated in Figure 2-37. On some plants, the speed of
this conveyor can be changed and is often increased Fuel

when a combination of new aggregate and RAP is being Most burners are designed to burn more than one
fed into the burner end of the plant. The greater speed type of fuel with only minor changes in the burner
of the slinger conveyor allows the combined aggregate to settings. Three types of fuel are used: gaseous, liquid,
be deposited farther down the drum, away from the and solid. Gaseous fuels include both natural gas and
flame. liquid petroleum gas. Liquid fuels include propane,
butane, No. 2 fuel oil, heavy fuel oil (Nos. 4 through 6) ,
BURNER SYSTEM and reclaimed oil. Pulverized coal and pelletized

The burner provides the heat necessary to dry and biomass are examples of solid fuels.
raise the temperature of the aggregate. Burners are The fuel selected should be at the proper consistency
rated by a Uniform Burner Rating Method that is based for complete atomization at the time of combustion .
on eight criteria: (a) percent excess air, (b) percent No. 2 fuel oil will burn at ambient temperatures, without

Page 2-29
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-37. New aggregate feed through slinger conveyor (J. Scherocman).

preheating, because it has a viscosity less than 100 the coarser aggregate particles, resulting in the forma-
saybolt seconds universal (ssu) . For proper atomization, tion of a brown stain on the aggregate and a reduction
heavy fuel oil, such as No. 5 or No. 6, must be preheat- of the film thickness of the asphalt cement on those
ed before burning to reduce the viscosity below 100 ssu surfaces. These two problems can affect the stiffness
in order to atomize the fuel properly for complete and the stability of the asphalt mix produced by the
combustion of the fuel. Some reclaimed oil, which has asphalt plant.
been filtered and dewatered, burns well. Other re- Unburnt fuel problems can be recognized in several
claimed fuel, contaminated with heavy metals, hazardous ways. A flame eye, which is an electronic device used to
waste, and/or water, burns erratically and incompletely sense the color of the burner flame, can be employed to
and generally should not be used in an HMA plant monitor the hue of the burner flame and shut down the
burner. Incomplete combustion is not normally a burner if the color is not proper to indicate complete
problem when gaseous fuels are used. combustion of the fuel. A uniform, constant roar from
Unburnt fuel can cause difficulty with the burner, the the burner is usually a good sound (although it is
plant, and the mix, and is a waste of money as well. It possible to have a problem with unburnt fuel even when
can cause clogging of the burner nozzle, difficulties in the noise of the burner is constant) . A " coughing,"
lighting the burner, and increased maintenance costs. "sputtering," "spitting" burner provides an indication of
Incomplete combustion can result in unburnt fuel enter- possible incomplete combustion of the fuel. If fuel is
ing the emission-control equipment: coating and blinding condensing on the filter bags, the pressure drop across
the filter bags in a baghouse (increasing the opportunity the baghouse will increase and the bags will be stained
for a baghouse fire) or covering the wastewater pond with fuel. When a wet-scrubber system is used, the
surface with fuel if a wet-scrubber system is used. It water in the wastewater pond surface will be covered
also reduces the amount of heat available to dry the with an oil sheen.
aggregate, and thus increases fuel consumption and
operating costs. Further, it can lower the temperature Burners
of the exhaust gases, which can result in condensation in The primary function of the burner is to blend the
the baghouse. proper amounts of air and fuel together to obtain com-
Unburnt fuel can change the properties of the HMA. plete combustion of the fuel. Two primary types of
First, the fuel can reduce the viscosity of the asphalt burners are used on aggregate dryers and drum mixers.
cement binder material and reduce the amount of Most plants are equipped with a burner that requires
hardening that the binder undergoes during the mixing from 30 to 45 percent of the air needed for combustion
process. It can also impinge directly on the surface of to be forced through the burner by a blower on the

Page 2-30
AC 150/5370-14
10/15/91
Appendix 1

A lack of either air or fuel will reduce the efficiency


of the burner. Usually the availability of air is the
AIR EXHAUST limiting factor. The exhaust fan, besides providing the
FAN
induced air, must also pull the moisture vapor (steam)
created in the drying process and the products of com-
bustion through the dryer or drum mixer. The capacity
of this fan is a controlling factor in the heating and
BURNER drying of the aggregate. The volume of the exhaust
BLOWER gases (air, moisture vapor, and combustion products)
30% FORCED AIR pulled by the fan is constant, depending on the setting
70% INDUCED AIR of the damper in the system.

Figure 2-38. Induced forced burner (Astec) . The efficiency of the system is also affected by air
leaks in the system. Because the fan pulls a constant
volume of exhaust gases, at a constant damper setting,
FUEL through the system from the burner and through the fan,
any air that enters the system downstream of the burner
reduces the amount of secondary air that can be pulled
by the fan. Air leaks should be eliminated in order to
provide the proper volume of air at the burner to com-
bust the fuel completely. A damper, operated manually
or automatically, should also be placed in the ductwork
to control the amount of air entering the system.
R

HEAT-TRANSFER PROCESS
BLOWER Temperatures Inside the Drum
The temperature ofthe burner flame exceeds 2500°F.
Figure 2-39. Forced-air burner (Astec) .
The temperature of the exhaust gases just before they
enter the emission-control equipment should be in the
range of 250°F to 320°F, depending on the discharge
burner itself. The remaining 70 to 55 percent of the temperature of the mix. Typical temperature profiles
combustion air is pulled by the exhaust fan on the plant for the exhaust gases and the aggregate along the length
into the combustion zone around the burner. This type of the drum are shown in Figure 2-40. The difference
of equipment, a combined induced and forced draft in the exhaust gas and the mix discharge temperatures
burner, is shown in Figure 2-38 . Some burners operate represents the efficiency of the heat-transfer process and
with all of the air needed for combustion being forced the amount of heat that is available to dry and heat the
through the burner by a blower. This second type of aggregates. Perfect heat transfer would require that the
burner, shown in Figure 2-39, is known as a force draft, mix temperature and the exhaust gas temperature be
a total air, or 100 percent air burner. These latter equal at the point at which the mix is discharged from
burners are generally much quieter than are the induced the plant .
draft burners and are more fuel efficient. A measure of the efficiency of the heat-transfer
Some burners must be adjusted by the plant operator process is, therefore, obtained by comparing the mix
(a) as the amount of aggregate inside the dryer or drum discharge temperature with the temperature of the
mixer changes, (b) as the amount of moisture in the exhaust gases at the time the gases exit the drum. It is
aggregate increases or decreases, and (c) as the aggre- often difficult, however, to determine the temperature of
gate discharge temperature is changed in order to the exhaust gases accurately at this location; this temper-
control the drying and heating of the material. Most ature differential is normally measured in the ductwork
burners are equipped with an automatic device that at a point between the end of the drum mixer and the
controls the fuel input to maintain a relatively constant entry of the exhaust gases into the emission- control
discharge temperature for the aggregate (or for the mix equipment. This is done by means of a thermocouple
in a drum mixer) . attached to the ductwork upstream of the point where

Page 2-31
AC 150/5370-14
Appendix 1 10/15/91

Gas Stream
VENTURI - MIXER Temp .
70° Recycle Material

1000 1600 2600


1800 1200 700 500 450 390 320 300

450° Virgin
70° Virgin Aggregate 290 Mix.
Temp.

Figure 2-40. Drum temperature profiles (CMI) .

the exhaust gases are drawn into the wet-scrubber or injected. Certain asphalt cements, depending on the
baghouse system. For efficient operation of the drum source of the crude oil and the refining process used to
mixer, the temperature of the exhaust gases, before produce the material, may contain small amounts of
entry into the emission-control system, should be within volatile material or "light ends" that can be driven off at
20°F of the mix discharge temperature . temperatures as low as 600°F. Visible emissions can be
A comparison cannot normally be made between the avoided if the temperature of the exhaust gases is below
mix discharge temperature and the temperature of the this value at the location where the asphalt cement
exhaust gases at the point at which they exit the plant enters the drum .
stack. If a wet scrubber is employed on the plant, the Exhaust gas temperatures will normally be higher
water used to impinge on the dust particles in the when a recycled mix is being produced . This is related
exhaust gases will naturally cool the gases. For both to the reduction in the density of the veil of aggregate
wet-scrubber and baghouse emission-control systems, any upstream of the reclaimed material entry point (when a
leakage air that is drawn into the ductwork and emis- split-feed system is being used) and less efficient heat
sion-control equipment between the end of the drum transfer. The greater the amount of RAP used in the
and the stack will reduce the temperature of the exhaust recycled mix, the lesser amount of new aggregate, and
gases before they leave the stack. Thus, the comparison the less complete the veil of material ahead of the re-
between the mix discharge temperature and the exhaust claimed material entry point . In order to prevent the
gas temperature must be made in the ductwork before production of visible emissions (blue smoke) during
the gases enter the emission-control equipment . The recycling, the temperature of the exhaust gases should
comparison should not be made between the mix be below about 400°F at the point the reclaimed materi-
discharge temperature and the stack temperature , al enters the drum to prevent the generation of visible
particularly for plants equipped with a wet-scrubber emissions from the plant stack.
system .
For example, if the exhaust gas temperature in the Flight Design
ductwork is 360°F and the mix discharge temperature is The aggregate fed into the burner end of the drum
280°F, the veil of aggregate inside the drum is probably mixer moves down the length of the unit by a combina-
incomplete and the drum is being operated inefficiently. tion of gravity flow and the lifting flights as the drum
This causes several problems: increased fuel use, possi- rotates. Factors that affect the length of time for an
ble separation of some of the very fine aggregate individual aggregate particle to pass through the drum
particles from the rest of the aggregate in the drum , and include: the length and diameter of the drum, the slope
increased deterioration of the filter bags, if a baghouse of the drum, the number and type of flights inside the
is used . drum , the speed of rotation of the drum , and the size of
The temperature of the exhaust gases must also be the aggregate particles. In general, it takes about 4 to
controlled at the location where the asphalt cement is 8 min for an incoming aggregate particle to reach the

Page 2-32
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-41 . Rotary drum mixer flights (J. Scherocman).

discharge end of the drum. the material through the exhaust gases. As the aggre-
Each drum plant manufacturer uses a different gate moves down the drum, an ever greater amount of
pattern, shape, number, and location for the flights aggregate is lifted and tumbled . Near the midpoint of
inside the drum, as shown in Figures 2-41 and 2-42. the length of the drum, a veil of aggregate is developed
Although named differently by the various manufactur- across the whole cross-sectional area. This veil is essen-
ers, the flights used in the various sections of the drum tial to accomplish the heat transfer from the exhaust
generally serve the same purpose: to expose the aggre- gases so that the drying and heating of the aggregate can
gate to the heat from the burner gases without dropping take place. The more complete the veil, the more
it through the flame, to remove the moisture from the efficient and effective the heat-transfer process, the less
aggregate, to coat the aggregate with asphalt cement, fuel consumed, and the lower the particulate emissions
and to heat the coated material to the proper discharge from the plant .
temperature . Near the drum midpoint, some drum mixers are
Because the drum mixer operates on a parallel - flow equipped with devices to retard the flow of the aggre-
basis, to protect the asphalt cement from the high gate down the drum. A ring can be inserted inside the
temperatures, the burner flame should be short and drum to reduce the diameter at that point. A buildup of
bushy and not extend very far into the drum. The burner aggregate occurs in front of the ring, creating a heavier
flame must have enough room, however, to expand and veil of material. Some drum manufacturers install
combust the fuel completely . The incoming aggregate "kicker" or reverse- angle flights at this same location to
cannot be deposited directly into the fire or it will intercept the aggregate and turn it back upstream,
quench the flame. Thus, the first flights at the upper concentrating the aggregate in one area in order to
end of the drum are used to direct the aggregate into increase the density of the veil and improve the heat
the drum beyond the tip of the flame. transfer. Although restricting the diameter of the drum
The next flights are used to lift some of the aggre- in some fashion is beneficial in order to increase the
gate from the bottom of the drum, and begin to tumble density of the veil of aggregate inside the drum, the

Page 2-33
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-42. Drum flights (J. Scherocman).

reduced cross-sectional area also causes the velocity of should be checked on a regular basis. (The amount of
the exhaust gases to increase, thereby potentially increas- wear on the flights depends on the operating conditions
ing the amount of emissions from the drum mixer. for the plant and the type of aggregate being processed .)
Farther down the drum length, the asphalt cement is Worn and missing flights should be replaced as neces-
injected into the drum and mixing flights are used to sary. In addition, if proper heat transfer is not being
combine the aggregate with the asphalt cement. These completed, the type and location of the flights used
flights also allow the asphalt cement-coated particles to inside the drum can be altered to improve the veil of
continue to be heated by the exhaust gases, complete the aggregate moving across the cross section of the drum at
heat-transfer process, and raise the mix temperature to its midpoint .
the desired level for discharge . At the rear of the drum, Early drum mix plants were constructed with a 4:1
discharge flights are employed to deposit the material length-to-drum-diameter ratio that was used for batch
into the discharge chute for transport to the surge silo. plant dryers; an 8-ft-diameter dryer was 32 ft in length.
As mentioned previously, the actual design of the The current trend is to use longer drums to obtain more
flights that may be present inside a particular mixing complete heat transfer from the exhaust gases to the
drum will be different for the various makes, models , aggregate and to reduce emission problems, particularly
and date of manufacture of the drum. The primary when a recycled mix is being produced. Some current
purpose of the flights is to accomplish the proper drum mixers have length-to-diameter ratios of 5: 1 and
transfer of heat from the exhaust gases to the aggregate 6: 1 . Thus, an 8 -ft-diameter drum mixer might be 40 to
and to blend the aggregate and asphalt cement together 48 ft in length .
adequately. As the flights inside the drum wear from
the abrasive action of the aggregate moving through the Increasing the Veil of Aggregate
drum, the efficiency of the heating and drying process To increase the density of the veil of new aggregate,
can be reduced. Thus, the condition of the flights kicker flights, dams, donuts, or retention rings are

Page 2-34
AC 150/5370-14
10/15/91
Appendix 1

MODRU CONTRA
M EQUIPMECTORS
NT CO
RECYCL
MAT

Figure 2-43. Adjustable drum leg supports for changing drum slope (J. Scherocman).

employed to retard the flow of material down the drum . slope also causes a denser veil of material across the
Another method used to achieve the same effect is to drum cross section, further improving the degree of heat
lower the slope of the drum, as shown in Figures 2-43 transfer.
and 2-44. The reduction in slope (from a maximum of Lowering the slope of the drum does not normally
6 percent to a minimum of 2 1/2 percent, or 3/4 in./ft to cause a change in the plant production rate. Although
5/16 in./ft) increases the dwell or residence time of the it takes somewhat longer for an individual aggregate
aggregate in the drum and thus provides more time to particle to travel through the drum when the slope is
complete the heat-transfer process . The additional decreased, the actual production rate should be un-
aggregate retained in the drum because of the lower changed in terms of tons per hour. Power requirements
S

BARBER -GREENE

UM
THERMODR

Figure 2-44. Measuring drum slope (J. Scherocman).

Page 2-35
AC 150/5370-14
Appendix 1 10/15/91

for the electric motors used to turn the drum are in- The aggregate enters the drum at ambient tempera-
creased because of the extra weight of aggregate in the ture and begins to be heated immediately. As the
drum . The net result, however, is a better veil of aggre- material moves down the drum, its temperature is
gate, more complete heat transfer, and a reduction in increased until it reaches a point upstream of the drum
the temperature of the exhaust gases at all locations in midpoint, where its temperature remains relatively
the drum . constant because the heat from the exhaust gases is
Several manufacturers have developed drum mixers being used to evaporate the moisture in the aggregate.
that change in diameter along the length. The drum is The amount of time the aggregate temperature remains
one diameter at one or both ends and a smaller diame- constant depends in part on the amount of moisture in
ter in the center portion of the drum, as shown in the incoming material. The porosity of the aggregate is
Figure 2-45. The change in diameter allows more room also a factor, with the more porous material taking
for combustion of the burner fuel and provides for longer to remove all the moisture from the internal
development of a denser veil of aggregate in the drum pores in the aggregate. Finally, because of its lesser
by squeezing the same volume of material that was mass and greater surface area per unit weight, the fine
tumbling in an 8 1/2-ft diameter drum, for example, into aggregate (sand) is typically heated more quickly than
a 7-ft-diameter section, significantly increasing the the coarse aggregate.
density of the aggregate veil. In this case, the reduced Once most of the moisture has been removed from
diameter works in the same manner as the installation of the aggregate, its temperature begins to rise again.
a ring inside the drum. This heavier veil improves the After the aggregate is coated with asphalt cement,
efficiency of the heat-transfer process. The velocity of mixing flights are employed in most drum mix plants to
the exhaust gases, however, is also increased because of tumble the mix, partially exposing the material to the
the smaller diameter, potentially increasing the amount exhaust gases. The mix reaches the required discharge
of particulate emissions carried out into the emission- temperature as it approaches the end of the drum . Thus
control equipment and also possibly reducing production the aggregate, as it proceeds down the drum, undergoes
levels. a heating, then a drying, and then another heating cycle.
The moisture content of the aggregate decreases gradu-
Heat Transfer ally in the front portion of the drum and then more
While the exhaust gas temperature is being reduced rapidly as it reaches the temperature needed to vaporize
as these gases move down the drum, the temperature of water. If the dwell time in the central portion of the
the aggregate is increasing as it travels in a parallel drum is long enough, the moisture content of the mix at
direction. The heat-transfer process takes place in three discharge can be reduced to less than 0.2 percent. The
ways. The first is convection; heat energy is transferred moisture content of the mix at discharge is almost always
from the exhaust gases to the aggregate. The second is less than 0.5 percent .
radiation; heat energy is transferred from one heated
aggregate particle to another aggregate particle and ASPHALT CEMENT INJECTION
from the shell and flights of the drum to the aggregate. On a few older drum mix plants, the asphalt cement
The third is conduction; heat energy is transferred within supply line enters from the front of the drum, at the
the aggregate particles. burner end . The diameter of the pipe used depends on

Figure 2-45. Dual-diameter drum (Caterpillar-CMI) .

Page 2-36
AC 150/5370-14
10/15/91
Appendix 1

the capacity of the plant, with a 2- to 4-in . line typically


used . The asphalt cement is not normally sprayed
through a nozzle but is injected into the drum merely by
passing out of the end of the pipe. The actual point of
discharge varies, but tends to be toward the midpoint of
the drum length rather than close to the burner.
One advantage of early asphalt cement introduction
is quick capture of the dust particles in the aggregate by
the binder material. This action reduces the amount of
particulate carryout by encapsulating the fines in the
asphalt cement. Three disadvantages are present: the
asphalt cement may be hardened more by exposure to
the higher-temperature exhaust gases, the production of
blue smoke from volatilization of the light ends from
certain asphalt cements can be increased because of
these higher exhaust gas temperatures, and an increase
in the moisture content in the mix at discharge may
occur because the asphalt cement coats the aggregate
particles before all the water in the material is removed.
On most parallel-flow drum mix plants, the asphalt
cement is injected through a pipe coming in from the
rear of the drum, as illustrated in Figures 2-46 and 2-47.
The location of the asphalt cement entry in many cases
is at a point approximately 40 to 30 percent of the
length of the drum from the mix discharge end of the
mixer (60 to 70 percent of the way down the drum from
the burner end) . At this location, the small amount of
moisture remaining in the aggregate causes the volume
of the binder to expand by foaming and helps to coat
the aggregate. In a drum mix plant, coating rather than
mixing may be the more appropriate term for the blend-
ing of the asphalt cement with the aggregate.
If the moisture content in the aggregate is still high
at the point where the asphalt cement is injected , the
coating of the aggregate particles may be delayed until
more moisture is removed . When the average moisture
content of the incoming aggregate is very low (less than
1 percent), incomplete coating of the aggregate may
occur. In this latter case, it may be necessary to add Figure 2-46. Asphalt and fines feed lines (J. Scher-

water to the incoming aggregate on the cold-feed belt or ocman) .

to change the design of the flights inside the drum in


order to improve the aggregate coating by the asphalt
cement. however, it should not be necessary to pull the asphalt
If the asphalt cement being used contains volatile cement line back. The movement of the supply line can
material and results in excessive blue smoke emissions, decrease the uniformity of the coating of the binder on
it may be necessary to pull the asphalt cement supply the aggregate if it is too close to the discharge end of
the drum .
pipe toward the mix discharge end of the drum. This
change reduces the exposure of the asphalt cement to Some drum mix plants, however, have the asphalt
the higher-temperature exhaust gases and decreases the cement injection line completely removed from the
generation of visible hydrocarbon emissions. If the veil drum. The aggregate is heated and dried in the drum
of aggregate at the mid length of the drum is adequate, but exits uncoated . The aggregate is discharged into a

Page 2-37
AC 150/5370-14
Appendix 1 10/15/91

Convection Coating Zone


of Thermodrum
From bulk mineral
Filler Storage

Fines Injection w
ww High Bin
ww
Indicator

Asphalt Injection Low Bin


Indicator
SURGE
HOPPER
Vane Feeder with
Variable Speed Drive

From Asphalt
Metering Pump
Pneumatic Fines
Blower

Figure 2-47. AC line discharge end and mineral filler feed system (Barber-Greene) .

single- or twin-shaft coater unit (screw conveyor), where rotate, but no material will be sent to the plant.
the asphalt cement is sprayed on it, as shown in Figure The mineral filler-type material can be delivered to
2-48. The mixing of the materials occurs as the aggre- the charging conveyor on the cold-feed system and
gate and asphalt cement are moved along the drum mix delivered into the drum as part of the aggregate. This
coater. The blended material is then deposited into a is not recommended for several reasons. First, there is
transfer device for transport to the surge silo. The drum a problem of dusting of the filler material when it is
mix coater plant is a return to the original continuous
mix plant technology.

MINERAL FILLER AND BAGHOUSE FINES FEED


SYSTEM
Two types of aggregate fines, mineral filler and
material collected in a dry emission-control system , can
be fed into a drum mix plant, either individually or in
combination with one another. The basic equipment
needed to handle each type of material is essentially the
same . The primary differences between the various
systems concern the degree of sophistication in the DustRen
controls used to meter the materials.

Mineral Filler
Mineral filler-type material, such as hydratedlime,
portland cement, fly ash, or limestone dust, is stored in
a silo or other appropriate container and is delivered to
the plant through a vane feeder system or small weigh
hopper located at the bottom of the silo, as seen in Figure 2-48. Mixing auger in "coater" drum mix plant
Figure 2-47. The speed of the feeder is related to the (Astec).
amount of new and reclaimed aggregate being delivered
to the drum . The silo is normally equipped with an deposited on the incoming aggregate. Second, the very
aerating system to keep the mineral filler from packing fine filler has a tendency to become airborne easily
into a tight mass and bridging the opening to the feeder. inside the drum (picked up in the exhaust gas air
If the flow of filler is restricted, the vane feeder will still stream) and carried either to the discharge chute on the

Page 2-38
AC 150/5370-14
10/15/91 Appendix 1

drum or into the emission-control equipment. Thus, aggregate. Because it comes into contact with the
some of the filler can be carried out of the drum mixer asphalt cement very quickly after exiting its feed pipe,
instead of being incorporated into the mix. the mineral filler has less chance of becoming airborne
It is also possible to blend the mineral filler-type and being carried out of the drum. If the mineral filler
material with the asphalt cement in the storage tank and asphalt cement are blended together in some form
before the combined materials are fed into the plant. of mixing device as the asphalt cement is being intro-
This is rarely done, however, because of problems of duced into the drum, minimal carryout of filler material
separation and settlement of the heavier mineral filler normally occurs.
(higher specific gravity) from the lighter asphalt cement
whenever plant production is interrupted. Baghouse Fines
The mineral filler from the vane feeder thus typically If a baghouse (fabric filter) is used as the emission-
enters the delivery pipe and is conveyed pneumatically control equipment on the plant, either all or a portion
through the line and into the rear of the drum. The of the material captured in that device can be fed back
filler can be discharged in one of several ways: deposited into the drum mixer. The fines captured in the bag-
from the line onto the aggregate at the bottom of the house are carried, usually by a screw conveyor, through
drum or fed into a mixing device, where it is coated with an air lock and then fed pneumatically through a pipe
the asphalt cement before it is dropped into the drum , into the rear end of the drum, as seen in Figure 2-50.
as shown in Figure 2-49. The baghouse fines are typically not metered but are
returned on a continuous basis and discharged into the
<
H LIQUID ASPHALT LINE drum in a fashion similar to that of mineral filler.
Occasionally a surge of fine material may be carried
<< DUST LINE back to the drum mixer. If plant operating characteris-
tics cause such surges of baghouse fines to occur regu-
larly, the fines should be collected in a small surge silo
and then metered back into the plant using a vane
feeder system. (If the baghouse fines are not needed to
satisfy mix design requirements, they can be wasted
IMPINGING CONE instead of being returned to the mix.)
The returned fines must be incorporated into the
asphalt mixture and not be allowed to recirculate back
to the baghouse. This is accomplished by ensuring that
the fines are kept out of direct contact with the high-
velocity exhaust gases and are quickly coated with
Figure 2-49. AC-MF- BH fines mixing device (Astec) .
asphalt cement. If the fines are carried back to the
If the mineral filler is discharged directly into the baghouse, they will be caught and again returned to the
drum mixer, it can be either upstream or downstream of drum mixer. Soon the baghouse will be overloaded with
fines, because new fines are continually being generated
the asphalt cement injection point. If the filler is placed
into the drum upstream of the asphalt cement entry by the plant. The baghouse will become plugged and
point, it is usually dropped directly on the aggregate in will not operate properly. It is essential, therefore, that
the bottom of the drum. Because the filler is dry and of any mineral filler and/or baghouse fines be coated with
very small particle size, it is easy for this material to be asphalt cement before they can be picked up by the
caught in the exhaust gas air stream . If this occurs, exhaust gases and carried out of the mixer.
some portion of the filler will remain in the mix, but a The amount and gradation of the baghouse fines
major portion of the material, depending on drum returned to the asphalt mix inside the drum can have a
operating conditions, can be carried out of the drum and significant effect on the properties of the mixture pro-
into the emission-control equipment. duced. Before any fines are returned to the mix, a
If the mineral filler is discharged from its feed pipe laboratory analysis should be conducted to determine
into the drum after the asphalt cement has been injected the characteristics of the baghouse fines and the change
into the drum mixer, a greater portion of the filler is in mix properties that may occur when various quantities
usually captured in the mass of asphalt cement and of baghouse fines are returned to the mix, or wasted .

• Page 2-39
AC 150/5370-14
Appendix 1
10/15/91

Convection Coating Zone


of Thermodrum

Collected dust
from Fabric Filter

Fines Injection
w
ww
Asphalt Injection

Vane Feeder
with Fixed
Speed Drive

From Asphalt
Metering Pump
Pneumatic Fines
Blower

Figure 2-50. Baghouse fines feed system (Barber-Greene).

RECLAIMED MATERIAL RECYCLING SYSTEMS efficiency of the heat shield can be determined by the
Single- Feed amount of blue smoke that is generated during the
On the few remaining plants that use a single-feed recycling operation.
system to deliver both the new aggregate and the RAP
to the burner end of the drum mixer, several methods Split- Feed
are used, alone or in combination, to protect the as- Because of inherent emission -control problems using
phalt-coated material from direct contact with the flame the single-feed method, split-feed systems, in which the
and to reduce the generation of visible hydrocarbon RAP is fed to the drum mixer separately from the new
emissions. One method is to spray water on the com- aggregates, are most often used to produce recycled
bined aggregate on the charging conveyor before it asphalt mixes. The new material is delivered to the
enters the drum . The degree of protection offered by burner end of the drum mix plant in a conventional
the additional water on the surface of the aggregate manner. The RAP is delivered into a separate entry
depends on the amount of moisture already in and on point near the midpoint of the drum length, as shown in
the reclaimed material, the amount of water applied Figure 2-52.
(typically between 1 and 4 percent by weight of re- A variety of designs are used for the intake system to
claimed aggregate), and the position of the reclaimed introduce the RAP into the drum. Typically, the drum
material on the charging conveyor --underneath or on has a series of ports or entry chutes, illustrated in Figure
top of the new aggregate. 2-53, cut into the shell to allow the RAP to be intro-
A second procedure is to increase the speed of the duced from the charging conveyor as the drum turns.
slinger conveyor under the burner in order to throw the At the point that the RAP enters the shell, a short
combined aggregates farther down the drum. The more length of the flighting is often removed or configured so
the asphalt-coated materials are kept from the flame, that the asphalt-coated material can easily be added to
the less hydrocarbon emissions are generated. the new aggregate. The RAP begins heating as soon as
A third method uses a heat shield to reduce the con- it enters the port . The combined aggregate is picked up
tact of the combined aggregate with the flame, as shown by the flights, and the heating and drying of the new
in Figure 2-51 . This device spreads the flame out material and the RAP is continued .
around the circumference of the drum and decreases the When reclaimed material is charged into the drum at
concentration of heat at any one point near the flame. its midpoint, less new aggregate is placed into the drum
The performance of the heat shield is dependent on its at the burner end, reducing the density of the veil of
location inside the drum , the amount of RAP in the mix, aggregate upstream of the RAP entry and decreasing the
the moisture content of new and reclaimed aggregate, amount of heat transferred from the exhaust gases to
and the required mix discharge temperature. The the new aggregate. Thus, the temperature of the gases

Page 2-40
AC 150/5370-14
10/15/91 Appendix 1

E
UR
R M RAT
I FO S M PE
10 ft-14 ft UN GA TE

FLOW OR
M ITY
IF S OC
FLOW MIXING CONE MIXING
ZONE UN GA VEL
DIRECTION →→
SLOT
COOLING FRESH AIR INTAKE
PORTS (SLOT COOLING)
BCE PYROCONE SYSTEM
STANDARD
STANDARD BURNER SETUP DRUM MIXER
AIR INTAKE

STANDARD
FEED
SYSTEM

Figure 2-51 . Heat shield inside drum (Boeing).

at the point they come in contact with the RAP is higher es in severity as the amount of RAP used in the recycled
and the chance to burn the asphalt coating on the mix increases. Methods to reduce the exhaust gas
reclaimed aggregate is increased. This problem increas- temperature involve ways to increase the density of the
veil of new aggregate upstream of the RAP entry
location as well as to raise the temperature of the RAP
before it comes into contact with the heated new
aggregate.
Normally, if 20 percent or less RAP is being incorpo-
rated into a recycled mix and a split-feed system is used,
minimal hydrocarbon emissions are produced , depending
on the adequacy of the veil of new aggregate inside the
drum and the discharge temperature of the mix. As the
percentage of RAP becomes greater, and as the mois-
ture content of the RAP increases, the potential for
emission problems increases. When the amount of RAP
used exceeds 50 percent, by weight of mix, the emission
of blue smoke during the recycling process can become
significant. A combination of procedures, outlined
above, is needed to assure adequate heat transfer from
the exhaust gases to the new aggregates before those
gases come in contact with the reclaimed material.
Only under ideal and carefully controlled production
conditions may it be possible to incorporate up to 70
percent reclaimed aggregates in a recycled mix without
major visible emission problems. Because of the reduc-
tion of production rates and the emission-control prob-
Figure 2-52. Center rotary drum inlet (Cedarapids). lems that occur when high percentages of RAP are used

Page 2-41
AC 150/5370-14
Appendix 1
10/15/91

RAP

BYPASS
CHUTE
SCRAPER
BLADE
INTAKE
BLADES

RETAINING
RING
ASPHALT
VAM INJECTION PIPE

DRYING
FLIGHTS

MIXING
FLIGHTS
FEED
PLATES
HOOD
SHADED AREAS ARE DRYING
OPENINGS TO INNER DRUM FLIGHTS
RUBBER
SEALS

Figure 2-53. RAP material center feed (Cedarapids).

in a recycled asphalt mix, it is normally good practice to aggregate moisture content removal of 5 percent, with
limit the amount of reclaimed material processed the plant operated at sea level. Plant capacities are also
through a split-feed drum mix plant to approximately 50 affected by a number of other variables including drum
percent of the total aggregate weight. diameter, fuel type, exhaust gas velocity, capacity of the
exhaust fan, amount of excess air at the burner, estimat-
PRODUCTION RATES ed air leakage into the system, and atmospheric condi-
Hot-mix asphalt drum mix plants are rated by the tions. Aggregate gradation may be a factor with mixes
number of tons of mix that can be produced per hour. containing a large percentage of coarse aggregate
The production capacity is usually related to the incom- because they are more difficult to heat uniformly than
ing aggregate temperature, the mix discharge tempera- mixes incorporating a balance of coarse and fine aggre-
ture, the specific heat of the aggregate, and an average gate particles.

Drum Diam .
Surface Moisture Removed (%)
& Length
(ft) 2 3 4 5 6 7 8 9 10

5x22 178 140 116 100 84 79 74 63 58


6x24 278 220 178 158 137 121 116 100 89
7x30 420 336 273 236 205 184 163 147 137
8x32 541 430 352 305 263 236 210 194 173
9x36 719 578 478 410 357 315 284 257 236
10x40 956 761 630 541 473 430 378 341 315

Figures for each size dryer are for asphalt concrete mix capacities.
Examples of the effects of moisture content on plant production rates are for one manufacturer's drum mix plants.

Figure 2-54. Nominal drum mix capacities (tons per hour) (Barber-Greene).

Page 2-42
AC 150/5370-14
10/15/91 Appendix 1

One of the variables that has the greatest effect on average moisture content of the aggregate directly
the actual production rate is the average moisture affects the capacity of a drum mix plant.
content of the coarse and fine aggregate. The moisture The mix discharge temperature, held constant at
content of the fine aggregate is usually higher than that 270°F in the example above , also affects the production
of the coarse aggregate. The average moisture content rate of the plant; as the mix discharge temperature
is thus a function of the amount of moisture in the decreases for a given aggregate moisture content and
coarse aggregate and its percentage in the mix, plus the drum size, the volume of mix that can be manufactured
amount of moisture in the fine aggregate and its per- in a given period of time increases. In Figure 2-55, for
centage in the mix. a drum mix plant from one manufacturer that is 7.33 ft
If, for example, 60 percent of the mix consists of in diameter and 28 ft in length, with 5 percent moisture
coarse aggregate, then 40 percent of the mix is fine
aggregate (assuming no mineral filler is used in the mix) .

MOISTURE
12
If the moisture content of the coarse material is 3.0 14-

FREE
percent and that of the fine aggregate is 8.0 percent, the
12 MIX TEMP.

%
average moisture content in the combined aggregate is 200° F
calculated to be: (60 percent x 3.0 percent) + (40 225° F

10
10-
= (1.8 percent) + (3.2 percent) 250° F
percent x 8.0 percent) 275° F
= 5.0 percent . If the amount of moisture in the fine 8- 300° F
aggregate was only 6.0 percent, the combined (average)
6

moisture content of the cold-feed materials would be:


(60 percent x 3.0 percent) + (40 percent x 6.0 percent) 4-
= (1.8 percent) + (2.4 percent) = 4.2 percent .

As the average percentage of moisture in the aggre- 2+


gate increases, the production capacity of a drum mixer 50 100 150 200 250 300 350 400 450 500 550

of a given diameter decreases because of the limited TPH OF MIX


maximum capacity of the exhaust fan. At a constant Figure 2-55. Moisture content- mix temperatures, as
average incoming moisture content, the production rate they affect production rate (Cedarapids).
increases as the drum diameter increases. The theoreti- removal, the production rate will increase from 255
cal relationship between average moisture content, drum tons/hr at a mix discharge temperature of 300°F to 300
diameter, and the calculated drum mix plant production tons/hr at a temperature of 250°F. When the moisture
rate (at a mix discharge temperature of 270°F) is shown content on the incoming aggregate is relatively high, the
in Figure 2-54 for different models for one particular production rate changes are not as great when the mix
make of plant, at a given volume of exhaust gas flow and discharge temperature is decreased . At 8 percent
set of operating conditions for each size of plant. (Simi- average moisture content, the production capacity of the
lar charts are available from manufacturers of other same plant increases from 175 to 200 tons/hr as the mix
makes of drum mixers.) discharge temperature decreases from 300°F to 250°F.
Using this figure, at an average moisture content of The production rate of a drum mix plant is also
5 percent, a drum mix plant having a diameter of 6 ft affected by the volume of the exhaust gases being pulled
would have a theoretical production capacity of 158 tons through the system by the exhaust fan. As the volume
of mix/hr. If a drum 8 ft in diameter were used instead , ofgases being pulled through the drum decreases and as
the manufacturing rate would increase to 305 tons of the velocity of those gases also decreases, the production
mix/hr. For a drum mixer 10 ft in diameter, the capacity capacity of the drum mixer will be reduced .
would increase to 541 tons of mix/hr at 5 percent mois- The production rate of recycled mixtures, for those
ture removal.
plants that operate on a split-feed system, is also a
As the moisture content in the aggregate decreases function of the volume of reclaimed material being fed
from 5 percent to 3 percent, the production rate for a into the drum mixer. For these plants, as the amount of
drum mixer that was 8 ft in diameter would increase to RAP delivered to the drum becomes greater than 50
430 tons of mix/hr from 305 tons/hr. If the aggregates percent of the total aggregate feed, the capacity of the
have a higher moisture content (for example, 8 percent) , plant is decreased, as shown in Figure 2-56, for one
the same 8-ft-diameter plant would only be able to particular make of drum mix plant . This is caused by
manufacture 210 tons of asphalt mix/hr. Thus, the the lack of an adequate amount of new aggregate in the

Page 2-43
AC 150/5370-14
Appendix 1
10/15/91

upper end of the drum mixer to provide for proper heat on a variety of factors including the volume of gases
transfer from the burner exhaust gases to the new being pulled through the system and the temperature of
aggregate . This, in turn , reduces the heat transferred those gases. In addition, several of the newer types of
from the new aggregate to the RAP material. continuous-mix plants, such as the counter flow drum
Using Figure 2-56, a recycled mix that is made up of mixer, are generally more efficient in the heat-transfer
60 percent RAP and 40 percent new aggregate, with the process and thus can process amounts of RAP above 50
weighted moisture content in the combined materials at percent with less effect on the production rate of the
5 percent, would have an index number of approximately plant.
0.70. The index number means that the plant could
produce only 70 percent as much mix/hr, at a 60/40 PLANT EFFICIENCY
blend of reclaimed and new aggregate, as could the Mix and Stack Temperatures
same plant producing mix using all new aggregate. If perfect heat transfer could take place inside the
Thus, if the plant could manufacture 308 tons/hr at 5 drum, the temperature of the mix upon discharge from
percent moisture removal with 100 percent new material, the parallel-flow drum mix plant would be equal to the
it would theoretically have a capacity of only 308 x 0.70 temperature of the exhaust gases at the same point .
= 216 tons/hr when 60 percent reclaimed aggregate is This equilibrium point would mean that the heat trans-
incorporated into the mix. As the amount of RAP used fer is in balance and that the drum mixer is running at
in the recycled mix increases above 50 percent, the maximum possible heat-transfer efficiency. Under
amount of mix that can be produced in a drum mix normal operating conditions, if the veil of aggregate
plant is reduced in proportion to the increasing amount inside the drum is complete, the exhaust gas tempera-
of reclaimed material used. ture, measured at the drum exit or before the gases
The index number above provides a means of enter the emission-control system, should be within 20°F
estimating the effect of the introduction of RAP into the ofthe temperature of the mix (assuming that no leakage
drum mixer on the production rate of the plant. The or cooling air is added in the ductwork between the end
actual production rate for a drum mix plant will depend of the drum and the point at which the gas temperatures

1.80

1.60

1.40
Index

1.20
T
No.

1.00
888

Mix Design %
.80
U

0-50/50
.60 60/40
70/30
.40

.20

0
1 2 3 4 5 6 7 8

Weighted Average Moisture, %

Figure 2-56. Effect of amount of reclaimed material on drum mix plant


production (Barber-Greene).

Page 2-44
AC 150/5370-14
10/15/91 Appendix 1

are measured in the ductwork) . Thus, if the mixture Mix Discharge Monitoring
discharge temperature is 280°F, the measured exhaust A second way to judge the efficiency of the drum mix
gas temperature should be less than 300°F. This small plant operation is to observe the asphalt mixture as it is
temperature differential implies that the drum mixer is discharged from the drum. The appearance of the mix,
operating efficiently and that minimum fuel/ton is being whether it consists of all new aggregate or a blend of
burned . new and reclaimed aggregate, should be uniform across
If the exhaust gas temperature is found to be more the width of the discharge chute. The color of the
than about 20°F above the mix temperature, the heat- aggregate particles should be consistent and the finer
transfer process inside the drum is not as efficient, aggregate particles should be evenly distributed through-
primarily because of the lack of an uniformly dense veil out the mixture.
of aggregate across the cross section of the drum . If the fuel used by the burner is not being completely
Temperature differentials of up to 100°F between the combusted, the coarser aggregate particles in the mix
mix and the exhaust gases are sometimes found , indicat- may appear to be covered with a dark brown stain
ing that the plant is not being maintained or operated instead of with the proper film thickness of asphalt
properly and that emission control might be a problem. cement. In addition, the adhesion of the asphalt cement
The degree of operating inefficiency is related to the binder to the aggregate may be reduced and the mix
difference in the two temperatures (mix discharge and would have an increased tendency to strip when tested
exhaust gas) before entry into the emission-control for potential moisture damage.
system . If the veil of aggregates inside the drum is not com-
During the production of a recycled asphalt mixture plete, the exhaust gases will travel down one side of the
in a single-feed drum mixer, the heat transfer between drum , depending on which direction the drum is turning,
the exhaust gases and the new and reclaimed aggregates at a higher velocity than on the other side of the drum.
should be similar to that for a mixture using all new Fine dust-sized particles are picked up in the gas stream
material. Thus, for this process, the exhaust gas temper- and carried to the rear of the drum. As the exhaust
ature should be within the 20°F temperature difference gases change direction to enter the ductwork, the larger
if the plant is operating correctly. If a split-feed-type dust particles drop out of the gas. These uncoated
plant is being employed, the difference in the two particles are discharged on one side of the mixture as it
temperatures might be greater than 20°F, depending on exits the drum. A steady stream of light brown , un-
the proportion of RAP introduced at the center inlet coated, fine aggregate particles on one side of the
point. As a higher percentage of reclaimed aggregate is asphalt concrete mix discharge chute thus provides an
incorporated in the recycled mix, the temperature indication that the veil of aggregate inside the drum is
differential increases. When 50 percent of the recycled incomplete .
mix consists of RAP, the temperature of the exhaust If a dry, powdered additive such as hydrated lime is
gases may be more than 70°F above the mix discharge being added to the incoming cold aggregate at the
temperature . burner end of the mixer, it is possible for very fine
The efficiency of the heating and drying operation, material to be picked up in the exhaust gases shortly
therefore, can be judged in part by observing the after it is charged into the plant. When the aggregate
temperature differential that exists between the mix veil is proper, the fine material will be trapped in the
upon leaving the drum and the exhaust gases measured tumbling mass of aggregate and incorporated into the
in the ductwork. Because both temperatures usually are mix. If the aggregate veil is incomplete, however, the
recorded continuously and are displayed on the plant powdered material can be carried down one side of the
control console, this method of monitoring the plant drum and then dropped into the bottom of the drum at
production process is easy to accomplish. the mix discharge point, depending on the size of the
High exhaust gas temperatures can also lead to particles relative to the exhaust gas velocity. The
significant, premature corrosion on one side of the powdered material will then be visible on one side of the
ductwork between the discharge end of the drum mixer. asphalt mixture as it is discharged from the drum, as
and the primary collector. This corrosion is another illustrated in Figure 2-57 . Thus, this method of adding
indication that the efficiency of the plant operation the mineral filler-type material should not be used unless
needs to be monitored and that the temperature of the that filler is well blended with the incoming aggregate
exhaust gases at the time they exit the drum mixer must before the two materials are charged into the drum
be controlled . mixer.

Page 2-45
AC 150/5370-14
Appendix 1
10/15/91

able to combust the fuel that it is trying to burn com-


pletely. Brown stains or a lesser asphalt cement film
thickness on the coarser aggregate particles at the
discharge end of the drum mixer also indicate unburnt
fuel problems.
• The density of the veil of aggregate inside the
drum near the midpoint of the length is the key to the
efficient operation of the drum mixer and economical
fuel usage. The completeness of the veil can be deter-
mined from a comparison of the discharge temperature
of the mix with the temperature of the exhaust gases at
the stack. The stack temperature should be no more
than 20°F higher than the mix discharge temperature if
the veil of aggregate inside the drum is complete across
the cross-sectional area of the drum (assuming that no
cooling air is added in the emission-control system).
Greater differences in temperature indicate that the
plant is not being operated efficiently.
• The presence of light brown, uncoated fine aggre-
gate on one side of the mix in the discharge chute is also
an indication that the veil of aggregate is incomplete
across the drum circumference.
• The generation of visible hydrocarbon emissions
from the stack further indicates that the temperature of
the exhaust gases inside the drum is too high at the
point where the asphalt cement is injected into the
drum .
The density of the veil of aggregate inside the
Figure 2-57. Unmixed hydrated lime at mix discharge drum can be increased through the use of kicker flights,
chute (J. Scherocman) . dams, donuts, or retention rings near the midpoint of
the drum length. It can also be increased by lowering
Typically a high stack temperature in comparison the slope of the drum to increase the dwell or residence
with the mix discharge temperature will be accompanied time of the aggregate in the drum.
by a stream of light-colored fines on one side of the mix • The mineral filler and/or baghouse fines should
discharge chute. Both of these phenomena are indica- be added through the mix discharge end of the drum.
tions that the drum mixer is not operating efficiently. These materials should be coated with asphalt cement or
The plant operator should alter the production process captured in the mix before they are exposed to the
to achieve a denser veil of aggregate in the drum. The exhaust gases moving down the drum .
plant should be operated at the most efficient produc- • If RAP is added to the drum through a split-feed
tion rate, irrespective of demand ; the plant should be system, the difference in the mix discharge temperature
shut down when the silos are full and restarted when and the exhaust gas temperature measured at the stack
mix is needed once again. will typically be greater than 20°F and will usually
increase roughly in proportion to the amount of RAP
SUMMARY OF DRUM MIXER OPERATING TECH- added to the mix.
NIQUES • Plant production rate is determined at a given mix
When observing the operation of the drum mixer, a discharge temperature and at an average moisture
number of factors should be considered to assure that content in the aggregate, usually 5 percent, at a given
the plant is operating properly. Those factors include: elevation (sea level) . An increase in the moisture
The sound of the burner should be monitored. A content and/or an increase in the mix discharge tempera-
uniform , constant roar is desirable. A coughing, sputter- ture decreases the capacity of the drum mixer in terms
ing, or spitting sound may mean that the burner is not of tons of mix produced per hour.

Page 2-46
AC 150/5370-14
10/15/91
Appendix 1

• Production rates for recycled asphalt concrete material per ton of mix, the production rate of the
mixes, up to a RAP content of 50 percent, will normally parallel-flow drum mixer will decrease as the amount of
be similar to the production rates for mixes containing reclaimed material increases.
all new aggregate . Above that amount of reclaimed

Page 2-47
AC 150/5370-14
Appendix 1
10/15/91

SECTION FIVE
SURGE AND STORAGE SILOS

INTRODUCTION The type of conveying equipment employed is seldom


The primary purpose of a silo on a batch plant is to a major factor in the uniformity of the mix delivered to
allow the plant to continue to produce material when the silo. The important point is the manner in which
trucks are not available to accept mix from the pugmill. the mix exits from the device and enters the top of the
For a drum mix plant operation, the main purpose of silo.
the silo is to convert a continuous mixing operation into
a discontinuous truck-loading process and to hold the BIN GEOMETRY
mix temporarily until the next transport vehicle is Silos come in a variety of shapes . The majority of
available. the silos currently in use are circular, but silos that are
This section discusses the conveying devices that are oval, elliptical, rectangular, and square have been used .
used to transport the mix from the batch plant pugmill The shape of the silo can affect the amount of segrega-
or from the drum mixer to the silo. It also reviews the tion that occurs both upon loading and unloading the
methods used to deliver the mix into the top of the silo silo. Less segregation of a given mix is generally found
in order to prevent segregation from occurring. Further, from a circular silo than from silos of other shapes.
discussion of discharge of the mix from the silo to the For circular silos, the probability of segregation
haul trucks emphasizes reducing the segregation that problems with mixes containing larger-size coarse aggre-
might occur in the mix during the truck-loading opera-
tion.

CONVEYING DEVICES
A variety of conveying devices are used to carry the
hot-mix asphalt from the discharge chute on the drum
mixer or from the hopper under the pugmill of a batch
plant to the surge silo. The most popular equipment is
the drag slat conveyor, as shown in Figures 2-58 and
2-59. In this system, a continuous set of flights connect-
ed together by a drag chain pull the mix up an inclined
metal conveyor. The amount of mix that can be carried
by the drag slats depends on the spacing between the
slats, the depth of the individual flights, the width of the
flights, and the slope of the conveyor, as well as the size
and speed of the drag chain and the power of the drive
motor. On some drag slat conveyors, the speed of the
conveyor can be altered to change the capacity of the
device to match the output of the drum mixer more
evenly.
A belt conveyor can also be used to deliver the mix
to the silo, as seen in Figure 2-60. This belt is essential-
ly the same as those that carry the incoming aggregate
into the drum except that it is able to withstand the
increased temperature of the hot material. As shown in
Figure 2-61 , a bucket elevator is also used on some
plants. This device is similar to the equipment used on
batch plants to carry the hot aggregate from the dis-
charge end of the dryer to the top of the mixing tower. Figure 2-58. Drag slat conveyor (Standard-Havens).

Page 2-48
AC 150/5370-14
10/15/91
Appendix 1

1000

Figure 2-59. Drag slat conveyor (Cedarapids) .

gate increases as the diameter of the silo increases. In TOP OF THE SILO
general, however, the silo geometry is not a major factor Mix Delivery
in segregation; the manner in which the silo is operated Segregation most typically occurs in mixes that
(loaded and unloaded) has a greater effect on the contain a significant proportion of large aggregate
uniformity of the mix and the amount of segregation . and/or are gap graded . The actual separation of the
large and small particles occurs when the asphalt mix is
placed in a conical pile and the bigger particles run
down the side of the pile , collecting at the bottom edge.
Segregation can also occur when all the mix is thrown to
one side of the silo, allowing the coarser pieces to run
across the surge silo to the opposite wall.
Prevention of longitudinal (side-to-side ) segregation
on the roadway begins at the top of the silo. Mix deliv-
ered to the top of the silo by slat conveyor, belt convey-
or, or bucket elevator will be discharged to the far side
of the silo by the natural centrifugal force of the convey-
ing device, as illustrated in Figure 2-62, unless some
means is employed to redirect the flow into the center
of the silo. On some silos, a series of baffles is used to
contain and change the direction of the material. Other
silos are equipped with a splitter system to divide the
Figure 2-60. Hot mix belt conveyor (J. Scherocman) .

Page 2-49
AC 150/5370-14
Appendix 1
10/15/91

particles will roll to one side of the silo. Loading the


haul truck with the vehicle facing in the opposite
direction to its normal loading pattern should cause the
longitudinal segregation to move from one side of the
lane to the other side. If this occurs, the cause of the
side-to-side segregation is in the loading of the mix into
the silo from the conveying device: drag slat conveyor,
conveyor belt, or bucket elevator.

Batcher
The most effective means to reduce segregation is to
employ some form of temporary holding hopper or
batcher at the top of the silo to momentarily store the
mix being transported by the conveying device. This
hopper, shown in Figure 2-63, collects the continuous
flow of mix. When the hopper is nearly full and the
hopper gates are opened, the mix is deposited in a mass
into the silo. The mass of mix will hit the bottom of the
empty silo or the top of mix already in the silo . Upon
contact, the mix will splatter in all directions uniformly,
minimizing segregation.
The system functions well unless the silo is almost
Figure 2-61 . Hot- bucket elevator charging surge bin full. In this case, the mix, when released from the
(Barber-Greene) . hopper, does not fall very far. When it hits the mix
already in the silo beneath the hopper, the falling mix
mix that is delivered, causing a portion of the mix to be lacks the momentum to spread out over the area of the
placed in each part of the silo. In general, use of the silo, and a conical pile is formed instead . This pile can
baffle and splitter systems can reduce the tendency for be the beginning of a segregation problem as more mix
longitudinal (side-to-side) segregation on the roadway is deposited on top of it . Most silos are equipped with
but does not always eliminate it. The use of a batcher high silo indicator warning systems that alert the plant
system provides a better means to reduce the segrega- operator to cut off the flow of incoming mix when the
tion problem . silo becomes too full.
Longitudinal segregation will occur on one side of The batchers may not prevent a segregation problem
the lane being paved because the coarser aggregate if the mix is delivered to it improperly. In some cases,
the transporting devices place the mix all on one side of
the hopper, as shown in Figure 2-62. This causes rolling
of the coarse aggregate in the batcher itself. It also
causes the mix to be dropped off-center into the silo.
Thus, even though the silo may be equipped with a
batcher, the mix must be deposited uniformly into the
center of the hopper and the mix must be delivered
from the batcher into the center of the silo to prevent
segregation of mixes with a large portion of coarser
aggregate.
Sometimes, the plant operator improperly leaves the
gates on the bottom of the batcher wide open. This
defeats the purpose of the batcher and allows the mix to
dribble in to the silo in a continuous stream. In other
cases, the batcher may be emptied more often than
Figure 2-62. Improper delivery of mix to batcher necessary; when it is only partially full. This continual
(NAPA) . dumping of the hopper reduces the mass of material

Page 2-50
AC 150/5370-14
10/15/91
Appendix 1

device revolves around at the top of the silo and depos-


its the mix in a circle around the circumference of the
silo. The flow of the asphalt mix is continuous , but the
development of conical piles of mix is minimized by
spreading the material out over a wider area. Because
the chute on the rotary spreader is subject to extensive
abrasion from the mix, it must be checked periodically
to assure that no holes have developed in the device.
Depending on the location of the hole, mix could either
be deposited all in the center of the silo or all around
the outside circumference of the silo. Because of
maintenance problems with this equipment, the rotating
chute system is rarely used.

SURGE VERSUS STORAGE


A silo can be used , during the normal daily operation
of the plant, to store asphalt mix between the arrival of
trucks at the plant. In this case, the silo is typically
termed a surge silo . If the silo is to be employed for
holding the mix for longer periods of time (overnight or
for several days) the silo may be termed a storage silo.
A storage silo can easily be used as a surge silo. A
surge silo may not be suitable for use as a storage silo.
Several differences exist between a surge and a
storage silo. First, the capacity of a storage silo is
typically greater than the capacity of a surge silo.
Second, the surge silo is usually insulated but not
heated. The silo used for mix storage is always insulated
and usually heated, either completely or partially. Third,
the gates at the bottom of the storage silo are heated
and sealed when mix is to be held for a long period of
time, in order to reduce the amount of air that can pass
up into the mix through the gates . The gates at the
bottom of the surge silo are not normally heated or
sealed.
The primary operation of both types of silos is
similar. Only the ability to store quantities of mix for
Figure 2-63 . Silo batcher (NAPA) . longer time periods without significant changes in the
properties of the mix differentiates the two types of
dropped into the silo and increases the opportunity for equipment. Whichever type of silo is used, the mix that
a conical pile of mix to form. Further, the timer device is held in the silo and then delivered to the haul truck
should be set so that the gates of the batcher are closed should meet the same mix specifications and require-
before the batcher is empty; some mix should remain in ments as the mix discharged directly from the pugmill on
the batcher. This will allow the mix to fall in a mass and a batch plant or as the mix at the discharge end of the
reduce segregation. A timer can be used to regulate the drum mixer, before passage into and out of the silo.
opening and closing of the batcher gates and permit the
batcher to be used properly. Insulation and Heat
Most surge silos are insulated . The purpose of the
Rotating Spreader Chute insulation is to reduce the loss of heat from the mix as
Mix can also be introduced into the silo using a it temporarily resides in the silo . The type of insulating
rotating spreader chute, as shown in Figure 2-64. This

Page 2-51
AC 150/5370-14
Appendix 1
10/15/91

material used and its thickness varies among the various


manufacturers.
The cone at the base of the surge silo is usually
heated. This is done to prevent the mix from sticking to
the wall of the cone and building up. The heat can be
provided by electrical or hot-oil systems. In some cases,
the vertical walls on the silo are also heated. The
heating allows the mix to retain the desired temperature
for an extended period of time. If the silo is to be used
strictly as a surge silo and is emptied of mix at the end
of each production day, heating of the silo walls is
usually unnecessary, but the cone is usually heated .

Storage
Occasionally it is necessary to retain an asphalt
mixture in the silo for a longer time period, such as
overnight or over a weekend . Usually this can be
accomplished quite successfully without undue hardening
or temperature loss in the mix. A well-insulated silo is
required, but heating of the silo vertical walls is general-
ly unnecessary. Mixes stored for several days in silos
equipped with heated cones have shown only minimal
oxidation and temperature loss. The amount of harden-
ing that occurs is related to the amount of mix in the
silo. The large mass of mix in a full silo will age less
than will a small volume of mix in a nearly empty silo.
In addition, the amount of temperature loss in the
stored mix will depend on a number of factors including
the initial mix temperature, the gradation of the materi-
al, and environmental conditions.
Asphalt mix (except open-graded mix) may be stored
for as long as a week when kept in a heated, air-tight
silo. An inert gas system can be employed to purge the
silo of oxygen, but this is rarely done. The gates at the
bottom of the silo as well as any openings at the top of
the silo must be well sealed to prevent the movement of
air into and through the mix. The silo must be com-
pletely heated and well insulated . Further, it is some- Figure 2-64. Batcher spreader chute (NAPA).
times advisable to remove a small amount of mix (at
least 2 or 3 tons of material) from the silo every day or ered directly to the paving site . This testing should
every other day during the storage period to assure that include measurement of the mix temperature upon
the mix at the bottom of the cone does not set up and discharge from the silo and the viscosity and/or penetra-
become impossible to discharge . Although mix can be tion of the asphalt cement recovered from the mix. As
stored for relatively long periods of time, it is rarely long as the mixture meets these specifications, the length
necessary to do so with continuous operation of the of time the material is held in the silo should not be
plant. Most silos, therefore, are used either as surge restricted. If an open-graded mixture is being stored ,
silos or periodically as storage silos for overnight storage however, care must be taken to keep the mix storage
of the asphalt material. temperature low enough so that the asphalt cement does
The mix held for more than two or three days in a not flow off of the aggregate and collect at the bottom
surge or storage silo should be tested to assure that it of the silo .
meets all the same requirements as asphalt mixes deliv-

Page 2-52
AC 150/5370-14
10/15/91
Appendix 1

THE CONE, LOADOUT, AND SEGREGATION Loading and Segregation


Silo Cone Just as it is important to deliver mix into the silo in
As shown in Figure 2-65, the bottom of the surge silo a mass, it is also important to deposit the asphalt mix in
is shaped like a funnel or cone. The angle of the cone a mass into the haul truck. The gates on the bottom of
varies with the different manufacturers, but is usually the cone should be opened and closed quickly. It is also
between 55° and 70° . This slope assures that the mix is necessary for the gates to open completely so that the
deposited as a mass into the truck. The angle needs to flow of mix is unrestricted. There is only one reason to
cut off the flow of mix into the vehicle once that deliv-
ery has started : to divide the delivery of the mix into
NCP different sections of the truck.
If all the mix is placed in the haul vehicle in one
drop from the silo, segregation of the larger aggregate
particles can occur. If the mix is deposited into the
center of the truck bed, the material will build up into
a conical-shaped pile, as illustrated in Figure 2-66 .
Because the growth of the pile will be restricted by the
sides of the truck, the bigger aggregate particles will roll
toward the front and the tailgate of the truck bed.
These pieces accumulate at both ends of the load and
are then delivered into the hopper on the paver from
the truck bed. The pockets of coarse material then
appear in the mat behind the laydown machine at the
end of the truckload of mix. In reality, some of the
large aggregate pieces come from the end of one
truckload and also from the beginning of the next
truckload of mix.
This segregation problem can be minimized by
dividing the delivery of the asphalt mix from the silo into
multiple drops, each delivered to a different section of
the bed of the hauling vehicle. If a tandem axle or
triaxle dump truck is being used, about 40 percent of the
total weight of the mix to be hauled should be loaded
into the center of the front half of the truck. The truck
should then be pulled forward so that the next 40
Figure 2-65. Discharge cone at bottom of silo (J. percent or so of the total load can be deposited into the
Scherocman). center of the back half of the bed, near the tailgate.

be steep enough, and the gate opening large enough, to


assure that the larger aggregate particles do not roll into
the center of the cone (rathole) as the mix is drawn
down, causing segregation.
The vast majority of the surge silos have low silo
indicator systems that warn the plant operator when the
level of mix in the silo is near the top of the cone. By 0.000
keeping the volume of mix in the silo above this mini-
mum level, segregation will be minimized . As very
coarse mixes or gap-graded mixes are pulled below the
top of the cone, there can be a tendency for the largest OO
aggregate particles to roll into the center of the crater.
Figure 2-66. Incorrect truck-loading sequence
(NAPA) .

Page 2-53
AC 150/5370-14
Appendix 1 10/15/91

2 needed to place the proper amount of material in each


truck bed. This amount can also be confirmed visually

8 by watching the height of the growing pile of mix in the


000
0. truck as the loading continues .
The operator should not be allowed to "top off" or
dribble mix into the haul vehicle. The gates on the silo
should not be opened and closed continually to deliver
only small amounts of mix to the truck. This occurs
most frequently in plants where the surge silos are
placed directly over the truck scales. Because the
OO
operator can quickly determine the amount of mix
Figure 2-67. Correct truck loading sequence (NAPA).
actually in the truck bed by observing the scale readout
on the control console, the tendency is to load the
The vehicle should then be moved backwards again so vehicle right up to the legal limit. This is done by using
that the remaining 20 percent of the mix can be dropped multiple drops of small quantities of mix at the end of
into the center of the bed, between the first two piles. the main delivery. If the discharge of mix from the silo
This loading sequence is shown in Figure 2-67. is timed, however, this procedure is unnecessary and the
If a larger truck is used to deliver the mix, the potential for mix segregation is reduced .
number of drops of material from the silo should be
increased to distribute the mix along the length of the Loading Hopper
truck bed. The first drop of mix should be into the Some silos have a loading hopper or batcher under
front portion of the bed and the second drop should be the cone. If the capacity of the batcher is significantly
near the tailgate. The remaining mix should be deliv- smaller than the capacity of the haul vehicle and if the
ered in evenly divided drops into the rest of the length truck position is changed between batches of mix, the
of the truck bed. In no case should the truck be loaded amount of truckload- to-truckload segregation may be
continuously by the truck driver moving forward under decreased somewhat through the use of the batcher.
the silo as the mix is being discharged . This operation
will cause the coarse aggregate particles to collect at the SUMMARY OF SILO OPERATING TECHNIQUES
tailgate of the truck and increase the amount of segrega- Segregation usually begins at the surge silo, in the
tion that will occur. loading and unloading process . The items that should
The objective is to minimize the distance that the be monitored include the following:
coarser aggregate pieces can roll . This significantly • The conveying device from the discharge chute of
reduces the chance for segregation in the mix. This a drum mix plant or from the hopper under the pugmill
procedure, however, requires that the truck driver of a batch plant must deposit the mix into the center of
reposition the truck under the silo after each drop so the silo if a batcher is not used, or into the center ofthe
that the asphalt mix is spread more evenly on the truck batcher at the top of the silo.
bed. In any case, the truck should not be loaded in one • Longitudinal (side-to-side) segregation is caused
drop of mix from the silo, even if the mix does not have by loading the silo to one side and by the coarser
a tendency to segregate. Multiple discharges are very aggregate particles rolling to the opposite side inside the
beneficial in keeping the mix uniform. Some plants are silo .
equipped with controls to deposit the mix automatically • If longitudinal segregation is present behind the
into the haul truck at predetermined amounts and paver, several haul trucks should be loaded under the
intervals. silo facing in the opposite direction from their normal
The silo discharge operator should be able to deter- loading pattern. When these truckloads of mix are
mine the time it takes to deliver the proper amount of unloaded at the paver, the location of the segregation
mix, per drop, into each haul vehicle. This can be done should change sides in the lane being paved . If this
by timing the discharge of the mix and comparing the happens, the cause of the side-to-side segregation is
time with the weight of mix delivered . Because trucks probably in the procedure used to place the mix into the
are a variety of sizes, the time per drop of mix may be silo from the conveying device .
different from truck to truck, but after a little practice, A batcher should be used at the top of the silo.
the operator should be able to judge accurately the time The batcher should not be operated with its gates wide

Page 2-54
AC 150/5370-14
10/15/91 Appendix 1

open, allowing the mix to pass right through it. The • Truckload-to-truckload segregation is usually
batcher should be filled up with mix and then should caused by the procedure used to load the trucks under
drop the mix in a mass into the center of the silo. the silo. The truck should never be loaded in only one
Further, the gate on the bottom of the batcher should drop of mix into the center of the truck bed. Multiple
be closed before all of the mix is discharged from the drops of mix are necessary, with the first drop located
batcher. near the front of the bed and the second drop of mix
• If the silo is to be used for overnight storage of near the tailgate. Additional drops of mix should be
asphalt mix, the cone should be heated and the silo walls made at intermediate points between the first two drops.
insulated. If mix is stored for more than two days, a • The truck should never be loaded by slowly
small quantity of mix should be withdrawn from the silo driving the truck forward as mix is being delivered from
at least every other day to prevent plugging of the cone. the silo. This will cause the coarser aggregate particles
• If the mix is stored for more than two or three to collect at the tailgate of the truck and significantly
days, the mix should be checked upon discharge for increase the amount of segregation that occurs.
temperature and for the penetration and/or viscosity of • The plant operator should not "top off" or dribble
the recovered asphalt cement from the mix. The mix mix into the truck bed in small drops to fill the truck to
should meet the same specification requirements as a legal capacity.
mix placed immediately after manufacture .

Page 2-55
AC 150/5370-14
Appendix 1
10/15/91

SECTION SIX
EMISSION CONTROL

INTRODUCTION size, weight, and moisture content of the fines; and the
This section discusses the three types of emission- amount ofvery fine particles in the reclaimed aggregate
control equipment found on batch and drum mix plants: (if used in a drum mix plant) . It is also related to the
dry collectors, wet collectors, and baghouses. The dry operation of the drum--the production rate (density of
collector is usually placed in front of one of the other the aggregate veil) , the location of the asphalt cement
two types of collectors and is termed a primary collector. injection pipe (for a drum mixer), and the velocity ofthe
The wet collector (wet scrubber) and the baghouse exhaust gases. The amount of carryout can vary widely
(fabric filter) are secondary collectors through which the with a change in the properties of the incoming aggre-
exhaust gases flow after passing through the primary gate and the production process.
collector. The primary collector is used to remove the The efficiency of the emission-control equipment is
larger fine particles from the exhaust gases and reduce the amount of particulates that are captured by the
the loading on the secondary collector, which is used to equipment versus the amount of particulate matter that
capture the very fine particles. The operation of each of enters the emission-control equipment. If 1000 parti-
the three emission-control devices is reviewed . cles/min enter a baghouse, for example, and 990 of those
particles are caught in the baghouse, the collection
FINES CARRYOUT system is 99 percent efficient. The efficiency can be
All batch and drum mix plants have a small amount determined, in part, by observing the amount of particu-
of fines aggregate carryout from the dryer or the drum lates being emitted from the stack. This is done by
mixer. In order to meet federal and state air quality checking the opacity of the exhaust gas beyond the end
codes, emission-control equipment is necessary to of the steam plume (if one is present) . If a dust trail is
capture particulate emissions that might otherwise be seen, the operation of the emission-control equipment
released to the atmosphere. In addition, some emission- must be checked.
control devices permit the plant operator to control the
amount of fines returned to the asphalt mixture. PRIMARY DRY COLLECTOR
The velocity of the exhaust gases inside a dryer or Dry collectors are not used or needed on all asphalt
drum mixer is primarily a function of the diameter of plants. If employed, the dry collector can be one of
the drum, the capacity of the exhaust fan, and the speed several types, which may be used in combination with
of the exhaust fan. A minimum volume of air is needed each other. When used in combination, the first collec-
for proper operation of the burner. This air, combined tor is referred to as the primary and the second collector
with the products of combustion from the burner and is known as the secondary collector. The original dry
the moisture vapor from the aggregate, moves through collector was a cyclone device that forced the exhaust
the dryer or drum mixer at a velocity that varies with the gases to swirl inside the collector. The dust in the gases
operating conditions of the plant. The amount of fines was removed by centrifugal force; it was thrown to the
carryout increases as the exhaust gas velocity increases. side of the cyclone as the gases moved in a circular
In a drum mixer, the amount of fines carryout can be motion. The operation of a cyclone-type dry collector is
reduced significantly by encapsulating or coating the shown in Figure 2-68.
aggregate with the asphalt cement early in the drying Most dry-collector systems in use today have an
process. The farther up the drum the asphalt cement is expansion chamber combined with a baghouse. The
injected, the more fines are captured in the asphalt expansion chamber or knockout box has a greater cross-
cement before they can become airborne. Typically the sectional area than the ductwork through which the
amount of fines carryout increases as the asphalt cement exhaust gases pass between the dryer or the drum mixer
pipe is positioned farther down toward the discharge end and the secondary collector. A typical knockout box
of the drum . (dry cyclone) used in combination with a baghouse is
The amount of fines carryout is a function of the shown in Figure 2-69. The exhaust gas velocity decreas-
amount of very fine material in the new aggregate; the es significantly when it reaches the increased area of the

Page 2-56
AC 150/5370-14
10/15/91
Appendix 1

dry collector. The largest and heaviest of the fine


particles fall out of the gas stream, in proportion to the
reduction in the speed of the exhaust gases and as the
velocity is decreased . These particles drop to the
bottom of the expansion chamber. The collected
particles can either be returned uniformly to the batch
plant or to the drum mixer, either alone or in combina-
tion with the fines collected by the baghouse, or they
can be wasted.
The efficiency of the primary collector depends in
part on the size of the fine particles in the exhaust gases
and on the type of collector used . Primary collectors
can have an efficiency (the percentage of the amount of
fines removed from the exhaust gases compared with the
total amount of fines in the gases) as low as 50 percent
for a knockout box to as high as 70 to 90 percent when
a dry cyclone is used . Thus, only a portion of the fines
in the exhaust gases are removed by this equipment.
The main purpose of the primary collector is to improve
the operation of the secondary collector by reducing the
fines loading on the wet scrubber or the baghouse.

Figure 2-68. Cyclone operation (Cedarapids).

Figure 2-69. Dry collector and baghouse (H&B) .

Page 2-57
AC 150/5370-14
Appendix 1
10/15/91
GAS WATER SPRAY
IN NOZZLES
WET COLLECTOR
After moving through a primary dry collector , the
exhaust gases on most newer plants equipped with a wet
collector system are forced through a narrowed opening,
or venturi, as shown in Figure 2-70 . When the gas flow
is concentrated in a small area, it is sprayed with water
from multiple nozzles and the fines are wetted . The
exhaust gases and wet fines then travel into the separa-
tor section of the collector.
The exhaust gases are sent into a circular motion
around the circumference of the unit, as seen in Figure THROAT ADJUSTING
2-71 , and the wetted fines, which are relatively heavy, SCREWS
GAS
are removed from the gas stream by centrifugal force OUT
and fall to the bottom of the collector. The clean gas
continues to swirl around the collector until it reaches
Figure 2-70. Venturi collector (Cedarapids).
the end, when it passes out the stack to the atmosphere.
Depending of the size of the fines particles in the
exhaust gases, a wet-scrubber system is usually 90 to 99 shallow, dirty water will be sent back to the scrubber. In
percent efficient in removing particulates from those order to maintain a supply of clean water for use in the
gases. In addition to being related to the size and fines collection equipment, the sediment on the bottom
amount of the fines present, the efficiency is a function of the pond must be removed periodically. In addition,
of both the cleanliness and the volume of water used to water lost from the pond through evaporation and leaks
spray the exhaust gases. If the water sprayed is clean in the piping system should be replaced as necessary.
and free from sediment and if all of the
nozzles in the scrubber are open and work-
ing, the amount of fines removed by the wet-
collector system will increase.
The cleanliness of the water and the
condition of the nozzles is related to the size
of the settling pond used to collect the water
discharged from the scrubber. The water
and fines, in the form of a sludge, are sent
from the bottom of the collector through a
pipe to the first section of the pond, where
the heaviest fines settle out of the water.
The cleaner water at the top of the pond in
this first section is drawn off through an
outlet on the opposite side of the pond.
Additional settling of the fines occurs in
each succeeding section of the pond. The
efficiency of the settlement process is directly
related to the size of the settling pond; the
bigger and deeper the pond, the more water
available, and the more time for the fines to
separate and settle before the water is
pumped from the pond back to the wet-
scrubber unit .
As the settling pond fills up with fines,
the time that the water remains in the pond
and the amount of settlement that can occur
will decrease. When a pond becomes too Figure 2-71 . Venturi separator (Cedarapids).

Page 2-58
AC 150/5370-14
10/15/91
Appendix 1

used as the filter cloth is usually a special type


of synthetic fiber that is resistant to high fines
loadings, high humidity, and high temperature
while undergoing multiple cycles of bending
and flexing. The fabric is dense enough to
catch the particulates while still permitting the
air to pass through. This synthetic fiber materi-
al will char and disintegrate if subjected to
exhaust gas temperatures above 450°F for
extended periods of time.
The fabric is fabricated into a cylindrically
shaped bag and is placed on a circular metal
framework or cage that is closed on the bottom
but open on the top, as shown in Figure 2-74.
The filter bags on the cages are arranged in
rows inside the baghouse, as illustrated in
Figure 2-75. The number of bags needed
depends on the size of the dryer or drum
mixer, the diameter and the length of each
individual bag, and the air-to- cloth ratio re-
quired to meet emission-control specifications.
In general, 1 ft² of filter cloth area is needed to
clean 5 to 7 ft³/min of exhaust gas . The most
common air-to-cloth ratio in use is 6: 1.
Each baghouse has a clean air side and a
dirty air side, as shown in Figures 2-76 and
2-77. The exhaust fan pulls the dirty air from
outside the filter fabric through the material to
the inside. The fines are caught on the outside
Figure 2-72. Baghouse fabric dust collector (Barber-Greene).
surface of the bag and the cleaned exhaust
gases, relieved of the dust, are carried out the
Any fines that are removed from the exhaust gases top of the bag and to the stack. The fines build up on
by the wet scrubber are no longer available for use in the outside of the bag with time and form a dust cake or
the mix. The gradation of the mix produced in the coating on each bag. The degree of coating determines
batch or drum mix plant is thus not the same as the the efficiency of the filter; if the bags are too clean, only
gradation of the incoming new and/or reclaimed aggre- the coarser fines will be caught and the finer particles
gate. In most cases in which the amount of fines
will pass through the fabric; if the bags are too dirty or
carryout is not great, the change in gradation will be blinded, the exhaust gases will be unable to pass through
small, but if a large volume of fines is captured in the the dust cake and the baghouse will stop operating. The
exhaust gases, a significant change can occur in the thickness of the dust cake is generally determined by the
aggregate gradation , particularly in the very fine particle frequency of the filter bag cleaning cycle .
sizes. To remove a portion of the built up dust on the filter
bags, the bags must be cleaned periodically. Bags are
BAGHOUSE cleaned in rows or in groups so that most of the bag-
The exhaust gases that pass through the primary house is in the collecting mode while a few bags are
collector can be pulled by the exhaust fan on the plant being cleaned . The cleaning occurs by flexing or shaking
through another type of secondary collector called a the bags, backflushing them with a pulse of clean air, or
baghouse or fabric filter, as shown in Figures 2-72 and by a combination of both procedures, as shown in Figure
2-73. (Although baghouses can be operated without a 2-78. The most common procedure is the pulse jet
primary collector, this generally reduces the efficiency of system, with a cleaning cycle occurring for only 1/10 sec
the system and is not normally done. ) The material approximately once every 3 min. The particulates

Page 2-59
AC 150/5370-14
Appendix 1 10/15/91

Figure 2-73. Baghouse fabric dust collector (J. Scherocman).

removed from the bags fall to the bottom of the house The synthetic fiber bags, when subjected to tempera-
and are collected for return to the plant or are wasted . tures above 450°F for extended periods of time, can
A baghouse can remove up to 99.9 percent of the char, disintegrate, and then burn . To prevent this,
fines in the exhaust gas stream. This efficiency is mea- temperature sensors and automatic shutdown devices are
sured in part by the amount of pressure drop--generally installed in the ductwork upstream of the baghouse.
in the range of 2 to 6 in. of water column--between the The sensor is typically set at a temperature of 400°F. If
dirty side and the clean side of the bags. Ifthe pressure the temperature of the exhaust gases exceeds this value,
drop is too low (1 to 2 in.), the bags are too clean and the sensor sends a visual and/or audible signal to the
some of the very fine dust particles will pass through the plant operator or may automatically shut off the fuel
filter and up the stack. If the pressure drop is too high flow to the burner. Some baghouses are fitted with
(greater than 6 in .), the fines buildup on the bags is automatic fire extinguisher devices if a fire does occur in
excessive, the exhaust gases will be restricted from the emission-control equipment.
passing through the fabric, and the capacity of the dryer The gradation of the asphalt mix produced in a batch
or drum mixer will be reduced. or drum mix plant may change depending on whether
The efficiency of the baghouse will be affected if the any or all of the baghouse fines are returned to the
temperature of the exhaust gases entering the baghouse
is below the dew point--the temperature of the exhaust
gas at which point the moisture begins to condense, as
CLEAN EXHAUST
shown in Figure 2-79. The moisture, combined with the
fines in the exhaust gases, forms a mudlike coating on
FILTER
BAG

the outside of the bags that cannot easily be removed


during the bag- cleaning cycle. If this happens, the
pressure drop across the bags increases significantly,
reducing the efficiency of the baghouse and even
choking off the burner flame in extreme cases. Το DIRTY EXHAUST
prevent this from occurring, the baghouse must be
preheated by running the burner on " low fire" without
aggregate in the drum before mix production is com- Figure 2-74. Baghouse fabric collector (Barber-
menced each day.
Greene).

Page 2-60
AC 150/5370-14
10/15/91
Appendix 1

plant. If the collected dust is returned, the mix


gradation will be approximately the same as the
gradation of the incoming new and reclaimed
aggregate (assuming minimal degradation of the
aggregate during processing through the dryer or
drum mixer). If the baghouse fines are wasted ,
there may be a considerable change in the mix
gradation. If the fines are returned , it is very
important that they be introduced into the batch
or drum mix plant continuously and uniformly.

FUGITIVE DUST
The primary source of emissions from a batch
or drum mix plant is the fines carryout present in
the exhaust gases during the aggregate heating
and drying process. Additional emissions are
possible, however, in the form of fugitive dust.
This is fine material that leaks from the plant
through holes in the equipment or ductwork
while the plant is operating.
For a batch plant, the three most likely
sources of fugitive dust are the hot elevator, the
plant screens, and the pugmill. As the aggregate
is delivered from the hot elevator to the screen
deck, it passes over the vibrating screens. This
movement creates dust, as does the mixing ofthe
aggregate in the plant pugmill during the dry mix
cycle. Fugitive dust can be eliminated by com-
pletely and tightly enclosing the screen deck area
and by keeping the dry mix time in the pugmill
to a minimum. In addition, a scavenger air
system (fugitive dust-evacuation system) creates
a negative air pressure inside the plant housing
Figure 2-75. Rows of filter bags in baghouse (ICA) . and reduces the amount of dust carryout during
plant operations. This system usually consists of
ductwork with adjustable dampers extending from the
FABRIC FILTER
screen deck, hot bins, weigh hopper, and pugmill
sections to the inlet of a fugitive dust fan, which then
DUST LADEN AIR blows the dust into the secondary collector. On some
plants, a fugitive dust fan is not used . In this instance,
the ductwork extends directly to the inlet of the second-
ary collector.
For both a batch plant and a drum mix plant, holes
in the emission-control equipment, primarily in the
ductwork between the end of the dryer or drum mixer
CLEAN AIR and the dry or wet collector, may allow the escape of
fine aggregate particles. These holes should be patched
to permit all of the dust in the exhaust gases to be
drawn into the emission-control collectors. Further, the

Figure 2-76. Clean air-dirty air sides of a filter (Bar- holes should be eliminated in order to prevent the
ber-Greene). exhaust fan from drawing in excess (leakage) air and

Page 2-61
AC 150/5370-14
Appendix 1 10/15/91

reducing the amount of air available for combustion at


the burner.

SUMMARY OF EMISSION-CONTROL OPERATING CLEAN SIDE


TECHNIQUES
The following items should be monitored when
observing the operation of the emission-control equip-
ment:
• The discharge of the exhaust gases from the stack
should be observed for a dust trail at the end of the DIRTY RIDE

steam plume. If one exists, the operation of the emis-


sion-control equipment should be checked.
• If a wet scrubber is used, the spray nozzles in the Figure 2-77. Clean air-dirty air sides in baghouse
venturi should be checked to assure that all are open (Barber-Greene).
and spraying water.
• The cleanliness of the water being returned to the
spray nozzles from the pond should be checked at the PNEUMATIC
FLEXING
point at which the water is drawn from the pond by the PREFERRED
water pump .
• If a baghouse is used, the pressure drop across
the bags should be in the range of 2 to 6 in. of water
column.
• The temperature of the exhaust gases entering the
baghouse should be less than 400°F. An automatic
shutoff device should be used to stop the operation of
the plant if the exhaust gas temperature exceeds this
value . The temperature should be considerably less if
the veil of aggregate inside the dryer or drum mixer is
correct.
Figure 2-78. Cleaning by flexing or shaking bags
• The relationship between the gradation ofthe mix (Barber-Greene).
produced in the batch or drum mix plant should be
compared with the gradation used in the mix design
process. The amount of change in gradation will depend
on whether a wet-scrubber system is used or whether the
baghouse fines are returned to the plant or wasted .

350
250
450
0 500
15

Figure 2-79. Bag blinding dew point (Barber-Greene).

Page 2-62
AC 150/5370-14
10/15/91
Appendix 1

SECTION SEVEN
BATCH PLANT

INTRODUCTION Figures 2-80 and 2-81 and are discussed in depth. The
Discussed in this section are the major components screening of the aggregate is discussed , as is the delivery
of a batch plant: the cold-feed system, asphalt cement of the aggregate to the pugmill . The required dry mix
supply system, aggregate dryer, and mixing tower, as and wet mix times for the blending of the aggregate and
shown in Figure 2-80. In most cases, the cold-feed the asphalt cement are given. The introduction of RAP
system for a batch plant is similar to the equipment used into the process is also presented .
for a drum mix plant. The asphalt cement feed system
operates, for the vast majority of the batch plants, on a AGGREGATE HANDLING
weight basis instead of a volume basis. The aggregate Aggregate Stockpiles
dryer operates on a counter flow basis in contrast to The stockpiling techniques used for handling aggre-
most drum mixers, which use a parallel -flow type of gate in a batch plant mixing operation are no different
system . The heating and drying of the aggregate from the procedures used for handling aggregate when
through the dryer is reviewed . producing a mix in a drum mix plant. Care needs to be
The batch plant tower is made up of several key taken to keep the various aggregate sizes separate and
components: hot elevator, screen deck, hot bins, weigh to prevent segregation of each size of aggregate in the
hopper, and pugmill . These components are shown in stockpile.

Figure 2-80. Batch plant layout (Cedarapids).

Page 2-63
AC 150/5370-14
Appendix 1 10/15/91

Hot
Asphalt Heating asphalt Measuring
cement
storage

Stockpiled Cold Drying


bins Screening aggregate Measuring Mixing Hot Mix
aggregates (Heating) storage
*0 =-=--

Mineral
filler Measuring
storage

Drying
(Heating)
Asphalt
cement
Screening

Mineral
3 2 1 filler
A
Measuring Measuring
Cold bins
Mixing

Stockpiled
aggregates

Figure 2-81 . Batch plant flow chart (Asphalt Institute) .

It is sometimes assumed that the screens in the batch aggregate to a scalping screen, if one is used. After the
plant tower will overcome any problems with variations aggregate passes through the scalping screen, it is
in the gradation of the incoming new aggregate. If the deposited onto the charging conveyor for delivery to the
proper proportion of each size of aggregate is not dryer. If no scalping screen is included in the system
delivered from the cold-feed bins, however, the amount (which is normally the case, because the screens at the
of aggregate in the hot bins will be out of balance. One top of the plant tower are used to remove oversize
or more of the hot bins may be starved for material or material) the aggregate is transferred directly from the
one of the hot bins may be overflowing if the aggregate gathering conveyor to the charging conveyor.
feed at the cold-feed bins is not correct because of lack
of separation between the aggregate stockpiles or segre- Cold-Feed Systems for RAP
gation of the aggregate in one or more stockpiles. Reclaimed asphalt pavement is usually held in a
Proper stockpiling techniques are as important for batch separate, steep-sided cold -feed bin that is equipped with
plant operations as they are for drum mix plant opera- either a variable-speed or constant-speed feeder belt.
tions. The material from the bin is deposited on the feeder
conveyor and/or onto a gathering conveyor for transport
Cold-Feed Systems for New Aggregates to a scalping screen. After passing through the scalping
Some batch plant cold-feed bins are equipped with a screen, the RAP is deposited on a charging conveyor for
constant-speed feeder belt under each bin. The amount delivery to the plant. An alternative to the use of the
of aggregate withdrawn from each bin is controlled by scalping screen at the transfer point between the gather-
the size of the gate opening at the bottom of the bin. ing conveyor and the charging conveyor is to place the
Most plants, however, have cold-feed bins that are scalping screen or grizzly on top of the cold-feed bin so
equipped with a variable-speed feeder belt beneath each that the RAP passes through the screen as it is being
bin. The amount of aggregate withdrawn from each bin placed in the bin.
is regulated by the size of the gate opening and the The RAP cannot be heated in the dryer because it
speed of the conveyor belt. The aggregate is discharged will generate visible hydrocarbon emissions when
from each feeder belt onto the gathering conveyor, exposed to the high-temperature exhaust gases from the
which runs underneath all of the bins and delivers the burner. Thus, the feed of the RAP must be separated

Page 2-64
AC 150/5370-14
10/15/91
Appendix 1

from the feed of the new aggregate. The RAP can counter flow principle. The aggregate is charged into
enter into the plant at one of three primary locations the dryer at the upper end of the drum and flows
downstream of the dryer: the bottom of the hot elevator, through the dryer by the action of the rotating flights
one of the hot bins at the top of the tower, or the weigh and gravity. The burner is located at the lower or
hopper. The last location is the preferred one. discharge end of the dryer. The exhaust gases move
toward the upper end of the dryer, in the opposite
ADDITION OF HYDRATED LIME direction to the flow of the aggregate--the counter flow
Hydrated lime can be added to the aggregate in a system. This process is shown in Figure 2-82.
batch plant mixing operation in one of two places. The
additive can be placed on the aggregate, either in dry or
slurry form, similar to the method of addition for a
drum mix plant. It can also be added in dry form to the
aggregate similar to a mineral filler.

ASPHALT CEMENT SUPPLY SYSTEM


Storage Tanks
The storage tank used for the asphalt cement for a
batch plant operation is the same as that used for a
drum mix plant. The material is stored at temperatures
generally between 300°F and 350°F, depending on the Figure 2-82. Counter flow dryer (Barber-Greene) .
grade and viscosity of the asphalt cement needed to mix
properly with the aggregate in the pugmill. The dryer is a rotating drum that is generally 5 to 10
ft in diameter and 20 to 40 ft long. The length of the
Pump System drum is normally proportional to the diameter at a ratio
The asphalt content of the mix is determined by of 4: 1 . Thus, a dryer with a diameter of 8 ft would
weight, not volume. Thus, no meter is used to propor- typically be 32 ft in length. The function of the dryer is
tion the amount of asphalt cement needed in the mix. to remove the moisture from the aggregate and to heat
The pump, which runs continuously, pulls the asphalt that material to the desired discharge temperature,
cement from the storage tank and either delivers it to generally in the range of 290°F to 325°F. The moisture
the weigh bucket or recirculates it to the tank, depend- content of the aggregate should be less than 0.5 percent
ing on the opening of the control valve at the weigh upon exiting the dryer and ideally less than 0.2 percent.
bucket. The aggregate is fed into the dryer from the charging
conveyor either by means of a charging chute at the top
ADDITION OF LIQUID ANTISTRIP ADDITIVES of the dryer or, occasionally, by a slinger conveyor at the
Liquid antistrip additives are added to the asphalt bottom of the dryer. The flights inside the dryer, shown
cement in the batch plant in a manner similar to that for in Figure 2-83, are used to lift and tumble the material
a drum mixer. The additive can be in-line blended with in a veil across the cross-sectional area of the dryer. As
the asphalt cement as that material is pumped out of the the aggregate flows down the dryer, it is heated by the
delivery vehicle or as it is pumped from the storage tank exhaust gases and the moisture is driven off. The
to the weigh bucket. In addition, it can be blended with burner flame, which generally has a much longer,
the asphalt cement in the storage tank by circulating the thinner shape than the short, bushy flame used with the
two materials together for a period of time before the burner on a drum mix plant, extends into the dryer to
treated material is pumped to the asphalt cement weigh penetrate the aggregate veil. The exhaust gases from the
bucket. burner heat and dry the aggregate by conduction,
convection, and radiation. Because of the higher
AGGREGATE HEATING AND DRYING efficiency of the counter flow system, a batch plant dryer
In contrast to the parallel-flow operation of a drum typically uses less fuel to heat and dry a given amount of
mixer, the dryer on the batch plant operates on a aggregate than does the parallel-flow system used in a

Page 2-65
AC 150/5370-14
Appendix 1 10/15/91

y l
or
Co c
xx
Figure 2-83. Flights inside dryer (Cedarapids).

drum mixer. SCREENING AND STORAGE OF HOT AGGREGATE


The dwell or residence time of the aggregate inside Hot Elevator
the dryer is a function of the length of the drum , the New Aggregate
design of the flights, the number of flights, the speed of The heated and dried aggregate is discharged from
rotation, and the slope of the dryer (typically between 2 the dryer through a chute into the bottom of the hot-
1/2 degrees and 6 degrees or 5/16 in./ft and 3/4 in./ft, bucket elevator. The material is transported by the
respectively) . If moisture greater than 0.5 percent continuously moving buckets up to the top of the batch
remains in the aggregate upon discharge from the dryer, plant tower as illustrated in Figure 2-84.
the density of the veil of aggregate inside the drum must
be increased , typically by lowering the slope of the dryer, Reclaimed Material
or by changing the number and/or type of flights used in It is not recommended to add the RAP into the plant
the dryer. Either of these will increase the dwell time of at the bottom of the hot elevator, particularly when the
the aggregate inside the dryer. amount of RAP exceeds approximately 10 percent in the
Because the aggregate typically makes up between 92 mix; however, small amounts of reclaimed asphalt
and 96 percent of the weight of the mix, it governs the material can be introduced there . The RAP should be
temperature of the asphalt mix produced in the pugmill. fed, if possible, into the new aggregate discharge chute
Excessive heating of the aggregate may cause excessive from the dryer so that it is on top of the new aggregate
hardening of the asphalt cement in the mixing process. and directed into the center of the buckets. If that is
If a recycled mix is to be produced, however, the new not feasible, the reclaimed material should be deposited
aggregate must be superheated in the dryer in order to into a separate steep-sided chute located above the new
accomplish the necessary heat exchange in the pugmill. aggregate entry at the bottom of the hot elevator. The
In this case, the temperature of the new aggregate is RAP must be placed in the buckets after the new aggre-
dependent on the amount and the moisture content of gate to prevent the asphalt-coated material from sticking
the RAP, as discussed later in this section. to the buckets as it is heated by contact with the super-

Page 2-66
AC 150/5370-14
10/15/91
Appendix 1

Figure 2-84. Hot- bucket elevator and batch plant tower (Portec) .

heated new aggregate. heated enough while in the hot-bucket elevator to stick
There is a limit to the amount of RAP that can be to the screen instead of passing through the screens .
fed into the bottom of the hot elevator and it is related This may clog (blind) the screens and eventually cause
to the heating process as the material travels to the top shutdown of the plant. Thus, the screens may be
of the tower. Depending on the percentage of RAP removed or bypassed when the RAP is added at the
used in the mix, the moisture content of the RAP, and bottom of the hot-bucket elevator if this becomes a
environmental conditions, the reclaimed material can be problem .

Page 2-67
AC 150/5370-14
Appendix 1 10/15/91

Screen Deck proper screens need to be used in the screen deck in


The aggregate is discharged from the hot-elevator order to produce the required gradation in the asphalt
buckets onto a set of vibrating screens that are used to mix. If mix gradations change significantly, it may be
separate the material into different sizes. Four screen necessary to change the screen sizes used at the top of
decks typically are used, arranged as shown in Figures the mixing tower. Different-size screens than those in
2-84 and 2-85. The top screen is generally a scalping the example above may be used for different combina-
screen to remove any oversized material from the aggre- tions of aggregate for different agency specifications.
gate flow and reject it to a bypass/overflow chute. The In addition, many screen decks will use a split-screen
remaining three screen decks divide the aggregate into setup in which screens with two different-size openings
four different fractions. The amount of material in each are placed at the same level (in the same deck) . For
fraction is dependent on the size and shape of the example, the top screen deck might employ a screen
openings in the screens. Each screen deck may have with an opening of 5/16 in . for the half of the deck
several different screen sizes in order to improve screen- nearest to the hot elevator and a screen with an opening
ing efficiency and to protect the smaller screens from of 1 1/4 in. for the half of the deck over the No. 3 and
oversize aggregate . No. 4 hot bins. This arrangement is done to improve
The screens can have square, rectangular, or slotted the efficiency of the screening operation .
openings, with square openings being most common. Not all of the material that should be in a particular
For example, for a typical batch plant that would bin always ends up in that bin. The amount of aggre-
manufacture base, binder, and surface course mixes, the gate that is sand-sized and that should pass through all
size of the openings in a square screen might be 1 1/4 in. of the screens and end up in the No. 1 bin but instead
for the top deck, 9/16 in . for the second deck, 5/16 in. is deposited into the No. 2 hot bin is called carryover.
for the third deck, and 5/32 in. for the bottom deck. A small amount of carryover, generally less than 10
The sand-sized aggregate, smaller than 5/32 in. in percent, from one bin to the adjacent bin is often found.
diameter, would pass directly through all of the screens The carryover is caused by the flow of aggregate moving
and be deposited into the No. 1 hot bin. Aggregate that across and through the screens. It is increased as the
was larger than 5/32 in., but no greater than 5/16 in., openings in the screens become clogged or blinded with
would be carried over the first screen and then dropped aggregate and as the amount of aggregate being deliv-
into the No. 2 hot bin. For any particular mix, the ered by the hot elevator is increased . The primary

Hot aggregates
from hot elevator

Rejected

oversize

20.00 aggregates




Fine aggregates Medium coarse


aggregates
Intermediate fine
aggregates Coarse aggregates

Figure 2-85. Screen deck (Asphalt Institute) .

Page 2-68
AC 150/5370-14
10/15/91
Appendix 1

problem is when the amount of carryover is variable gradation than will be the aggregate on the opposite side
from one time to another, causing the gradation of the of the same hot bin.
aggregate found in each of the hot bins to change . This The partitions between each hot bin should be
is often caused by continued variation in the rate of feed checked regularly to ensure that no holes have devel-
of the aggregate from the cold-feed bins. oped and that aggregate in one bin is not flowing into
If the screen develops tears or holes, some of the the adjacent bin. The overflow pipes at the top of each
aggregate that should be deposited in another bin will bin should be open. Fines sometimes build up in the
pass through the screen and end up in a bin with corners of the No. 1 bin. When the level of aggregate
smaller-sized material. The screens at the top of the in the bin is low, the collected fines can break loose and
tower should be checked regularly to ensure that there a slug of the material can enter the weigh hopper. If
are no holes and that the screens are not clogged with this is a continuing problem with a particular plant,
aggregate and blinded . fillets can be welded in the corners of the No. 1 bin to
In some locations, batch plants are routinely operat- reduce the buildup of the fine material, or a plate can
ed without screens; the screen deck is removed or a be used at the top of the No. 1 bin to deflect the fines
screen bypass chute is used . All of the aggregate that is into the center of the bin.
transported up the hot elevator is deposited directly into Even though the screens on the batch plant are used
the No. 1 bin. Without screens, the batch plant will be to regrade the aggregate that is fed into the plant from
operated in essentially the same manner as a drum mix the cold-feed bins, the proportion of material delivered
plant and will depend on the consistency of the grada- from each cold -feed bin must be correct or one of the
tion of the aggregate in the cold-feed bins to determine hot bins will either run out of material or overflow.
the final gradation of the mix. Because no screening is Because all the aggregate that is discharged from the
done to separate the aggregate into sizes, the various cold-feed bins will end up in the mix, it is very important
gradations that were proportioned out of the cold-feed that the aggregate placed in the cold-feed bins is graded
bins (unless only one aggregate blend is used to make consistently. The screens should not be used to attempt
the mix) will be deposited directly into the No. 1 hot bin to overcome a problem with a variable incoming aggre-
upon discharge from the hot elevator . All of the aggre- gate gradation .
gate used in the mix will then be drawn from this one
hot bin into the weigh hopper and then into the pugmill. RAP
Although not a recommended practice, RAP has
Hot Bins been deposited directly into one of the hot bins on the
New Aggregate plant. A separate charging conveyor or bucket elevator
The total capacity of the hot bins is usually propor- is used to carry the reclaimed material to the top of the
tional to the size of the pugmill. The capacity of each plant. The RAP is deposited through a screen bypass
of the hot bins, however, is not the same. The greatest
capacity is in the No. 1 (sand) bin, as seen in Figure
2-84. Generally about 40 percent by weight of the
aggregate delivered by the hot elevator passes through
the screens and into this bin. The typical capacity (the
percent of the total hot-bin capacity) of each of the
remaining three bins is 30 percent for bin No. 2, 20
percent for bin No. 3, and 10 percent for bin No. 4.
Some segregation of the aggregate occurs in each hot
bin, and particularly in the No. 1 sand bin, as shown in
Figure 2-86. This is caused by the finer material in each
size fraction passing through the screens more directly
than the coarser material of the same aggregate size.
Thus, the aggregate on the side of each hot bin that is
the closest to the hot elevator will generally be finer in
Figure 2-86. Hot-bin segregation (Asphalt Institute).

Page 2-69
AC 150/5370-14
Appendix 1 10/15/91

directly into the No. 1 hot bin with the sand or into the located on the plant tower just above the weigh hopper.
No. 4 hot bin if no other aggregate is in that bin--when It is then added to the weigh hopper by means of a
a surface course mix is being produced and no large horizontal screw conveyor . On some batch plants, the
aggregate is needed . Further, if the RAP is placed in filler is weighed separately from the other aggregate and
the No. 1 hot bin, the heat-transfer process can begin then augered into the main aggregate weigh hopper
between the superheated sand and the ambient-tempera- after the aggregate from the hot bins has been weighed.
ture RAP while both are together in the hot bin. If the On other plants, the filler is weighed as a fifth aggregate
asphalt-coated material is placed in the No. 4 bin, no as it is added to the material already in the hopper.
such heat advantage is realized because of a lack of
heated new aggregate in that bin. Reclaimed Material
The disadvantage of placing the RAP in either the The best location to add RAP to a batch plant is into
No. 1 or the No. 4 bin is that some of the asphalt- coated the weigh hopper. Once the aggregate from the hot
particles will stick to the walls of the bin. This can be a bins has been deposited in the hopper and weighed, the
major problem, particularly if the amount of reclaimed reclaimed material is usually fed into the hopper as a
material used in the mix and the moisture content of fifth aggregate (or as the sixth aggregate, if mineral filler
that material are both high. If superheated new aggre- is used in the mix), although it can actually be added to
gate is in the bin adjacent to the RAP, a significant the weigh hopper in any order except first. The charg-
amount of the RAP will stick to the partition between ing conveyor used to deliver the RAP to the weigh
the two bins . hopper, shown in Figure 2-87, must be oversized in this
case because it does not run continuously. The RAP
WEIGH HOPPER should be deposited into the weigh hopper in approxi-
New Aggregate mately 5 sec.
If a base course mix is being produced, all four of The RAP must be discharged from the charging
the hot bins may be filled with aggregate. If a binder or conveyor into a steeply angled chute (in order to prevent
surface course mix is manufactured, only two or three of it from "hanging up" in the chute) and then into the
the hot bins will normally be needed . The aggregate in center of the weigh hopper, as shown in Figure 2-88 . If
the hot bins can be discharged into the weigh hopper in this material is deposited on one side of the weigh
any order, and typically the coarse aggregate is dis- hopper to the point that the hopper is unbalanced, an
charged into the weigh hopper before the fine aggregate accurate weight will not be determined . The charging
is deposited. Normally the gate at the bottom of the chute should be equipped with a flop gate to prevent the
No. 3 hot bin is opened and the aggregate is discharged escape of fugitive dust from the weigh hopper area when
into the weigh hopper until the correct weight is the aggregate is emptied into the pugmill.
reached . The gate on the No. 3 bin is then shut and the
gate on the No. 2 hot bin opened and the weigh hopper PUGMILL
filled with that material until the correct cumulative Capacity
weight (combined weight of the No. 3 bin and the No. 2 The aggregate and the asphalt cement are blended
bin material) is reached . The aggregate in each of the together in a twin-shaft pugmill. Mixing paddles, shown
last two hot bins (the No. 1 and No. 4 bins) is added to in Figure 2-89, are attached to two horizontal shafts that
the weigh hopper in the same manner. The weighing of rotate in opposite directions . The aggregate is first
each aggregate is accomplished in about 5 sec. It is discharged from the weigh hopper into the pugmill and
important that the aggregate delivered from each hot is mixed for a very brief time (dry mix time) before the
bin be deposited as near the center of the weigh hopper asphalt cement is introduced into the pugmill and the
as possible so that the hopper is not unbalanced on the wet mix time begins. When the mixing is completed, the
scale and spillage of the aggregate does not occur. asphalt mix is discharged from the pugmill directly into
If mineral filler is needed in the mix, it is normally a haul truck or into the conveying device for transport
added to the aggregate already in the weigh hopper. to the silo.
The filler is delivered pneumatically or mechanically The size of the batch produced depends on the size
from a storage silo to a small holding hopper typically of the pugmill. Some batch plants have a pugmill

Page 2-70
AC 150/5370-14
10/15/91
Appendix 1

too much aggregate is placed in the pugmill, the materi-


al above the paddle tips will tend to stay on top and not
be mixed with the other aggregate. If too little aggre-
gate is deposited into the pugmill, the material will be
thrown around by the paddles instead of mixed . These
two conditions are illustrated in Figures 2-91 and 2-92.
Batch size should not be varied from batch to batch.
Consistent mix is obtained by selecting a batch size at or
slightly less than the nominal capacity of the pugmill and
producing all batches at that tonnage. If the plant is
equipped with a 3-ton pugmill and the average haul
truck being used can hold 14 tons of mix, the batch size
selected should be 2.8 tons ( 14 tons per truck divided by
five batches). The plant operator should not attempt to
produce four batches of 3 tons each and a fifth batch of
only 2 tons. Consistent batch size is one of the keys to
a consistent mix.

Mixing Time
Dry Mix Time
Dry mix time is defined as the time between when
the aggregate starts to be charged and when asphalt
injection starts. Dry mix time should be minimal;
normally no more than 1 or 2 sec. Although the aggre-
gate in the weigh hopper is layered, the different-size
aggregates can be blended adequately during the wet
mix cycle and do not need to be premixed during the dry
mix cycle. The main purpose of the dry mix time is to
allow some aggregate to enter the pugmill before the
asphalt cement is discharged so that it does not run out
of the gates at the bottom of the pugmill.
There is no evidence that a longer dry mix time
improves the quality of the asphalt concrete mix. Dry
mix times of various lengths, from 1 to 20 sec, have been
used and gradation tests conducted on the mix produced
Figure 2-87. RAP conveyor to batch plant weigh from the batch plant. No difference was found in the
hopper (J. Scherocman). uniformity of the aggregate gradation regardless of the
length of the dry mix time. Thus, increasing dry mix
capacity as little as 1 ton. Most batch plants, however, time decreases the plant production rate without benefit-
are equipped with pugmills that have capacities between ing the mix, and causes additional wear on pugmill
2 and 5 tons. One of the largest batch plant pugmills paddles and liners.

made has the capability to mix 11.5 tons (23,000 lb) of


Wet Mix Time
mix in a single batch . The total mixing time for all of
the different batch sizes is the same--typically as short 35 While the aggregate is still being discharged from the
sec/batch. The only difference is the size of each batch, weigh hopper into the pugmill, the addition of the
not the time needed to produce it. asphalt cement commences. This material is fed into the

Nominal pugmill capacity is determined by the pugmill by gravity flow or pressure spray and is added
dimensions of the live zone, as shown in Figure 2-90 . If through one pipe in the center of the pugmill or through

Page 2-71
AC 150/5370-14
Appendix 1
10/15/91

Figure 2-88. Reclaimed material chute to weigh hopper (J. Scherocman).

two pipes, one over each of the two mixing shafts, as 10 sec for all the asphalt cement to be discharged from
seen in Figure 2-93. The wet mix time starts when the the weigh bucket. Pressure injection systems can be
asphalt enters the pugmill. Typically it takes from 5 to used to reduce the time to introduce the asphalt cement

Figure 2-89. Twin-shaft pugmill (Cedarapids).

Page 2-72
AC 150/5370-14
10/15/91
Appendix 1

into the pugmill.


Wet mix time should be no longer than it takes to
coat the aggregate with asphalt cement. If the paddle
tips and pugmill liners are in good condition and the
LIVE

Х
pugmill is full, the wet mix time can be as short as 27 ZONE
sec. If the paddle tips are worn, the wet mix time will
be extended slightly but typically should not be more
than 33 sec. Because they affect the amount of wet mix
time, the condition of the paddle tips should be checked
regularly and the tips should be changed when neces- Figure 2-90. Pugmill live zone (Asphalt Institute).
sary. As a general rule, a 30-sec wet mix time is very
adequate to distribute the asphalt cement and coat the
aggregate.
The mixing time should be as short as possible to
avoid excessive hardening of the asphalt cement when it
is exposed to high temperatures in a thin film around
the aggregate particles. The required wet mix time can
be established using the Ross Count procedure to
determine the degree of particle coating of the coarse
aggregate in the mix as given in ASTM D 2489. Once
the asphalt cement is properly distributed, additional wet
mix time does not improve the coating but only oxidizes
Figure 2-91 . Too much aggregate (Asphalt Institute).
(hardens) the asphalt cement.
Coating of the aggregate in a pugmill occurs first
with the smallest-size aggregate particles. If wet mixing
was only done for 10 sec and the material discharged
from the pugmill at the end of that time, only the
smaller fine aggregate (the material finer than the
No. 30 or No. 40 (600 μm or 425 μm) sieve) would
typically be coated with the asphalt cement; the coarser
aggregate particles, however, would only be partially
coated with asphalt. If wet mixing time was extended to
20 sec and the material discharged from the pugmill at
the end of that time, only the aggregate of No. 4 (4.75
mm) sieve size and smaller would typically be coated Figure 2-92. Too little aggregate (Asphalt Institute).
with asphalt cement; the coarser aggregate particle
would still remain uncoated . Complete coating of all the tion capacity of a plant. If a 1 -sec dry mix time and a
coarse aggregate in the mix usually takes about 26 to 28 27-sec wet mix time are used, proper mixing of the two
sec of wet mixing time in a pugmill with paddle tips and materials can be accomplished in 28 sec. Given approxi-
lining in good condition. Thus the Ross Count proce- mately 7 sec more to open the gates at the bottom of
dure, which looks only at the degree of asphalt coating the pugmill, discharge the mix, and close the gates, the
on the coarse aggregate particles (larger than the No. 4 total cycle time to produce a batch of asphalt concrete
sieve) , is an effective way to determine the minimum mix is 35 sec. This time is the same whether the batch
amount of wet mix time needed to properly distribute size is 2 tons or 5 tons. Theoretically, if a plant having
the asphalt cement throughout the aggregate. a pugmill capacity of 5 tons is run continuously for 1 hr,
514 tons of asphalt mix can be manufactured .
Total Mix Time If a 5-sec dry mix time and a 35-sec wet mix time
Mixing time also has a direct effect on the produc- were required by specification, the total cycle time to

Page 2-73
AC 150/5370-14
Appendix 1 10/15/91

SCALE
DIAL

Pugmill Fill pipe


spray bars

Scale-mounted
weigh bucket
PUGMILL
Surge tank

Spray pump for


pressure system

Asphalt cement is weighed separately


in a scale-mounted weigh bucket .

Figure 2-93. AC flow to pug mill (Asphalt Institute) .

produce the mix would be 47 sec ( assuming a 7-sec gate performance of the mix will be less than when the wet
opening/closing and mix discharge time) . This increased mix time is lengthened . Again, the plant should not be
cycle time (47 sec compared with 35 sec) would decrease idled during the wet mix time.
the amount of mix produced in a 5 -ton-capacity pugmill When the incoming aggregate has a high moisture
from 514 tons to 383 tons/hr. If a 60 -sec total cycle time content, the dryer may not have enough capacity to
were used , the production rate for the same plant would remove all of the moisture efficiently. In some cases,
be reduced to only 300 tons/hr. As expected, the dry the capacity of the screens is not great enough to handle
and wet mix times have a significant effect on the all of the aggregate being delivered, particularly if the
amount of mix produced by a given plant. screens are clogged or blinded . The production rate of
If the plant is not equipped with a silo, there will be the plant will be reduced (total cycle time increased)
times when the plant production may have to be inter- while waiting for dry material in the hot bins. If this
rupted because of a lack of available haul trucks . This problem occurs, the plant operator must not increase the
problem must be monitored by the plant operator. In total cycle time by arbitrarily increasing the wet mix
no case should the plant mixing time be extended during time. The total cycle time should be increased by
the wet mix cycle. If the asphalt cement has been added delaying the discharge of the aggregate from the weigh
to the aggregate and the wet mixing time is extended to hopper into the pugmill and thus "mixing air" instead of
40 or 50 sec or longer, excessive hardening of the aggregate (increased dry mix time) or instead of asphalt
asphalt cement will occur. This extended wet mix time mix (increased wet mix time).
can be very detrimental to the long-term performance of
the mix on the roadway. PRODUCING RECYCLED MIX
If trucks are not available, the plant should be idled Recycling Variables
with no material in the pugmill; the paddles should be The temperature of the new aggregate governs the
"mixing air." The second choice, but not nearly as good amount of reclaimed material that can be introduced
as the first choice, is to let the plant wait during the dry into a recycled mix produced in a batch plant. For the
mix time; the aggregate is in the pugmill but the asphalt heat transfer to take place from the heated new aggre-
cement has not been added . Depending on the length gate to the ambient-temperature RAP, the new aggre-
of the extended dry mix time, some degradation of the gate must be superheated --heated to a temperature
aggregate may occur, but the effect on the long-term above that needed to produce a conventional asphalt

Page 2-74
AC 150/5370-14
10/15/91 Appendix 1

concrete mixture. This heat transfer can take place in only 20 percent reclaimed material is used and if the
the hot elevator, in the hot bins, in the weigh hopper, or moisture content of that material is 4 percent for a mix
in the pugmill, depending on where the RAP is intro- discharge temperature of 280° F, the new aggregate
duced into the plant. For most dryers, in order not to discharge temperature would need to be 415°F, as
reduce the life of the dryer and to keep from driving off determined from Section B of Figure 2-94 . Increasing
internal (hygroscopic) moisture in the aggregate, the the amount of RAP to 50 percent, using Section E of
maximum new aggregate temperature upon discharge the same table and for the same value of moisture
from the dryer should be about 500°F. content (4 percent) and mix discharge temperature
The three primary variables that determine the (280°F), the new aggregate temperature must be raised
temperature to which the new aggregate has to be to 760°F to accomplish the heat-transfer process. This
heated to accomplish the necessary heat transfer are the latter temperature significantly exceeds the recommend-
moisture content of the reclaimed material, the dis- ed maximum new aggregate temperature of 500°F .
charge temperature of the final recycled mix, and the
amount of reclaimed material used . Depending on the Dryer Operation
values for these variables, up to 50 percent RAP can be If the temperature of the new aggregate exiting the
blended with new aggregate to manufacture a recycled dryer exceeds approximately 500 °F, the cost of operating
asphalt concrete mix. and maintaining the dryer can increase significantly.
Because of extremely high aggregate temperatures and
Moisture Content the reduced volume of aggregate in the dryer when a
As the moisture content of the reclaimed material large percentage of RAP is used in the recycled mix
increases, the required new aggregate temperature compared with a normal mix, the veil of aggregate inside
increases significantly. This is illustrated in Figure 2-94. the dryer will typically not be adequate. This lack of veil
If 20 percent RAP is used in the mix, the moisture will increase the temperature of the dryer shell and may
content of that material is 1 percent, and the required require increased maintenance on the inside of the
mix discharge temperature is 260°F, the temperature to dryer, especially on the discharge flights.
which the new aggregate would need to be heated would If the mix production is stopped for a long period of
be 350°F, as seen in Section B of this table. If the same time because of a lack of haul trucks or because of
RAP had a moisture content of 4 percent, however, the mechanical problems, the superheated new aggregate
new aggregate temperature would need to be increased will lie in the bottom portion of the dryer. If the
to 390°F for the same amount of reclaimed material and temperature of this material is greater than about 500°F,
the same mix discharge temperature . warping of the drum shell can occur and the dryer will
be out of round. Further, at the end of each production
Mix Discharge Temperature cycle, the dryer should be allowed to run empty with the
Using Section C of Figure 2-94 as an illustration, the exhaust fan operating for a reasonable cooling down
amount of RAP incorporated into the mix is 30 percent. period after aggregate feed shutdown. This cooling
If the moisture content of this material is 3 percent as it procedure will protect against possible warping of the
is delivered to the plant, the new aggregate temperature dryer shell and the flights.
would need to be at least 385°F when the mix discharge
temperature is only 220°F. If the discharge temperature Visible Emissions
was 280°F, the temperature of the new aggregate would When the RAP is deposited on top of the super-
need to be increased to 475°F, however. Thus, a higher heated new aggregate in the weigh hopper and when the
mix discharge temperature for the recycled mix from the two materials are mixed together in the pugmill, emis-
pugmill requires an increase in the new aggregate tem- sions of both moisture and dust can occur. These
perature from the dryer. emissions are caused by the escape of the moisture, in
the form of steam, from the RAP. The amount of
Amount of Reclaimed Material moisture vapor, as well as blue smoke, released can be
As the amount of RAP in the recycled mix increases, quite large. For a mix containing 50 percent reclaimed
the new aggregate temperature also must increase . If material in a 3-ton batch of recycled mix, with a mois-

Page 2-75
AC 150/5370-14
Appendix 1
10/15/91

Required Aggregate Temperatures

A. Ratio: 10% RAP/90% Aggregate

Reclaimed Material Recycled Mix Discharge Temperature, " F


Moisture Content 220 F 240 F 260 F 280 F
% 104 " C 116 C 127 C 138° C
012345

250 280 305 325


260 290 310 335
270 295 315 340
280 300 325 345
285 305 330 350
290 315 335 360

B. Ratio: 20% RAP/80% Aggregate


DON

0 280 310 335 360


O
-

1 295 320 350 375


2 310 335 360 385
3 325 350 375 400
4 340 365 390 415
5 355 380 405 430

C. Ratio: 30% RAP/70% Aggregate


CION

315 345 375 405


335 365 395 425
360 390 420 450
-
0

3 385 415 445 475


410 440 470 $ 500
5 435 465 495 525

D. Ratio: 40 % RAP/60% Aggregate.


0 355 390 425 460
1 390 425 460 495
2 425 460 495 530
3 470 600 535 370
4 500 535 970 010
5 545 575 310 645

E. Ratio: 50 % RAP/50% Aggregate


CSON

410 455 495 540


1 465 515 550 590
520 560. 605 650
0
-

575 620 660 705


540 680 715 760
5 600 735 775 820

NOTE: 20 ° F. loss between dryer and pugmill assumed in these calculations

Figure 2-94. Moisture RAP temperature capacity chart (NAPA) .

ture content of 3 percent, approximately 14,900 ft³ of the weigh hopper and the pugmill.
water vapor will be released in about 5 sec. This release One way to control the particulate emissions is to
of vapor usually causes carryout of dust particles from reduce the amount of moisture and/or reduce the

Page 2-76
AC 150/5370-14
10/15/91
Appendix 1

amount of RAP used in the recycled mix. The moisture and possibly end up in the mix. Thus, returning the
content of the reclaimed material can be kept low by not baghouse fines to the hot elevator is probably not as
crushing this material until just before it is needed and good as placing the fines directly in the weigh hopper.
by preventing rain from falling on the RAP by keeping If the plant is equipped with a baghouse and a
it under a roof. Another approach, required in some recycled asphalt mix is , being produced with a high
areas, is to adequately vent the weigh hopper and percentage of reclaimed material, the temperature of the
pugmill into the emission -control system on the plant. exhaust gases from the dryer to the baghouse should be
monitored continuously to assure that the bags in the
LOADING THE TRUCK OR SILO emission-control device are not damaged by excessive
If the mix discharged from the pugmill is loaded heat. The higher the temperature to which the new
directly into the haul truck, each batch should be aggregates must be heated, the greater the chance for
deposited into a different location on the truck. The problems with the baghouse operation.
first batch should be placed in the front of the bed. The
driver should move the truck forward so that the second CALIBRATION
batch is placed into the rear of the truck bed, adjacent The calibration procedure for a batch plant involves
to the tailgate. The remaining batches should be checking the accuracy of the scales, both for the aggre-
discharged into the center of the bed, with the position gate weigh hopper and for the asphalt cement weigh
of the truck under the pugmill changing for each batch . bucket. This is usually accomplished by adding a known
This procedure will minimize the distance the coarse amount of weight to each scale and reading the weight
aggregate particles can roll in the bed and, thus, reduce shown on the scale dial. For this purpose, a set of 10
the possibility for segregation of the mix. 50-lb weights is normally used .
If the mix is to be stored in a silo temporarily, it The aggregate scale is unloaded and set to a zero
should be discharged into the center of a hopper and reading. The 10 50-lb weights are hung from the scale
then into a conveying device, which can be a drag slat and the reading on the dial recorded . The weights are
conveyor, a belt conveyor, or a bucket elevator. The silo removed and 500 lb of aggregate are then added to the
should be operated in a manner similar to the silo used weigh hopper. The 10 weights are again hung from the
with a drum mix plant. scale and the next reading on the dial ( 1000 lb) is
recorded. The weights are removed once again and an
EMISSION -CONTROL EQUIPMENT additional 500 lb of material is added . The weights are
Because the asphalt cement is not added to the placed on the scale and the next dial reading recorded
aggregate inside the dryer, the amount of dust carryout ( 1500 lb) . This process continues (adding the weights,
from a batch plant dryer is generally greater than from recording the dial reading, removing the weights, adding
a drum mixer. The operation of the emission-control 500 lb of aggregate to the weigh hopper, and then
equipment--wet-scrubber system or baghouse (fabric repeating the sequence) until the capacity of the aggre-
filter)--is the same, however, regardless of the type of gate scale is reached.
plant used. For the asphalt cement weigh bucket, the same
If the baghouse fines are fed back into the mix, the process is employed , except that only one 50 -lb weight
fines should be fed into a filler-metering system before typically is used. First the weigh bucket is unloaded and
being introduced into the weigh hopper on the tower. the scale set to a zero reading. Next one 50 -lb weight is
This procedure will assure that the baghouse fines are hung from the scale and the dial reading recorded . Fifty
delivered uniformly, into the mix. On some plants, the lb of asphalt cement is then introduced into the weigh
fines are transported to the bottom of the hot elevator bucket. The 50 -lb weight is placed back on the scale
and deposited on top of the new aggregate that is dis- again and the dial reading recorded . Fifty lb of asphalt
charged from the dryer. As long as the fines are deliv- cement is added to the weigh bucket (for a total of 100
ered consistently, this method of fines return is accept- lb) . The procedure continues (adding the weight,
able, particularly if the aggregate will pass through the recording the dial reading, removing the weight, adding
screen deck. If screens are not used, however, small 50 lb of asphalt cement, and then repeating the
lumps of fines can be deposited into the No. 1 hot bin sequence) until the capacity of the asphalt cement weigh

Page 2-77
AC 150/5370-14
Appendix 1 10/15/91

bucket scale is reached . • The wet mix time for blending the asphalt cement
For both scales, a comparison is made of the actual and the aggregate should be no longer than needed to
dial reading after each set of weights is added to the properly coat the aggregate and can be as short as 27
scale and the " theoretical" scale reading. If the two sec.
readings are the same (within 0.5 percent) , the scale is • The plant operator must not idle the plant during
in calibration. If the two readings differ by more than the wet mix cycle and should not do so during the dry
that amount, the scale must be adjusted . Adjustments mix time. When the plant is waiting for trucks, there
must be accomplished using the procedures provided by should be no material in the pugmill.
the scale manufacturer. • The total mix cycle time to produce a batch of
mix, regardless of the size of the pugmill, could be as
short as 35 sec.
SUMMARY OF PLANT OPERATING TECHNIQUES • If reclaimed material is introduced into the plant
The following factors should be considered when at the bottom of the hot elevator, it should be placed on
monitoring the operation of a batch plant: top of the superheated new material in the buckets .
• The moisture content of the aggregate when dis- • If reclaimed material is charged into the weigh
charged from the dryer should be less than 0.5 percent. hopper, it should be placed into the center of the
• The amount of carryover of the aggregate from hopper so that the weigh hopper is not unbalanced and
one hot bin to the next bin should be relatively constant an accurate weight can be determined .
and generally less than 10 percent. • The temperature to which the new aggregate must
• The screens should be checked regularly for holes be heated to obtain adequate heat transfer to the re-
and blinding. claimed material is a function of the amount of RAP
• The pugmill should be operated at nominal used in the recycled mix, the amount of moisture in the
capacity. Both overloading and underloading of the RAP, and the mix discharge temperature . The new
pugmill with aggregate will decrease the efficiency of the aggregate generally should not be heated to a tempera-
mixing process significantly. Batch size should be ture greater than 500° F to prevent potential damage to
consistent from batch to batch. The paddle tips and the the dryer. If the temperature of the new aggregate, as
pugmill lining should be checked periodically to assure found in Figure 2-94, is greater than this value for the
that they are in good condition. amount of RAP and the moisture content of the RAP,
• The dry mix time for the aggregate in the pugmill it will be necessary to reduce the percentage of RAP
should be minimal--usually no more than 1 or 2 sec. added to the recycled mix.

Page 2-78
AC 150/5370-14
10/15/91 Appendix 1

BIBLIOGRAPHY

50 Series Continuous Asphalt Plants, Manual Page 7500, Colorado State University (December 1973) 14+ pp.
Release: 101 , Barber-Greene Co. (1971) 7 pp. Benson, B.A. , "Recycling--A Breakthrough in Technolo-
Aggregate Dryers, Bulletin ADR-3, Cedarapids, Inc. (June gy," presented at the National Asphalt Pavement
1977) 13 pp. Association Annual Meeting (January 1986) 16 pp.
Alternate Fuels for Hot Mix Asphalt Facilities, Quality Binz, L.V. and J.A. Scherocman, "Technical Notes:
Improvement Series 107, National Asphalt Pavement Drum Mix Recycling, The Effect of Materials on
Association (May 1985) 27 pp. Visible Emissions " (undated) 4 pp.
The Asphalt Handbook, Maual Series No. 4 (MS-4) Bio-Flame Systems, General Combustion Corp. (undat-
Asphalt Institute ( 1989) 640 pp. ed) 3 pp.
Asphalt Hot-Mix Recycling, Manual Series No. 20 (MS- Bituma-Stor Hot-Mix Self-Erect Surge-Storage Systems, 70
20) Asphalt Institute ( 1986) 52 pp . to 150 Tons Big, Bituma-Stor, Inc. (undated) 6 pp.
Asphalt Plant Feed Equipment, Bulletin AF-2, Cedar- Bituma's Portable Drum-Mixer Plant... Stationary Plant
apids, Inc. (April 1976) 7 pp. Muscle and Automation, World's Biggest Self-Erect,
Asphalt Plant Manual. Manual Series No. 3 (MS-3) Bituma Construction Equipment Co. (undated) 10
Asphalt Institute ( 1988) 192 pp. pp.
"Asphalt Heaters Lower Costs, Improve Efficiency," Bracegirdle, P.E., "A New Process and Apparatus for
Roads & Streets (February 1975) p . 70+ . Making Asphalt Concrete," in Transportation Re-
Barber-Greene Continuous Type Asphalt Plants, Manual search Record 986: Construction Quality Control and
Page 7150, Barber- Greene Co. (March 1963) 19 pp. Specifications, Transportation Research Board,
"Basic Energy/Environmental Analysis," Information National Research Council, Washington , D.C. ( 1984)
Series 67, National Asphalt Pavement Association pp. 22-26.
(August 1978) 21 pp. Bracegirdle, P.E. , "A New Process and Apparatus for
Batch Type Asphalt Mixing Plants, Bulletin APB-2, Making Asphalt Concrete" (1983) 10 pp .
Cedarapids, Inc. (July 1973) 7 pp. Brock, J.D. , Asphalt Distillation in Drum Mix Plants,
BCE Drum Mixing, Boeing Construction Equipment Co. Bulletin No. T- 109, Astec Industries, Inc. ( 1983) 21
(undated) 6 pp. pp.
BE Batchpac Pugmills, Manual Page 7954.3, Release Brock, J.D. , Asphalt Distillation Occurring During Mixing
101 , Barber-Greene Co. (undated) 4 pp. in a Drum Mix Asphalt Plant, Astec Industries, Inc.
BE Series Batchplants: Batchpac, Manual Page 7952, (December 1983) 18 pp.
Release: 101 , Barber-Greene Co. (1977) 10 pp. Brock, J.D. , " Dryer Drum Mixer," Technical Paper
Beaty, R.W. , "Pugmill Capacity Factors : Environmental, T- 119, Astec Industries, Inc. (January 1 , 1989) 17 pp.
Design and Operational," Proceedings, Canadian Brock, J.D. , " Energy Conservation on Asphalt Plants,"
Technical Asphalt Association, Volume IX (Novem- Bulletin No. T- 102, Astec Industries, Inc. ( 1980) 12
ber 1964) 28 pp. pp.
Beaty, R.W. , " Surge Bins and Storage Hoppers," Pro- Brock, J.D. , " Productivity: Producing Profits for the
ceedings, Association of Asphalt Paving Technolo- 80's," Bulletin No. T- 106, Astec Industries, Inc.
gists, Vol. 39 (1970) pp. 635-643. (1981) 23 pp.
Beaty, R.W. and A. Cherif, "Low Cost Asphalt Mixtures Brock, J.D. , " Segregation Causes and Cures," Technical
Produced by the Dryer Drum Mixing Method," Paper T- 117, Astec Industries, Inc. (undated) 24 pp.
presented at the Arab Engineers Federation Confer- Brock, J.D. and E.G. Mize, " The Drum Mix Process,"
ence on Low Cost Roads, Kuwait (November 1974) Bulletin No. T- 110, Astec Industries, Inc. ( 1984) 24
17 pp. pp.
Beaty, R.W. and B.M. Bunnell , "The Manufactu of Brown, C. , "Effect of New Equipment on Asphalt Pave-
re
Asphalt Concrete Mixtures in the Dryer Drum ," ment Construction : New York State Experience ,"
presente at the First Annual Paving Seminar, Proceedings, Association of Asphalt Paving Technolo-
d

Page 2-79
AC 150/5370-14
Appendix 1
10/15/91

gists, Vol. 39 (1970) pp. 623-627 . Dickson, P.F. , Heating and Drying ofAggregate, National
Brule , W. , "Effect of New Equipment on Asphalt Pave- Asphalt Pavement Association (May 1971) 50 pp.
ment Construction: New York State Experience," The Double Barrel, Astec Industries, Inc. (January 1989)
Proceedings, Association of Asphalt Paving Technolo- 6 pp .
gists, Vol. 39 ( 1970) pp . 620-623. "Double- Drum Plant Pumps out 560-700 tph," Highway
Brule, W. , P.E. Ducharme, and R. Karis, "An Experi- & Heavy Construction (January 1989) pp. 52-54.
mental Project Using a Drum Mix Asphalt Concrete Drum Mix Coater, Astec Industries, Inc. (January 1985)
Plant," Technical Report 20, New York State Depart- 5 pp .
ment of Transportation ( October 1975) 42 pp. Dryer Principles, Manual Page 9205 , Barber- Greene Co.
Bury, B.B., S.P. Lynch, and C.G. Rauh, "Plant Opera- (November 1960) 15 pp .
tions," Proceedings, National Asphalt Pavement Dual Zone Thermodrum, Manual Page 7654.1 , Release
Association Annual Meeting (January 31 , 1985) pp. 101 , Barber- Greene Co. (undated) 3 pp.
185-210. Dual-Zone Thermodrum Asphalt Mixing Plants, Manual
"Capacity Is King at New Asphalt Plants," Roads & Page 7654.1 , Release: 101 , Barber-Greene Co.
Bridges (January 1987) pp . 46-47. (undated) 6 pp .
Cedarapids Burners and Burner Controls, Bulletin 1B- 1 , The Effects of Field Variables and Design Variables on
Cedarapids, Inc. (March 1980) 5 pp . Hot-Mix Asphalt Production Using 100% Virgin Aggre-
Champion, R.J. , "Development of Aqua-Black (Coal gate, Document No. 3906, Standard Havens Products,
Water Slurry) for Hot-Mix Asphalt Plants and Other Inc. ( 1987) 15 pp.
Fuel-Intensive Industries," Proceedings, Canadian Elliott, E.J., Coal Burning in the Asphalt Industry: One
Technical Asphalt Association, Vol. XXXIII (No- Year from the First Step (undated) 22 pp .
vember 1983) pp. 39-53. "An Evaluation of Lower Mixing Temperatures for
Chollar, B.H., J.A. Zenewitz, J.G. Boone, K.T. Tran, Bituminous Paving Mixes," Interim Report State
and D.T. Anderson, " Changes Occurring in Asphalts Study No. 69, Mississippi State Highway Department
in Drum Dryer and Batch (Pug Mill) Mixing Opera- (June 1981 ) 35 pp.
tions," in Transportation Research Record 1228: As- Fabric Filter Dust Collectors, Bulletin FF-2, Cedarapids ,
phalt Mixtures and Asphalt Chemistry, Transportation Inc. (May 1977) 5 pp.
Research Board Annual, National Research Council, Fail-Safe Device Asphalt Weigh Buckets, National Asphalt
Washington, D.C. ( 1989) pp. 145-155 . Pavement Association (undated) 3 pp.
Coal-An Overview ofIts Characteristics and Properties for Farrell, J.L. and W.H. Wright, "Screenless Plant Opera-
Genco Burners, General Combustion Corp. (undated) tion with Cold Feed Control," in Highway Research
5 pp . Record No. 316: Construction and Construction Equip-
Coal Pulverizat and the Effect of Sizing on Combusti ment: 9 Reports, Highway Research Board , National
ion on
, General Combust C (undated ) Research Council, Washington, D.C. ( 1970) pp. 63-
Characteri
stics ion orp.
30 pp . 69.
Cold Aggrega F S , Manual Page 9410 , Re- Faulkner, L.C. and D.E. Jervis, " Recycling of Bitumi-
te eed ystems
lease : 102 , Barber -Greene Co. (undate ) 5 pp . nous Materials Using a Central Drum -Mixer Plant,"
d
Cold Feed Hints, HS -7, 1982 , Nationa Asphalt Paveme Quarry Management and Products (September 1981 )
l nt
Associa
tion (undated ) 2 pp . pp. 617-622.
Comparative Production Cost Study-Drum Mix vs. Batch Fehsenfeld, F.M. and A.J. Kriech, The Effect of Plant
Plant, Barber-Greene Co. (undated) 12 pp. Design Changes on Hot Mix Asphalt, Heritage Re-
"Corrosion in Hot Mix Asphalt Facilities," Quality Im- search Group (undated) 14 pp.
provement Series 106, National Asphalt Pavement Ferne, B.W. , " Evaluation of a Fully Automatic Asphalt
Association (May 1985) 8 pp. Mixing Plant," Report 1073, Transport and Road
Crawford, C., "Whatever Happened to Light Ends in Research Laboratory (1983) 39 pp.
Asphalt Cement?" Focus, National Asphalt Pavement The Flo-Mix System, Paving the Way, Astec Industries,
Association (Winter 1987) p . 20+. Inc. (undated) 16 pp.
Design Considerations for a New Approach to Hot-Mix "Florida Test Sections May Alter the Rating of As-
Asphalt Production: The Standard Havens Magnum phalts," Roads & Bridges (January 1986) pp. 41-42.
Drum-Mixer, Document No. 3928, Standard Havens Foster, C.R., " Effect on New Equipment on Asphalt
Products, Inc. ( 1987) 15 pp . Pavement Construction : Plant Automation," Proceed-

Page 2-80
AC 150/5370-14
10/15/91
Appendix 1

ings, Association of Asphalt Paving Technologists, and J.H. Dijkink, " Comparison of Mechanical Prop-
Vol. 39 (1970) pp. 615-620 . erties of Drum Mix and Batch Mix Asphalt Concrete
Foster, C.R. , "Heating and Drying of Aggregates--BTU Through Dynamic Testing," Proceedings, Association
Requirements and Exhaust Volumes," Information of Asphalt Paving Technologists, Vol. 57 ( 1988) pp.
Series 47, National Asphalt Pavement Association 176-196.
(1973) . "Huge Production, No Pollution," Highway & Heavy
Foster, C.R., "Hot Mix Storage Bins," Proceedings, Construction (November 1986) pp . 60-61 .
Association of Asphalt Paving Technologists, Vol. 39 Instruction Manual: Starjet Burner Unit, Hauck Manufac-
(1970) pp. 628-635. turing Co. (undated) .
Fuel Conservation in Asphalt Hot-Mix Construction, Kandhal, P.S. and M.E. Wanger, "Storage of Bituminous
Construction Leaflet No. 8, The Asphalt Institute Concrete in Inert Gas," in Transportation Research
(July 1974) 4 pp. Record 468: Asphalt and Asphalt Mix Technology: 10
Fugitive Dust Control andthe Hot-Mix Plant, Information Reports, Transportation Research Board, National
Series 73, National Asphalt Pavement Association Research Council, Washington, D.C. ( 1973) pages
(undated) 22 pp. 61-72.
"The Fundamentals of the Operation and Maintenance Kennedy, T.W. and A.S. Adedimila, "Engineering
of the Exhaust Gas System in a Hot Mix Asphalt Characteristics of Dryer-Drum Asphalt Mixtures," in
Facility," Information Series 52/87, National Asphalt Transporatation Research Record 712: Bituminous
Pavement Association ( 1987) 110 pp. Materials and Skid Resistance, Transportation Re-
The Genco Solid Fuel Combustion Systems, General search Board, National Research Council, Washing-
Combustion Corp. (1984) 5 pp. ton, D.C. ( 1979) pp. 12-15.
Gilmore F.S., Mixing Time Investigations, QIP 52, Na- Kennedy, T.W. and G.A. Huber, "Effect of Mixing
tional Bituminous Concrete Association (June 1962) Temperature and Stockpile Moisture on Asphalt
14 pp. Mixtures," in Transportation Research Record 1034:
Good Housekeeping--Your Responsibility," Information Asphalt Materials, Mixes, Construction, and Quality,
Series 43, National Asphalt Pavement Association Transportation Research Board, National Research
(undated) 24 pp. Council, Washington, D.C. ( 1985) pp. 35-46.
Goodsall, G.D. and B.W. Ferne, "Bituminous Drum- Kennedy, T.W. , M. Tahmoressi, and J.S. Scherocman,
Mixing Plants in the USA," Report 691 , Transport "Drum Mix Plants--Equipment and Operations,"
and Road Research Laboratory ( 1976) 42 pp. Texas Research Report 440-1F (November 1986) .
Granley, E.C. , "An FHWA Look at Hot-Mix Production Let's Clear the Air about Drum Mixers!, Boeing Construc-
Developments," Presented at the National Asphalt tion Equipment Co. (undated) 8 pp .
Pavement Association Annual Meeting (February Lund, J.W. and J.E. Wilson, " Evaluation of Asphalt
1975) pp. 97-103. Aging in Hot Mix Plants," Proceedings, Association of
Granley, E.C. , "The Dryer Drum Process for Producing Asphalt Paving Technologists, Vol . 53 (April 1984)
Bituminous Concrete Mixes," presented at the pp. 1-18.
American Association of State Highway Officials The Maintenance of Exhaust Systems in the Hot Mix
Annual Meeting (November 1972) 12 pp. Plant, National Asphalt Pavement Association ( 1977)
Haas, S., "Drum Dryer Mixing in North Dakota," Pro- 19 pp.
ceedings, Association of Asphalt Paving Technolo- "Mixing Time for Hot-Mix Asphalt," Information Series
gists, Vol. 43 (1974) pp. 417-435. 26, National Asphalt Pavement Association (undat-
Heating and Drying ofAggregate, Capture of Waste Heat, ed) 10 pp .
QIP 96, National Asphalt Pavement Association New Dimensions, Astec Industries, Inc. (undated ) 16 pp.
(November 1975) 21 pp. The New Generation Storage Bin, Astec Industries, Inc.
Here's How You Wanted It. The Drum-Mixer Plant That's (January 1989) 10 pp.
Contractor-Built and Contractor-Proven... Bituma., "Noise in and around Asphalt Plants," Information
Bituma Construction Equipment Co. (undated) 12 Series 75, National Asphalt Pavement Association
pp. (undated) 38 pp.
"High Technology Enhances Hot Mix Plant Production," The Only Drum-Mixer that Completely Replaces a Batch
Roads & Bridges (January 1986) pp. 48-50. Plant, Form No. 398, Standard Havens, Inc. (Septem-
Hopman, P.C. , A.C. Maagdenberg, M.H.M. Coppens, ber 1982) 23 pp.

Page 2-81
AC 150/5370-14
Appendix 1
10/15/91

Operation and Maintenance Instructions: CR- 130 Hot Mix Smith, W.N. , "Asphalt Heating," Technical Paper T- 111 ,
System, Cedarapids, Inc. (August 1986) . Astec Industries, Inc. (undated) 17 pp .
Operation and Maintenance Instructions: Model HC Starjet Burners, QA1 , Hauck Manufacturing Co. (July
Batch-Type, Asphalt Mixing Plant, Cedarapids, Inc. 1987) 4 pp .
(March 1987) . "Stockpiling and Cold Feed for Quality," Information
"The Operation of Exhaust Systems in the Hot Mix Series 69, National Asphalt Pavement Association
Plant," Information Series 52, National Asphalt (June 1979) 7 pp.
Pavement Association ( 1975) 51 pp. Terrel, R.L. and D.J. Holen, "Performance of Asphalt
Operator's Manual for Drum Mix Plants, CMI Corp. Concrete Pavement Mixture Produced by the Drum
(undated). Mixer Process," Proceedings, Association of Asphalt
Page, G., K.H. Murphy, and B.E. Ruth, "Asphalt Con- Paving Technologists, Vol. 45 ( 1976) pp . 169-198.
crete Mixture Production Problems Related to Light Theoretical Computations of the Fuel Used and the
Constituents in Asphalts," Proceedings, Association of Exhaust Produced in Drying Aggregates," Informa-
Asphalt Paving Technologists, Vol. 55 ( 1986) pp. tion Series 61 , National Asphalt Pavement Associa-
277-313. tion (January 1977) 12+ pp.
Parr, W.K. and J.D. Brock, "Statistical Study of Effect of Thermodrum Aggregate and Asphalt Blending System,
Hot Storage on the Composition and Properties of Manual Page 7654.3, Release : 101 , Barber-Greene
Asphalt Concrete," Proceedings, Association of Co. (undated ) 3 pp.
Asphalt Paving Technologists, Vol. 41 ( 1972) pp. 1- The Things We Build, Astec Industries, Inc. (January
20. 1989) 45 pp.
Peattie, K.R., "Drum Mixing Processes," Shell Bitumen Transportation Research Circular Number 262: Second
Review, No. 53 (March 1976) pp. 10-17. Look at Moisture Restrictions in Hot-Mix Plant Opera-
Potts, C.F. , " Effect of Drummix Plants on Asphalt Mixes tions and Construction, Transportation Research
in Florida," Proceedings, Association of Asphalt Board, National Research Council, Washington, D.C.
Paving Technologists, Vol. 53 ( 1984) pp. 638-641 . (August 1983) 23 pp.
Preventing Fires and Explosions in Hot Mix Asphalt The Uniform Burner Rating Method for Aggregate Dryers,
Plants, Information Series 86, National Asphalt Information Series 76, National Asphalt Pavement
Pavement Association (undated) 32 pp. Association (January 1981) 3 pp .
Principles of Construction of Hot-Mix Asphalt Pave- Update on Fuel Conservation, National Asphalt Pave-
ments, Manual Series No. 22 (MS-22) , Asphalt ment Association (July 1978) 7 pp.
Institute (1983) 300 pp. Von Quintus, H.L. and T.W. Kennedy, "Drum Mix
"Production of Asphalt Concrete with the Dryer-Drum Versus Batch Plants: Pavement Performance Com-
Mixer," CL-20, The Asphalt Institute (April 1976) 4 parisons," Proceedings, Association of Asphalt Paving
pp. Technologists, Vol. 52 ( 1983) pp . 224-253.
Recent Advances in the Evolution ofDrum-Mixer Design Wagner, L., " Preventive Maintenance," Bulletin No.
Maximize the Potential for Production Quality, Effi- T-104, Astec Industries, Inc. (1980) 15 pp.
ciency, And Economy, Document No. 4078, Standard Who Buys Surge-Storage from Bituma-Stor? Hundreds
Havens Products Inc. ( 1988) 15 pp. Who Compare!, Bituma-Stor, Inc. (undated) 16 pp.
Rodriguez, M. and T.W. Kennedy, "The Resilient and Witkoski, F.C. , Mixing Time Investigation in Pennsylvania,
Fatigue Characteristics of Asphalt Mixtures Pro- QIP-59, National Bituminous Concrete Association
cessed by the Dryer-Drum Mixer," Report 183-8, (February 1963) 7 pp.
University of Texas (December 1976) 57 pp. Zdeb, M.S. and R.A. Brown, "Storage of Asphalt Con-
Schreter, R.E. , "How Baghouses and Related Equipment crete," in Transportation Research Record 515: Char-
Can Affect Combustion Performance of Aggregate acteristics of and Factors Influencing Bituminous
Dryers" (December 1973) 27 pp. Materials and Mixes, Transportation Research Board,
Six Pack Plants, Astec Industries, Inc. (January 1987) 12 National Research Council, Washington , D.C. ( 1974)
PP. pp. 79-88.

Page 2-82
AC 150/5370-14
10/15/91 Appendix 1

Part Three

LAYDOWN AND COMPACTION


AC 150/5370-14
10/15/91 Appendix 1

PART THREE

TABLE OF CONTENTS

33
SECTION ONE MIX DELIVERY ... 3-1

!
TYPES OF TRUCKS ... 3-1
End Dump Trucks 3-1
Bottom Dump Trucks 3-1
Live Bottom Trucks 3-3
Material Transfer Vehicle 3-3
HAULING PROCEDURES 3-4
Cleaning and Oiling the Bed 3-4
Insulation 3-6
Loading 3-6
From the Pugmill 3-6
From the Silo 3-7
Tarpaulins 3-7
Crusting of the Mix 3-8
Rain 3-8
Bumping the Paver 3-8
Unloading 3-8
SUMMARY OF MIX DELIVERY TECHNIQUES 3-9

SECTION TWO SURFACE PREPARATION ... 3-10


INTRODUCTION 3-10
PREPARATION OF EXISTING SURFACE 3-10
HMA over HMA 3-10
Pavement Replacement and Patching 3-10
Crack Filling 3-10
Leveling Courses 3-10
Milling 3-11
Hot-Mix Asphalt over Portland Cement Concrete 3-11
Base Preparation 3-11
Subgrade Soil 3-11
Granular Base Course 3-13
TACK COAT .... 3-13
SURFACE PREPARATION TECHNIQUES 3-15

SECTION THREE MIX PLACEMENT ... 3-17


INTRODUCTION 3-17
THE TRACTOR UNIT 3-17
Propulsion Systems 3-17
Push Rollers 3-17
Paver Hopper 3-18
Slat Conveyors 3-21
Flow Gates 3-21
Augers 3-21
Material Feed System 3-22
Manual Control- Constant Speed 3-22
Manual Control-Variable Speed 3-22
Automatic Control 3-22
AC 150/5370-14
Appendix 1
10/15/91
Part Three Contents (continued)

THE SCREED UNIT 3-25


Tow (Pull) Point 3-26
Forces Acting on the Screed 3-27
Paver Speed 3-27
Head of Material 3-28
Thickness Control Cranks for Manual Operation 3-29
Reaction of the Screed 3-29
Changing Screed Pivot Point 3-30
Changing Tow Point Elevation 3-30
Screed Strike-offs 3-31
Screed Heaters 3-32
Screed Crown Control 3-32
Screed Vibrators 3-33
Screed Extensions and End Plates 3-33
Hydraulically Extendable Screeds 3-35
MIX PLACEMENT TECHNIQUES . 3-37

SECTION FOUR AUTOMATIC SCREED CONTROLS 3-40


INTRODUCTION 3-40
AUTOMATIC SCREED CONTROLS • 3-41
GRADE CONTROL 3-43
Types of Grade References 3-43
Erected Stringline 3-43
Mobile References 3-44
Joint Matching Shoe 3-47
Location of the Grade Reference 3-48
SLOPE CONTROL 3-48
YIELD, MINIMUM THICKNESS , AND SCREED CONTROLS • 3-48
AUTOMATIC SCREED-CONTROL OPERATING TECHNIQUES 3-52

SECTION FIVE JOINT CONSTRUCTION 3-53


INTRODUCTION 3-53
TRANSVERSE JOINTS 3-53
End of Paving 3-53
Butt Joints 3-53
Tapered Joints 3-54
Handmade Joints 3-59
Start of Paving 3-59
Removal of the Taper 3-59
Use of Starting Blocks 3-59
Nulling the Screed and Setting the Angle of Attack 3-60
Raking the Joint 3-61
Compacting the Joint 3-63
LONGITUDINAL JOINTS 3-64
Cutting Back the Joint 3-64
Overlapping the Joint 3-64
Raking the Joint 3-65
Compacting the Longitudinal Joint 3-65
Rolling from the Hot Side 3-66
Rolling from the Cold Side 3-67
Echelon Paving 3-68
JOINT CONSTRUCTION OPERATING TECHNIQUES 3-69
AC 150/5370-14
10/15/91
Appendix 1

Part Three Contents (continued )

SECTION SIX COMPACTION ... 3-70


INTRODUCTION 3-70
DEFINITIONS ... 3-70
FACTORS AFFECTING COMPACTION 3-70
Properties of the Materials 3-70
Aggregates 3-70
Asphalt Cement 3-71
Mix Properties 3-71
Environmental Variables 3-72
Layer Thickness 3-72
Air and Base Temperature 3-72
Mix Laydown Temperature 3-74
Wind Velocity 3-74
Solar Flux 3-74
Obtaining Proper Density under Varying Environmental Conditions
3-74
Laydown Site Conditions 3-75
Compaction Equipment 3-76
Static Steel Wheel Rollers 3-77
Pneumatic Tire Rollers 3-77
Vibratory Rollers 3-78
COMPACTION VARIABLES 3-81
Roller Speed 3-81
Number of Roller Passes 3-82
Rolling Zone 3-83
Roller Patterns 3-83
Direction of Travel and Mode of Operation for Vibratory Rollers 3-85
DETERMINATION OF THE ROLLING PATTERN 3-86
Choice of Compaction Equipment 3-86
Rolling Patterns 3-86
ROLLER OPERATING TECHNIQUES 3-87

SECTION SEVEN EQUIPMENT AND MAT PROBLEMS 3-89


INTRODUCTION 3-89
SURFACE WAVES 3-89
Description 3-89
Cause 3-89
Solution 3-91
Performance 3-91
TEARING 3-91
Description 3-91
Cause 3-92
Solution 3-92
Performance 3-92
NONUNIFORM TEXTURE .... 3-92
Description 3-92
Cause 3-92
Solution 3-93
Performance 3-93
AC 150/5370-14
Appendix 1 10/15/91

Part Three Contents (continued)

SCREED MARKS .... 3-93


Description 3-93
Cause 3-93
Solution 3-94
Performance 3-94
SCREED RESPONSIVENESS 3-95
Description 3-95
Cause 3-95
Solution 3-95
Performance 3-95
SURFACE SHADOWS .. 3-95
Description 3-95
Cause 3-96
Solution 3-96
Performance 3-96
PRECOMPACTION LEVELS 3-96
Description 3-96
Cause 3-97
Solution 3-97
Performance 3-97
JOINT PROBLEMS ... 3-97
Description 3-97
Cause and Solution 3-97
Performance 3-98
CHECKING ... 3-98
Description 3-98
Cause 3-98
Solution 3-99
Performance 3-100
SHOVING ... 3-100
Description 3-100
Cause 3-100
Solution 3-101
Performance 3-101
BLEEDING AND FAT SPOTS 3-101
Description 3-101
Cause 3-101
Solution 3-102
Performance 3-103
ROLLER MARKS .... .... 3-103
Description 3-103
Cause 3-103
Solution 3-104
Performance 3-104
SEGREGATION .. 3-104
……
Description 3-104
Cause 3-104
Solution 3-106
Performance 3-106
OTHER PAVEMENT PROBLEMS ...... 3-107

BIBLIOGRAPHY ... 3-108


AC 150/5370-14
10/15/91 Appendix 1

SECTION ONE
MIX DELIVERY

TYPES OF TRUCKS problem. Contact between the truck bed and the paver
The purpose of the haul vehicle is to transport the can be a problem, however, when large semitractor
asphalt mixture from the asphalt plant to the laydown trailer units are used as haul vehicles, particularly when
machine. This must be done without delay and without the truck bed is extended to its highest point. When the
any change in the characteristics of the mix during the weight of the truck is being carried by the paver, the
delivery process . Three primary types of trucks are laydown machine may lose its ability to operate properly.
usually employed to transport the mix: end dump, Typical end dump trucks are shown in Figures 3-1 and
bottom or belly dump, and live bottom (conveyor) 3-2.
trucks. All of these trucks are loaded in the same
manner, either directly from the pugmill at a batch plant Bottom Dump Trucks
or from the surge silo at a batch or drum mix plant. A bottom or belly dump truck delivers its load to the
The three types of vehicles differ in how each unloads roadway in front of the paver. The mix is deposited
the mix at the paver. from underneath the truck bed into a windrow, as seen
in Figure 3-3. For this method of mix delivery, it is
End Dump Trucks important that the correct amount of mix be placed in
An end dump truck delivers the mix directly into the the windrow to assure that the paver hopper does not
hopper of the paver. The mix is unloaded by raising the run out of mix or become overloaded with too much
truck bed and allowing the mix to slide down the bed mix. Continuous operation of the paver, which must be
into the hopper. When the bed is raised , it should not equipped with a pickup machine (windrow elevator) , can
be in contact with the hopper and should not press only be accomplished if a continuous and consistent
down on or ride on the paver. For the smaller-capacity supply of mix is available to it.
dump trucks, contact with the paver is not normally a The windrow can be formed in one of two ways. A

JACOR

0
0

K8-952

Figure 3-1 . End dump truck (J. Scherocman).

Page 3-1
AC 150/5370-14
Appendix 1 10/15/91

Mack

RAVENS

Figure 3-2. End dump truck (J. Scherocman).

spreader box (windrow sizer) can be employed. In this is highly dependent on the skill of the person controlling
case, the mix is deposited into the box and is uniformly the discharge gates and on the attention of the truck
metered out onto the roadway as the truck moves driver in operating the truck at the required speed .
forward. The amount of mix placed in the windrow is Manual control of the discharge requires constant
determined by the setting of the discharge opening in attention of the "dump person" to assure that neither too
the box. This procedure provides the most accurate little mix nor too much is being fed in to the paver
means of keeping a constant supply of mix in front of hopper. For both of these methods, the amount of mix
the paver. delivered is dependent on the width and the thickness of
The second, and more common, method is to control the layer being placed . Thus, a different gate opening
the amount of mix discharged by the width of the gate in the windrow sizer or the truck bed is needed for each
opening under the truck and the speed of the truck. set of project conditions and truck speed.
Although this procedure is quicker than the use of a Once the amount of mix being delivered to the paver
windrow sizer, the amount of mix deposited at any time gets out of balance with the quantity of mix needed by

000

Figure 3-3. Bottom dump truck (J. Scherocman) .

Page 3-2
AC 150/5370-14
10/15/91
Appendix 1

FLOWBOYS
MODEL TS-800

Figure 3-4. Live bottom (flow boy) unit (J. Scherocman).

the paver, an adjustment must be made in the discharge much mix in the paver hopper.
operation of the bottom dump trucks. If the problem is
noticed before the paver is underloaded or overloaded, Live Bottom Trucks
the amount of mix deposited on the roadway can easily A live bottom truck is one that employs a conveyor
be altered by changing the width of the gate opening on belt or slat conveyor in the bottom of the truck bed to
the truck and/or by the speed of the truck during dis- discharge the mix without the need to raise the bed.
charge. When there is no mix in the hopper of the This type of truck, often generically called a flow boy
paver, however, mix must be deposited in the hopper truck, deposits the mix directly into the hopper of the
without the paver moving forward. Depending on the paver as does an end dump truck. Because the bed of
equipment available to the contractor, this can be very this type of truck is not raised, there is no potential
difficult. When the hopper is overloaded with mix, some problem with the bed pressing on the paver hopper. A
of the material in the windrow in front of the paver live bottom truck is illustrated in Figure 3-4.
must be removed so that the paver can move forward
without additional mix being picked up. When the mix Material Transfer Vehicle
in the hopper reaches its desired level (the hopper As shown in Figure 3-5, an additional method used
should be half full), the paver again needs to start to deliver mix to the paver is a material transfer vehicle.
picking up additional mix from the windrow. This piece of equipment is basically a surge bin on
Because of the difficulty in adjusting the quantity of wheels. Asphalt mix is deposited into the hopper on the
mix needed by the paver when the hopper is either front of the vehicle. The device is equipped with twin
underloaded or overloaded, it is very important that the remixing augers . The mix is transported from the
windrow of mix produced by the bottom or belly dump hopper through the augers and to a conveyor, which
truck be as consistent as possible. The ability of the delivers the mix to the extended hopper on the paver.
paver to place a smooth layer of mix will be affected by The purpose of the auger system is to reblend the coarse
the uniformity of the windrow available for use by the and fine particles of the mix and reduce the amount of
paver. Keeping the size of the windrow constant is segregation that might occur in the mix because of the
easier than correcting the problem of too little or too operation of the surge/storage silo or the truck-loading

Page 3-3
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-5. Material transfer vehicle (J. Scherocman) .

procedures. in front of the paver or off to one side, as shown in


The material transfer vehicle also allows the paver to Figures 3-6 and 3-7. Because of the weight of this piece
be operated almost continuously (without stopping of equipment when it is full of mix, it must be deter-
between truckloads of mix) if a continuous supply of mix mined ahead of time that the pavement over which this
is available from the asphalt plant. This provides for a machinery will be running can support the weight of the
smoother mat behind the paver screed by permitting the device without being overstressed and damaged .
paver operator to keep the head of material in front of
the screed constant by supplying a continuous flow of HAULING PROCEDURES
mix back to the screed . The equipment also eliminates Cleaning and Oiling the Bed
the problem of the haul trucks bumping the paver and The bed of the haul truck, whether an end dump,
truck drivers holding the brakes on the truck when being bottom dump , or live bottom truck, should be free of all
pushed by the paver. deleterious materials before mix is placed in it. Any
The material transfer vehicle can be operated directly debris in the bed from previous use of the truck should

0
7

Figure 3-6. Material transfer vehicle directly in front of paver (J. Scherocman).

Page 3-4
AC 150/5370-14
10/15/91
Appendix 1
1

Figure 3-7. Material transfer vehicle on lane adjacent to paver (Barber-Greene).

be removed. The bed should be reasonably smooth and release agent, as shown in Figure 3-8, to prevent the
free from any major indentations or depressions where HMA from sticking to the bed . Nonpetroleum-based
the truck bed release agent and the HMA can accumu- materials, such as lime water or one of a variety of
late. commercial products, should be used for release agents.
Once the bed is clean, it should be coated with a The lubricant or release agent should be sprayed uni-

Figure 3-8. Spraying lime water solution as a truck bed release agent (J. Scherocman).

Page 3-5
AC 150/5370-14
Appendix 1 10/15/91

formly over the sides and bottom of the truck bed and outside face with plywood or similar cover, as shown in
should be used in the minimum quantity necessary to Figure 3-9. Missing or torn insulation should be re-
cover the surface area of the bed without runoff. Any placed.
excess lubricant that is used should be drained from the
truck bed before the truck is loaded with mix. Loading
Diesel fuel should not be used as a lubricant for the One objective of the truck-loading operation is to get
truck bed . If an excessive amount of diesel fuel is used the vehicle filled with mix and on its way to the paver as
and if it accumulates in depressions in the bed of the quickly as possible. This objective must be balanced,
truck, the material can cause changes in the properties however, with the need to minimize segregation of the
of the binder material with which it comes in contact. mix that occurs during the loading process. Proper
In addition, use of diesel fuel can contribute to environ- loading procedure, discussed in Section 5 of Part 2,
mental problems as it evaporates or if it soaks into the requires that multiple drops of mix be made into the
ground. Thus, although often convenient and economi- truck instead of a single discharge of mix into the bed.
cal to use, diesel fuel should not be used as a release This is necessary to minimize the distance that the
agent in the bed of a haul truck. coarse aggregate particles in the mix can roll and to
keep the mix consistent in gradation throughout the load
Insulation of material.
If environmental conditions warrant it, the sides and
bottoms of the truck bed should be insulated . The From the Pugmill
insulation should be tight against the body of the bed; The haul truck, regardless of its type and length,
there should not be any gaps between the side of the should be loaded in multiple drops of mix in several
truck and the insulation through which wind could enter. different locations in the bed. If loaded directly from
The insulation material should be protected on its the pugmill of a batch plant, the criteria for multiple
drops of mix into the bed will necessarily be accom-
plished . The truck should be moved, however, between
each delivery of mix from the pugmill. If it takes three
batches of mix to reach the capacity of the haul truck,
one pugmill batch should be loaded into the front of the
truck bed. The truck should then be moved forward and
the second batch of mix should be discharged into the
rear of the truck, just in front of the tailgate. The third
batch of material should be delivered into the center of
the bed, between the first and second batches of mix.
This procedure is illustrated in Figure 2-67 from the
section on surge and storage silos in Part 2.
If the capacity of the pugmill and the truck are such
that five batches of mix are needed to fill the truck bed,
the first batch of mix should be emptied into the front
of the truck and the second batch into the rear of the
truck at the tailgate. The next batch of material should
then be deposited into the center of the truck bed. The
O fourth batch should be placed between the front and
middle batches, whereas the fifth and last batch should
be delivered into the bed between the back (second) and
the middle (third) batches.
For other numbers of batches, multiple drops of mix
should also be used, with the first batch delivered to the
front of the truck bed, the second batch deposited at the
tailgate end of the bed, and the remaining drops of mix
Figure 3-9. Plywood cover over insulation on haul placed evenly in between the first two. Such a loading
truck (J. Scherocman). sequence will minimize the distance the coarse aggregate

Page 3-6
AC 150/5370-14
10/15/91
Appendix 1

particles can roll and thus minimize the amount of be accomplished by dribbling mix in to the truck from
segregation that is produced in the mix. the silo after the majority of the mix is already in the
truck. Only a limited number of trucks typically are
From the Silo used by a contractor during a paving project. The plant
Segregation of the mix can occur when mix dis- operator should be able to judge the time needed to
charged from the surge silo is deposited into the haul place each drop of mix into each individual truck bed
truck in a single drop. If the mix is loaded in only one and be able to come close to the legal capacity of each
drop from the silo, the material will form a cone-shaped truck without resorting to the use of a number of addi-
pile in the truck bed . The coarser aggregate particles tional small dribbles of mix at the end to finish the
will tend to separate from the mass of mix and roll to loading process. The discharge of small amounts of mix
the front and rear of the bed, collecting at both ends. from the silo greatly increases the chance for segregation
Some rolling of the coarser material may also occur of the mix as the coarse aggregate particles roll down
along the sides of the bed. This segregation problem the sides of the piles of mix already in the bed .
can be minimized by loading the truck in multiple drops
of mix from the silo, similar to the procedure used for Tarpaulins
loading from the batch plant pugmill. Every haul truck should be equipped with a tarpau-
The number of drops used depends on the length lin, which can be employed as needed to protect the mix
and capacity of the truck. Even on the smallest trucks, in case of inclement weather. The tarp should be made
at least three drops should be used: the first at the front of a water repellent material, should be of sufficient
of the bed, the second at the rear of the bed, and the weight and strength to resist tearing, should be in good
last in the middle of the first two. When a semitractor condition, and should not have any holes or tears in it.
trailer truck is to be loaded, at least five and probably Most important, the tarp should be large enough to
seven different discharges of mix should be made before cover the top of the load and to extend down over the
the truck capacity is reached. In every case, the mix sides and the tailgate of the truck. The requirement for
should first be deposited at the front of the bed and the overlap of the tarp over the sides of the truck is to
then at the tailgate of the truck. The space in between assure that the mix is protected adequately from wind
the first two drops should be filled in with small, sepa- and water. The tarps should have enough tie-down
rate piles of mix placed between the initial "batches" of points to secure the tarp properly and prevent it from
mix. The use of multiple drops of mix is slower than flapping in the wind during delivery of the mix to the
loading the truck in a single discharge of material from paver.
the silo. It is necessary, however, in order to reduce the Some trucks are equipped with tarps that run from
amount of segregation that occurs during the loading the front of the truck to the back in a rail on the top of
process for mixes that have a tendency to segregate. the side boards of the truck. The rail keeps the tarp
One procedure that should never be used when a stretched across the top of the load of mix and covers
truck is loaded from the silo is to move the truck slowly the mix without the tarp extending over the sides of the
forward while the mix is being discharged from the surge truck bed . As long as the tarp is tight, this type of tarp
bin. If this is done, all the coarse aggregate particles in can provide adequate cover for the mix. For safety
the mix will continually run down the cone that is reasons, it is desirable to use tarps that can be extended
formed and will be pushed toward the tailgate of the by mechanical means over the bed of the truck without
truck, where they will accumulate. This will significantly the driver having to climb up on the sides of the vehicle
increase the amount of truckload-to-truckload segrega- to unroll the tarp.
tion that is seen behind the paver. Thus, proper loading A tarp that does not cover the load during transport
procedures require that the truck driver move the is worse than not having a tarp on the load at all.
vehicle backward and forward several times in between Unless the tarp extends over the sides of the truck, air
delivery of loads of mix. Although this increases the will flow under the tarp during movement of the truck
time needed to load the truck and send it to the paver, and increase the rate of cooling of the mix. In addition,
it is necessary that it be done to minimize segregation. during rainy weather, any water that falls on the tarp
There is a tendency for the plant operator to fill the will run into the truck bed instead of off the side of the
truck to its legal capacity to reduce haul costs, particu- vehicle. Further, even if the tarp covers the bed, if there
larly if the truck is sitting on a scale under the silo. is any water on the tarp when the truck is ready to
Although this is good economic practice, it should not discharge mix into the paver hopper, the water should

Page 3-7
AC 150/5370-14
Appendix 1
10/15/91

first be removed from the tarp by raising the bed of the the paving schedule (waiting for warmer ambient
truck and letting the water run off before the truck temperatures).
backs into the hopper.
Tarps are not normally necessary in warm weather Rain
and with relatively short haul distances between the These same variables are also present when rain
plant and the paver. If a tarp is used , however, it should occurs at the paving site and mix is still in the trucks
be removed from the top of the bed before the truck is waiting to be unloaded . Judgment is needed . One
unloaded into the laydown machine . This allows the mix alternative is to stop paving and return any mix in the
to be inspected visually for defective material before it trucks to the plant to be recycled at a later date. If the
is discharged into the paver. rain is relatively light and appears to be going to con-
tinue for some time, and if the pavement surface has
Crusting of the Mix been tacked and does not contain puddled water, the
There is no set limit as to how far a load of HMA trucks can be unloaded as quickly as possible and the
can be transported. There are many variables that affect rollers brought up directly behind the paver to compact
the maximum haul distance, but the key factors are the the mix before it cools completely. If the rain appears
workability of the mix while it is passing through the to be of short duration--a passing shower--the mix
paver and the ability to get the mix compacted once it should be held in the haul truck instead of being
has been placed by the paver. Both of these factors are dumped into the paver hopper and laid after the surface
highly dependent on the temperature of the mix. has dried. Again, because of the mass of mix in the
Hot-mix asphalt in a mass, such as when the mix is truck bed, the mix will lose temperature slowly if the
confined in a truck bed, will maintain a reasonable load is properly tarped and the sides of the truck are
temperature for as long as 2 or 3 hr. The rate of cool- insulated. Once the rain has stopped and any puddles
ing of the mix depends on such variables as the temper- of water have been swept from the roadway surface, the
ature of the mix at the time of production, the ambient mix can be unloaded from the waiting trucks into the
air temperature, the velocity and the temperature of the paver and laid down . As long as chunks of mix do not
wind that passes over the mix, and the efficiency of the appear behind the screed and the rollers can densify the
insulation on the sides of the truck. When it is hauled mix adequately, little harm is done in holding the mix in
long distances without being covered by a tarp, the mix the haul trucks for even 2 or 3 hr, depending on envi-
will develop a crust on the top and cool and begin to ronmental conditions.
harden. The formation of the crust provides an insulat-
ing layer for the rest of the mix in the truck bed and Bumping the Paver
reduces the rate of cooling for the remainder of the When an end dump or a live bottom truck is used to
mass of material. Thus, within limits, the formation of deliver mix to the paver, the truck driver should back
the crust on the outside of the mass of mix is beneficial the truck up to the laydown machine but stop just short
to maintaining the internal temperature of the rest of of the push rollers on the front of the paver. Once the
the mix in the truck bed. truck has come to a halt and the driver has released the
If the load of mix is properly tarped, the amount of brakes on the vehicle, the paver operator should start
crust buildup will be minimized because the wind will the machine moving forward, picking up the stopped
have significantly less effect on the rate of cooling of the truck. The key to this process is that the paver picks up
mix. The slight crust thickness that does form during the truck instead of the truck backing into and bumping
transport should be able to be broken up completely as the paver. Use of the proper procedure will reduce the
the mix is discharged from the haul vehicle into the incidence of screed marks and roughness in the mat.
paver, is carried by the slat conveyors back to the
augers, and is passed under the paver screed . As long Unloading
as chunks of asphalt mix do not affect the quality of the If an end dump truck is used and if the mix being
mat behind the paver, the crust that forms on top of the delivered to the paver has a tendency to segregate, the
mix during delivery will not be detrimental to the long- bed of the truck should be raised a short distance in
term performance of the mix. If chunks of mix can be order to allow the mix in the bed to slide against the
seen behind the screed, however, changes need to be tailgate before the tailgate is opened . Once the tailgate
made in the mix production temperature, the amount of is opened, this procedure will allow the mix to be dis-
insulation, the covering of the load with the tarp , or with charged from the truck in a mass and to flood the

Page 3-8
AC 150/5370-14
10/15/91
Appendix 1

hopper of the paver, reducing the possibility of segrega- Additional drops of mix should be placed in the middle
tion behind the paver screed. portion of the truck as necessary to minimize the dis-
The same procedure should be employed, if possible, tance that any coarse aggregate particles can roll in
when a live bottom truck is used to transport the mix. order to prevent segregation. (This procedure is dis-
The belt or slat conveyor should be started for a few cussed in detail in the section on surge and storage
seconds before the end gate on the truck is opened . silos. )
This action will create a mass of material that can be • The plant operator should not continually open
delivered to the hopper instead of allowing any coarse the silo gates and dribble in small amounts of mix in
aggregate particles that have rolled to the end gate to order to "top off" the load of mix in the haul truck.
exit into the hopper first. • The truck should be equipped with a tarpaulin
For bottom dump trucks, a windrow-sizing box that is in good condition: without tears and holes. The
should be used to control the dimensions of the wind- tarp should be large enough to cover the bed and to
row. If this is done, the gates on the bottom of the wrap over the sides and end of the truck bed. The tarp
truck bed can be opened wide to allow a mass of mix to should have enough fasteners to allow it to be tied down
be discharged instead of only some of the mix dribbled completely and to prevent it from flapping in the wind.
out. If manual methods are used to control the truck If side rails are used to hold the tarp in place, the tarp
discharge, the gates should still be opened widely so that should be stretched tightly over the load of mix.
a mass of mix is deposited on the roadway. The size of • End dump and live bottom trucks should stop
the windrow should then be controlled by the forward short of the paver and allow that machine to pick up the
speed of the haul truck. truck instead of the truck bumping into the stopped
paver.
SUMMARY OF MIX DELIVERY TECHNIQUES • The bed on an end dump truck should be raised
Several primary factors should be observed when the a short distance and the mix in the truck allowed to slide
truck loading, hauling, and unloading operation is moni- against the tailgate before the tailgate is opened to
tored . They are: discharge mix into the paver hopper. The belt or slat
• The truck bed should be free of all contaminants. conveyor on a live bottom truck should be started a few
The bed should be lightly and uniformly coated with a seconds before the end gate is opened in order to
nonpetroleum release agent. Diesel fuel should not be discharge a mass of asphalt mix into the hopper instead
used. of just a dribble of coarse aggregate particles.
• If required, the insulation around the truck bed • The load carried in a bottom dump truck should
should be tight to the sides and bottom of the truck. be deposited uniformly on the roadway in front of the
• The truck should be loaded in multiple drops of paver so that the amount of mix picked up by the wind-
mix from either the pugmill or surge silo. The first row elevator allows the paver operator to maintain a
delivery of mix should be at the front of the truck bed. uniform head of material in front of the paver screed.
After the truck moves forward, the second drop of mix • End dump trucks should not be allowed to
should be at the rear of the truck near the tailgate. contact or transfer any weight to the paver hopper.

Page 3-9
AC 150/5370-14
Appendix 1 10/15/91

SECTION TWO
SURFACE PREPARATION

INTRODUCTION and squared up with the sides as vertical as possible, the


The performance of a hot-mix asphalt pavement loose material and water in the hole removed, a tack
under traffic is directly related to the condition of the coat applied to the sides and bottom of the pothole, and
surface on which the pavement layers are placed. For a the mix placed in the hole. If the pothole is deeper than
full-depth asphalt pavement, if the condition of the 4 in., the mix should be placed in layers and each layer
subgrade soil is poor (particularly if it is wet and rutted compacted properly.
under the haul trucks) the ultimate durability of the
roadway may be reduced. For HMA layers placed on Crack Filling
top of a new, untreated granular base course, that base Badly cracked pavement sections, especially those
material should be stable and the surface should be dry with pattern cracking (e.g., map or alligator) , are nor-
and should not be distorted by the trucks carrying mix to mally patched or replaced . The benefits of filling other
the paver. For mix laid on top of existing asphalt layers, cracks in the existing surface depend, in part, on the
the present surface should be free of potholes and major width of the cracks. If the cracks are narrow (less than
distress, reasonably smooth, and clean. 3/8 in. in width) , it is doubtful that the crack sealing
material will actually enter the crack instead of pooling
PREPARATION OF EXISTING SURFACE on the pavement surface . These cracks can be widened,
HMA over HMA if desired, with a mechanical router before sealing is
If an HMA overlay is to be placed on top of an attempted. If wider cracks are present, they should be
existing asphalt pavement, the existing surface must be cleaned of debris. The crack sealing material should be
prepared properly before any mix is laid. The degree of inserted when the cracks are clean and dry. The level of
preparation needed depends on the condition of that the crack filling material should be slightly lower than
surface. At a minimum, the failed areas should be that of the surrounding pavement surface.
removed and replaced, the potholes properly patched, The amount of reflective cracking that occurs in an
the cracks cleaned out and sealed, and the ruts filled in overlay sometimes may be reduced by the use of a
or, preferably, removed by cold milling. surface treatment on the existing pavement, depending
on the cause of the cracking. If that pavement structure
Pavement Replacement and Patching contains a great number of cracks, consideration should
To attempt to bridge failed areas with the new be given to the application of a surface treatment
overlay material is usually foolish unless a very thick instead of an individual crack filling operation . The
overlay is to be constructed . Removal and replacement cracks should be cleaned, if feasible, by being blown out
should be carried out on all pavement areas on which with air. The surface treatment should be applied when
severe load-related distress has occurred . All of the the pavement surface is clean and dry and should consist
asphalt concrete mix and granular base materials that of a single application of asphalt binder material (as-
have failed should be excavated or cold milled and phalt cement, cutback asphalt, or asphalt emulsion) and
either recycled or wasted . Subgrade distortion should be cover aggregate. Alternatively, a slurry seal consisting of
repaired by undercutting and replacement with suitable a slow-setting emulsion, fine aggregate, and water may
backfill material. Proper subsurface drainage should be be used. Such a crack filler operation may be more eco-
installed as necessary. New granular base course nomical than a standard crack sealing process, depend-
material, stabilized base course layers, and/or asphalt ing on the extent of the cracking.
mix should be placed in order to bring the strength of
the pavement structure in the failed area to the same Leveling Courses
level as the surrounding good pavement layers. If Common practice in the past has been to place a
asphalt concrete mix is used to patch a large area, the leveling course on the existing pavement surface in order
mix should be placed with a paver. to improve the rideability of the pavement structure.
Localized failed areas should be patched properly. This leveling course, sometimes also called a wedge and
Each failed area should be cut back to sound pavement level course or a scratch course, was designed to fill in

Page 3-10
AC 150/5370-14
10/15/91
Appendix 1

the low spots on the pavement surface. This leveling multiple sweepings with a mechanical broom are usually
action was accomplished through the principle of the needed to remove all of the residual grit from the milled
floating screed on the paver. The thicker mix, however, surface. In some cases, it may be necessary to dampen
typically compacts more than the mix in thinner loca- the milled surface before sweeping or to air blow and/or
tions. This problem, called differential compaction, flush the milled surface with water in order to remove
requires that multiple courses be constructed over a dust and very fine material completely. Any dust and
pavement surface that is badly out of shape before a dirt left on the milled surface will greatly affect the bond
smooth surface can be obtained. The mix, as it passes between that course and the new asphalt overlay.
from under the paver screed, is in loose condition. Because of the increased surface area of the milled
After compaction by the rollers, the thickness of the pavement (from the grooves left by the cutting teeth on
layer will be reduced . The rule of thumb is that conven- the milling machine) , an additional quantity of tack coat
tional mixes will compact approximately 1/4 in. per 1 in. material may be required in order to assure adequate
of compacted thickness. Thus, for a 1 -in.-thick (com- bond between those layers. That increased quantity is a
pacted) course, about 1 1/4 in. of mix would have to be function of the type, number, condition, and spacing of
placed by the paver. Similarly, 3 3/4 in. of mix would the teeth used on the cutting mandrel of the milling
need to pass from under the paver screed in order to machine .
construct a layer with a compacted thickness of 3 in.
When a leveling course is placed, the mix laid in the Hot-Mix Asphalt over Portland Cement Concrete
low areas (in the wheelpaths if the pavement is rutted) When HMA is placed over a PCC pavement, the
will be thicker than the mix placed over the high points PCC surface should be prepared properly. The follow-
in the surface (between the wheelpaths). The thicker ing is a general overview of PCC surface preparation.
mix will compact more under the rollers, particularly if Any severely distressed areas in the PCC slabs should be
a pneumatic tire roller is used, than will the mix that is cut out, removed, and replaced using full-depth slab-
thinner. Thus, although some smoothing is repair techniques with PCC or HMA. Corrective work
accomplished with a single leveling course of mix, low should also be completed on the underlying subbase or
spots will still exist in the wheelpaths where the mix has subgrade material, if necessary. Any severely spalled
been compacted to a different degree than the mix areas at joints should be repaired using partial-depth
between the wheelpaths. Multiple layers of mix are slab-replacement methods. Portland cement concrete
usually needed to eliminate the roughness in the existing should be used for partial-depth repairs. Rocking slabs
pavement surface completely. This potential problem must be stabilized . Depending on the condition of the
can sometimes be addressed by using a motor grader to PCC pavement, procedures such as crack and seat, break
place mix in the low spots ahead of the normal paving and seat, or rubblizing can be used before the overlay is
operation, if traffic conditions permit. placed. Further, consideration can be given to the use
of a crack-relief layer between the existing PCC pave-
Milling ment and the new overlay.
Milling, also called cold planing, can be used in lieu Joints that are poorly sealed should have the old seal
of placing a leveling course (filling in the low spots) to material removed and then the joints should be cleaned.
remove the high points in the existing surface. Milling The joints, when dry, should be resealed with appropri-
can be accomplished in any width necessary, from 6 in. ate joint seal material. Care should be taken not to
to more than 13 ft. Figures 3-10 and 3-11 illustrate two overfill the joints, particularly in cool weather when the
different types of milling machines. Equipped with joints are open wide. Once the patching and resealing
automatic grade and slope controls similar to those used has been accomplished, the surface of the PCC pave-
on an asphalt paver, the milling machine is capable of ment should be cleaned completely using mechanical
producing a level surface in one pass over the present brooms and air blowing and/or water flushing where
roadway. The RAP produced by the milling process can needed.
be hauled back to the asphalt plant for future recycling.
In addition, the texture of the milled surface enhances Base Preparation
tack and bond and may reduce the possibility of slippage Subgrade Soil
of an overlay over the existing surface. If the asphalt pavement is to be placed directly on
A pavement surface that has been milled typically is the subgrade soil, that subgrade material should meet all
very dusty and dirty. Once the pavement has dried, applicable requirements for moisture content, density,

Page 3-11
AC 150/5370-14
Appendix 1 10/15/91

LAR
CATERPIL

Figure 3-10. Rear-loading milling machine (Caterpillar).

and smoothness . After the subgrade soil has been foundation before the asphalt paving commences. If
determined to be ready for paving, and before paving is distortion of the subgrade soil occurs during the paving
allowed to commence, the subgrade should be checked operation, the placement of the mix should be stopped
to be certain that it will be able to support the weight of until the condition of the soil can be corrected .
the haul traffic. The subgrade must provide a firm There is generally no need for a prime coat of

MILLTEC RX-50

Figure 3-11. Front-loading milling machine (Barber-Greene).

Page 3-12
AC 150/5370-14
10/15/91
Appendix 1

asphalt emulsion or cutback asphalt to be placed on the If the specifications require the application of a
subgrade soil. This is especially true when that soil is a prime coat to a new or existing granular base course
silty clay or clay material because the prime coat mate- layer, the prime coat material should be applied with a
rial cannot be absorbed into the subgrade material. The pressure distributor to the base course at least 48 hr
use of a prime coat on sandy subgrade soils is also before paving is to begin. Typically a cutback asphalt
questionable. If the sandy material displaces excessively (MC- 30 or MC-70) is used as the prime coat material,
under the wheels of the haul trucks, that material should if available. An asphalt emulsion is not normally used
probably be stabilized with some type of binder material because it will not penetrate very far into the granular
before paving. The application of a prime coat in that material, although some inverted emulsions (emulsion
case will generally not be enough to hold the sandy soil containing limited amounts of cutter material) have been
in place during the paving operations. A prime coat applied successfully. The application rate should be
should not be used as a substitute for proper prepara- varied with the openness (porosity) of the base course
tion of the subgrade soil. material. Typical application rates range from 0.15
gal/yd² for a tight surface to 0.40 gal/yd² for an open
Granular Base Course surface. No more prime should be applied than can be
If the asphalt layer is to be constructed directly on a absorbed completely by the granular base course in 24
new or existing untreated granular base layer, that hr. If not absorbed, the excess should be blotted with
material should meet all the requirements for moisture sand and removed.
content, density, and smoothness. Proof rolling should
be done, however, on top of the granular base material TACK COAT
and the amount of deflection of the base and the The purpose of a tack coat is to ensure a bond
amount of indentation of the truck wheels into the between the existing pavement surface and the new
granular base course material noted . If the base mate- asphalt overlay. The tack coat should not be used in
rial is stable and dry and does not deflect and indent lieu of cleaning the present pavement surface : removing
significantly under the wheels of a loaded tandem axle accumulated dust and dirt by mechanical brooming or by
truck, placement of the prime coat and/or the new flushing with air and/or water. If a good bond is not
asphalt mix should be permitted to start. If the condi- formed between the existing surface and the new
tion of the granular material is not satisfactory, the base overlay, a slippage or sliding-type failure can easily
course should be reworked or stabilized to put it into occur. The new overlay can be shoved in a longitudinal
the proper condition for overlay. direction by traffic, particularly at locations where the
There is a considerable difference of opinion as to traffic accelerates or where the vehicle brakes are ap-
the benefits of a prime coat of asphalt material on a plied. Thus, the pavement surface must be completely
granular base course layer. Advocates of the use of a clean before the tack coat is applied .
prime coat feel that the material acts as a temporary The tack coat material should be applied by a pres-
waterproofing layer that protects the base course and sure distributor, as shown in Figure 3-12. All nozzles on
prevents it from absorbing excess moisture during rain the distributor should be open and functioning. All
before paving, allows the base course to be used for light nozzles should be turned at the same angle to the spray
traffic, binds together any dust on the surface of the bar; approximately 30°, depending on the manufacturer
granular base layer, promotes the bond between the of the distributor. In addition , the spray bar should be
base course material and the new asphalt overlay, and at the proper height above the pavement surface to
prevents slipping of thin pavement layers. In many provide for a double or triple lap of the liquid asphalt
cases, however, a prime coat is not needed on a granular material. This will provide the proper amount of over-
base course layer. A prime coat does not add anything lap between the nozzles and a uniform application ofthe
to the structural capacity of the pavement layers, and, if tack coat material to the road surface. The tack coat
the granular base course yields under the wheels of a material, which is normally asphalt emulsion but can also
loaded truck, the application of the prime coat material be asphalt cement or cut back asphalt, should be heated
generally will not improve the condition of that base to the proper temperature so that it is fluid enough to
course material enough to allow paving to be done on be sprayed from the nozzles instead of coming out in
top of the base layer. As pointed out under "Subgrade strings.
Soil," the use of a prime coat is not a substitute for Uniformity of application and use of the proper
proper preparation of the granular base course material. application rate is the key to the success of the tack coat

Page 3-13
AC 150/5370-14
Appendix 1 10/15/91

NYME an open-textured surface requires more tack


coat than a surface that is tight or one that
is "fat" or flushed . In addition, more tack
coat material may be needed on a milled
surface because of the increased surface
area. In the last case, the application rate

could be as great as 0.08 gal/yd² of residual
asphalt cement .
The amount of water in an asphalt emul-
sion and the amount of diluent material in a
cutback asphalt must be taken into account
BITUMETER when determining the proper application
WHEEL SPRAY BAR
rate to be sprayed from the distributor. Too
little tack coat will not provide sufficient
Figure 3-12. Asphalt distributor (Asphalt Institute) . bond between the old and the new pavement
layers. Too much tack coat may contribute
process. Figure 3-13 illustrates a tack coat application to the sliding of the overlay on the existing pavement
that is too light--not enough tack coat has been sprayed surface and bleeding of the tack coat material through
on the road surface . Figure 3-14 shows the opposite a thin overlay.
problem--too much tack coat material on the existing If an asphalt cement is used as the tack coat materi-
pavement. Ifthe correct amount of tack coat is sprayed al, it will cool to ambient temperatures very quickly.
on the surface, some of the existing surface will still be Further, because there is no carrier material to evapo-

visible through the tack coat--not all of the existing rate, paving may follow the asphalt cement tack coat
pavement surface will be covered with the tack coat . application immediately. If a cutback asphalt is em-
Use of a diluted asphalt emulsion tack coat (slow-setting ployed as a tack coat, sufficient time must be allotted
asphalt emulsion diluted 1 : 1 with water) will result in between the application of the tack coat and the start of
complete coverage of an extremely thin residual asphalt paving to permit the diluent in the cutback material to
film . evaporate. The rate of evaporation will depend on the
The proper tack coat application will leave a residual type and grade of the cutback asphalt used and on
asphalt cement content of approximately 0.04 to 0.06 environmental conditions. If an asphalt emulsion is used
gal/yd² on the roadway. The amount of tack coat used for the tack coat, a delay must also occur between the
will depend on the condition of the pavement surface; emulsion application and the placement of the overlay.

Figure 3-13. Too little tack coat (J. Scherocman).

Page 3-14
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-14. Excessive tack coat (J. Scherocman) .

The emulsion must break (change color from brown to not needed, however, when a layer of new mix is being
black) and the water must evaporate from the emulsion placed over another layer of asphalt pavement that has
before the new mix can be placed over the tack coat been laid within a few days. As long as the underlying
material. new layer has not become dirty under traffic or from
If the overlay is to be constructed under traffic, the windblown dust, a tack coat may be deleted between lifts
tack coat is normally placed only a short distance in of mix placed within a period of several days.
front of the paver; within the lane closure and far
enough ahead for the tack to cure properly before the SURFACE PREPARATION TECHNIQUES
mix is laid on top of it. Traffic is kept off of the tack Before an asphalt pavement course is placed over an
coat at all times. If the roadway being paved is closed existing surface (subgrade soil, aggregate base, asphalt
to traffic, the tack coat can be placed as early as 24 hr stabilized material, or portland cement concrete) that
ahead of the laydown operation . This will assure that surface must be prepared properly for the new layer.
the tack coat will be well cured before the mix is placed Some of the recommended preparation procedures
on top of it. Under unusual circumstances, if traffic include:
must travel over the tack coat before the overlay is • Any failures in the existing surface must be re-
placed, a light layer of sand can be spread on top of the moved and replaced or repaired by patching unless a
tack coat to prevent the pickup of the tack coat material very thick overlay is constructed.
by traffic. The application rate of the sand should be in · Cracks in an existing asphalt pavement surface
the range of 4 to 8 lb/yd², depending on the application generally should be sealed individually or some type of
rate of the tack coat material and the gradation of the surface treatment should be applied to the whole road-
sand . Excess sand should be broomed from the pave- way area. Joints in a PCC pavement that are poorly
ment surface before the overlay is placed to assure the sealed should be routed out and resealed . Rocking PCC
proper bond between the overlay and the existing slabs should be stabilized .
surface . • Arough, uneven asphalt surface should be leveled
The application of the tack coat material is essential with asphalt mix (using a paver to place mix in large
when an overlay is being constructed on an existing areas) to fill in the low spots in that surface or should
pavement surface; either portland cement concrete, hot- be cold planed with a milling machine to remove the
mix asphalt, or surface treatment. A tack coat often is high spots.

Page 3-15
AC 150/5370-14
Appendix 1 10/15/91

• After the needed repairs are completed , the pave- asphalt or PCC pavement surface. The distributor that
ment surface should be cleaned of all dust, dirt, and is used should be checked to assure that all the nozzles
other debris. This should be accomplished using multi- are open and set at the correct angle and that the spray
ple passes of a mechanical broom. If brooming does not bar is at the proper height above the pavement surface.
remove all of the accumulated dirt, flushing with air • The application rate for the tack coat must be
and/or water may be required. based on the residual amount of asphalt cement on the
• A prime coat is generally not needed on subgrade road surface, which should be between 0.04 and 0.06
soil. A difference of opinion exists on the benefits of gal/yd² for normal surfaces. Milled pavements may need
the use of a prime coat on a granular base course, but a greater amount of residual tack coat. Too little tack
in many cases a prime coat can be eliminated without coat will not provide the needed bond between the old
detrimental effect on the performance of the pavement and new layers. Too much tack coat may promote
structure . slippage of the new overlay on the old pavement or
• The application of a tack coat must be accom- bleeding of the tack material through a thin overlay.
plished before an overlay is constructed on an existing

Page 3-16
AC 150/5370-14
10/15/91
Appendix 1

SECTION THREE
MIX PLACEMENT

INTRODUCTION Propulsion Systems


The purpose of the paver is to place the hot-mix The paver is mounted on either crawler tracks or
asphalt to the desired width and thickness and to pro- rubber tires. The crawler tracks could be all steel, steel
duce a satisfactory mat texture . The paver consists of equipped with rubber pads, or flexible bands with steel
two primary parts: the tractor unit and the screed unit. shoes and rubber pads. If the paver is used on top of a
The tractor unit provides the motive power to the paver yielding surface, the crawler track system will provide an
and transfers the asphalt mixture from the receiving increased area over which to spread and support the
hopper on the front of the machine to the spreading weight of the paver. If the paver is moved regularly
screws at the back of the paver. The second unit con- under its own power between paving locations, the
sists of the paver screed. This leveling device is attached rubber tire machine is normally used, because its travel
to the tractor unit at only one point on each side of the speed is much greater than that of the crawler track
paver and is able to " float" on the asphalt mix and paver. The type of propulsion system does not affect
provide initial texture and compaction to that material the basic functions of the paver.
as it passes out from under the screed . The parts of the
tractor unit and the screed unit are shown in Figure Push Rollers
3-15. The push rollers, located on the front of the paver
hopper, are used to maintain contact with the tires of
THE TRACTOR UNIT the haul truck and to push that truck ahead of the
The tractor unit fulfills all of the functions necessary paver. The rollers must be clean and free to rotate to
to receive the asphalt mix from the haul trucks, carry allow smooth forward travel of the paver. If the push
that material back to the spreading screws, and distrib- rollers are not cleaned periodically and do not rotate
ute the mix across the width of the screed. The tractor freely, the truck tires will slide on the rollers and in-
unit is powered by its own engine and provides the crease the load on the paver. Moreover, if one roller
required propulsion energy to move the machine for- rotates freely and the other does not, the paver may
ward, either on rubber tires or crawler tracks. It is tend to change direction.
composed of several major components including the Many pavers are equipped with a truck hitch that is
truck push rollers , mix-receiving hopper, material flow located underneath the push rollers on the front of the
gates, twin slat conveyors, and a pair of screw conveyors paver hopper. The purpose of the hitch is to keep the
or augers. truck in contact with the paver and prevent the truck

TRACTOR

HOPPER

DEPTH CRANK

SCREED

PUSH ROLLERS SIDE ARM AUGERS PIVOT POINT


TOW POINT CONVEYORS

Figure 3-15. Components of an asphalt paver (Blaw-Knox).

Page 3-17
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-16. Paver hopper (Barber-Greene).

driver from pulling away from the paver and inadver- haul vehicle or the pickup machine. The hopper must
tently dumping mix on the pavement in front of the be wide enough to allow the body of the haul truck to fit
paver. The hitch, controlled by the paver operator, inside of it. In addition, particularly for smaller pavers,
comes in contact with the rear wheels of the truck on the hopper must be low enough to permit the truck bed
each side of the truck. Once the truck bed has been to be raised without the bed placing excessive weight on
emptied of mix, the truck hitch is withdrawn and the the front of the hopper. The front of the hopper must
truck is able to pull away from the paver. be designed in a way to minimize the spillage of mix out
of the hopper during the dumping of the hopper wings.
Paver Hopper This is normally accomplished by using rubber belts or
The paver hopper, shown in Figure 3-16, is used to flaps attached to the wings.
receive and temporarily hold the asphalt mix from the If a windrow elevator (illustrated in Figure 3-17) is

Figure 3-17. Windrow elevator attached to front of paver (Ko-Cal; Koehring Co.) .

Page 3-18
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-18. Thin layer of asphalt concrete left on pavement surface under windrow
elevator (J. Scherocman) .

used to feed mix to the paver, the hopper must be able


to hold the proper volume of mix without unbalancing
the paver. The blades on the slat conveyor of the wind-
row elevator must be set at the right level to pick up all
of the mix that has been placed on the existing pave-
ment. No mix should be left in the windrow; this thin
layer of material (Figure 3-18) will cool quickly and may
result in difficulties in compacting the mix. In addition,
longitudinal streaks may occur in the mat behind the
paver at the edges of the windrow, as shown in Figure
3-19.
As shown in Figure 3-20, the sides, or wings, of the
hopper are movable. Mix, if left to stand for a long
period of time in the corners of the hopper, will cool
and may appear as chunks of mix back of the screed
when it passes through the paver. Thus, the mix is
periodically moved from the sides of the hopper into the
middle of the hopper by folding the wings (sides) and
allowing the mix to be deposited into the area of the slat
conveyors.
Many paver operators dump (fold) the wings of the
paver after each truckload of mix has been emptied into
the hopper. Further, to prevent spillage of the mix out
the front of the hopper, the operator often pulls the
amount of mix left in the hopper down during discharge
and after the truck has left the hopper by continuing to
run the slat conveyors to feed mix back to the augers.
This may result in the slat conveyor running completely Figure 3-19. Parallel streaks same width as windrow
empty. This practice can lead to increased mat prob- behind paver screed (J. Scherocman).

Page 3-19
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-20. Folded wings on paver hopper (Blaw-Knox).

lems if segregated mix is deposited on the conveyor slats, formed that cannot be broken up as that mix moves
either from the paver wings or from the haul truck, and through the paver to the augers and under the screed.
carried back to the augers and screed . It is not good On colder days, the hopper wings will need to be
practice to dump the paver wings after each truckload of dumped more frequently than on warmer days.
mix has been delivered or to deposit the mix held in the In all cases, the paver hopper should be at least
wings into the empty paver hopper, because either pro- partially full at the time that the wings are dumped into
cedure can decrease the quality of the finished mat. the center of the hopper; the amount of mix in the
To minimize segregation, the paver operator should hopper should be approximately at the level of the
fold the wings as seldom as possible. The frequency at bottom of the flow gates at the back of the hopper.
which the wings are dumped depends on the rate of This will provide enough mix to heat the cooler material
delivery of the mix to the paver, the temperature of the in the wings before it goes through the screed . The slat
mix, and the environmental conditions. The wings conveyors should not be visible at the time that the
should be emptied before the mix that collects in the wings are raised. As discussed later, keeping the hopper
corners of the hopper cools so much that chunks are relatively full between truckloads of mix keeps the head

PUSH ROLLERS CONVEYORS AUGERS CROWN


ADJUSTMENT

MATERIAL
FLOW

MATERIAL
FLOW

FRESHLY PLACED MAT


DIRECTION of TRAVEL

Figure 3-21 . Slat conveyor at bottom of paver hopper (Blaw-Knox) .

Page 3-20
AC 150/5370-14
10/15/91
Appendix 1

of asphalt mix in front of the paver screed constant and flow gates (too high, too low, and correct) in relation to
also reduces any segregation that might be present in the head of material in front of the paver screed.
the mix. In addition, the wings should not be "banged"
repeatedly as they are emptied. Augers
The mix that is carried to the back of the tractor unit
Slat Conveyors by the slat conveyors is deposited in front of the screw
At the bottom of the paver hopper is a set of slat conveyors or augers (Figures 3-24 and 3-25). Just as the
conveyors. As shown in Figure 3-21 , these devices are two slat conveyors operate independently of each other,
used to carry the asphalt mix from the hopper through the augers on each side of the paver are run separately
the tunnel on the paver and back to the spreading from one another. The auger on one side of the paver,
screws. The slat conveyor on one side of the paver however, is run in conjunction with the slat conveyor on
operates independently from the movement of the slat that same side of the paver. The mix placed in the
conveyor on the other side of the machine. Thus, the auger chamber from the slat conveyors is distributed
amount of mix that can be carried back through the across the width of the paver screed by the movement of
paver on one side can be different from the volume of the augers. At the junction of the two augers in the
material that is being delivered on the other side. This center of the paver, adjacent to the auger gear box,
procedure allows the paver operator to feed more or there typically is a different-shaped auger (reverse auger
less material to one side of the paver or the other in or paddle) to tuck mix under the gear box and assure
order to pave ramps, mail box turnouts, and tapers. The that the mix placement at this location is the same as
slat conveyors are a continuous system, with the slats that across the rest of the width of the mix being laid .
being rotated back to the bottom of the hopper under- This reverse auger (paddle) is shown at the upper left
neath the paver itself. side of the main screw auger in Figure 3-26. It is
important that the augers carry a consistent amount of
Flow Gates mix across the front of the screed so that the pressure
At the back of the paver hopper is a set of flow (head of material) on the screed is kept as constant as
gates . These gates, one over each of the two slat con- possible.
veyors, are used to regulate the amount of mix that can
be delivered by the conveyors to the augers. The gates
move vertically, either by manual manipulation or me- FLOW GATE FLOW GATE

chanically. Depending on the vertical setting of the


gates, more or less mix is permitted to enter the paver
tunnel. The location of the flow gates is shown in
Figure 3-22. The flow gates should be adjusted to
provide a uniform head of material (at a level at or just Gates too HIGH -- augers overloaded
above the center of the auger shaft) in front of the
screed. Figure 3-23 shows three possible positions of the
FLOW GATE FLOW GATE

Gates too LOW -- insufficient material supply

FLOW GATE FLOW GATE

Correct adjustment -- Uniform material volume / flow

Figure 3-22. Flow gates at back of paver hopper Figure 3-23. Position of flow gates (Blaw-Knox).
(Cedarapids).

Page 3-21
AC 150/5370-14
Appendix 1 10/15/91

reduced slightly as the screed pivots


about the tow point.
If the gates are set too low, the
material feed system will not be able to
deliver enough material to the augers,
thus reducing the head of mix in front
of the screed and the force pushing on
the screed. This action reduces the
thickness of the mat being placed as
the screed settles and increases the
angle of attack of the screed as it
O
pivots about the tow point. With the
older paver system, in which the mate-
rial feed system operates at a single
speed on an off-on basis, the only way
the operator can control the head of
material in front of the screed is by
proper setting of the flow gates at the
back of the paver hopper. The flow
gates and feeder on-off switches must
be set at a position that requires the
slat conveyors and augers on each side
of the machine to run as close to 100
percent of the time as possible.

Manual Control-Variable Speed


Some pavers are designed so that in
the manual mode the paver operator
can select one of several speeds for the
slat conveyor, each essentially a per-
centage of the maximum speed of the
conveyor. Once the conveyor speed is
Figure 3-24. Paver auger (J. Scherocman).
selected, the speed of the spreading
screw conveyor (auger) is proportioned
Material Feed System to the speed of the slat conveyor. The operator is
Manual Control-Constant Speed responsible for controlling the slat conveyor and augers
As shown in Figure 3-25, the slat conveyor and auger in order to keep a constant level of asphalt mix in front
on one side of the paver act independently from the slat of the paver screed . The flow of material to the screed
conveyor and auger on the other side of the paver. On essentially is regulated by the height of the hopper flow
older pavers , in the manual mode, the slat conveyor and gates and by the starting and stopping of the slat
the auger speed are constant. The paver operator can conveyor and auger on each side of the paver. With this
only control the amount of mix being carried back to the manual system , no changes occur in the head of material
screed by adjusting the height of the flow gates. If the in front of the screed as the speed of the laydown ma-
gates are set too high, the material feed system will chine changes unless the speed of the whole material
provide a "slug" of asphalt mix to the augers whenever delivery system is changed by the paver operator.
the slat conveyors and the augers are operated . This
will significantly increase the head of material in front of Automatic Control
the paver screed and cause increased pressure on the Most pavers are equipped with an automatic feed
screed. This greater force will lift the screed and system that supplies mix to the paver screed in propor-
increase the thickness of the mat being placed . Because tion to the need for the material . For this system, a
of this action, the angle of attack of the screed is feed control sensor (a type of limit switch) is used to

Page 3-22
AC 150/5370-14
10/15/91 Appendix 1

LEFT SIDE RIGHT SIDE


FEED SYSTEM FEED SYSTEM

LEFT SIDE
FLOW GATE RIGHT SIDE
FLOW GATE

LEFT SIDE
CONVEYOR
RIGHT SIDE
CONVEYOR
LEFT SIDE
AUGER

RIGHT SIDE
AUGER

HEAD OF MATERIAL

Figure 3-25. Dual-feed system (slat conveyor and auger) (Blaw-Knox).

determine the amount of mix in the auger chamber, as amount of material in front of the screed . Instead of an
shown in Figure 3-27 . If the volume of mix available in on-off system, the speed of the delivery system is
front of the screed falls below the desired amount, the increased when more mix is needed and the speed of the
feed control sensor will move enough to engage the slat slat conveyor and auger system (on each side of the
conveyor and auger system, pulling more mix back to the paver) is decreased when the head of material in front
screed area. As the material is distributed in front of of the screed is too great. This type of equipment is
the screed, the feed control sensor will rise and disen- illustrated in Figure 3-28.
gage the feed system. This action will maintain the In addition to these limit switch-type and variable-
preselected head of material in front of the screed. This speed systems, both ultrasound and infrared sensing
sequence repeats itself, continuously maintaining a devices can be used to determine the amount of mix in
consistent head of mix as long as material is available in the auger chamber. These two types of systems operate
the hopper. On some pavers, a variable-speed (po- on the same basis as the limit switch system; measuring
tentiometer-type) feed system is used to control the the amount of mix in front of the screed and controlling

Figure 3-26. Reverse paddle on auger at gear box (Cedarapids).

Page 3-23
AC 150/5370-14
Appendix 1
10/15/91

as close to the outside end of the augers as possible. If


rigid paver screed extensions are used, as discussed later,
the control arm should be mounted beyond the end of
the augers, just inside the end gate on the paver screed.
The amount of mix carried in the auger chamber

0
should be as constant as possible . The proper depth of
material on the augers should be at the center of the
auger shaft (Figure 3-29) . The level of material carried
in front of the screed should not be so little as to expose
the lower half of the screw conveyor flights. Further,
the level of mix delivered to the screed should never be
so great as to cover the upper portion of the auger, as
shown in this same figure.
If the feed system is set and operating properly, the
slat conveyor and augers on each side of the paver will
rarely shut off. This continuous action of the conveyors
and augers is accomplished by setting the proper posi-
tion for the hopper flow gates and determining the
correct speed setting for the slat and screw conveyors.

Figure 3-27. On and off automatic feed control The primary key to the placement of a smooth pavement
layer is the use of the material feed system to keep the
system (Barber-Greene).
head (level) of material in front of the screed constant,
primarily by keeping the slat conveyor and augers running
the slat conveyor and auger feed system to maintain a as close to 100 percent ofthe time as possible. Intermit-
constant head of mix at the screed. tent operation of the slat conveyor and auger system
For the automatic feed control system to function could cause both auger shadows and ripples in the mat
properly, the feed sensor control arm should be located behind the screed, as discussed in the section on mat

FEED CONTROL
.Approx

SENSOR
31/2

OFF
SLOW
MEDIUM FAST VARIABLE DISTANCE
4 1/2 Approx.

Figure 3-28. Variable auger speed automatic feed control systems (Blaw-Knox).

Page 3-24
AC 150/5370-14
10/15/91
Appendix 1

NOT THIS

THIS

Figure 3-29. Correct and incorrect mix levels in the paver auger chamber (Bar-
ber-Greene).

problems. and model of paver is shown in Figure 3-30.


The principle of the free-floating paver screed was
THE SCREED UNIT developed in the early 1930s . That concept allows the
The screed unit, which is towed by the tractor unit, paver screed, which is attached to the tractor unit at
establishes the thickness of the asphalt layer and pro- only one point on each side of the machine (the tow or
vides the initial texture to the new surface. In addition, pull point), to average out changes in grade that are
the screed imparts some level of density to the material experienced by the wheelbase (rubber tires or crawler
being placed through the vibratory or combination tracks) of the tractor unit . The floating-screed principle
tamping and vibratory action of the screed. A diagram is employed on all of the modern asphalt pavers in use
showing the parts of the screed for one particular make today.

SCREED PULL POINT


FREE FLOATING
SCREED

Figure 3-30. Screed unit (Barber-Greene).

Page 3-25
AC 150/5370-14
Appendix 1 10/15/91

SCREED DEPTH CRANK

F3

-TOW POINT

PIVOT POINT

F2

F1

Figure 3-31 . Screed tow point and tow arm forces acting on paver screed (Blaw-Knox) .

Tow (Pull) Point being spanned by the tractor wheelbase. For the float-
The screed unit is attached to the tractor unit at only ing-screed principle to work properly, under manual
one point on each side of the paver. This point, shown control, it is important that the pull points on both sides
in Figure 3-31 , is called the tow point or the pull point of the tractor be at the same level above the ground .
by the different paver manufacturers. The tow point is The position of the screed pull points can be altered by
really a pin-type connection that allows the leveling arms raising or lowering the rods on which the pull points are
(also called side arms or pull arms) of the screed to mounted. For most asphalt mixtures, the pull or tow
rotate or pivot around that point . This pin connection point is positioned near the center of the rod . For some
reduces the transmission of movement between the asphalt mixtures being placed, however, it may be
tractor unit and the screed unit. advantageous to change the elevation of the pull points:
The concept of the pull point and the free-floating raise or lower that elevation to improve the texture of
screed allows the tractor unit to provide the wheelbase the mat being placed . (If the paver is being operated
for the screed unit . The screed then pivots around the under automatic grade and slope control, as discussed in
pull or tow point and responds to the average grade the following section, the elevation of the pull point
typically is centered when paving is started . The loca-
Pull Point tion then changes as necessary as paving proceeds in
Too High order to maintain the proper angle of attack of the
screed .)
Abnormal On some pavers, under manual control, when the
wear
pull points are too high, the front of the screed is tilted
down in order to maintain the proper angle of attack for
proper mat thickness. Premature wear on the strike-off
and the leading edge of the screed can be experienced
Pull Point
Too Low (as shown in Figure 3-32), the smoothness of the mat
can be reduced, and the degree of compaction imparted
Abnormal
wear to the mix will be lessened . When the pull points are
too low, on the other hand, the front of the screed is
tilted up in order to maintain the correct thickness of
Pull Point the asphalt mix being placed . Additional wear can occur
Correct on the trailing edge of the screed .
Normal For a paver not equipped with automatic screed
Uniform Wear
controls, the relationship between a change in the ele-
vation of the tow point on one end of the leveling arm
and the movement of the screed on the opposite end of
the leveling arm is shown in Figure 3-33. Typically an
Figure 3-32. Effects of pull point height on screed 8:1 ratio exists between the movement of the tow point
wear (Cedarapids).

Page 3-26
AC 150/5370-14
10/15/91
Appendix 1

1 (25mm) Movement at Tow Point--

produces

0 41/8" (3mm) Movement


at
Leading Edge of Screed

Figure 3-33. Ratio of tow point movement to mat thickness (Blaw-Knox).

and the change in the angle of attack of the front edge this figure. This force varies as the speed of the tractor
of the paver screed . This means that if the tow point is unit increases and decreases.
moved vertically upward 1 in., the angle of attack of the The second force on the screed is the head of mate-
screed will be increased by 1/8 in. As discussed in detail rial pushing against the screed, F2. As the amount of
below, the paver must move forward approximately five asphalt material in the auger chamber that pushes
lengths of the leveling arm before the screed will move against the screed changes, the net force acting on the
up to the new level of the tow point and the forces on screed also changes. As the forces acting on the screed
the screed will again be in equilibrium. change, the screed must come to a new angle of attack
The combination of the screed pivot point at the end in order to compensate for the change in force acting on
of the leveling arm attached to the tractor and the it.
thickness-control device at the screed provides for The forces on the screed must be in equilibrium (all
adjustments to be made to the angle of attack of the forces equal) for the screed to remain at a constant
screed unit. The angle of attack is shown in Figure 3-34. angle of attack as it is towed by the tractor unit . When
Because of the method by which the screed is attached a change in one force occurs, the screed will rise or fall
to the tractor, the screed acts in a manner similar to that and will change the thickness of the mat being placed .
of a water skier being pulled by a speed boat. This will also result in a change in the angle of attack of
the screed. The screed will react to the change in the
Forces Acting on the Screed force against it until it reaches a new equilibrium
The screed assembly, including the tow point, the elevation in which the forces are in balance.
leveling or towing arm, the screw conveyor or auger, the
thickness-control crank, and the screed with its pivot Paver Speed
point, is shown in Figure 3-31 . There are two primary Because the speed of the paver has a major effect on
forces that constantly act on the paver screed as the the angle of attack of the paver screed, it is good paving
paver places the mix. The first force acting on the practice to keep the speed of the paver as consistent as
screed is the towing force of the tractor, F3 as shown in possible during laydown operations. Under manual

TRAVEL

ANGLE -LINE- of SHEAR


of
ATTACK

Figure 3-34. Screed angle attack position (Blaw-Knox).

Page 3-27
AC 150/5370-14
Appendix 1 10/15/91

material flow control and screed control, if the forces on possible without jerking the machine . The next truck
the screed remain constant except for the change in should then be backed toward the paver, stopping short
paver speed, an increase in the speed of the paver will of the paver; 1 or 2 ft away. For a dump truck, the bed
cause the thickness of the asphalt layer being placed to should be raised in the air, without releasing the tailgate,
decrease. Similarly, a decrease in the speed of the so that some mix can slide against the tailgate. The
tractor unit will cause an increase of the thickness ofthe paver should be started and brought back to the prese-
mat being laid. This will only occur, however, as long as lected paving speed as quickly and smoothly as possible.
no other changes are made in the system; the location of The tailgate on the truck should be released as soon as
the pull points (tow points) of the screed remain at a the push rollers on the paver make contact with the
constant level and the rate of feed of mix to the augers vehicle tires, and the mix should be delivered to the
remains constant. As paver speed increases, if no paver hopper before the level of mix in the hopper
additional mix is delivered by the slat conveyors to the drops below the level of the bottom of the flow gates.
augers, less mix is available to pass under the screed and This procedure of stopping and restarting the paver
the thickness of the layer would be reduced. quickly will minimize the change in the forces acting on
Under manual material flow control, the paver the screed and will allow a near-constant mat thickness
operator would have to increase the amount of mix to be placed .
transferred to the augers in order to maintain a constant Maintaining a constant paver speed is one of the
head of material in front of the screed and a constant primary advantages associated with the use of a pickup
layer thickness. Under automatic material flow control, machine or material transfer device to deliver mix to the
however, the volume of mix delivered to the augers paver. By keeping the speed of the paver constant, a
would increase as the paver speed increased, maintaining consistent head of material can be maintained by the slat
a constant head of mix in front of the screed. In this conveyors and the augers and a constant layer thickness
latter case, the forces against the screed would remain will be the result. If dump-type haul trucks are used,
balanced at the new speed and the thickness of the layer however, a smoother-riding pavement can be constructed
would be unchanged even as the paver speed was by quickly reducing the speed of the paver and then
increased. Thus, through the use of automatic material- stopping the paver when a truckload of mix is depleted
control devices on the paver, the head of material can instead of by keeping the paver creeping along until the
be maintained at a constant level regardless of paver next truck arrives at the hopper. Once the next truck-
speed, and the layer thickness placed will remain con- load of mix is in the hopper, the paver operator should
stant. Under manual flow control, however, the paver quickly increase the speed of the paver back to normal
operator must alter the amount of mix delivered to the operating speed.
augers and screed as the speed of the paver is changed .
In addition, the paving speed should be selected to Head of Material
match the amount of mix being delivered from the plant . If the volume of mix in the auger chamber is in-
When changing trucks, it would be best if the trans- creased, the force on the screed will also increase,
fer could be done without slowing down or stopping the causing the screed to rise . This action will then cause
paver. At relatively slow paving speeds, it might be the angle of attack of the screed to decrease until a new
possible to make the truck exchange while keeping the equilibrium position is reached . If the amount of
head of material in front of the screed constant. This material being carried on the augers is decreased, the
would require, however, that the level of mix in the thickness of the mat will be reduced, all other factors
hopper be kept at a level at least even with the bottom being equal, as the screed falls. This results in an
of the flow gates at all times. Use of a windrow elevator increase in the angle of attack of the screed until the
or a material transfer device eliminates this problem . forces on the screed are once again in equilibrium.
If the normal paving speed is fast enough or the One of the primary factors that affects the head of
truck exchange is slow enough that the proper amount material in the auger chamber is the action of the slat
of mix cannot be maintained in the hopper (on the slat conveyor and auger on each side of the paver. When
conveyors and on the augers) between loads, it would be the slat conveyors and augers are operating, the mix is
better to stop the paver when the transfer of trucks pulled from the paver hopper, through the tunnel, and
occurs . As soon as one truck is emptied, it should pull is distributed across the front of the screed . As long as
away from the paver. The paver should be brought from this flow of material is relatively constant, the head of
paving speed to a stop as quickly and smoothly as material pushing against the screed will be relatively

Page 3-28
AC 150/5370-14
10/15/91
Appendix 1

0%

ANGLE of ATTACK

Figure 3-35. Angle of attack (Blaw-Knox).

constant and the mat being placed will be smooth and screed to fall and reduce the layer thickness.
have a consistent texture.
If the head of material is allowed to vary, however, Thickness Control Cranks for Manual Operation
the screed will move up and down in relation and reac- The screed is attached to the leveling or tow arms on
tion to the forces acting on it . As the amount of mix each side of the paver through a hinge or pivot point, as
being carried by the augers is decreased because the slat illustrated in Figure 3-31 . The thickness-control mecha-
conveyor and auger system is shut off, the screed will nism, usually either a crank or a handle, allows the
move downward, reducing the thickness of the mat screed to be moved or rotated around the pivot point.
behind the screed. As the slat conveyor and auger The key to the leveling action of the screed is its ability,
system comes on, more mix is carried back to the augers by rotating around the pivot point and being attached to
and across the front of the screed. This increases the the tractor unit at only the tow point, to establish an
force on the screed and causes it to rise to a new equilibrium attitude based on the forces applied to the
elevation, resulting in a thicker mat. Thus, the elevation screed, as illustrated in Figure 3-35. As the mix passes
of the flow gates becomes very important in regulating under the screed plate, the screed floats on the mix,
the amount of mix in front of the screed . determining the mat thickness and the texture of the
There is a potential for the head of material to be material as well as providing the initial compaction of
affected each time the slat conveyors and augers are the asphalt mix.
turned off and on. This is true particularly if the head For a constant position of the tow point (the tractor
of material is not properly set initially. For this reason, unit running on a level surface and without automatic
the use of a proportional automatic feed-control system screed controls), altering the setting of the thickness-
is very important, because this device keeps the slat control devices changes the attitude (angle of attack) of
conveyors and augers running as much of the time as the screed and changes the forces acting on the screed .
possible, provided the flow gates are properly set . This, This, in turn, causes the screed to move up to, or down
in turn, keeps the head of material relatively constant to, a new elevation as the paver moves forward, and thus
and allows the screed to place a mat of consistent alters the thickness of the mat being placed. The reac-
thickness. A constant head of material against the paver tion of the screed to changes in the position of the
screed reduces the occurrence of ripples and auger thickness-control settings, however, is not instantaneous.
shadows. Rather, there is a lag in the reaction of the screed that
Another factor that affects the uniformity of the allows the screed to average out variations in the input
head of material in front of the screed is the tempera- forces acting on it.
ture of the mix. If a cold load of material is deposited
in the paver hopper and carried back to the screed by Reaction of the Screed
the slat conveyors and the augers, the colder, stiffer mix Figure 3-36 provides information on the reaction
will increase the force acting on the screed and cause time of the screed when a change is made in the angle
the screed to rise, increasing the thickness of the layer of attack of the screed either at the screed or at the
placed. If a hot load of mix, on the other hand, is location of the tow point. After the tow or pull point
delivered to the paver, the decrease in viscosity of the has been raised, as shown in this figure, it takes ap-
binder material will reduce the stiffness of the mix and proximately five times the length of the leveling or tow
reduce the force of the mix on the screed when the mix arms on the paver screed for the screed to complete 99
is deposited in front of it. This action may cause the percent of the change, up or down, to the desired new

Page 3-29
AC 150/5370-14
Appendix 1
10/15/91

ORIGINAL
SCREED LEVEL

VERTICAL
DISPLACEMENT

NEW SCREED LEVEL


FWD. TRAVEL FIVE TOWLENGTHS
in TOWLENGTHS Start 1
DISPLACEMENT
REMAINING 100% 36.8% 13.5% 5.0% 1.8% 0.7%

Figure 3-36. Screed reaction time (Blaw-Knox).

elevation. This means that if the length of the leveling percent of the elevation change is done by the time a
arm is 9 ft, the paver would have to move forward for a distance of 27 ft has been traveled (three leveling arm
distance of at least 45 ft before the required input to the lengths of 9 ft each). It is not until the paver has moved
thickness-control device was completely carried out by down the roadway a distance equal to at least five
the paver screed . leveling arm lengths, however, that some 99+ percent of
the thickness change has been completed.
Changing Screed Pivot Point The same exercise holds for a reduction in the
As an example, assume that it is desired to increase thickness-control settings at the screed . A screed oper-
the thickness of the mat being placed from 1 in. to 1 1/2 ator desiring to reduce the depth of the asphalt layer
in. A change is made in the thickness-control crank, by turns the thickness-control crank in the opposite direc-
turning it clockwise or counterclockwise depending on tion and causes the screed to rotate around the hinge
the make of the machine, to change the angle of attack point. As the paver moves forward , the decreased angle
of the screed. The movement of the thickness-control of attack of the screed causes it to move downward,
mechanism causes the screed to move around the hinge thereby reducing the amount of mix being fed under the
or pivot point and increase the angle compared with the screed. The screed will continue its downward move-
road surface. The change in mat depth, however, is not ment until the forces acting on it are again in equilibri-
immediate. The paver must move forward for some um. If the pavement layer depth were being changed
distance before the modification in mat thickness can be from 1 1/2 in. to 1 in., it would still require the paver to
completed. move a distance of more than five lengths of the leveling
As shown in this figure, approximately 63 percent of arm before 99+ percent of the thickness change would
the thickness change is accomplished after the paver has be completed .
moved forward a distance equal to one leveling arm
length, or 9 ft in this example. As the paver moves Changing Tow Point Elevation
forward another 9 ft, about 87 percent of the desired The same principle applies to a change in the loca-
thickness change has been completed . Approximately 95 tion of the tow point or pull point of the screed leveling

ANGLE of ATTACK
Manual or Automatic Control of Tow Points

Figure 3-37. Angle of attack (Blaw-Knox).

Page 3-30
AC 150/5370-14
10/15/91
Appendix 1

arm where it is attached to the tractor unit. If the tow screed is consistent in comparison to the reference. This
point is displaced, as shown in Figure 3-37, the change allows the screed to carry out the leveling action needed
in elevation of the tow point is translated to a change in over a longer reference length in order to reduce the
the angle of attack of the paver screed. The paver must roughness of the existing surface through the application
still move forward for a distance of approximately five of the new asphalt layer.
times the length of the leveling arm on the machine for
the screed to react to the change in the location of the Screed Strike-offs
tow point and move up to or down to the new elevation. Depending on the make of the paver, the screed may
As a roadway is being paved without the use of be equipped with a device on its front edge that is called
automatic grade and slope controls, the tractor unit a strike-off by some manufacturers and a prestrike-off by
moves upward and downward in response to the grade others. The purpose of this device
of this device is to control the feed
of the underlying material. The vertical movement of of the asphalt mix under the paver screed, thereby
the tractor translates into vertical movement of the tow regulating the amount of mix that reaches the nose of
point on the side of the paver. Each time the tractor the screed plate. Further, the strike-off or prestrike-off
goes over a hump or into a dip in the existing pavement is used to reduce the wear on the leading edge of the
surface, the elevation of the pull point changes. This, in screed . The location of the strike -off assembly is shown
turn, alters the angle of attack of the paver screed, in Figure 3-38.
causing the amount of material flowing under the screed When the strike-off is attached to the front of the
to be decreased or increased. The fact that it takes five screed, its position becomes important relative to the
times the length of the leveling arm before the screed ability of the screed to handle the asphalt mix properly.
completely reacts to a change in the location of the tow If the strike-off is set too high, as shown in this same
point allows the screed to reduce the thickness of the figure, extra material will be fed under the screed . This
asphalt mix being placed over the high places in the action will cause the screed to rise. The resulting in-
existing surface and to place more mix in the low spots crease in the mat thickness will be overcome by man-
on the present roadway. It is this averaging or leveling ually reducing the angle of attack of the screed, using
action that forms the basis for the floating screed the thickness-control cranks. This, in turn, will cause the
principle of the asphalt paver. screed to pivot around its hinge point and ride on its
When a paver is being operated manually, as in the nose. Rapid wear of the nose plate will result . In addi-
above examples, it is very important for the screed tion, the screed will settle when the paver is stopped
operator to realize that the reaction to a change in the between truckloads of mix because the weight of the
setting of the thickness-control crank is not immediate. screed is carried only on the front part of the screed .
The paver must move forward at least one leveling arm When the strike-off is set too low, as shown in Figure
length before 63 percent of the thickness change is 3-38, the thickness of the lift will be reduced because of
completed. If a second change is made in the setting of the lack of mix being fed under the screed . In order to
the thickness-control crank before the first change is maintain the proper thickness, the angle of attack of the
accomplished, the first change will never be completed. screed must be altered, causing the screed to ride on its
It will still take an additional five times the length of the tail. This increases the wear on the back of the screed
leveling arm for the second thickness change to be and also causes the screed to settle whenever the paver
carried out. For this reason, continual changes in the is stopped because of the concentration of weight of the
setting of the thickness-control devices are usually screed on a smaller surface area.
detrimental to the development of a smooth mat. The exact location of the strike-off depends on the
The use of automatic paver controls, discussed in the type of paver being used and on the depth of the layer
next section, allows the paver to construct a smoother being placed by the paver. For relatively thin layers of
pavement by keeping the location of the screed pull or pavement (1 in. thick or less) , the strike-off is usually
tow point constant relative to a predetermined reference placed lower than when thicker lifts of mix are being
as the tractor unit moves up and down vertically in placed. Similarly, for thick lifts of asphalt pavement
response to small changes in the grade of the underlying (greater than 2 in.), the strike-off assembly is usually
pavement surface. By maintaining the tow point at a raised slightly above the normal position. In general,
constant relationship to the predetermined reference the strike-off is located in the range of 3/16 in . to 1/2 in.
while the tractor moves vertically, the force on the above the bottom plane of the main screed plate . No
screed remains constant and the angle of attack of the compaction of the mix occurs under the strike-off.

Page 3-31
AC 150/5370-14
Appendix 1 10/15/91

taken to avoid overheating , which can cause permanent


warping of the screed . Usually within 10 min after
paving begins, the temperature of the screed plate has
increased to the point at which it can generally be
Strike -off
maintained by the temperature of the mix passing under
it. Thus, the burners are not needed and are shut off.
The screed heaters cannot be used to increase the
temperature ofthe mix being placed because the amount
of time that the mix is actually under the screed is much
too short to accomplish any temperature rise in the mix.
In cool weather, when the plant is cold, the haul
Strike-off Positioned Properly
trucks are cold, and the paver is cold, it is sometimes
advantageous to place the second or third truckload of
Rocks are Dragged mix delivered to the paver first. This second or third
Fines Accumulate load of mix is typically higher in temperature than is the
Strike -off first load and will serve to heat the paver more and
reduce the amount of tearing that might occur under the
screed. By placing the second or third truckload of mix
Wear
first, two warm loads of mix are laid down instead of
one cooler first load. This procedure can provide for a
more uniform surface texture of the mix when paving
must be accomplished in lower ambient temperatures.

Strike-off Positioned Too Low


Screed Crown Control
The screed on the paver can be angled at its center
to provide for positive or negative crown. The amount
of crown that can be introduced into the screed varies
Strike-off
Wear with the width of the basic screed and with the make
and model of the equipment. The adjustment of the
crown is typically done using a turnbuckle device to flex
the bottom of the screed and impart the desired degree
ofcrown. When rigid extensions are used in conjunction
with the main or basic screed , the crown being placed in
the pavement by the paver can usually also be altered at
Figure 3-38. Strike-off position (Cedarapids).
any of the points where the extensions are joined. If a
hydraulically extendable screed is being used with the
Screed Heaters paver, the crown can be introduced not only in the
The screed is equipped with heaters or burners, the center of the main screed but also at the points between
primary purpose of which is to increase the temperature the basic screed and the hydraulic extensions.
of a cold bottom screed plate to approximately 300°F. Most of the paver manufacturers recommend that
It is necessary for the screed to be at the same tempera- the screed be warped slightly, from front to back in the
ture as the asphalt material passing under it in order to center of the screed, to facilitate the passage of mix
assure that the mix does not stick to the screed plate under the screed and to obtain a more uniform texture
and tear, providing a rough texture to the mat. A on the asphalt mat. This involves setting the lead crown
properly heated screed, particularly at the start of the on the screed slightly greater than the tail crown on the
day's paving operations or after any extended shutdown screed. In general, there should be more lead crown
of the laydown process, provides for a more uniform mat than tail crown, but the amount of difference depends
surface texture. on the make of paver and the type of screed on the
To preheat the screed, the burners are normally machine. Normally the lead crown setting is 1/32 in. to
operated for a period of 10 to 20 min before the com- 3/16 in. greater than the tail crown position, with 1/8 in .
mencement of the laydown operation. Care should be being the average difference in the crown settings.

Page 3-32
AC 150/5370-14
10/15/91
Appendix 1

Screed Vibrators should be used near the maximum possible frequency .


Early pavers were equipped with tamper bars that On screeds where it is possible to change the amplitude
were located on the leading edge of the paver screed . of the applied vibrational force, the amplitude setting
These tamper bars were used to tuck the asphalt mix selected is related to the thickness of the mat being
under the screed and to provide some degree of initial placed; lower amplitude for thinner lifts and higher
compaction to the mix as it passed under the screed. amplitude for thicker lifts.
The tamper bar system was replaced by the more effi- The amount of density obtained by the paver screed
cient vibratory screed system. A few of the most recent is also a function of the speed of the paver. The faster
pavers (and many pavers used in other countries) are the paver moves, the less time the screed sits over any
equipped with combination screeds--both tamper bars particular point in the new mat, and, thus, the amount
and a vibratory screed . The discussion below, however, of compactive effort applied by the screed decreases.
is limited to pavers having vibratory screeds only. For asphalt concrete mixes, it can be expected that
The amount of compaction imparted to the asphalt approximately 70 to 80 percent of the theoretical maxi-
mix is a function of many variables. The properties of mum density of the mix will be realized in the mix when
the mix itself are very important; the stiffness of the mix, it passes out from under the paver screed.
the temperature of the mix, and the amount of asphalt
cement and moisture in the mix all affect the ability of Screed Extensions and End Plates
the screed to densify the mix. Two factors within the When the basic width of the paver screed (8 ft for
screed itself also contribute to the degree of compaction. small pavers and 10 ft for the larger machines) needs to
The first is the frequency of vibration and the second is be changed to accommodate increased paving widths,
the amplitude of the compactive effort. rigid screed extensions can be employed, as seen in
The frequency of vibration is controlled by the rotary Figures 3-41 and 3-42. These extensions come in several
speed of the vibrator shaft. Increasing the revolutions widths, usually 6-in., 1 -ft, 2-ft, 3-ft, and 5-ft sections. In
per minute of the shaft will increase the frequency of order to keep the paver in balance, the width of the
the vibration. The applied amplitude is determined by rigid extensions added to the paver screed should be
the location of the eccentric weights that are located on approximately equal on both sides of the machine, if
the shaft. The position of the eccentric weights can be possible.
altered to increase or decrease the amount of compact- It is important for the screed extension to be at-
ive effort applied to the mix by the screed , as illustrated tached securely to the main screed . Further, it is very
in Figures 3-39 and 3-40. In general, the vibrators important that the extension be set at the same elevation

Figure 3-39. Screed vibrator shaft with weights (Blaw-Knox).

Page 3-33
AC 150/5370-14
Appendix 1 10/15/91

MINIMUM NORMAL INCREASED MAXIMUM

Figure 3-40. Eccentric- weight positions (Blaw-Knox).

and angle as the basic screed to prevent the presence of screed extensions are employed, the strike-off or pre-
a transition line or ridge at the intersection of the main strike-off assembly must also be added to the extension,
screed and the extension or between different sections and set at the same location as the strike-off on the
of extension. Alignment of the front edge of the main screed.
extension is typically controlled independently of the An end plate (or end gate or edger plate) is attached
alignment of the rear edge of the extension. to the end of the screed to restrict the outward move-
Whenever a rigid screed extension is employed on ment of the mix around the end of the screed, as shown
the basic paver screed , auger extensions and the accom- in Figure 3-43. The vertical alignment of the end gate
panying auger tunnel extensions should also be added . is adjustable so that mix can be bled out from under the
The length of all the auger and tunnel extensions should, gate if necessary. In typical operating mode, however,
in general, be the same length as the added screed the end plate is positioned tight to the surface being
extensions to allow room between the end of the auger paved to retain the mix and control the width of materi-
and the end plate of the screed. Typically the distance al being placed.
between the end of the auger extension and the end Cutoff shoes can be used, if necessary, to reduce the
plate should be about 18 in. Further, whenever rigid width of mix placed to a width that is less than the basic

Figure 3-41 . Rigid screed extensions (J. Scherocman).

Page 3-34
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-42. Rigid screed extensions (Blaw-Knox) .

main screed width. As illustrated in Figure 3-44, the longitudinal mark or ridge will occur in the surface of
standard cutoff shoes are attached to the paver end gate the mix at the junction between the two screeds. This
and are employed to restrict the width of mix being laid mark can easily be eliminated by adjusting the elevation
between the end plates. Typically the cutoff shoes come of the extendable screed in relation to the main screed .
in widths of 1 ft or 2 ft, and are adjustable in increments In addition to the longitudinal mark, a mismatch in the
of 1 1/2 in. or 3 in . , depending on the manufacturer. elevation between the two screeds can also result in a
possible difference in surface texture in the mix behind
Hydraulically Extendable Screeds the extended screed and the main screed . Finally, the
Most paver manufacturers have developed hydrauli- lack of proper alignment between the two screeds can
cally extendable paver screeds that trail the primary or cause a difference in the degree of compaction that is
basic screed on the paver. One make of pavers, howev- obtained in the mix under the extendable screed.
er, is equipped with a power extendable screed that If a hydraulically extendable screed is to be used at
places the extendable portion of the screed in front of a fixed extended width for a period of time, the paver
the main screed. An example of each type of extendable should be equipped with auger extensions equal to the
screed is shown in Figures 3-45 and 3-46.
For all hydraulically extendable screeds, it is very
important that the angle of attack for the extendable
screeds (one on each side of the main screed) is the
same as the basic screed (see Figure 3-47). On some
makes and models of pavers, it may be necessary for the
trailing (rear) screeds to have a slightly positive attack
angle compared with the main screed. In general ,
however, the forces that act on the extendable screed
are similar to those that are present on the main paver
screed. Further, if a strike-off assembly is used on the
main screed, similar strike -off devices should be used on
the extendable screed sections.
If the extensions on the extendable portion of the
screed are not properly aligned with the main screed, a Figure 3-43. End plate (Blaw-Knox).

Page 3-35
AC 150/5370-14
Appendix 1 10/15/91

SCREED FRAME
SCREED DEPTH CRANKS

PRE - STRIKE OFF SHIELD

VIBRATORS-
EDGER PLATE

BEVEL EDGER

SCREED HEATERS

SCREED PLATE

CENTER CROWN STATION

CUT-OFF SHOE

Figure 3-44. Screed components (Blaw-Knox).

width of the extended screed (and ending approximately If a hydraulically extendable screed is to be employed
18 in. from the end plate) . The use of the auger exten- at variable widths with the width being paved changing
sions will enhance the distribution of the asphalt mix frequently, some paver manufacturers recommend that
across the width being paved and help keep a constant the machinery be equipped with kick out paddles or
head of material pushing on the whole width of the augers at the end of the main auger. This particular
screed. Further, auger tunnel extensions should also be device helps push the mix out to the end of the extend-
added to the paver. able screed and keeps the head of material in front of

SERIES

BARBER - GREENE
35-9004

Figure 3-45. Rear- mounted extendable screed (J. Scherocman) .

Page 3-36
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-46. Front- mounted extendable screed (J. Scherocman) .

TURN CW TURN CCW


TO RAISE TO LOWER

Clamping Hdwr .

No Adjustment is Necessary.
Factory Set.
Strike - Off

" Ext . Main

Ground Line

Set Strike - Off ¼ " (.6cm) Above Main Sceed .


Set Screed Extensions ¼ " ( .6cm ) Below Main Screed .

Figure 3-47. Angle of attack on extendable screed (Blaw-Knox).

the screed as constant as possible . Some pavers may be MIX PLACEMENT TECHNIQUES
equipped with augers that extend automatically as the When standing next to an asphalt paver, there are
screed is extended. For either of these procedures, the several key operating techniques that should be observed
material feed sensors should be mounted on the end to determine whether the paver is operating properly.
gate of the screed to assure that an adequate amount of Those items are:
material is delivered to the outside edge of the screed . If the mix is being delivered by a haul truck that

Page 3-37
AC 150/5370-14
Appendix 1 10/15/91

dumps mix directly into the paver hopper, the truck brought up to paving speed as quickly as feasible and
should stop short of the paver. The paver should be operated at a constant speed in proportion to the
moving forward when it comes in contact with the truck; amount of mix being delivered from the plant. This will
the paver should pick up the truck instead of the truck keep the head of material in front of the screed as
backing into the paver. This procedure will eliminate constant as possible.
indentations of the screed in the mix if the truck were to • The paver should not be operated at a slow speed
hit the paver. while the truck exchange is being completed . When the
• Before the tailgate on the haul truck is opened to paver continues to move forward while one truck is
deliver mix to the paver hopper, the truck bed should leaving and the second truck is moving into position, the
slowly be raised in the air until the mix in the truck bed amount of mix in the hopper will be drawn down, possi-
begins to slide against the tailgate. This procedure will bly to the point that the hopper is emptied. This proce-
allow the mix to flood the paver hopper when the tail- dure will cause the amount of mix at the augers to be
gate is opened and will reduce the amount of segrega- reduced, in turn also causing the screed to fall and the
tion that appears behind the screed . If the tailgate- thickness of the mat to decrease. The reduction in the
opening lever cannot be reached when the truck bed is speed of the paver, from normal paving speed to crawl
raised, it should be modified to allow for operation from speed between truckloads, will also change the forces
ground level when the bed is raised . acting on the screed, further altering the thickness ofthe
If a windrow elevator is used to gather mix from asphalt layer. In addition, when the newly delivered mix
a windrow on the roadway and deliver the mix to the is emptied into the hopper and is pulled back to the
paver hopper, the slat conveyor should pick up all of the augers by the slat conveyors, the large amount of mix
mix that is in the windrow without leaving any mix on (head of material) against the screed will cause the
the existing surface . screed to rise, increasing the thickness of the mat.
• The windrow should be sized so that the hopper Thus, slowing the paver between truckloads of mix while
on the paver is from 25 percent to 75 percent full . The emptying the hopper causes significant changes in the
paver hopper should contain enough mix so that the slat forces acting on the screed and accompanying changes
conveyors are not visible on the bottom of the hopper, in the thickness of the layer being constructed .
and the hopper should not be so full that mix runs out • The flow gates on each side of the machine on
the front of the hopper. the back of the paver hopper should be set at a height
• When a truck has completed delivery of mix and to permit the slat conveyor and corresponding auger to
pulls away from the paver, the paver should be stopped operate as close to 100 percent of the time as possible.
as quickly and smoothly as possible without jerking the The key to a smooth layer of mix is a constant head of
paver. Enough mix should remain in the paver hopper material in front of the screed . The key to a constant
to be at least at the level of the bottom of the flow head of material is a constant paver speed and continu-
gates. In no case should the hopper be emptied to the ous operation of the paver augers, with a good rule of
point that the slat conveyors at the bottom of the hop- thumb being that the amount of material in front of the
per are visible. The slat conveyors also should not be screed should be located near the center of the auger
visible when a windrow elevator or a material transfer shaft.
device is used to deliver mix to the paver hopper. • Ifthe paver is equipped with automatic flow-con-
When the paver is stopped to allow the next trol devices, the flow- control equipment should be set at
truckload of mix to move into position, the wings on the a location near the end plate in order to maintain a
paver can be folded, but only when necessary to prevent constant head of mix in front of the screed by causing
buildup of cold mix in the hopper corners. The wings the auger to run continuously. The location of the
should not repeatedly be banged as they are emptied . device is important to prevent too much or too little mix
The wings should be dumped into a relatively full paver from being carried at the outside edge of the screed .
hopper; the slat conveyors should not be visible at the • Ifthe paver screed is being operated under manu-
time the wings are emptied. Dumping the wings into a al control, the screed operator should not change the
relatively full hopper may result in some mix spilling out angle of attack of the screed by turning the thickness-
of the front of the hopper; rubber flaps should be used control cranks except to increase or decrease the thick-
to contain as much mix as possible. ness of layer being placed. After the controls are
Once the new truckload of mix has begun to be turned , it takes five times the length of the tow arm on
emptied into the half-full hopper, the paver should be the paver before the screed completes the input change

Page 3-38
AC 150/5370-14
10/15/91
Appendix 1

in thickness. If the paver is being operated under position, will simply correct any changes made in the
automatic grade and slope control, the screed operator angle of attack of the screed by changing the position of
should not attempt to change the angle of attack of the the tow point where the screed is attached to the tractor
screed by turning the thickness-control cranks . The in order to reestablish the original angle of the screed.
automatic controls, if they are mounted in the proper

Page 3-39
AC 150/5370-14
Appendix 1 10/15/91

SECTION FOUR
AUTOMATIC SCREED CONTROLS

INTRODUCTION the morning, no changes would ever need to be made to


The screed unit on the paver is attached to the the setting of the thickness-control handles.
tractor unit at only one point on each side of the paver: In the real world, however, the tractor unit operates
the pull or tow point. As the tractor follows the grade on a grade that is variable. As the elevation of the
of the existing pavement surface with the rubber tires or existing surface moves up and down, the wheelbase of
crawler tracks, the length of the wheelbase of the paver the tractor unit (either crawler or rubber tire) follows
becomes the reference for the screed. Because of the that grade. This vertical movement of the tractor as it
reaction time of the screed, as discussed in the previous moves forward causes the elevation of the tow or pull
section, the screed will react more slowly to changes in point on the tractor to change in direct relation to the
grade than will the tractor. Thus, under manual screed movement of the tractor unit. As the location of the
control, the screed will average out deviations in the tow point is altered by the movement of the tractor, the
roughness of the present pavement layer, placing more angle of attack of the screed is changed.
mix in the low spots and less mix over the high points in If the elevation of the pull point is raised, the screed
the underlying pavement . will be rotated upward at a ratio of 1 :8 compared with
Automatic screed controls are employed to keep the the change in elevation of the tow point. As the paver
elevation of the tow points on the paver at a more moves forward a distance equal to at least five times the
constant elevation relative to the reference being used. length of the leveling arm on the machine, the screed
Deviations in the pavement surface are averaged out will float up to the new elevation and the asphalt mat
over the length of the reference (either a preset string- will be thicker. If the tractor unit moves into a dip in
line or a long mobile ski) . As the tractor unit moves up the existing pavement surface, the elevation of the tow
and down over the existing grade, the elevation of the point will be lowered, reducing the angle of attack of the
tow point moves over a smaller range of elevations than screed. If no other changes are made in the forces
if the relatively short wheelbase of the tractor provided acting on the screed, the screed will move downward as
the reference . Keeping the elevation of the tow points the paver travels forward, lessening the thickness of the
constant permits the screed to maintain a more consis- layer being placed .
tent angle of attack. This provides for a smoother mat The self-leveling action of the screed takes place
behind the screed. continuously as the tractor unit travels over the roadway.
Many factors, however, affect the smoothness of the The reaction of the screed to the location of the tow
mix placed by the paver. The use of automatic screed point, the speed of the tractor, and the head of material
controls by themselves will not necessarily assure that in the auger chamber determine the thickness of the mat
the mat constructed will always be smooth. Proper being laid. This whole operation occurs without the
attention to the operation of the paver, as discussed in thickness-control cranks on the screed ever being
the previous section, is extremely important is obtaining changed . The floating screed principle permits the
a smooth-riding pavement layer. paver to reduce the thickness of the mix placed on high
If the paver always moved over a level grade, the points in the existing pavement surface and increase the
forces on the screed would be constant as long as the depth of the material deposited in the low spots on the
paver was moving at a constant speed. The towing force same surface .
on the screed would be stable and the head of material If the thickness-control cranks or handles are turned
in front of the screed would be consistent as long as the by the screed operator, the screed will react to the
feed-control system was set to operate as much of the change in setting (change its angle of attack) by rotating
time (close to 100 percent) as possible. Under these around the hinge or pivot point where it is attached to
conditions, a very smooth asphalt mat could be ob- the leveling arm and thus to the tow point of the screed .
tained from behind the paver without a screed operator As the paver moves forward , the screed will float up to
ever changing the setting of the thickness-control cranks or down to the new elevation. Similar to the change in
on the back of the screed. Indeed, once the angle of elevation of the tow point on the leveling arm, however,
attack of the screed is set when the paver starts up in the paver must travel forward a distance of at least five

Page 3-40
AC 150/5370-14
10/15/91
Appendix 1

lengths of the leveling arm before the change in the Finally, when it is desired to produce a constant
depth of the mat is fully realized . cross-slope across the width of the lane being paved,
On many projects, particularly those involving the automatic grade and slope devices can be employed to
resurfacing of an existing pavement, the screed operator control the elevation of the tow points of the screed on
is forced by the job specifications to maintain a certain both sides of the paver at the same time. This is very
yield of asphalt mix per square yard or per station. It is difficult to do manually, even with two very experienced
not uncommon to watch a screed operator continually screed operators. Grade control can be used on both
check the thickness of the mat being placed by the paver sides of the machine, or, more commonly, on one side
and then adjust the setting of the thickness-control of the paver, with slope control used on the other side.
cranks to increase or decrease the amount of mix being
placed . This change in the setting of the thickness- AUTOMATIC SCREED CONTROLS
control system is done without regard to the changes The primary purpose of automatic screed controls is
being made at the same time to the screed as the to produce a smoother asphalt pavement layer; smoother
elevation of the tow point changes while the tractor unit than the paver can accomplish by itself and smoother
moves forward over the variable grade. than a screed operator can accomplish by continually
Two inputs, then, are being introduced into the self- changing the setting of the thickness-control cranks.
leveling system at the same time. The first input the The automatic screed control functions by maintain-
vertical movement of the tow point of the screed, which ing the elevation of the screed tow points in relation to
reacts to changes in the movement of the wheelbase of a reference other than that of the wheelbase of the
the paver. The second input is the manual changing of paver itself. Figure 3-48 illustrates the automatic grade
the thickness-control cranks by the screed operator. The and slope control system for one particular make of
input from the movement of the tow point and the input paver.
from the change in setting of the thickness-control The elevation of the tow point is kept at a constant
device may be in the same direction as one another or elevation in relation to a given grade reference. The
they may be opposite to one another, even canceling automatic system does not permit the relative position
each other out. of the tow or pull point to change even though the
Under manual screed operation, the ability of the tractor unit is moving up and down vertically in response
screed operator to produce a consistently smooth asphalt to the roughness of the surface over which it is traveling.
layer is dependent on a number of factors. The first is Thus, by maintaining the tow point at a constant eleva-
the frequency at which the operator feels the need to tion, the angle of attack of the screed is also maintained
adjust the setting of the thickness-control cranks: The at a constant setting. This allows the screed to ride at
more the screed operator changes the angle of attack of a consistent angle, permitting the screed to do an even
the screed, the more uneven the resulting asphalt pave- better job of reducing the quantity of mix placed over
ment will be. The second factor is the roughness of the the high spots in the existing pavement surface and
existing pavement surface : The more the screed operator increasing the amount of mix laid in the low spots. The
tries to assist the self-leveling action of the screed, the principles of the automatic screed control system are
rougher the resulting pavement surface will be. shown in Figure 3-49.
The third factor is the need to meet a certain maxi- Before the automatic screed control is engaged, the
mum yield specification . It is usually not possible, screed should be nulled (angle of attack set in flat
particularly for thin courses, to produce a smooth pave- position) before paving starts and the proper angle of
ment layer and stay within a certain volume of material attack should be set for the screed.
usage at the same time. This is particularly true if a If automatic controls are being used on the paver,
minimum overlay thickness is specified at the same time the screed operator should not try to change the angle
as the yield criteria are to be met. This problem is of attack of the screed manually by turning the thick-
discussed later in this section. ness-control cranks. If this is done while the machine is
The fourth factor is related to the need of the screed moving, the automatic grade and slope controls will
operator to match the elevation of the longitudinal joint attempt to compensate for the manual input by changing
in the adjacent lane. As paving speeds have increased the elevation of the tow point. Manual input will be
because of greater plant production rates, it has become needed , however, if the tow point actuator has reached
more difficult manually to maintain the level of the new the limit of its travel--the tow point hydraulic ram is at
mat relative to the adjacent mat. its upper or lower limit. In this case the paver should be

Page 3-41
AC 150/5370-14
Appendix 1
10/15/91

HOW THE SYSTEM WORKS slope controller. slope automatically across the full
The grade control unit sensor Since the system is " nulled out" width of the screed ( % " [3.18
follows an erected stringline, or "zeroed in" before startup, the mm] in 24' [7.32 m] ) . Any deviation
mobile reference, adjacent mat or desired relationship is maintained from slope is sensed bythe
other suitable reference and by the hydraulic cylinder at the tow controller and the appropriate
controls the edge of the screed on point on the grade controller side. correction is made at the tow point.
the side of the paver on which it is As corrections are required to keep Like the grade controller, the slope
operating. The other side of the the screed on grade, the tow point control is a proportional unit. A
machine can be controlled manually is automatically adjusted to remote set dial allows the screed
through the thickness control compensate for variations. operator to change slope while the
screws, by another grade controller Once properly set, the slope machine is paving as required by
sensing to a reference or by a controller accurately maintains job specifications.

HYDRAULIC RAM

TOW POINT LEVELING ARM

HYDRAULIC RAM

H
.

TOW POINT TRANSVERSE BEAM

LEVELING ARM GRADE REFERENCE

GRADE CONTROLLER

SLOPE CONTROLLER

Figure 3-48. Automatic grade and slope control (Barber-Greene).

stopped and the tow arm reset at the centerpoint of its slope, it is necessary to run the grade sensor on one side
travel. The screed should be nulled, the proper angle of of the paver automatically and the slope sensor on the
attack input to the screed, and paving restarted again. other side of the paver manually. This process will
In addition, when a superelevated curve is being permit changes to be made in the amount of super-
paved that requires a change from the existing cross- elevation and provide the required degree of cross-slope.

Page 3-42
AC 150/5370-14
10/15/91
Appendix 1

laydown machine. When a grade reference is used in


Pull Point Rises
Screed Angle conjunction with a slope-control device, the grade sensor
Cylinder Extends to
Remains Unchanged Compensate is typically positioned on the centerline side of the
paver, with the slope controller determining the depth of
the mat on the outside edge of the pavement.

Erected Stringline
Adjusted Thickness
Theoretically, the use of an erected stringline, shown
in Figure 3-50, should allow for the smoothest possible
Travel asphalt mat behind the paver screed. This method of
Screed Angle
for Level Paving supplying an elevation input provides the most consistent
reference for the paver tow point. Thus, its principal
advantage is that a predetermined grade can be matched
very accurately if the controls are used properly.
Laser technology has been used successfully on a
number of paving projects. Additional care must be
exercised when using this equipment.
Travel Screed Angle Practically, however, the use of the erected stringline
Pull Point Drops
Remains Unchanged Cylinder Retracts has a number of drawbacks that may offset the theoreti-
to Compensate cal increase in smoothness obtained by its use. The
elevation of the erected stringline must be set by a

Adjusted Thickness

Travel

Figure 3-49. Principle of automatic screed control


(Cedarapids).

GRADE CONTROL
Types of Grade References
Grade sensors are used to monitor the elevation of
the existing pavement surface in a longitudinal direction .
There are three basic types of grade references that can
be employed to maintain the elevation of the screed tow
point: (a) the erected stringline, (b) the mobile refer-
ence, and (c) the joint matching shoe.
Each type of grade control can be used alone on
either side of the paver. Grade sensors can also be
employed on both sides of the paver at the same time.
This use ofthe references will average out the variations
in the grade of the existing pavement surface on both
sides of the lane being paved . The same type of grade
reference can be used on both sides of the machine or
a different type of grade reference can be mounted on
each side of the paver; a preset stringline on one side
and a mobile reference on the other side, for example.
Use of double grade references generally will not
produce a uniform cross-slope for the new asphalt layer
Figure 3-50. Erected stringline reference (Barber-
except if a preset stringline is used on both sides of the
Greene).

Page 3-43
AC 150/5370-14
Appendix 1 10/15/91

surveying crew. The accuracy of the elevation of the jects, an erected stringline is not used . For airport
line and resulting pavement smoothness is directly runway paving, however, the use of a stringline may be
dependent on the care taken in its erection . If the grade cost-effective in providing a smooth-riding pavement,
set by the surveyors is incorrect in any way, the paver proper lateral drainage, and the correct elevation of the
screed will duplicate that error in the pavement surface. overlay in relation to abutting pavement structures.
On horizontal curves, it is very difficult to use an erected
stringline to control the grade of the new pavement Mobile References
layer. The string cannot be set in a curve, and therefore Different paver manufacturers use different types of
a series of chords must be used around the radius of the mobile reference devices to extend the relative wheel-
curve. This, in turn, requires the positioning of a large base for the automatic screed-control system . The
number of support posts and rods, usually at 5-to-20 -ft operation of these reference systems, however, is essen-
intervals, around the curve . The surveying done to set tially the same. The purpose of the mobile reference is
the stringline must be accurate in order to prevent a to average the deviations in the existing pavement
misalignment of string and the setting of the wrong surface out over a distance that is greater than the
grade reference for the paver. wheelbase of the tractor unit itself.
The stringline must be very taut when it is set. One paver manufacturer offers two different versions
Typically, the string is supported at 25-ft intervals on of a mobile reference or ski. They both employ a
metal posts and rods. The string is anchored at one end semirigid tubular grade reference (pipe) that is 20, 30, or
of its length and then pulled tight and anchored at its 40 ft in length, as seen in Figure 3-51 . For one version,
other end. It is extremely important that the string be the pipe or tube rides directly on the existing pavement
stretched very taut, without any dips or sags in the line surface. A spring-loaded wire is stretched between the
between the support rods. If the string is not stretched quarter points of the ski, on top of the pipe . The grade
tightly, the sensor wand on the paver, which can run sensor that inputs the electrical signal to the paver tow
either on the top or below the stringline, will react to point rides on top of the wire. As the pipe moves up
the sags in the line and duplicate those sags in the new and down (and flexes) over the existing grade, the
pavement surface. Even when high-strength line (great- stretched wire on the ski is used to average out the
er than 100 lb tensile strength) is used, it is not always differences in elevation that occur under the mobile
possible to keep the line tight enough to prevent some reference .
small sags from occurring between the support posts. The second variation employs the same semi-rigid
Another disadvantage of the erected stringline is the tubular grade reference pipe with the spring-loaded wire,
fact that the haul trucks and all paving personnel must but it is equipped with numerous spring-loaded wheel
keep away from the line and not disturb it in any way. assemblies attached to the pipe at 2 1 /2-ft intervals .
Once the line is set at the proper elevation, it is imper- This version is similar to a floating beam.
ative that the line remain untouched both before and Another paver manufacturer provides a different type
after the paver sensor passes over the line. Any change of mobile reference, termed a floating beam. A series
in the elevation of the line caused by someone hitting of feet or shoes are attached to the bottom of the
the line or a truck backing into the line will result in a floating beam, as shown in Figure 3-52 . The purpose of
change in the input to the grade sensor and movement the shoes is to allow one or more of the feet to pass
of the pull point on the paver leveling arm. over a singular high or low point in the existing pave-
With a properly set and maintained stringline , the ment surface without altering the slope of the whole
mat placed by a paver equipped with automatic screed beam. The feet are spring loaded (see Figure 3-53) to
controls can be very smooth and at the correct elevation. allow them to be deflected by a large stone on the
This is primarily because of the extended length of the pavement surface, for example, without pushing the
reference being used compared to the more limited whole beam upward . The grade sensor usually rides
length of a mobile reference. Unless smoothness, or directly on the beam at its midpoint. As with the other
compliance with a predetermined grade reference, is an types of mobile references, this floating-beam system
extremely important criterion on a paving project, averages out the variation of the existing grade over a
however, it is questionable that the added price of 30- or 40-ft distance.
erecting and maintaining the stringline is cost -effective A third paver distributor also supplies a floating-
for the typical hot-mix asphalt highway-paving job. beam type of mobile reference system. The beam is
Thus, for the vast majority of the highway-paving pro- normally 30 or 40 ft in length. Instead of multiple feet

Page 3-44
AC 150/5370-14
10/15/91
Appendix 1

CR541

Cedaranids

Figure 3-51 . Tubular grade reference (Cedarapids).

spread out along the length of the beam, however, a Of the three types of mobile reference devices de-
series of shoes is placed at each end of the beam (Figure scribed above, the floating-beam type reference that uses
3-54). These shoes are allowed to rotate and can be multiple feet or shoes typically results in a smoother
individually displaced by isolated disruptions in the pavement compared with the mat placed with the rigid
existing pavement surface without changing the height of tubular grade-control device . The beam will typically
the whole beam. This allows the beam to average the provide a reference for the paver that will ignore
grade of that surface over the length of the reference isolated deviations in grade (a rock on the roadway) and
without being influenced by the presence of a single high provide a smoother layer behind the paver. Further, the
point or dip in that surface . As for the other mobile longer the grade reference used, within reason, the
reference systems, the grade sensor is located in the better the paver will average out variations in the
center of the length of the beam . elevation of the existing pavement surface . A mobile

BLAN-KNOK

Figure 3-52. Floating- beam grade reference (J. Scherocman) .

Page 3-45
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-53. Spring-loaded shoe on mobile grade reference (J. Scherocman) .

reference will not, however, assure that the mix being .


system senses the grade of the existing pavement surface .
placed will be at the proper elevation; the elevation is To the rear of the screed, riding on a series of spring-
controlled by the elevation of the underlying pavement loaded wheels, is another floating beam that is used to
surface. reference the grade of the newly placed asphalt mix. A
As shown in Figure 3-55, one paver manufacturer has set of intermediate bridge beams, which go up and over
produced a mobile reference ski that is 55 ft in length the screed , are used to join the two parts of the floating
from front to back. Part of the reference beam is beam together. The grade sensor rides on one of the
located in front of the paver screed . This is basically a intermediate bridge beams and transmits the average
floating-beam-type system, equipped with a series of grade of the front and back beam to the paver tow point
spring-loaded shoes. This portion of the reference to control its elevation. This device may not be practi-

G-260B

Figure 3-54. Different make of mobile grade reference (J. Scherocman).

Page 3-46
AC 150/5370-14
10/15/91
Appendix 1

179

ROSE

Figure 3-55. Over the screed mobile grade reference (J. Scherocman).

cal, however, in hilly terrain or on a pavement that Because of its short length, the joint matching shoe
has a great number of vertical curves. will not remove any major variations that occur in the
pavement surface. Indeed, the purpose of the shoe is to
Joint Matching Shoe duplicate the grade of the adjacent surface . This grade-
The third type of reference is the joint matching control device should be used with caution because
shoe, which is shown in Figure 3-56. This device con- pebbles, rocks, and other obstructions over which the
sists of a short (approximately 1 -ft-long) shoe or ski that shoe might ride will input grade changes into the screed
is used to reference the grade of an adjacent piece of tow point. When placing the second lane of a base
pavement or curb. This type of mobile reference is used course or a binder course layer, it may be better to use
only when the grade being sensed is relatively smooth. a longer mobile reference (a 30-ft-long ski) instead of
The shoe rotates around its own pivot point and supplies the joint matching shoe. The mobile reference will
an input signal to the paver tow point when the shoe or provide the input needed to construct a smoother
ski is displaced (see Figure 3-57) . The shoe should be pavement surface than will the joint matching shoe. For
checked to assure that it is free to rotate properly. the surface course layer, however, the joint matching
shoe may be used to assure that the elevation of the mix
on both sides of the longitudinal joint is the same,
although the use of a longer mobile reference is still
better paving practice.

Figure 3-56. Joint matching shoe grade reference Figure 3-57. Joint matching shoe (Barber-Greene).
(Blaw-Knox).

Page 3-47
AC 150/5370-14
Appendix 1 10/15/91

Location of the Grade Reference SLOPE CONTROL


Different paver manufacturers have different recom- In most cases, paving that is done with automatic
mendations for the placement of the grade reference- screed controls is accomplished with a combination of
control sensors. Occasionally the grade sensor will be grade control on one side of the paver and slope control
mounted adjacent to the tow point on the paver (Posi- to determine the grade on the other side of the ma-
tion 1 ), as seen in Figure 3-58. As also shown in this chine. The slope control operates through a slope
figure, the grade sensor is sometimes located at various sensor that is located on a cross-beam between the two
positions (Positions 2 and 3) on the leveling arm. This side arms of the screed . One side of the paver screed is
side-mounting position typically is recommended when controlled by the grade sensor. The other side of the
it is desired to correct long vertical deviations in the screed is controlled by the slope controller, as shown in
present pavement surface. When located on the leveling Figure 3-48.
arm, the reaction time to changes in grade is short and When slope control is used, the thickness of the mat
the angle of attack of the screed is altered quickly. On on the side of the machine (usually the outside edge of
some occasions, and particularly for wide-width paving, the roadway) that is controlled by the slope sensor could
the grade sensor is mounted near or on the paver screed be variable in depth, depending on the condition of the
(Position 4) . To function properly, the grade sensor existing pavement surface. The desired degree of cross-
must be located in front of the pivot or hinge point of slope, shown in Figure 3-59, is dialed in to the slope
the screed . controller, seen in Figure 3-60 . This cross-slope is then
The location of the grade sensor makes a difference regulated by a pendulum-type device that is part of the
in the reaction of the tow point and the screed to the slope -control system. Without regard to the grade of
.
grade being sensed . There is no set rule that can be the existing pavement, the slope controller maintains a
followed, however, as to the proper location to place the constant cross-slope regardless of the resulting thickness
grade sensor. It is recommended, therefore, that the of the asphalt layer placed. If there is a high point in
paver manufacturer's suggestions be followed for the the present pavement surface, the slope controller will
particular make and model of paver being used. If no place less material over that location . If there is a low
information is available about the suggested location for point in the existing pavement, the slope controller will
the sensor for a particular paving operation, it is recom- allow the screed to deposit more mix in that location.
mended that the sensor be hung on the leveling arm, at For a wide pavement, such as an airport runway, it is
a point between one-third and two-thirds of the length good practice to check the slope of the outside edge of
of the arm between the tow point and the screed. the mix being placed after two passes of the paver in the
The operation of the grade-control sensor should be longitudinal direction. If the slope is not set properly or
checked regularly. The sensor wand should be lifted the slope sensor setting is changed accidentally, it is
1/32 in. when the machine is stopped and the movement possible to compound the error in the slope setting all
of the tow point observed. Input to the sensor should the way across the pavement. This can result in a very
result in a corresponding movement of the tow point. thick or a very thin layer of mix on the edge of the
When the paver is moving, the up and down lights on runway, unless proper monitoring is completed regularly
the grade sensor should either blink occasionally or blink during the paving operation. Thus, the use of one or
constantly but change in intensity, both top and bottom , more stringlines across a wide pavement may be benefi-
to indicate that a signal is being sent to the tow point cial in providing the proper cross-slope .
actuator. If the grade sensor uses a meter instead of
lights, the reading on the meter should change when the YIELD , MINIMUM THICKNESS, AND SCREED
sensor wand is moved as well as when the paver is CONTROLS
placing mix on the roadway. In addition, the elevation The paving specifications for hot- mix asphalt overlay
of the tow point should change occasionally, depending projects are written in a variety of ways. In some cases,
on the amount of roughness of the existing pavement the specifications call for a minimum thickness of mix to
surface, in order for the angle of attack of the screed to be placed. For this type of requirement, in order for the
remain constant as the tractor unit follows the underly- minimum thickness specification to be met at all points
ing pavement grade. The change in elevation, however, in the pavement layer, it is usually necessary for the
should be smooth; the screed should not be moving up paver to place a mat thickness that is greater than the
and down rapidly and constantly. minimum depth required in the contract. The amount

Page 3-48
AC 150/5370-14
10/15/91
Appendix 1

BLAW-KNOX
PF-500 PAVER

4
CA

3
2

Choo

BLAW-KNOX BLAW- KNOX


PF 180H PAVER PF 100H PAVER

Figure 3-58. Mounting position for grade sensor (Blaw-Knox).

Page 3-49
AC 150/5370-14
Appendix 1 10/15/91

Inches Per Foot Inches Inches Inches Inches Inches Inches Inches Inches Inches Inches Inches
Percent Per Per Per Per Per Per
Slope Actual Approx. Per Per Per Per Per
Decimal Fraction 10' 11' 12' 13' 14' 15' 16' 17' 18' 19' 20'
0.10% .012 & 4/8 18 + + } 32 32
0.18% .015 A $ + À A 32 3z 14 4 +
0.20% .024 1/4 1/4 & 31 % % 32 18 30 35
0.26% .031 17 f 11 % 32 18 32 3/2 13 ጸ 12 %
0.80% .036 A 8/3 32 to 1/2 33 f 5% 31 11 32
0.40% .048 डी 3/6 17 ₤ 5% 32 H 18 /
% 32
0.50% .060 to 11 # 32 38 31 38 3 13 1 18 1
0.52% .062 to 5% 4 34 18 7/8 18 1 1 18 1 114
0.60% .072 & 32 H %
/ 18 1 1 132 12 1 1% 1

1128
0.78% .093 18 132 11/8 137 1% 132 11/2 132 111 139 1%
0.80% .096 $ 31 18 1 114 144 17 % 117 15% 132 118 132
112
112

1.0% .120 3/8 1 1 17% 18 178 112 139/20 2 2 2 211


1.5% .180 Å 178 14 23/ 211 211 21 2% 3TH 314 311 811
2% .240 1/4 27% 25 % 2% 38 3% 31319/20 337 432 4fo 4 438
8% .360 % 35 % 331/12/20 4fo 41 53 5H 54 618 614 631 71%
4% .480 H 41 53/2 54 614 611 7% 71* 8 8% 9% 912
5% .600 H 6 6313/12/20 71% 718 811 9 9/19/200 10 101 1132 12
6% .720 H 7 731 85% 938 102 1013 1111 1214 12 1311 144
7% .840 81 914 10,33 103/ 1134 12/31/1/1/20 131% 143/2 1518 1531 161
8% .960 # 9109/90 10f 1111 121/1/20 13178 142191 1538 16 17/2 1814 19
9% 1.08 1 1011 11 % 12 1432 15 % 16 17 / 188 19 2011/1 21H
10% 1.20 1 12 131 14332 1531/20 16 18 19f 2011 2131/9/20 2213 24
11% 1.32 1f 138 1411 1533 17/2 18192 1912 21 % 221 2334 25 261
12% 1.44 18 144 1531/12/2 17 1833 2032 211/ /
9 2332 2411 25392 2738 281

Inches Per Foot Inches Inches Inches Inches Inches Inches Inches
Percent Inches Inches Inches
Actual Approx. Per Per Per Per Per Per Per Per Per Per
Slope 21' 22' 23' 24' 25' 26' 27' 28' 29' 30'
Decimal Fraction
0.10% .012 A 1/4 1/4 ਹੰਝ ਲੰਨ f fo H H 38
0.13% .015 B + H H 3/8 3/8 H 18 TH H
0.20% .024 1/2 # f P H 5/8 H 18 11 #
0.26% .031 32 H ** 32 3/4 H 축구 7/8 12
0.30% .036 & 3/4 H 18 8 39983 12 H 1 14 1
0.40% .048 # 11 1 13 1ਨ 1YA 114 13/2 TH 112 17%
0.50% .060 to 114 1% 138 1 11/2 116 158 118 134 118
0.52% .062 + 1 18 17180 11/2 1 18 172 13/4 1a 1%
122

0.60% .072 & 11/2 14 1H 13 112 1% 112 22 2 2


0.78% .093 + 1吋 218 2ਲ 214 211 218 211 28 231 218
0.80% .096 + 23/12 218 2 2FF 243 212 219190 21 24 2%
1.0% .120 18 211 2% 234 2% 3 318 314 338 312 3%
1.5% .180 f 311 31/1 418 4f 412 411 48 512 57 543
2% 240 14 53% 5 511 534 6 614 613 63 6吋 7t
3% .360 3/8 71 % 718 8 85 % 9 938 933 10秒 10 1011
4% .480 1/2 10 10 11 1147 12 12/2 12 1318 1318 14
5% .600 H 121 13 / 1318 1432 15 15310/9/20 16 161 17121 18
6% .720 H 15 % 1537 16f 17 18 18332 19 2013/2 20 % 21H
7% .840 H 17 % 18 号 19f 20 / 21 213 2211 2311 248 25
8% .960 H 20 21 % 22 23 24 24곡초 2531 268 2711 2813
9% 1.08 14 221 2334 2431 2531 27 28 29 3014 31 3211
10% 1.20 1A 25 261 271 281 30 31f 321 3311 3418 36
11% 1.32 1 2711 29 30 % 31 33 34f 35 % 3631 383/9/2 3911
12% 1.44 17 3014 311 33 % 34 36 377 / 38 % 40 4134 43f

All figures shown in feet are measured horizontally.


All figures shown in inches are measured vertically and are accurate to within inch.

Figure 3-59. Slope conversion table (Cedarapids).

Page 3-50
AC 150/5370-14
10/15/91
Appendix 1

ness of 1 in.
The paver screed, left to operate without human
intervention on the thickness-control cranks and run
LEFT SIDE CHONY SIDE
either with or without automatic controls, will typically
SLOPE CONTROL
overyield mix. This means that the paver will require
more material than generally expected in order to react
to variations in the grade of the existing pavement and
SLOPE
to shave off the high spots and fill in the low spots in
that surface. In order to meet the yield requirement,
PERCENT SLOPE
therefore, it is usually necessary to reduce the thickness
of the mat being placed slightly in order to comply with
the yield requirement. An additional problem with a
CONTROL STATION yield-type specification is the longitudinal distance used
to determine the yield value. In some cases, yield is
1 MANUAL checked after every truckload of mix. This frequency of
JOG MONITOR
MONI checking often leads to continual changes in the thick-
AUTOMATIC ness-control cranks on the paver. Yield should only be
checked periodically: the tons of mix placed over a
distance of 1000 ft or more than an hour's duration of
paving.
The third type of specification is one that requires a
certain degree of smoothness for the finished pavement
surface. Many different smoothness specifications exist.
Figure 3-60 Slope-control device (Blaw-Knox). Most are related to the amount of deviation permitted
from a straightedge of a given length or to a certain
of extra thickness depends on the roughness of the maximum number of inches of roughness per unit of
existing pavement: The more uneven the pavement being length, typically a mile or some part of a mile . Although
paved, the greater will be the volume of mix needed to it is normally possible to meet such smoothness specifi-
assure compliance with the minimum thickness require- cations through the use of automatic screed controls, the
ment. ultimate success in making the requirements depends on
As an example of this type of specification, if the the amount of mix available to be placed, the condition
existing pavement is relatively uneven, and if a minimum of the existing pavement, and the number of layers of
asphalt concrete overlay thickness of 1 in. is required, mix to be laid. The amount of mix necessary to meet a
the paver thickness-control system would need to be set smoothness requirement will usually be greater than the
so as to place an average depth of uncompacted layer of amount needed to meet a given yield requirement.
asphalt concrete of approximately 1 1/2 in. This means The problem comes when it is desired to meet some
that the angle of attack of the screed would have to be specified yield requirement and to meet a minimum
positioned so that the average thickness placed would thickness or smoothness requirement at the same time.
assure that the minimum depth of mix was laid over all Because of the principle of the floating screed, it gener-
the high spots in the pavement surface. ally is not possible to accomplish both of the specifica-
The second type of specification calls for the place- tions at the same time on the same project, depending
ment of a given amount of mix, in terms of pounds of on the smoothness of the pavement being overlaid.
mix per square yard, over the pavement surface area. In Particularly for thin overlays, the paver is normally not
this case, the thickness requirement is an average depth, capable of meeting a minimum thickness and/or a
not a minimum depth. If the specifications for a project smoothness specification at the same time as a yield type
called for the placement of 110 lb of mix/yd² (approxi- requirement. The governing criteria (yield, minimum
mately 1 in. of compacted thickness for an asphalt thickness, or smoothness) should be determined at the
concrete mixture), the angle of attack of the paver time the job is designed and verified to the contractor
screed would not have to be set at as great an angle in before paving commences (during the preconstruction
order to place the mix an average depth of 1 in . (com- meeting) .
pacted) compared with a minimum specification thick-

Page 3-51
AC 150/5370-14
Appendix 1 10/15/91

AUTOMATIC SCREED-CONTROL OPERATING The grade sensor wand should ride easily over the
TECHNIQUES stringline and not be displaced in a vertical direction
When automatic screed controls are used on a paver when it passes over a support arm. Every effort should
to control the grade and/or the slope of the pavement be made to keep all personnel and equipment from
layer being constructed , there are several key operating coming in contact with the stringline and disturbing it,
techniques that should be observed to determine wheth- either longitudinally or vertically.
er the automatic controls are being used properly. • If a mobile reference is used for the grade con-
Those items are: trol, the sensor should ride on the reference at the
• The screed operator should not attempt to make midpoint of its length . This allows the input to the
manual changes in the angle of attack of the screed by paver to be made equally over the length of the mobile
turning the thickness-control cranks, because the auto- reference. If the mobile reference is equipped with
matic controls will attempt to change the elevation of multiple feet or shoes, each of the devices should be
the pull point to compensate for the manual input to the checked to assure that each is clean and free to move or
screed . rotate around its own hinge or spring point. The length
• The grade sensor should be checked to assure of the mobile reference should be as long as practical to
that it is working. If the wand (which rides on the provide for the greatest averaging out of variations in
stringline or mobile reference device) is raised 1/32 in., the elevation of the existing roadway surface .
there should be a corresponding movement of the • If a joint matching shoe is employed for grade
actuator at the tow point on the paver. If the wand is control, the shoe should be checked to assure that it is
raised (or lowered) and the actuator does not move, free to move or rotate around its own hinge or spring
either the system is not turned on or the sensitivity of point .
the sensor is set too wide--with too great a dead band or • If the automatic-control system includes grade
sensitivity setting. control on one side of the paver and slope control on
• When the sensor is set on the grade reference the other side of the paver, the cross-slope of the layer
and the paver is moving forward, the up and down lights placed should be checked regularly to assure that the
on the sensor should blink occasionally or the constantly proper cross-slope is being built in to the pavement layer
blinking lights should change intensity occasionally, both by the paver. This is particularly important on very wide
top and bottom, to indicate that a signal is being sent pavements, such as an airport runway.
from the sensor to the tow point cylinder. On grade • For most paving situations, the grade-control
sensors that use a meter, the meter should indicate a sensor should be hung on the leveling (tow) arm of the
change in reading as the paver travels down the road- paver, typically between one-third and two-thirds of the
way. Further, the movement of the tow point actuator way between the tow point and the screed . For some
should be smooth, without constant up and down paving jobs, the sensor can be placed just in front of the
movement. screed and but never behind the pivot point of the
• If a stringline is used as the grade reference, the screed. The sensor, except in conjunction with the use
linehould be very taut. There should not be any sags of a joint matching shoe, should generally not be located
in the line, particularly between the vertical support at the tow point.
locations. This can be checked by sighting down the line.

Page 3-52
AC 150/5370-14
10/15/91
Appendix 1

SECTION FIVE
JOINT CONSTRUCTION

INTRODUCTION joint by drawing down the mix in the paver hopper. In


During the construction of hot-mix asphalt pave- most instances, the hopper is emptied and the amount
ments, two types of joints are encountered . The first of mix carried on the augers is minimal. This process
type of joint is a transverse joint. This joint occurs reduces the head of material in front of the paver
whenever the paving operation is interrupted for a screed, causing the screed to fall, thereby decreasing the
period of time--from an hour or so to overnight. The thickness of the mat at the joint. It is a much better
second type of joint is the longitudinal joint. This kind practice to locate the transverse joint at the point where
of joint occurs when one lane of asphalt mix is con- the amount of material in front of the screed is normal
structed adjacent to a previously placed lane of mix. than it is to run the hopper and the auger chamber
The techniques for constructing each type of joint are empty and then construct the transverse joint at the
discussed in this section. point the paver runs out of mix.

TRANSVERSE JOINTS Butt Joints


End of Paving For a butt joint, a vertical face is constructed by hand
When the placement of the asphalt mix is to be methods across the width being paved . This operation
suspended for a period of time, it is necessary to con- consists of raking, shoveling, and then removing the mix
struct a transverse joint across the pavement being that is located downstream of the selected joint location,
placed. This is accomplished in one of several ways, as shown in Figure 3-61 . The asphalt mix that is in
depending primarily on whether traffic is to travel over place upstream of the joint is not touched in any man-
the asphalt mix between the time the paving is stopped ner. The mix that is removed from the downstream side
and it is started again. of the joint is then recycled or discarded.
If traffic is not going to pass over the end of the Compaction of the mix on the upstream side of the
paving, a vertical butt joint can be constructed . If traffic joint is accomplished in normal fashion. It is necessary,
will be permitted to travel over the transverse joint, a however, for the rollers to compact the mix immediately
tapered joint will be necessary. In either case, the adjacent to the joint. For this to be done properly,
operation of the paver is essentially the same. The runoff boards must be placed next to the joint. The
actual construction of the joint itself, however, is differ- thickness of the boards should be approximately equal
ent. to the compacted thickness of the layer being placed . In
It is very important that the paver be run in normal addition, the boards must be wide enough and long
fashion right up to the point at which the transverse enough to support the full length of a roller. The
joint is constructed . This means that
the head of material carried in front
of the screed should be as consistent
as possible at the location of the joint .
This requirement permits the forces
acting on the screed to be constant
and maintains the angle of attack for
the paver screed. The result of such
a paving operation is a uniform mat
thickness at the joint, the same thick-
ness as for the previously placed mix.
It is a common but incorrect prac-
tice, however, to empty out the paver
hopper whenever a transverse joint is
to be built. The paver operator nor-
mally anticipates the location of the Figure 3-61 . Construction of transverse butt joint (J. Scherocman).

Page 3-53
AC 150/5370-14
Appendix 1 10/15/91

HYSTCD

Figure 3-62. Constructing transverse butt joint with cutting wheel (J. Scherocman) .

compaction equipment passes over the mix at the joint upstream of the joint and a weak spot and bump in the
and onto the boards before the rolling direction is pavement structure. The use of runoff boards for the
reversed. This assures that the transverse joint receives rolling equipment is thus necessary to assure the correct
the same degree of densification as the rest of the mix construction of a butt-type transverse joint. This prob-
in the pavement layer. lem is eliminated by cutting the mix back to a point of
Runoff boards should be used; when they are not constant thickness and density, as illustrated in Figures
used, the front wheel of the compaction equipment is 3-62 and 3-63.
normally run up to the transverse joint, stopping just
short of the joint. The roller direction is then reversed Tapered Joints
and the rest of the mat is compacted . Occasionally, one If traffic is to be carried over the transverse joint, it
wheel or roll of the roller will be driven over the end of is necessary to build a tapered joint. For this type of
the course, over the vertical face of the joint. Passing joint, as for the butt joint, it is proper for the paver
the rollers over the edge of the transverse joint, without operator to keep the head of material in front of the
having any boards beyond the edge to support the paver screed as consistent as possible up to the point
weight of the rollers, will cause rounding of the edge of that the joint is to be built. This process assures that
the joint. The degree of rounding that will occur will the thickness of the mix being placed is uniform up to
depend on the number of times the roller runs off of the the joint. There is more opportunity for this to be done
joint and the thickness of the layer being constructed . in practice with tapered joint construction than with butt
This latter type of joint construction results in two joint construction because the mix left in the paver
problems. First, the rounding of the edge of the butt hopper can be used to build the taper.
joint prevents the construction of a proper vertical joint At the point of the transverse joint, the asphalt mix
when paving is restarted . Second, the amount of downstream of the joint is temporarily pushed aside,
compactive effort applied to the asphalt mix adjacent to away from the joint. A vertical edge is formed at the
the joint is typically not adequate . The lack of proper upstream face of the mix. If the tapered joint is to be
compaction results in a high air void content in the mix only temporary, treated paper or other similar material

Page 3-54
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-63. Constructing transverse butt joint by sawing (J. Scherocman).

is then placed downstream of the joint directly on the long and the width of the lane being paved. If the
existing pavement surface (Figures 3-64 and 3-65) . This length of the paper used is too short, the roller might
paper is used because the asphalt mix will not stick to it. tend to shove the mix, causing rounding of the joint at
The length of the paper is dependent on the thickness the upstream side of the paper.
of the course just placed but is typically about 3 or 4 ft Once the paper is in place, the asphalt mix is shov-

Figure 3-64. Placing treated paper for tapered joint (J. Scherocman).

Page 3-55
AC 150/5370-14
Appendix 1
10/15/91

Paper Rolled Mat

a.

remove

paper
& ramp

New Mat Rolled Mat

b.

Figure 3-65. Paper transfer joint (NAPA).

eled back over the paper and a ramp is formed in this way to form the transverse joint is to use a board that is
mix with a lute or rake. Any asphalt mix that is not the same thickness as the compacted pavement layer.
used to construct the ramp or taper is discarded . If the The paver passes over the joint location and the mix is
joint is to be left in place permanently, the taper is
constructed in the same manner except that the treated
paper is not used.
Instead of treated paper, sand or dirt from the edge
of the roadway is sometimes spread on the road surface,
as shown in Figure 3-66. This is not good practice.
Although the sand or dirt does prevent the asphalt
material in the taper from sticking to the underlying
pavement surface, it is also very difficult to remove the
sand or dirt completely from the surface once the mix in
the taper has been removed . Typically some of the
bond-breaking material remains on the existing surface
even after that surface has been swept with a hand
broom. This dirty surface will provide a slip plane for
the new asphalt mix, and a shoving failure can occur at
that point when the new pavement is subjected to traffic.
This is true even if a tack coat is applied on top of the
dirty surface to "improve" the bond of the new mix to
the existing pavement. Indeed , in many cases an extra
amount of tack coat material is applied near the joint to
compensate for the dirt at that location. The extra tack
coat material, particularly if it is not cured before the
new mix is placed on it, can increase the chances for
slippage to occur at that point. Constructing a tempo-
rary tapered transverse joint using sand or dirt as the
bond-breaking medium is not an acceptable paving
practice. Figure 3-66. Placing sand for tapered joint (J. Scher-
As shown in Figures 3-67 and 3-68, an alternative ocman).

Page 3-56
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-67. Transverse joint with boards (J. Scherocman).

shoveled away from the joint. A vertical face is formed and down the taper. To prevent dislodgement of the
in the upstream side of the joint, but the mix adjacent to board by traffic, the board must be the same thickness
the joint on that side is not disturbed . Once the vertical as the layer being constructed and must be straight and
face is formed, the board is set in place, immediately not bowed upward where the wheels of the vehicle can
downstream of the vertical face and against it. The mix hit it and jar it loose. In practice, this type of transverse
that had been removed from the joint is then shoveled joint is rarely constructed because of movement of the
back against the board and a taper formed from the boards under traffic.
edge of the board to the existing pavement surface. A third type of tapered joint is the nonformed , sawed
Traffic runs over the edge of the joint, over the board, joint. For this type of joint, the paver operator keeps

Ramp Lumber Rolled Mat

a.

remove
A
lumber
& ramp

New Mat Rolled Mat

b.

Figure 3-68. Use of boards for transverse joints (NAPA) .

Page 3-57
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-69. Tapered joint completed by running out of mix in paver hopper (J. Scherocman).

the paver operating normally until there is no more mix wasted. Figure 3-70 illustrates the compaction of such
in the hopper or in the auger chamber (Figure 3-69) . a tapered transverse joint.
At the point where the mix becomes nonuniform across One advantage of the tapered joint is the fact that
the width of the lane being paved, a ramp is constructed the compaction equipment can run over the edge of the
with the "left-over" mix. No vertical face is formed, and transverse joint and down the ramp without rounding
the mix is merely tapered from the proper layer thick- the joint. Because the rollers can pass over the end of
ness to the level of the adjacent existing pavement. Any the mat easily, the compaction of the mix upstream of
mix not needed to make the ramp is removed and the joint is usually superior to the mix adjacent to the

Figure 3-70. Compacting tapered joint (J. Scherocman).

Page 3-58
AC 150/5370-14
10/15/91
Appendix 1

butt-type joint. A second advantage is that there the taper. This can be very difficult to do , depending on
generally is less mix to shovel from the joint, because the amount of traffic that has passed over the transverse
some of the extra mix is used to make the ramp or joint and the environmental conditions at the site. Once
taper. The disadvantage of this kind of joint is that this the mix has been removed, the board is then removed ,
mix must eventually be removed before paving com- exposing the vertical face of the joint .
mences downstream of the transverse joint. If a nonformed tapered transverse joint is used, it is
necessary first to saw a transverse joint in the asphalt
Handmade Joints mat. The advantage of this type of joint is that the saw
In areas where the new hot-mix asphalt layer abuts cut can be made at any longitudinal point in the asphalt
an existing structure, such as a bridge deck, it is often layer (Figure 3-63) . It can be placed far enough back
necessary to place the mix adjacent to the joint by hand. from the taper to assure that the thickness of the layer
The mix that is needed to complete the joint is deposit- is constant. Once the joint is cut completely through the
ed in the area to be paved either by the paver or by asphalt mat, a front-end loader is used to pry up the mix
being dumped from a haul truck. In order to avoid that is downstream of the saw cut. As with the tapered
overworking the mix and possibly causing segregation, joint that uses the board, one disadvantage of this type
the mix should be placed as close as feasible to its final ofjoint is that it is often very difficult to remove the mix
location. The mix is then spread by hand methods, downstream of the saw cut from the existing roadway.
normally using rakes or lutes. As an alternative, a cold-milling machine can be used
In addition, the mix must be "left high" in order to both to form the vertical edge of the transverse joint and
allow for the compression of the material by the com- to remove the mix in the taper.
paction equipment. Because the mix is being placed by A straightedge should be used to determine the
hand, it will not be as dense as it would be if it were laid condition of the transverse joint before paving begins.
by the paver. Thus the 1/4 in./1 in. rule of thumb If the mix upstream of the joint is level, the location of
usually used will not be valid for hand-spread mix. To the transverse joint is fine. If the straightedge indicates
permit proper compaction of the mix and have the mix that the previously placed mix is not level, the location
end up at the proper elevation to match the adjacent of the transverse joint should be moved to a point where
structure, the level of the mix should be approximately the proper thickness and smoothness of the pavement
3/8 in. higher than the surrounding pavement for each 1 layer exists. The mix downstream of the new joint
in . of compacted layer thickness. location should be removed and recycled.
The hand work area must be rolled by the compac-
tion equipment as soon as possible after the mix is in Use of Starting Blocks
the proper location. Because of the time necessary to The asphalt mix that passes out the back of the paver
place the mix, rolling will be delayed and the mix will be screed still must be compacted . As a rule of thumb, an
cooling during the placement process. In order to asphalt concrete is expected to densify approximately 20
achieve the required density, extra rolling may be percent under the action of the compaction equipment.
needed. This means that the mix must be placed about 1 1/4 in.
thick in order to produce a compacted mix that is 1 in.
Start of Paving thick. This rule must be applied when the paver is used
Removal ofthe Taper to place mix at a transverse joint.
If a tapered joint has been constructed at the trans- If the layer being placed is to be 2 in. thick, the mix
verse joint, the mix in the ramp or taper must be passing out from under the screed should be approxi-
removed before the paving can be started . For a taper mately 2 1/2 in. in depth to allow for compaction. It is
built with treated paper, there is no bond between the therefore improper and very poor practice to set the
mix in the ramp and the underlying pavement. The paver screed directly on the old mat upstream of the
paper and mix are readily removed and returned for transverse joint and start the placement of the new mix
recycling. A vertical face is left at the upstream edge of by dragging the screed off of the previously placed
the joint. material. If this is done, not enough mix will be placed
For a taper constructed with the board and a ramp on the downstream side of the joint, and a dip in the
of asphalt mix, the material downstream of the board compacted pavement surface will result. Proper paving
will be partially bonded to the existing pavement surface. practice requires that the paver screed be placed on a
A front-end loader typically is used to pry up the mix in set of starting blocks on the upstream side of the

Page 3-59
AC 150/5370-14
Appendix 1 10/15/91

transverse joint. The thickness of the blocks, or strips of additional blocks placed under each extension .
wood, should allow the additional thickness of the layer If the paver is starting out at a new location where
to be placed, which will be compacted to the required there is no old mat on which to set the starting blocks
asphalt thickness. and screed, the thickness of the starting blocks must be
The starting blocks should be placed completely increased to compensate for the lack of mix on the
under the length of the screed, front to back, as illustrat- upstream side of the joint (Figure 3-73) . In this case, if
ed in Figures 3-71 and 3-72. At least three strips of a 2-in. (compacted) layer of mix is being constructed, the
wood should be used for a standard screed up to 16 ft blocks should be about 2 1/2 in. thick in order to allow
for the compaction of the mix by the rollers. For a
3-in.-thick compacted mat, the depth of the starting
wood strips should be approximately 3 3/4 in.

Nulling the Screed and Setting the Angle of Attack


Once the paver screed has been set on starting blocks
of the proper thickness, the screed should be nulled.
This means that the angle of attack of the screed should
be set in the neutral or flat position. The thickness-
control cranks should be able to be turned slightly in
Figure 3-71 . Starting blocks under paver screed at
both directions when the screed is in the nulled position
transverse joint on asphalt overlay (schematic) (Blaw-
without any pressure being put on the screed and
Knox).
without the angle of attack of the screed being altered.
An angle of attack should then be set into the screed .
wide equipped with rigid extensions. If the width of the This is accomplished by turning the thickness-control
screed with rigid extensions is greater than 16 ft, at least cranks approximately one full turn (depending on the
four blocks should be placed under the screed . For a make of the paver) and introducing an up angle to the
screed equipped with hydraulic extensions, at least three front of the screed . Both thickness-control cranks or
blocks should be set under the main screed and two handles (one on each side of the machine) must be

Figure 3-72. Starting blocks under paver screed at transverse joint on asphalt overlay (J. Scherocman).

Page 3-60
AC 150/5370-14
10/15/91
Appendix 1

This will provide the proper head of material


against the screed. Once the auger chamber
is properly filled, the paver is started , the
screed is pulled off of the starting blocks
(Figure 3-74), and the paver is brought up to
the desired laydown speed as quickly as feasi-
ble. The angle of attack of the screed is
adjusted, as needed, as the paver moves down
the roadway, in order to provide the proper
thickness of the asphalt mat. If the paver
screed is nulled and the angle of attack set
correctly while the screed is on the starting
blocks, the amount of adjustment necessary to
the screed should be minimal .

Raking the Joint


If the transverse joint is constructed prop-
erly up to this point, the amount of raking that
needs to be done also is minimal, as shown in
Figure 3-75. If the paver screed starts out on
blocks and if the head of material against the
screed is constant, the thickness of the mat
downstream of the joint will be correct. Very
Figure 3-73. Use of starting blocks on new construction (J. little mix, if any, will need to be brushed back
Scherocman). from the joint. There is never any reason to
rake a transverse joint excessively (Figure
adjusted in order for the screed to be set properly. 3-76).
Before the paver pulls off of the starting blocks, the When a joint is raked, there is a tendency for the
material feed system on the machine is activated and raker to reduce the thickness of the new, uncompacted
mix is deposited in the auger chamber in front of the mat to match the elevation of the compacted pavement
screed. The amount of mix delivered should be enough on the upstream side of the transverse joint. This is
to cover the augers up to the center of the auger shaft. accomplished by pushing the mix at the joint down-

INSUFFICIENT MATERIAL

TOO MUCH MATERIAL

Figure 3-74. Head of material of transverse joint (Blaw-Knox) .

Page 3-61
AC 150/5370-14
Appendix 1
10/15/91

Figure 3-75. Proper raking of transverse joint (J. Scherocman) .

stream farther onto the new mat. When the level of the is smooth by running a straightedge across the joint, as
new, uncompacted mat is the same as the old, compact- seen in Figure 3-77. The straightedge should rest on the
ed mat, the final elevation of the newly placed material, uncompacted mat and extend over the already compact-
after compaction by the rollers, will be lower than the ed mix. The distance between the bottom of the
mix on the upstream side of the joint. Thus, only straightedge and the top of the compacted mat should
minimal raking should be done. be equal to the amount of rolldown that will occur
Before the material on the downstream side of the during the compaction process, approximately 1/4 in./in.
joint is compacted, it should be determined if the joint of compacted mat thickness. The straightedge should be

Figure 3-76. Excessive raking (J. Scherocman) .

Page 3-62
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-77. Checking transverse joint elevation (J. Scherocman) .

used again to check the level of the joint once the width of the joint receives equal compactive effort. This
compaction process has been completed. is very difficult to accomplish unless the wood boards
placed on each side of the lane are long enough to allow
Compacting the Joint the roller to move completely off the mix on both sides
As shown in Figure 3-78, ideally, a transverse joint of the pavement .
should be compacted transversely. This means that the If the roller cannot compact the joint in the trans-
equipment that is used to roll the joint should operate verse direction because of site restrictions (adjacent
across the width of the lane instead of longitudinally guardrail or steep side slope, for example) or traffic in
down the mat. If the rolling is done transversely, wood the next lane, the transverse joint will have to be rolled
boards must be used to support the roller as it moves in the longitudinal direction (Figure 3-79) , similar to
beyond the longitudinal edge of the pavement . The rolling of the mix at other locations. The initial (break-
roller should operate in a manner so that the whole down) rolling should be accomplished, however, as

DYNAPAC
apac

4.530
394 530
apac

Figure 3-78. Compacting transverse joint (J. Scherocman).

Page 3-63
AC 150/5370-14
Appendix 1 10/15/91

DYNAPAC apac apac

Figure 3-79. Compacting transverse joint in longitudinal direction (J. Scherocman).

quickly as possible after the paver has moved off of the however, can typically be obtained without cutting back
joint. The roller should pass slowly and completely over the longitudinal joint: by properly overlapping, raking,
the joint before the machine is reversed . If the joint has and compacting the joint. If the joint is not cut back
been constructed properly, the compaction process is no and the mix along the joint is clean, a tack coat is not
different from the application of ordinary compactive normally needed .
effort on any other part of the asphalt mixture.
Overlapping the Joint
LONGITUDINAL JOINTS The key to the construction of a good longitudinal
Cutting Back the Joint joint between lanes of asphalt mix is the amount of
In some cases, before the longitudinal joint between overlap between the new mat and the previously placed
two adjacent lanes of pavement is constructed, the mat . The end gate on the paver should extend over the
longitudinal edge of the previously placed mix is cut top surface of the adjacent mix a distance of not more
back for a distance of 1 to 2 in. This is accomplished than 1 to 1 1/2 in., as shown in Figure 3-80. This
with a saw or with a cutting wheel attached to a grader amount of overlap provides just enough material on top
or front-end loader. The purpose of this operation is to of the joint to allow for proper compaction without
remove that portion of the mix at the longitudinal joint having extra mix, which must be pushed back from the
that may have a lower density than the main portion of joint by a raker. The height of the new mix above the
the mat because of the lack of confinement of the mix compacted mix should be 1/4 in. for each 1 in. of
during the compaction process. If this is done, a tack compacted mix.
coat should be placed on the newly exposed face of the One major problem with longitudinal joint construc-
longitudinal joint. tion is an excessive amount of overlap of the paver
Further, a vertical face is formed at the longitudinal screed over the previously placed mat . (This may be
joint instead of the normal inclined face (typically about caused, in part, by a ragged or wavy longitudinal edge
a 60-degree angle) . This generally permits an increase on the first paver pass. Use of a string to guide the
in density to be obtained in the newly placed mat paver operator as the first lane is placed will usually
adjacent to the cut joint. Adequate joint density, reduce this problem greatly.) Because this extra asphalt

Page 3-64
AC 150/5370-14
10/15/91
Appendix 1

the new lane. The excess mix should be picked up and


recycled, as shown in Figures 3-81 and 3-82.
Poor longitudinal joint construction is often related
to " over-raking" the joint. Instead of any excess mix
being pulled away from the joint, most often the extra
material is brushed back onto the new mix, as shown in
Figure 3-83. During the raking process, there is a
tendency for too much material to be pushed off of the
joint, leaving the level of the mix adjacent to the longitu-
dinal joint at the same elevation on both sides of that
joint. In some cases, so much mix is raked off the joint
that a dip occurs at the longitudinal joint even before
compaction of the mix is done. When either of these
two problems occurs, it becomes impossible to obtain
the required density at the joint.
Mix that is pushed off the longitudinal joint is
deposited on the new asphalt mat. This material
changes the surface texture of a portion of the mat
where the mix is deposited . Depending on the gradation
of the mix being placed, the extra mix raked onto the
new mat can make a significant difference in the texture
of the mat from one side of the lane to the other.
Excessive raking of the longitudinal joint is detrimental
to the long-term performance of that joint.
Excellent longitudinal joints can be constructed
without raking the joint at all. If the proper amount of
overlap of the new mix on the previously placed mat has
been done, raking of the longitudinal joint can be
eliminated, as shown in Figure 3-84. It is recommended
Figure 3-80. Overlap of new mix at longitudinal joint that raking of this joint be deleted if proper overlap and
(J. Scherocman). compaction can be obtained .

mix cannot be pushed into the compacted mat, the Compacting the Longitudinal Joint
material is raked or luted onto the new mat. If the If the level of the new, uncompacted mix is even with
longitudinal edge of the first lane is straight and if the or below the level of the compacted mix in the adjacent
correct amount of overlap is used, the amount of raking lane, the compaction equipment will not be able to
that must be done will be minimal. densify the mix along the joint properly. Whether the
first pass of the roller is on the cold side of the joint or
Raking the Joint on the hot side of the joint (Figure 3-85) , part of the
If the amount of overlap of the new mix on the old weight of the roller will be supported on the previously
lane is 1 to 1 1/2 in., any raking that is done should be compacted mat. This means that the compaction
used merely to "bump" the joint, pushing the mix off of equipment will bridge the mix in the joint, leaving it
the old lane and onto the new mat directly over the essentially uncompacted or only partially compacted.
joint, as shown in Figure 3-81 . This will leave the mix a (Use of an intermediate pneumatic tire roller instead of
little high at the joint and will create a slight amount of a steel wheel roller--static or vibratory--will reduce this
extra mix to be compacted by the roller. If the adjacent problem.) Thus, the level of the mix at the longitudinal
lane is overlapped too far and too much mix is deposited joint must be above the elevation of the compacted mix,
on the old mat, the excess material should be pulled by an amount equal to approximately 1/4 in. for each 1
away from the new mat instead of being pushed onto in. of compacted pavement, if proper compaction of the
the new mix. The mix should not be broadcast across mix at the joint is to be accomplished .

Page 3-65
AC 150/5370-14
Appendix 1 10/15/91

25-50 MILLIMETERS 14T


(1-2 INCHES)

UNROLLED MAT ROLLED MAT

EZEZNEMENTENENES
(a) OVERLAP OF ADJOINING LANE.

-BUMPED MATERIAL

UNROLLED MAT ROLLED MAT

(b) OVERLAP CROWDED BACK READY TO BE ROLLED.

SQUARE- ENDED
SHOVEL

UNROLLED MAT ROLLED MAT

NENENEENENESI
(c) MAKING A TRIMMED JOINT.

Figure 3-81 . Constructing longitudinal joints (NAPA) .

Rolling from the Hot Side


The most efficient way to compact the longitudinal
joint is to put the roller on the hot mat and overlap the
joint by a distance of approximately 6 in. over the cold
mat, as shown in Figure 3-86. This places the majority
Figure 3-83 . Excess raking of longitudinal joint (J.
of the weight of the compaction equipment where it is Scherocman).
needed . The mix at the joint is still pushed into the
joint area by the roller as long as the elevation of the
new mix at the joint is proper. The longitudinal joint

Figure 3-82. Removing excess mix from longitudinal joint .

Page 3-66
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-84. Longitudinal joint not raked (J. Scherocman).

can be compacted effectively by keeping the roller on to any significant degree. If the mix design is proper,
the new mix instead of on the already compacted mix. this method of compacting the joint does not provide
Any type of roller used for the breakdown rolling of the any advantage over moving the first pass of the roller
mix can be employed to compact the longitudinal joint outward 1 ft (from 6 in. inside the joint to 6 in. outside
as long as the elevation of the mix at the joint is above the joint) .Rolling the mat by lapping the roller over
the level of the cold mat and the mix is still hot. the adjacent old pavement typically is the more efficient
Sometimes the first pass of the roller is completed way to provide roller coverage for the whole pavement
with the edge of the machine about 6 in. inside of the width.
longitudinal joint. The theory behind this method of
compaction is that the mix will be shoved toward the Rolling from the Cold Side
joint by the roller, and better compaction will be ob- It has been common practice in the past to do the
tained. If the mix being placed is stable enough, the initial rolling of the longitudinal joint from the cold
roller should not be able to move the material laterally (previously placed mat) side of the joint, as seen in
Figure 3-87. The major portion of the weight of the
COLD roller was supported by the cold, compacted mat . Only
TANDEM HOT
VIBRATORY 6 in. or so of the width of the roller hung over the fresh
mat, compressing the mix along the joint. The majority
of the compactive effort was wasted because the roller
essentially was applying its compactive effort to an
N already-compacted asphalt material.
TI
During the time that the roller was operating on the
cold side of the longitudinal joint, the mix on the hot
side of the joint, and the rest of the mix in the course
COLD
SINGLE being laid, was cooling. Depending on the environmen-
HOT DRUM
tal conditions and the thickness of the mix being placed,
VIBRATORY
the process of compacting the joint from the cold side

Figure 3-85. Compacting longitudinal joint (Dynapac). often proves to be detrimental to the ability to obtain

Page 3-67
AC 150/5370-14
Appendix 1 10/15/91

R66
DYNAPAC
McDONALD
INDUSTRIES

HYSTET

Figure 3-86. Compacting longitudinal joint from hot Figure 3-87. Compacting longitudinal joint from cold
side (J. Scherocman). side (J. Scherocman) .

density on the whole pavement layer. is essentially similar to the building of a joint against a
The reason often given for rolling the joint from the cold, compacted pavement layer. In this case, however,
cold side of the joint was that this compaction method the amount of overlap between the first and second
allowed the rollers to " pinch" the joint and obtain a lanes is very important. The distance that the screed
higher degree of density. There is no evidence that this and end gate of the trailing paver should extend over
is true. Indeed, regardless of the method used to the uncompacted mat behind the first paver should be
compact the longitudinal joint, the level of density limited to no more than 1 in. The end gate of the
obtained at that location is typically 1 to 2 percent below second paver must be set at the same level as the
the average density that can be produced in the main bottom of the screed plate of the first paver. This will
part of the mat. This is primarily because of the fact prevent the end gate of the screed of the second paver
that the first placed lane has an unsupported edge that from dragging on the mix placed by the first or leading
is always more difficult to compact. It is the lack of paver.
density in this original part of the longitudinal joint that No raking of the joint need be accomplished . The
affects the level of density that can be obtained when compaction process is modified to require the rollers
the new mix is placed along the joint. densifying the mix behind the lead paver to stay about
6 in. away from the free edge of the mat on the side
Echelon Paving toward the second paver. Once the mix from the second
If echelon paving (two pavers running next to each or trailing paver is placed against the uncompacted edge
other) is used, the construction of the longitudinal joint of the mix from the first paver, the rollers compacting

Page 3-68
AC 150/5370-14
10/15/91
Appendix 1

the second lane are employed to densify the mix on both paver is starting to pave at a new location, the thickness
sides of the joint. Properly lapped and properly com- of the starting blocks should be the thickness of the
pacted, it is usually difficult to see the longitudinal joint compacted new layer plus 1/4 in./in . of compacted
produced by the echelon paving process. In addition, thickness. It is impossible to construct a proper trans-
use of this technique will normally result in the density verse joint if the blocks are not used to bring the screed
ofthe longitudinal joint being equal to the density of the to the proper elevation on the cold side of the joint
adjacent mat. before paving is started .
• The mix on the downstream side of the transverse
JOINT CONSTRUCTION OPERATING TECHNIQUES joint must be higher than the mix on the compacted side
Several key techniques should be observed when of the joint. This is necessary to allow for adequate
viewing the construction of both transverse and longitu- compaction of the freshly placed mix.
dinal joints in an asphalt pavement. They are: • Minimal raking needs to be done at a properly
• If a transverse butt joint is to be built, the paver constructed transverse joint. The rakers should never be
operator should maintain a constant head of material in allowed to disturb the paver-placed mix at the joint
front of the screed to a point downstream of the loca- except to clear away any new mix that has been dribbled
tion where the joint is to be made. In order to prevent or overlapped onto the upstream or previously compact-
a decrease in the layer thickness upstream of the ed side of the joint.
transverse joint, the operator should not be allowed to • Ideally, the transverse joint should be compacted
run the hopper, slat conveyors , and augers empty of mix in a transverse direction with the rollers. On a practical
before the joint location is reached. basis, the transverse joint can be compacted properly
• For the construction of a transverse butt joint, with the roller running in a longitudinal direction as long
either treated paper or a wooden board should be used as the initial elevation of the new mix is above that of
just downstream of the actual butt joint location. the old mix on the cold side of the joint.
Provision must be made to compact the mix adjacent to • During the construction of a longitudinal joint,
the butt joint to the same degree as the previously the end plate or end gate of the paver should overlap
placed mix. the previously placed lane by no more than 1 1/2 in.
⚫ For the construction of a tapered transverse joint, Any increase in the amount of overlap beyond this
the thickness of the layer should be maintained to a distance will provide excess material that will need to be
point downstream of the location where the vertical face raked off of the joint . The thickness of the new mix
of the joint will eventually be constructed . Treated should be 1/4 in./in . higher than the compacted mix.
paper, not sand or dirt, should be used as a bond- • Minimal or no raking of the longitudinal joint
breaker material under the taper. should be necessary if the amount of overlay of the
• When paving is restarted, the asphalt mix down- paver screed on the adjacent lane is 1 1/2 in . or less. If
stream of the transverse joint should be removed and raking is done, the raker should not broadcast the mix
recycled . A vertical face should be present at the across the newly placed mix. The excess material should
selected joint location. A tack coat should be applied to only be pushed 1 in. or 2 toward the longitudinal joint
the existing pavement surface adjacent to the joint location and be deposited just on the uncompacted side
location. of the joint.
• The screed of the paver must be set on "starting • Compaction of the longitudinal joint should be
blocks" on the cold side of the transverse joint. The accomplished by rolling from the hot side of the layer
thickness of the starting blocks should be 1/4 in. for each with the roller wheels lapping approximately 6 in. over
1 in. of compacted layer thickness when the blocks and on the cold mat.
paver screed are set on another pavement layer. If the

Page 3-69
AC 150/5370-14
Appendix 1 10/15/91

SECTION SIX
COMPACTION

INTRODUCTION voidless condition) . The maximum theoretical density of


Compaction is the single most important factor that a mix can be calculated from the percentages and the
affects the ultimate performance of a hot-mix asphalt specific gravities of each component in the mix. It can
pavement. Adequate compaction of the mix increases also be determined from a laboratory test (the Rice
the fatigue life, decreases permanent deformation procedure, ASTM Test Method D 2041 ) , which is the
(rutting) , reduces oxidation or aging, decreases moisture recommended procedure .
damage, increases strength and stability, and decreases Because it is impossible on the roadway to compact
low-temperature cracking. An asphalt mixture that has a well-designed mix to a level of a voidless condition, all
all the desirable mix design characteristics will perform asphalt mixes will contain some void spaces or air voids
poorly under traffic if that mix is not compacted to the when the compaction process is completed by the rollers.
proper density level. A properly compacted mix with The air void content of the mix is simply the volume of
marginal properties will often outperform a mix with the space between the asphalt-coated particles. Because
desirable properties if that mix that is inadequately the volume of those air voids is impossible to measure
compacted. directly, a ratio of actual unit weight to the theoretical
maximum density is used . The air void content is ex-
DEFINITIONS pressed as the ratio of the difference between the maxi-
The terms density and compaction are often used mum theoretical density and the actual density of the
interchangeably to describe the process of compressing mix, as shown by the formula percent air voids = 100[ 1-
asphalt mix and increasing its unit weight. The two (bulk specific gravity/maximum theoretical specific
terms, however, have different definitions. gravity) ] and in ASTM Test Method D 3203. Thus, if
The density of a material is simply the weight of the the compacted density of an asphalt concrete mix is
material that occupies a certain volume of space . For 147.0 lb/ft³ and the maximum theoretical density of the
example, an asphalt concrete mixture containing lime- same mix is 154.0 lb/ft³, the air void content of the mix
stone aggregate might have a compacted density of 147 would be the difference in the two values ( 154.0 - 147.0
lb/ft³ . This density, or unit weight, is an indication of =
7.0) divided by the value of the maximum theoretical
the degree of compaction of the mixture . Different density ( 154.0) , or 4.5 percent.
paving materials made with different aggregates can
have significantly different densities. An asphalt con- FACTORS AFFECTING COMPACTION
crete mixture manufactured with lightweight aggregate, Four primary factors affect the ability of the compac-
for example, might have a compacted density of only 85 tion equipment to densify an asphalt mixture : the
lb/ft³ of volume. properties of the materials in the asphalt mixture,
Compaction is the process through which the asphalt environmental variables, conditions at the laydown site,
mix is compressed and reduced in volume. Compaction and the type of compaction equipment used . Each of
permits the unit weight or density of the mix to be these factors is discussed below.
increased by placing more materials in a given volume of
space or by taking a given amount of material and Properties of the Materials
compressing it into a smaller space or volume. As a Aggregates
result of the compaction process, the asphalt-coated Three properties of the coarse aggregate particles
aggregates in the mix are forced closer together, which used in an asphalt mixture that can affect the ability to
increases aggregate interlock and interparticle friction obtain the proper level of density are the particle shape
and reduces the air void content in the mix. of the aggregate, the number of fractured faces, and the
It is possible, under controlled laboratory conditions, surface texture . As the crushed content of the coarse
to compact an asphalt concrete mixture to a certain aggregate increases, as the nominal maximum size ofthe
maximum value . At this point, called the maximum aggregate increases, and as the hardness of the aggre-
theoretical density, no further compaction would be gate (granite compared with limestone, for example)
possible and no air voids would remain in the mix (a increases, the compactive effort needed to obtain a

Page 3-70
AC 150/5370-14
10/15/91
Appendix 1

specific level of density also increases. Angular particles This stiffness trend, however, is affected by the tempera-
offer more resistance to manipulation than do rounded ture viscosity relationship for each particular binder
aggregate particles. This angularity increases the material.
resistance to the applied compactive effort. The surface The degree of hardening that occurs in the asphalt
texture of the individual aggregate particles is also cement during the manufacture of the mix affects the
important, with aggregates that have a rough surface compactibility of that material. Different asphalts
texture being harder to compact than aggregates with a harden differently during the mixing process, and that
smooth surface texture . The compactive effort is also hardening is related , in part, to the chemical properties
affected by the shape of the aggregate, with a cubical or of each asphalt cement and its temperature susceptibili-
block-shaped aggregate needing a greater degree of ty. The degree of hardening is also a function of the
manipulation than a rounded particle shape before type and operating characteristics of the plant; more
achieving a given density level. hardening will typically occur when a drum mix plant is
A continuously graded (dense-graded) aggregate, operating at partial capacity compared with when it is
from coarse to fine, may be easier to compact than a producing mix at full capacity. Further, hardening is a
mixture with any other aggregate gradation . A harsh function of the mixing temperature at the plant, with
mix typically requires a significant increase in compactive higher manufacturing temperatures typically producing
effort to obtain the desired level of density. An over- stiffer mixes.
sanded or finely graded mix, on the other hand , tends to The asphalt cement content of the mix influences its
be extremely workable . It still might be difficult to compactability. In general, a mix with too little asphalt
achieve density on such a mix, however, because of the cement may be stiff and require an increase in compac-
inherent tender nature of such an oversanded mix. tive effort, whereas a mix with too much asphalt cement
Mixes that contain an excess of midsize fine aggregate may shove under the rollers.
[between the No. 30 and No. 50 (600 μm and 300 μm)
sieves or between the No. 40 and No. 80 (425 μm and Mix Properties
180 μm) sieves] also are difficult to compact because of A mix that is placed at a higher temperature will be
their lack of internal cohesion; they tend to displace easier to compact than will a mix that is lower in
laterally rather than compress vertically. The dust temperature when it is laid . If the initial mix tempera-
content [ amount of aggregate passing the No. 200 (75 ture is too high, however, the mix may be tender and
μm ) sieve] affects the compactive effort needed. A mix difficult to compact until the mix temperature decreases
designed with a high dust content will generally be more and the viscosity of the asphalt cement increases . If the
difficult to compact than a mix designed with a lower mix temperature is too low, an increased amount of
dust content. compactive effort will be needed to obtain the required
All of the properties of an aggregate that are benefi- density, and, if the temperature is too low, required
cial in terms of improving the characteristics of the mix density may never be achieved .
in regard to resistance to fatigue and permanent defor- The workability of the mix is affected by the temper-
mation typically increase the difficulty in obtaining a re- ature susceptibility of the asphalt cement. For a highly
quired level of density with a given compactive effort. temperature-susceptible asphalt binder material, less
Thus, the compactive effort needs to be increased to time will be available for compaction because the mix
achieve the density level needed in the mix. will change stiffness more quickly with a change in
temperature than will a mix containing a less tempera-
Asphalt Cement ture-susceptible asphalt.
The grade and amount of asphalt cement used in the The fluids content of the mix, not just the asphalt
mix affects the ability to densify the mix. An asphalt content, affects the compactive effort needed . Fluids
cement that is higher in viscosity or lower in penetration content is the sum of the asphalt cement content and
will generally provide for a stiffer mix at a given mix the moisture content of the mix. If the amount of
temperature and therefore require a greater compactive moisture in the mix from the plant is high, the extra
effort. Thus, a mix produced with an AC-20 viscosity- fluids content may make the mix unstable and difficult
graded asphalt will typically be stiffer, at any particular to compact. Thus, the moisture content of the mix
temperature, than a similar mix that contains an AC- 10 should be less than 0.5 percent, by weight of mix, when
asphalt cement . The stiffer the mix, the more com- the mix is discharged from the plant.
pactive effort needed to reach a given density level.

Page 3-71
AC 150/5370-14
Appendix 1 10/15/91

Environmental Variables used for mix laydown temperatures of both 250°F and
Research work completed in the early 1970s deter- 300°F. Figure 3-89 is to be used when the mix laydown
mined the time available for compaction of various temperature is 225°F or 275°F. The range of base
asphalt concrete mixes. The time available for compac- temperatures for each set of curves is from 10°F to
tion was defined as the time, in minutes, it took for a 60°F. The range of mix layer thicknesses is from 1/2 in.
mix to cool from laydown temperature to a minimum to 6 in.
compaction temperature. Laydown temperature is the
mix temperature when the paver screed passes over the Layer Thickness
mix. Minimum compaction temperature for this study Layer thickness is probably the single most important
was set at 175°F. Below this temperature, it was found variable in the rate of cooling of asphalt mixtures,
that the internal friction and cohesion of the mix especially for thin lifts. In many places, for early spring
increases to the point that little density gain is achieved and late fall paving, layers of mix less than 2 in. in
with the application of additional compactive effort. compacted thickness are very susceptible to premature
Any additional rolling with steel wheel rollers, except to failure because of the inability of the compaction equip-
remove roller marks, may result in fracture of the ment to densify the mix adequately before it cools below
aggregate in the mix and in a decrease in density. (It the minimum compaction temperature . It is very difficult
is emphasized, however, that rolling should occur at as to obtain the desired density on thin lifts of mix in cool
high a temperature as possible, given the properties of weather because of the rapid loss in temperature in the
the asphalt mix, in order to achieve the required level of mix.
density with minimum compactive effort . At tempera- As the thickness of the layer being placed increases,
tures near 175°F, the probability of significantly increas- the time available for compaction also increases. For
ing density or reducing air voids is very low except for example, in Figure 3-88, for a mix laydown temperature
unusual mix behavior or with the use of special rolling of 250°F and a base of 40°F, a 1 -in.-thick mat will cool
techniques such as heavy vibratory rollers or pneumatic from that 250°F temperature to the 175°F compaction
tire rollers with very high tire pressures.) cutoff point in less than 4 min . For a 2-in.-thick layer,
Six variables were found to have an effect on the rate under the same mix and base temperature conditions, it
of cooling (and, therefore, on the possibility of obtaining will take about 10 min for the material to cool to 175°F .
a required level of density) of a layer of asphalt placed Doubling the lift thickness from 1 to 2 in. increases the
on top of another existing layer of the same type of time available for compaction from 4 to 10 min . If the
material. Those variables are: layer thickness, air layer depth is 4 in., the time to cool changes to about 29
temperature, base temperature, mix temperature, wind min, a significant increase in available compaction time
velocity, and solar flux. under similar temperature conditions.
A series of "cooling curves" for asphalt concrete Using the same figure, the relative effect of pave-
mixtures, which are shown in Figures 3-88 and 3-89, ment lift thickness is the same for a mix laydown
illustrate the amount of time available for compaction temperature of 300°F and a base temperature of 40°F.
under different combinations ofvariables. For these two As the course depth is decreased from 4 in. to 2 in. to
figures, it is assumed that the material being compacted 1 in., the time available for the mix to cool from 300°F
is a dense-graded asphalt concrete mix. Ambient air to 175°F decreases from more than 40 min to 16 min to
temperature is assumed to be equal to the surface only 6 min, respectively. From these data, it is apparent
temperature of the base. A constant wind velocity of 10 that the time available to compact a thin layer of asphalt
knots (about 11.1 miles/hr) and a constant degree of is extremely limited in cold weather.
solar radiation (solar flux of 50 BTU/ft²/hr) is also used
to generate the graphs. The curves then provide the Air and Base Temperature
time, in minutes, for the mix to cool from the laydown A portion of the heat in the asphalt layer is lost to
temperature to the minimum compaction temperature the air. All other factors being equal, an increase in the
(175°F) for different compacted layer thicknesses. ambient air temperature decreases the rate of cooling of
To use the graphs it is necessary to determine the the mix. This increase in air temperature allows more
value of three different variables: initial mix laydown time for the compaction equipment to achieve the
temperature, base surface temperature (which is often desired density level in the mix.
assumed to be equal to the ambient air temperature), Heat in the mix is also lost to the layer on which the
and compacted layer thickness. Figure 3-88 is to be new material is placed . There usually is more rapid

Page 3-72
AC 150/5370-14
10/15/91
Appendix 1

OL
+ 8
50

Minutes
Time
Cool
Mat
175
for
to
°F
40

30-
Time for mat to cool to 175 ° F vs.
mat thickness for lines of constant
20 mix and base temperatures.
Alm , temp………, same as base temp.
Solar flux 50 Blu/ft²/hr
10 Wind velocity . 10 knots

Mat Thickness, Inches


0 2 3 4 5 6

Figure 3-88. Time for mat to cool to 175°F vs. mat thickness for lines of
constant mix and base temperatures (250°F or 300°F behind paver)
(Dickson and Corlew; AAPT 1970).

cooling of the mix downward to the base than upward be less than the ambient air temperature early in the
into the air. Base temperature is actually more impor- morning. The air temperature may be "40°F and rising,"
tant than air temperature in determining the time but the base might be 5°F or 10°F below the air temper-
available for compaction. Most specifications, however, ature. This low base temperature will cause the newly
specify a minimum air temperature for paving and placed course to cool quickly, reducing significantly the
compaction operations. time available to achieve adequate density. Base
It is often assumed that air and base temperature are temperatures are often higher in the late fall than in the
the same. This is not necessarily true, particularly in early spring for the same overnight air temperature.
cool weather. In early spring, the base temperature Thus, less heat is lost to the base and it is easier to
(surface temperature of an existing pavement layer) will compact a given thickness of material in the fall com-
Base
Mix

5 2233
275

g
,10

50
inutes
Time
Cool
Mat
M175
for
to
°F

40-

30-

Time for mat to cool to 175 °F vs.


20 mat thickness for lines of constant
mix and base temperatures.
Atm . temp. . same as base temp.
10 Solar flux 50 Btu/ft2/hr
Wind velocity 10 knots
Mat Thickness, Inches
0
5

Figure 3-89. Time for mat to cool to 175°F vs. mat thickness for lines of
constant mix and base temperatures (225°F or 275°F behind paver)
(Dickson and Corlew; AAPT 1970) .

Page 3-73
AC 150/5370-14
Appendix 1
10/15/91

pared with the spring. The effect of mat laydown temperature is more
A moist base layer significantly increases the cooling significant at lesser mat thicknesses and lower base
rate of the new overlying asphalt layer. Heat is lost temperatures. As the time to cool to 175°F becomes
from the mix to the moisture, turning water into steam shorter, an increase in the mix laydown temperature
and increasing the rate of heat transfer. Paving on a extends the compaction time significantly in most cases.
wet surface is detrimental to the ability to gain proper
density in the mix. The presence of the moisture may Wind Velocity
cause the mix to cool quickly and reduce the time A thin layer of mix will cool more quickly in a strong
available for compaction. wind than when there is little or no wind . Wind has a
As the temperature of the ambient air and existing greater effect at the surface of the mix than within the
pavement surface increases, the time for the mix to cool mix, and can cause the surface to cool so rapidly that a
from the laydown temperature to 175°F also increases. crust will form. This crust must be broken down by the
In Figure 3-89, for a mix of 275°F and a lift thickness of rollers before the actual compaction process can begin.
3 in., it takes only 22 min for the mix to cool when the The velocity of the wind must be considered more for
base and air temperatures are both 20°F. The time thin layers of mix placed in cool weather than for thicker
available is extended to 25 min for a base/air tempera- layers laid in warmer temperatures.
ture of 40°F and to 30 min for a 60°F base/air tempera-
ture . Solar Flux
For a 2-in. lift thickness, using the same mix laydown The amount of radiant energy available from the sun
temperature of 275°F in Figure 3-89, the time to cool to (solar flux) is a function of many variables, including the
175°F increases from 11 min, to 13 min, and to 15 min position of the sun above the horizon, the distance
for a base/air temperature of 20°F, 40°F, and 60°F, above sea level of the paving project, the amount of
respectively. The temperature of the ambient air and turbidity in the air, and the degree of cloud cover. A
base surface are important, but not nearly so crucial as mix will cool more slowly on a sunny day compared with
mat lift thickness in determining the time available for a cloudy one. The amount of solar flux is more impor-
compaction. tant in its effect on base temperature than its effect on
mix temperature. The base temperature will be higher
Mix Laydown Temperature on a sunny day, for a particular ambient air temperature,
Asphalt mixes are usually produced at temperatures than it will be on a day with heavy cloud cover. This
between 270°F and 325°F. Depending on environmental higher base temperature will reduce the rate of cooling
conditions and the length of haul, the mixture can lose of the mix and increase the time available for compac-
between 5°F and 25°F from the plant to the paver. It is tion.
not the plant mixing temperature that is important in
determining the time available for compaction but the Obtaining Proper Density under Varying Environmental
temperature at which the mix comes out from under the Conditions
paver screed. As the initial mix laydown temperature is Compaction of the mix requires common sense. If
increased, the time available for compaction also in- the lift thickness decreases, if the air and base surface
creases. Within limits, the mixing temperature should be temperatures are both reduced , if the laydown tempera-
determined by the laydown and compaction temperature ture is less, if the amount of solar flux is decreased ,
requirements. and/or the wind velocity is increased, then the time
As the temperature of the hot-mix asphalt being available to properly obtain the required level of density
placed is increased, the time available for compaction is before the mix cools to 175°F also decreases. A signifi-
greater. This is seen in Figure 3-88 for laydown temper- cant change in any one of the above factors can make
atures of both 250°F and 300°F. For a lift thickness of the difference between constructing a durable pavement
2 in. and a base/air temperature of 40°F, the time to structure or building one that would be subject to an
cool to 175°F increases from 9 min to 16 min as the early pavement failure .
placement temperature increases from 250°F to 300°F. If possible, the best solution to a potential compac-
For a 4-in. course thickness and a 60°F base/air temper- tion problem is to increase the thickness of the material
ature, a change in laydown temperature from 300°F to being placed. One-in.-thick layers cool so quickly, even
250°F reduces the time available for compaction from 36 in good environmental conditions, that proper density is
min to 21 min. almost impossible to obtain. The minimum course

Page 3-74
AC 150/5370-14
10/15/91
Appendix 1

thickness that should be specified under the best of the speed of the paver and that the density obtained is
circumstances should be 1 1/2 in. For early spring or measured to assure that the required level of compac-
late fall paving projects, at least 2 in. of compacted tion is achieved uniformly across the width of the mat.
asphalt mix should be placed in a single lift, if possible . One procedure that should not be done in an attempt
The easiest solution to a potential time- availability to increase the level of density in the mix is to increase
problem is to increase the discharge temperature of the the asphalt cement content of the mix arbitrarily.
asphalt mix at the plant, if this procedure does not cause Although the additional asphalt cement may be benefi-
other problems with the mixture . This will permit an cial in increasing the workability of the mix, it defeats
increase in the laydown temperature of the mix behind the purpose of mix design and may create long-term
the paver screed, thereby allowing more time for the mix performance problems for the mix under traffic, such as
to cool to 175°F, all other factors being constant. rutting and shoving. Thus, the required level of density
Increasing the mix temperature may not be enough, should be obtained by changing the compaction opera-
however, to provide adequate time for compaction under tions instead of increasing the asphalt content of the
adverse environmental conditions and for thin layers of mix.
material. If the mix temperature is increased too much,
the mix may be tender under the compaction equipment . Laydown Site Conditions
The mix must then be allowed to cool before the A number of factors at the laydown site directly
compaction process can be commenced . Thus, there is affect the ability of the compaction equipment to gain
an upper limit to the amount of temperature increase to the required level of pavement density. The most
which the mix can be subjected . important of these is the thickness of the layer being
Compaction effort can be increased by simply using placed . As discussed previously, the thicker the lift, the
more rollers to compact the pavement layer. In addi- more slowly the mix will cool down and the more time
tion, rollers that are wider and/or heavier can be substi- will be available for compaction. The retained heat of
tuted for narrower and/or lighter compaction equipment. the thicker courses makes it easier to obtain the desired
A double-drum vibratory roller, for example, that is 7 ft air void content.
wide can be employed in place of a static steel wheel The relationship between lift thickness and nominal
tandem roller that is only 4 1/2 ft wide. maximum aggregate size in the mix is another variable
Another means to achieve proper compaction levels that affects the amount of density that can be obtained.
is to use the compaction equipment more effectively. If the course depth is at least twice the nominal maxi-
Depending on the width being paved and the width of mum aggregate size, adequate density can be achieved
the rollers, the rollers can be placed almost "side by with normal compactive effort. When the lift thickness
side" instead of end to end. Two rollers running in is less than two times the dimensions of the largest
echelon can cover a given area much more quickly than aggregate pieces, a rough surface texture may result
two rollers operating in conventional fashion. The level when the large aggregate pieces are dragged by the
of density obtained will be increased because more paver screed. The voids created in the mix from the
compactive effort may be applied before the asphalt mat dragged aggregate negate any efforts to obtain the
cools to 175°F. In essence, this method provides for two proper level of density in the mix.
breakdown rollers instead of one breakdown roller and The uniformity of the lift thickness is another factor
one intermediate roller. To obtain the required density to be considered. It is much easier to obtain a required
levels, however , use of an intermediate roller or rollers level of density in an asphalt layer that has a constant
may still be necessary. thickness compared with a course that varies in depth.
If two different types and/or sizes of rollers (such as Asphalt leveling courses that, by their very nature and
a vibratory roller and a pneumatic tire roller) are used purpose, are nonuniform in thickness, are often difficult
for echelon rolling, it is important that each roller cover to densify to a given air void content uniformly, especial-
all of the mix surface. This may mean that the rollers ly when placed over a rutted or wavy road.
have to cross back and forth and run different roller Depending on the width and the depth of the rut,
patterns and numbers of passes. In addition, if one of static steel wheel rollers tend to bridge over the rut,
the rollers is compacting a longitudinal joint, consider- particularly if the rut is relatively deep and narrow.
ation of this fact must be made in setting the rolling Vibratory rollers also tend to be supported by the high
pattern for each piece of compaction equipment. It is points in the surface, but the vibratory action has some
very important that both rollers are able to keep up with beneficial effect in compacting the mix in the rut . Thus,

Page 3-75
AC 150/5370-14
Appendix 1 10/15/91

225 HIGHWA
ASPHAL

Figure 3-90. Static 3-wheel roller (J. Scherocman) .

adequate density is usually not obtained throughout the Compaction Equipment


mix, particularly in the rutted areas where it is needed The type of equipment used to compact the asphalt
the most. Use of a pneumatic tire roller may be helpful mix obviously has a significant effect on the degree of
in achieving density in the low spots (ruts) as well as in density that can be obtained in a given number of passes
the high spots on the pavement surface if proper tire of a particular roller . Three types of self-propelled
inflation pressure and wheel load are used. compaction equipment are currently being used: static

827
HIGHWAY
ER

ASPHALT CO

Figure 3-91 . Static tandem roller (J. Scherocman) .

Page 3-76
AC 150/5370-14
10/15/91
Appendix 1

steel wheel rollers, pneumatic tire rollers, and vibratory compactive effort applied to the mix is a function of the
rollers. wheel load of the machine, the tire pressure , the tire
design (tire size and ply rating) , and the depth of pene-
Static Steel Wheel Rollers tration of the tires into the mix. All of the tires on the
Static steel wheel rollers, shown in Figures 3-90 and roller should be the same size, ply, and tire pressure.
3-91 , normally range in weight from 3 to 14 tons and The area of each tire footprint and the wheel load of
have compression drums or rolls that vary in diameter the roller are the primary factors in judging the effec-
from approximately 40 in. to more than 60 in. The gross tiveness of a rubber tire roller. The greater the contact
weight of the roller can usually be altered by adding pressure between the tire and the mix, the greater the
ballast to the roller, but this adjustment cannot be made compactive effort applied by the roller. To be effective
while the roller is operating, and is not normally when used in the breakdown roller position , larger tire
changed during the term of a paving project. For this size rollers should be used . Rollers that are equipped
type of roller, the gross weight of the machine and the with tires that are 7.50 x 15 or less are not normally
contact area of the rolls with the mix are both important effective as a breakdown roller; pneumatic tire rollers
in determining the compactive effort applied by the with larger-size tires should be employed . If these
roller. rollers are used as intermediate rollers, the minimum
Effective weight or contact pressure, in terms of tire ply rating should be 10 ply and the tire pressure
pounds per square inch of contact area, is the key should be 60 psi or greater.
variable for this type of equipment and is dependent on The tire pressure used depends in part on the
the depth of the penetration of the rolls into the mix. number of plies used in the tires. In general, a 6 -ply tire
The greater the depth of penetration, the greater the is limited to a tire pressure of 60 psi, whereas a 10-ply
contact area and thus the less the contact pressure . This tire can carry a pressure up to 90 psi. A 12-ply tire,
means that on the first pass of the roller, when the normally used on most large pneumatic tire rollers, can
indentation of the rolls into the mix is the greatest, the be inflated up to 120 psi to compact asphalt mixes. The
roller exerts less compactive effort on the mix. On minimum weight of the pneumatic tire roller should be
subsequent passes of the roller over the same mix and as 15 tons.
the mix gets more dense, the rolls on the roller pene- If the mix is tender, a lower tire pressure will dis-
trate the mix to a lesser degree and the compactive place the mix less than will a higher pressure in the tires.
effort obtained by the roller is increased. For a stiff mix, a higher tire pressure can be used,
Drawbar pull is defined as the horizontal force because the mix will be stable enough to support the
required to move the roller forward . The most efficient weight of the roller without the mix shoving laterally
roller is the machine with the smallest drawbar pull. under the tires. Tire pressure is normally kept constant
Rollers with large-diameter rolls have lower drawbar for a particular project, but the level selected should be
pull (rolling resistance) because they do not tend to dependent on the properties of the mix being compacted
penetrate as far into the mix as does a roller with and the position of the roller on the mat. The tire
smaller-diameter rolls. pressure should not necessarily be the same if the
Once the size and weight of a static steel wheel roller pneumatic tire roller is used in the breakdown position
is selected , the variables under the control of the roller compared with the intermediate position in the roller
operator are the speed of the roller, the position of the train.
roller on the mat in relation to the paver, operation with Some pneumatic tire rollers have the capability of
the drive wheel toward the paver, and the number of changing tire pressure during the compaction process;
passes made with the roller. the "air on the run" or centralized tire inflation-control
system. In theory, this feature allows the roller operator
Pneumatic Tire Rollers to change tire pressures as the mix becomes more dense;
Most pneumatic rollers are operated in the interme- that is, a low tire pressure is used for the initial passes
diate roller position, behind a vibratory or static steel of the roller and a higher tire pressure is used as the mix
wheel breakdown roller and in front of a static steel stiffness is increased (as the density of the mix becomes
wheel finish roller. These rollers are sometimes used, greater) . In practice, however, this process seldom is
however, for initial rolling of the mix as well as occa- used because the operator cannot develop a consistent
sionally for finish rolling. rolling pattern and is not able to adjust the tire pressure
For this type of roller, shown in Figure 3-92, the continually as the mix and environmental variables

Page 3-77
AC 150/5370-14
Appendix 1
10/15/91

change throughout the day. tire roller is not adequate, the operator should alter the
The tires on the pneumatic roller will often pick up wheel load on the tires and/or change the inflation
the mix when an oversanded surface course mix or a mix pressure in the tires.
with some particular additives is being compacted .
Many times attempts are made to eliminate this pickup Vibratory Rollers
problem by spraying water or a release agent on the Vibratory rollers come in a variety of configurations.
tires during the rolling process. This does not always Single-drum vibratory rollers, illustrated in Figure 3-93,
solve the problem. A better solution is to allow the tires are manufactured with both a rigid frame and an articu-
on the roller to reach the same temperature as the mix
being compacted without adding water or release agent
to the tires. When the pneumatic tires and the mix are
at the same temperature, the amount of pickup will be 227302
minimized or eliminated . Skirts, consisting of pieces of
plywood or rubber sheeting, are sometimes hung down
from the sides of the roller around the tires for the
purpose of shielding the tires from the wind and keeping
them hotter. The benefits of such a practice are not
well documented .
If this type of roller is to be used as the breakdown
roller in the roller train at the start of paving in the
morning, it is suggested that, in order to minimize
pickup, the roller should be run back and forth for 10 Figure 3-93. Single-drum vibratory roller (J. Scheroc-
man).
min or so, before the paver begins to lay mix, in order
to start heating up the tires. Once paving commences, lated frame. Double-drum vibratory rollers, shown in
the rubber tire roller should be operated in the interme- Figures 3-94 and 3-95, come in rigid-frame, single-articu-
diate position, behind a static steel wheel roller or a lated -frame, and double-articulated -frame models.
vibratory roller, for another 10 min while the tempera- These rollers can be operated in any one of three
ture of the tires increases to the same level as the mix.
modes: static (with the vibrators off), with one drum
During the heating process, some pickup
of the mix may occur with the tires.
Once the tires have reached the same
temperature as the mix, however, the
pneumatic tire roller can be moved into
the breakdown position and should be
able to operate successfully without pick-
up of the mix. If the paving process is
interrupted for any significant length of
INGRAM
time, this heating start-up procedure will
have to be repeated . In no case should
the pneumatic tire roller, or any other
roller, park on the hot mat while waiting
for the paving operation to start again.
Once the size of the pneumatic tire
roller and the tire pressure to be used
are selected, the only variables that can
be controlled easily by the operator are
the rolling speed, the location of the
roller with respect to the paver, and the
number of roller passes over each point
in the pavement surface. If the com-
pactive effort applied by the pneumatic Figure 3-92 . Pneumatic roller (J. Scherocman) .

Page 3-78
AC 150/5370-14
10/15/91
Appendix 1

This

DYNAPAC

Figure 3-94. Double-drum vibratory roller (J. Scherocman).

vibrating and one drum static, and with both drums derived from the impact force is produced by a rotating
vibrating. eccentric weight located inside the drum (or drums) . As
These rollers thus have two types of compactive force the eccentric weight rotates about the shaft inside the
that is applied to the hot-mix asphalt: static weight and drum, a dynamic force is produced . This force
dynamic (impact) force. The compactive effort derived proportional to the eccentric moment of the rotating
from the static weight of the roller is caused by the weights and the square of the rotational velocity, as
weight of the rolls and frame. The compactive effort shown in Figure 3-96. Changing the eccentric moment

5-28

Figure 3-95. Articulated double-drum vibrator roller (J. Scherocman) .

Page 3-79
AC 150/5370-14
Appendix 1 10/15/91

arm or adjusting the eccentric mass has a directly of vibration. Some vibratory rollers can operate at only
proportional effect on the dynamic force. one frequency or have a very limited selection of
Although it is possible to combine the static and the frequencies. Other vibratory rollers can alter the
dynamic forces to determine a total applied force, this frequency of the applied load between 1600 and 3000
procedure is not recommended for comparing vibratory vibrations/min. Frequencies below 2000 vibrations/min
rollers of the same or different classes. Each component are not normally acceptable to compact asphalt mixtures.
of the total applied force should be evaluated separately. The spacing of the impacts of the applied force is a
The elements of comparison for the dynamic component function of the frequency of the vibration and the travel
of a vibratory roller are the magnitude of the centrifugal speed of the roller. A decrease in the frequency of
force, its vibrating frequency, the nominal amplitude, vibration and an increase in the roller speed both serve
and the ratio of the vibrating and nonvibrating masses to increase the distance between impacts on the surface
acting on the drum. The nominal amplitude is defined of the mix. Conversely, an increase in the vibratory
as equal to the weight of the drum divided by the frequency and a decrease in the roller speed both cause
eccentric moment of the rotating weight and is a func- the number of impacts per foot of distance to increase,
tion of the weight of the drum and the location of the thereby increasing the compactive effort applied by the
eccentrics. roller. A smaller impact spacing (a greater number of
Normal values of nominal amplitude range from 0.01 impacts per foot) is thus usually preferred. It must be
to 0.04 in. Some rollers can operate at only one fixed realized, however, that the productivity of the roller can
amplitude. Other rollers have "high" and "low" ampli- be decreased as the roller speed is reduced .
tude positions. For these rollers, the "low" nominal It has been suggested by several roller manufacturers
setting is typically 50 percent of the "high" nominal that the ideal impact spacing is in the range of 8 to 10
amplitude setting. The actual amplitude differs from the impacts/ft in order to provide a balance between roller
nominal amplitude because of the variation in damping productivity and layer smoothness. This spacing can be
effect of different materials at different states of com- determined by dividing the roller speed by the frequency
paction. An increase in the applied nominal amplitude of vibration: Impact spacing = roller speed in feet per
of vibration increases the compactive effort applied to minute divided by the frequency in vibrations per
the asphalt mixture. For a given frequency, changing minute. Eight impacts/ft = 1.5 in. between impacts,
the amplitude setting has a proportional effect on the whereas 10 impacts/ft = 1.2 in. between impacts. At a
dynamic force. For a given amplitude, changing the vibratory frequency of 2400 vibrations/min, a roller
frequency influences the dynamic force to the second speed of 3.4 miles/hr would provide an impact spacing of
power. 8 impacts/ft, and a roller speed of 2.7 miles/hr would
The effectiveness of an increase in the amplitude result in an impact spacing of 10 impacts/ft . If the
value, however, is sometimes dependent on the thickness vibratory frequency was 3000 vibrations/min, the corre-
of the layer being densified . For relatively thin layers of sponding roller speeds would be 4.1 and 3.3 miles/hr for
mix, generally less than approximately 1 1/4 in. in an impact spacing of 8 and 10 impacts/ft, respectively.
compacted thickness, the vibratory roller should typically In general, the vibratory roller should be operated at
be operated in the static mode--without vibration . This as high a frequency as possible. A roller capable of
is because the roller will bounce after a few passes (and running from 2000 to 2400 vibrations/min should be
possibly decompact instead of compact the mix) on such operated at the upper end of this frequency range.
thin layers of mix because of the variable stiffness of the Similarly, a roller that can be run at 3000 vibrations/min
underlying pavement courses. In general, for layers should be run at or near that maximum frequency
1 1/4 in. thick or greater, a "low" amplitude setting instead of some lower frequency. The use of the highest
should be used on the vibratory roller. As the layer possible frequency of vibration increases the number of
thickness increases, it is often advantageous to increase impacts per foot at a given roller speed . Most rollers
the nominal amplitude applied to the asphalt mix. are designed so that the highest frequency can be
Unless "high" amplitude is needed to achieve a particular employed at the highest amplitude setting. For some
density level, the vibratory roller should be operated in rollers, however, it is necessary to operate at a somewhat
"low" amplitude. lower frequency when the roller is used in the highest
The frequency of vibration is the number of complete amplitude setting. In any case, the most appropriate
cycles that the eccentrics rotate per minute. The faster impact spacing varies with the lift thickness and the
the rotation of the eccentrics, the greater the frequency properties of the asphalt mixture . The selected impact

Page 3-80
AC 150/5370-14
10/15/91
Appendix 1

vibratory roller more versatile than either the static steel


wheel or the pneumatic tire rollers. Construction of a
F roller test strip is needed, however, to determine the
optimum combination of rollers, roller speed, and
vibratory amplitude for each particular set of project
conditions. If the required compactive effort cannot be
achieved, the speed of the roller should typically be
decreased and the nominal amplitude setting being used
should be changed .
(4 π 242Fr) Care should be taken when operating a vibratory
Centrifugal force, N (Ib) =
g roller in areas where buildings are nearby. (A safe
where: F = weight of eccentric, N (1 lb) distance from buildings would be about 3 ft for each ton
r = eccentricity, m (ft)
Fr = eccentric moment , Nm (1 lb - ft) of roller weight.) In addition, the use of vibration on
f = frequency , Hz (cycles /s) the roller when underground utilities and drainage
g = acceleration due to gravity, 9.81 m /s2 structures are directly under the pavement layer being
MOVEMENT

(32.17 ft/s2)
compacted needs to be considered carefully.
Centrifugal force .
COMPACTION VARIABLES
UP

The primary compaction variables for all types of


AMPLITUDE rollers that can be controlled during the rolling process
(A) are: (a) roller speed , (b) number of roller passes, (c)
rolling zone, and (d) roller pattern . In addition, for
TIME
DOWN

vibratory rollers, vibration frequency, vibration ampli-


tude, and direction of travel are also under the control
TIME (T) FOR FULL CYCLE of the operator. Each of these factors has an effect on
the level of density achieved under the compactive effort
Frequency, f = the number of hertz (cycles/s) -- a applied to the mix.
single cycle is one full rotation of 1
the eccentric weight. Frequency =
Amplitude, A = the maximum deviation from position at Roller Speed
rest -- one-half of the total movement.
The faster a roller passes over a particular point in
Frequency and amplitude. the new asphalt surface, the less time the weight of the
roller "dwells" on that point. This in turn means that
Figure 3-96. Basic formulas for vibratory compaction
less compactive effort is applied to the mixture . As
effort (Asphalt Institute).
roller speed increases, the density achieved with each
roller pass decreases. The roller speed selected is
spacing (and corresponding roller speed and vibratory dependent on a combination of factors: productivity,
frequency) should optimize the amount of compaction layer thickness, and the position of the equipment in the
obtained per pass of the roller and the smoothness of roller "train ."
the pavement. Static steel wheel rollers can normally operate at a
The roller operator is in control of more variables speed between 2 and 5 miles/hr (176 and 440 ft/min) .
when using a vibratory roller and thus should be well Pneumatic tire rollers typically run between 2 and 7
educated in the proper selection and interaction of the miles/hr ( 176 and 616 ft/min) , whereas vibratory rollers
variables. In addition to roller speed, location on the can operate at speeds between 2 and 3 1/2 miles/hr (176
layer being compacted, and number of passes made, and 308 ft/min) . In the breakdown position, the roller
both the nominal amplitude and the frequency of the used should be operated at the lower end of its speed
vibratory impact can be varied . Roller speed and range. In the intermediate position, the speed of the
vibratory frequency are combined to determine the roller can be increased somewhat, typically into the
impact spacing. Further, for double-drum vibratory middle of the speed range. In the finish rolling position,
rollers, the operator can vibrate either one or both rolls. the maximum speed of each type of roller can be near
This allows the operator to control the compactive effort the upper end of its range of compaction speeds. The
applied to the mix to a greater degree and makes the following table provides an indication of the range of

Page 3-81
AC 150/5370-14
Appendix 1 10/15/91

roller speed for three different types of rollers and three Roller speed is usually established by the speed of
different operating positions: the paver; if the paver pulls away from the rollers, the
roller speed is increased in order to catch up . This only
TYPICAL RANGE OF ROLLER SPEEDS, IN causes the density developed in the asphalt mixture to
MILES PER HOUR decrease for the same number of roller passes. If the
TYPE OF ROLLER Breakdown Intermediate Finish paver continually pulls ahead of the rollers, several
Static steel wheel 2-32 22-4 3-5 courses of action can be taken. First, paver speed can
Pneumatic 2-32 22-4 4-7
be reduced to match both plant production and roller
Vibratory 2-3 22-32
production. Too often, the paver is operated on a
"hurry and wait" basis between truckloads. If plant
Rollers can move faster or slower than these speeds, production capacity necessitates higher paver speeds,
but compaction varies directly with roller speed. Com- additional rollers will be required to achieve adequate
pactive effort is significantly improved at slower roller density. Wider rollers can be employed ; a 7-ft-wide
speeds. Roller speed will also be governed by the lateral vibratory roller can be used in place of a 4 1 /2-ft-wide
displacement or tenderness of the asphalt mix. If the tandem roller, for example. The type of roller used can
mixture moves excessively under the rollers, the speed of also be changed; a double-drum vibratory roller em-
the compaction equipment should be reduced . In ployed in lieu of a single-drum vibratory roller.
addition, for vibratory compactors, roller speed also Varying the speed of the compaction equipment
affects the impact spacing as shown in Figures 3-97 and merely causes variations in density. Too often roller
3-98. As discussed above, this spacing is important for operators hustle along to catch up with the paver, park
controlling the amount of dynamic compaction energy on the hot mat, and sit and talk to the rest of the paving
applied to the mix and also for obtaining the proper crew. "Slow and steady" is the key to proper compac-
surface smoothness. tion.

Number of Roller Passes


To obtain the target air void content and uniform
density in an asphalt mixture , it is necessary to roll over
each point in the pavement mat a certain number of
times. The actual number of passes depends on many
m!!!
Т I
variables. The type of compaction équipment is one
very important consideration. Three-wheel steel rollers
1 MPH | 2 MPH❘ 3MPH
have different compaction capabilities than tandem steel
Figure 3-97. Effect of roller speed on impact spacing wheel rollers, than pneumatic tire rollers, and than
(Asphalt Institute). single- or double-drum vibratory rollers.

Roller Speed
Frequency Miles per hour (ft/minute)
(cycles per
minute) 1.5 (132) 2.0 (176) 2.5 (220) 3.0 (264) 3.5 (305)

1000 7.6 5.7 4.5 3.8 3.2


1200 9.1 6.8 5.5 4.6 3.9
1400 10.6 8.0 6.4 5.3 4.5
1600 12.1 9.1 7.3 6.1 5.2
1800 13.6 10.2 8.2 6.8 5.8
2000 15.2 11.4 9.1 7.6 6.5
2200 16.7 12.5 10.0 8.3 7.1
2400 18.2 13.6 10.9 9.1 7.8
2600 19.7 14.8 11.8 9.8 8.4
2800 21.2 15.9 12.7 10.6 9.1
3000 22.7 17.0 13.6 11.4 9.7

Figure 3-98. Impacts per linear foot (Utah DOT).

Page 3-82
AC 150/5370-14
10/15/91
Appendix 1

The capabilities of each type of roller vary, however, 175°F.


with mat thickness, mix temperature, mix design ( asphalt To reach the required density level the quickest,
content and aggregate characteristics) and environmental initial compaction should occur directly behind the
conditions. In addition, the number of passes required laydown machine. If the stability of the asphalt mixture
depends on the position of the rollers in the roller train. is high enough, breakdown rolling can be carried out
To determine the minimum number of roller passes very close to the paver, while the mat temperature is still
needed to achieve proper density levels, a test strip high. More density is obtained with one pass when the
should be constructed at the start of any major paving mix temperature is 250°F than with a similar pass when
project. A number of different combinations of rollers the mat is at 220°F. Thus, the rolling zone (the distance
and roller patterns should be tried to determine the the breakdown roller operates behind the paver) should
"optimum" combination of compactive efforts to achieve be as short as possible.
the required density level as efficiently as possible. Sometimes when a tender mix is placed, the initial
Rarely will the first combination of rollers, roller passes, rolling is delayed (the rolling zone is lengthened) to
and rolling zones tried provide the most economical avoid excessive shoving or checking of the mix by the
rolling sequence unless the mix is one with which the rollers. Depending on the characteristics of the mix, it
contractor is thoroughly familiar. is still often possible to obtain the required level of
Roller passes must be distributed uniformly over the density of the mix as long as the proper combination of
width and length of the mat. All too often, the center rollers and compactive effort is applied to the mix. In
of the paver lane (the area between wheelpaths of a some cases, however, the mix is so tender that rolling
single -lane pavement) receives adequate roller coverage must be delayed to the point that the desired density
whereas the edges of the mat receive considerably less level cannot be achieved. In this case, other solutions
compactive effort . As discussed further under the need to be tried . When a tender mix is encountered ,
section on roller patterns , the uniformity of roller the cause of the tenderness must be determined and
passes is just as important as the number of passes. changes made in the mix production and paving opera-
A nuclear density gauge can be employed to deter- tion to assure adequate density of the asphalt mix. A
mine the optimum number of roller passes necessary to discussion of causes for checking and shoving in the mix
obtain the required density level. If this piece of equip- is given in the following section on mat problems.
ment is used, however, a proper correlation to the actual
density of the asphalt pavement layer, measured by Roller Patterns
cores, must be completed to assure that the density Rollers are " busy" most of the time on a paving
measured by the nuclear gauge is equal to or greater project. The question is whether they operate correctly
than the specifications requirements. Nuclear gauges and effectively. Generally, compaction is applied , but
typically measure relative density of the mix, not actual not necessarily in the right place. Numerous compaction
density as determined by the specific gravity of pavement studies have shown that the middle of the width of the
cores. paver pass typically receives more compactive effort than
the edges of the pavement. This is unfortunate, because
Rolling Zone traffic uses the wheelpath areas and travels near the
Compaction must be achieved while the viscosity of edge of the pavement more often than in the center of
the asphalt cement in the mix and the stiffness of the a lane.
mix is low enough to allow for reorientation of the On an actual asphalt concrete-paving project of an
aggregate particles under the action of the rollers. In Interstate roadway, the mixture was placed in a trench
other words, the mat must still be hot for effective section, 12 ft wide, in two 3 -in. compacted lifts . Initial
compaction. The rule of thumb commonly used is that or breakdown rolling on the first layer was accomplished
the proper level of air voids should be obtained before by the contractor using a 7-ft-wide vibratory roller. For
the mix cools from laydown temperature to 175°F. the 12-ft-wide paver pass, two passes of the vibratory
Many variables affect the rate of cooling of the mixture, roller could cover the whole mat width, with a 2-ft
as discussed previously, and the mix compaction cutoff overlap in the center. To gain adequate density, the
temperature is a function of all of those variables. breakdown roller operator had to keep the vibratory
Harsh mixes, for example, may require a higher cutoff roller tight to each side of the trench. In order to cover
temperature, whereas a tender mix may be able to be the complete width of the lane, the operator needed to
compacted adequately at a much lower temperature than make each roller pass, on each side of the lane, directly

Page 3-83
AC 150/5370-14
Appendix 1 10/15/91

Lane width 12'


.OT number of roller passes are provided on each edge of
10' 2 4 6' 8 12
the lane being compacted, the density level in the center
PAVER of the lane will always be more than enough to meet
specifications. Thus, roller patterns should be designed
Pass Five 4
+ to assure proper compaction of the whole lane width.
For each roller employed on a project, the mat width
can be divided by the width of the compaction rolls to
determine the number of passes needed to cover each
Pass Four transverse point in the surface. A pass is defined as one
trip of the roller in one direction over any one spot.
Multiple passes are needed to completely compact the
transverse width of the lane being paved as well as over
each point in the pavement surface to assure attainment
Pass Three +
of the required level of density.
If the width of the roller drums (or tires) is 84 in. (7
ft) , only two passes of the roller are needed to cover the
12-ft-wide lane, including a 6-in.-wide overhang at each
Pass Two
edge of pavement. This is shown in Figure 3-100 . The
two passes of the 84-in.-wide roller overlap for a dis-
tance of 12 in. in the center of the lane. If allowance is
made for the fact that the roller operator may not
Pass One + always be able to maintain a 6 -in. overhang on the edge
of the pavement, the 12- in.-wide overlap in the center of
the lane is still sufficient to permit the whole pavement
width to be compacted in two passes of the 84- in .-wide
Figure 3-99. Improper roller pattern (J. Scherocman) .
roller with a minimum of a 6-in.-wide overlap needed
between roller passes .
toward and away from the paver without ever making an A roller that is 72 in. (6 ft) wide cannot cover the
attempt to roll the center of the lane. complete 12-ft lane width in only two passes, as shown
On the job, however, the roller operator made his on the second line of Figure 3-100 . Two passes do not
first pass, 7 ft wide, up the left-hand side of the mat allow for any overhang at the edge of the lane or any
(Figure 3-99). Upon reaching the back of the paver, the overlap at the center. Thus, three passes of the 72-in.-
roller operator reversed direction, changed lateral wide roller would be necessary to properly compact the
direction slightly, and moved away from the paver by lane, as shown in the third line of the figure .
traveling down the center of the mat, with 2 1/2 ft of If the roller had drums or tires that were 60 in . (5 ft)
free area on both sides cf the vibratory roller . The third in width, three passes of the roller would be required ,
pass, again toward the paver, was along the right-hand similar to the roller with the 72-in.-wide drums. This is
edge of the driving lane The fourth pass (away from illustrated on the fourth line of Figure 3-100 . If 6 in. is
the paver) was once more down the center, similar to allowed for edge- of-lane overhang, the amount of
pass number two. The final roller pass, to catch up to overlap between roller passes is 12 in. This allows for
the paver, was a reversal of pass four--up the center of ample steering variation by the roller operator and will
the lane. The roller operator continued to repeat this permit the 12- ft lane width to be covered with three
five-pass pattern as the paver moved down the roadway. passes of the 60-in.-wide roller.
Five passes of this breakdown roller were applied to A roller with drums that are 54 in . would need to
the center of the 12-ft area, a place where no traffic make four passes across the width of a 12-ft lane in
runs. Only one pass each was provided over each order to completely cover the lane width. As shown in
wheelpath and the edge of the lift. The roller was the fifth line of Figure 3-100 , if this roller overhangs
simply not being used properly because no rolling each edge of the pavement by 6 in. and only three
pattern had been set up and followed. A future failure passes across the lane width are made, the roller drums
was built because proper density was not obtained in the would only overlap 3 in. between the first and second
wheelpaths, where it was needed . If an adequate passes and 3 in. between the second and third passes

Page 3-84
AC 150/5370-14
10/15/91 Appendix 1

‫من‬
iu-
O' 2 8 10 12
- I 1 1

6" 12"
Line 1

84" Drum

0"
Line 2

72" Drum

io
6" 30" 12" 30"
Line 3

72" Drum

6" 12" 12″ 6"


Line 4

60" Drum
in

6" 6"
Line 5

54" Drum

6" 24" 12" 24"


Line 6

54" Drum

Figure 3-100. Lane width versus roller width (J. Scherocman) .

across the width. This amount of overlap between compaction process to start at the low side of the pave-
passes would not be adequate and four passes of the ment lane and proceed toward the high or upper side of
54-in.-wide roller would be necessary to properly com- the lane on subsequent passes of the rollers. With
pact a paving lane that is 12 ft wide , as shown in the last modern compaction equipment and more stable asphalt

line of Figure 3-100. mixes, this requirement usually is not necessary but may
In a longitudinal direction , the rollers should not stop be advisable for superelevations and lifts that are thick
at the same transverse end point with each pass of the in relation to maximum particle size. In addition , some
roller. The reversal points should be staggered to of these same specifications stated that the rollers had
prevent shoving of the mix. A slight change in direction, to overlap the width of the previous pass by at least half
or curl, is beneficial at each reversal spot to further the width of the roller. This procedure leads to very
reduce the tendency of the mix to shove under the nonuniform compaction across the width of the pave-
ment lane . It is thus recommended that each subse-
compactor and to eliminate the possibility of a bump at
the point where the roller reversal occurs . The roller quent pass of a roller overlap the previous pass by a
should not sit and wait while parked on the hot mat. A minimum of 6 in.

long delay, caused by lack of haul trucks at the paver or


filling the compactor with water, allows the roller to Direction of Travel and Mode of Operation for
indent the new mat . It is generally impossible to roll out Vibratory Rollers
these marks once the mat has cooled . When using a single-drum vibratory roller, the com-
Many old compaction specifications require the pression drum should normally be operated toward the

Page 3-85
AC 150/5370-14
Appendix 1 10/15/91

paver. This assures that the maximum compactive effort tion test section. The thickness of the layer compacted
of the compression drum is placed on the mat before should be the same as that to be used for the rest of
the lesser compactive effort of the steering drum . In that particular layer, and the length of the test strip
addition, it provides a denser layer to better resist should be at least 300 ft . The condition of the underly-
displacement of the mix caused by the continual move- ing layers should be representative of that on the rest of
ment of the tiller drum during the steering action. A the project .
single-drum articulated-frame roller should also be Due consideration should be given to the selection of
operated with the driven drum toward the laydown rollers that are to be employed to densify the pavement
machine. Again, this assures that the maximum com- layer. The combination of rollers used on a previous
pactive effort is applied to the mix as quickly as possible. project might not be the most cost-efficient or effective
When only one drum is operated in vibration, for the variables involved in the present job. Although
double-drum rollers are often operated with the vibrated vibratory rollers are usually used for breakdown rolling
drum toward the laydown machine and with the static and pneumatic tire rollers for intermediate rolling, a
drum trailing. A double-drum articulated-frame roller greater degree of density with a lesser number of total
that has two driven drums (a vibratory tandem roller) roller passes might be obtained on some mixes (e.g.,
operates the same in either direction; thus, the direction when a large pneumatic tire roller is used in the break-
of travel is not a consideration for this type of roller. down position with the vibratory roller following in the
For harsh or stiff mixtures, breakdown rolling is intermediate position) . Determination of the "optimum"
normally accomplished with both drums vibrating. combination of rollers and roller patterns might require
Subsequent compaction passes are also made in the full the construction of two or more test sections .
vibratory mode. For mixtures with normal stability, If a large pneumatic tire roller is used in the break-
breakdown rolling with a vibratory roller should be down position, it is generally difficult to determine the
accomplished in the full vibratory mode or in a combina- degree of density obtained in the mat through the use of
tion mode (with one drum vibrating and the other drum a nuclear gauge because of the rough texture of the mat
static). The full vibratory mode is typically more after the first several passes of the pneumatic tires.
efficient in terms of compactive effort, however, than is Nuclear readings must be taken after the mix has been
the combination mode. For tender mixtures, breakdown smoothed out with the intermediate roller. A compac-
is usually accomplished in the static mode. Subsequent tion test strip should be conducted to determine the
passes are usually made in the combination mode if most effective sequence of rollers to achieve the re-
mixture displacement is not too significant. When in the quired degree of compaction, the smoothness of the
combination mode for tender mixtures, the trailing drum mat, and economical production.
instead of the front drum is usually vibrated. Desired density levels are easier to obtain when the
asphalt mix is hot. Instead of using the rollers in the
DETERMINATION OF THE ROLLING PATTERN traditional roller "train" concept, consideration should be
Choice of Compaction Equipment given to using two breakdown rollers (of the same type)
Different mixes may require considerably different instead of a breakdown roller followed by an intermedi-
levels of compactive effort and thus different compaction ate roller. This will be particularly beneficial on thin
equipment and rolling procedures. An asphalt mix layers of mix under unfavorable environmental condi-
containing large aggregate, for example, may need tions.
different types of rollers to achieve a required level of
density than an asphalt concrete mix made with smaller- Rolling Patterns
size coarse aggregate . The first calculation needed concerns the amount of
The actual rolling pattern to be used to compact the mix to be produced by the plant, the width of the pave-
mix on a paving project should be determined at the ment lane, and the depth of the mix. Once the typical
start of the project through the construction of a roller speed of the paver is known, the maximum speed of the
test strip . This strip should be located at a convenient rollers should be selected . The actual speed selected for
point where the pavement layer placed will remain as each roller will depend on the type of roller and its
part of the final pavement structure. The mix should be width as well as its position in the rolling sequence . It
representative of the material to be produced for the will also depend on the ability of the roller to achieve a
project; generally the plant should produce mix for a balance between achieving density, smoothness, and an
short period of time before mix is made for the compac- unblemished pavement surface .

Page 3-86
AC 150/5370-14
10/15/91
Appendix 1

The next calculation that must be made concerns a obtained. When a pneumatic tire roller is used in the
comparison of the width of the layer being placed and compaction process, particularly in the breakdown mode,
the width of the rollers to be used in order to determine it is often very difficult to obtain an accurate density
the number of transverse roller lanes needed to cover reading with a nuclear gauge . One or more passes with
the whole width of the pavement. (A pass is defined as a steel wheel roller may be necessary before a valid
one trip of the roller in one direction over any point on nuclear gauge reading can be obtained .
the pavement surface . ) With the paver speed , the roller The density value determined with the nuclear gauge
speed, and the number of transverse lanes needed to is relative and is generally not the same as the density
obtain full-width coverage of the roadway surface, the value obtained from cores cut from the pavement. The
number of passes that each roller can place over each gauge reading indicates the density that can be obtained
point in the pavement and still keep up with the paver at one given time, under one set of environmental
can be determined . The number of passes, however, conditions , with one combination of rollers. Thus a
must be matched to the plant production rate and to the correlation must be developed between the nuclear
speed of the paver. density reading and the actual unit weight of the pave-
The number of roller passes needed over each point ment. The correlation is determined from cores that are
on the pavement surface is a function of a large number cut from the test section after the rolling process is
of variables . One of the most important variables is the complete. That unit weight must be compared to the
level of density required in the pavement layer. If a maximum theoretical unit weight of the mix in order to
method-type specification is being used, the required calculate the actual in-place air void content of the layer.
number of passes can simply be counted . What is not If the proposed test section rolling pattern does not
known, however, is what degree of density (air void achieve the required density, as measured by the cores,
content) will be obtained in the mix after the specified changes to the pattern should be made. An initial
number of passes is completed . If a certain percentage adjustment might be to reduce the speed of the rollers.
of laboratory density or theoretical maximum density is The frequency of vibration and the applied nominal
needed, the higher the required percentage , the more amplitude from a vibratory roller might be increased.
compactive effort that will have to be applied to the The air pressure in the tires of a pneumatic tire roller
pavement layer. might be increased and/or the weight on the roller could
The type of breakdown roller used also will be very be increased. The first two rollers might be run in
important. Under some conditions, one vibratory roller echelon instead of end to end, as in a normal roller
may be all that is needed to achieve density, depending train. If none of these changes can increase the density
on the properties of the mix. In other cases, if checking of the mix enough and still permit the rollers to keep up
in the mix occurs, several passes of a pneumatic tire with the production requirements of the paver, addition-
roller may be necessary to reach the density level al rollers may be needed to obtain the required density
needed . One or more passes of a static steel wheel levels.
roller is normally needed to remove roller marks,
particularly if a pneumatic tire roller has been used . ROLLER OPERATING TECHNIQUES
Because of the number of variables involved, it is To compact an asphalt layer properly, the rollers
impossible to generalize about the "best" combination of should be used efficiently while the mix is still above the
rollers and roller pattern to use. minimum compaction temperature . The factors that
The most common method for monitoring changes in should be observed when monitoring the compaction
density with roller passes is through the use of a nuclear process follow. The techniques noted in Section Five
density gauge. Density is estimated by transmitting for joint construction should also be observed .
gamma rays into the mix and measuring the amount of • The time available for compaction is primarily
radiation reflected back to the device in a given amount related to the thickness of the layer being placed. An
of time. The count data that are obtained can be increase in lift thickness can substantially increase the
related to the relative density of the layer. Nuclear time available for the roller to densify the mix.
gauge readings should be taken after each pass of each • An increase in the laydown temperature of the
roller, and the rate of increase in density after each pass mix behind the paver can increase the amount of time
determined. When no appreciable increase in density is available for compaction significantly. The feasibility of
obtained with the application of additional roller passes, this approach, however, depends on the properties of
the maximum relative density for that mix has been the asphalt concrete mix at the elevated temperature

Page 3-87
AC 150/5370-14
Appendix 1
10/15/91

and the tenderness of the mix under the compaction roller should be determined by the characteristics of the
equipment. mix and by the thickness of the layer being compacted.
• A decrease in the speed of the rollers will in- In general, vibratory rollers should be operated in the
crease the compactive effort applied to the mix. static mode when the compacted lift thickness is less
• The breakdown roller and intermediate roller than about 1 1/4 in. For greater lift thicknesses, the
should be operated as close to the paver as possible in roller should normally be operated at low nominal
order to obtain density before the mix cools to a mini- amplitude. If density cannot be obtained, the nominal
mum temperature of 175°F. amplitude may be increased to determine if additional
• If the mix cannot support the weight of the compactive effort will be beneficial in achieving the
compaction equipment, the mix should be redesigned or required density level. In general, the nominal ampli-
the compaction procedures should be changed . tude setting can be increased in proportion to the
• The roller pattern should be monitored to assure increase in compacted thickness of the layer.
that the compaction equipment is applying the same • The optimum combination of rollers and roller
amount of compactive effort at all points transversely patterns for a past project may not be the same opti-
across the lane being paved. mum combination for a current project or even for a
• The speed of the compaction equipment will different type or layer of mix on the same project. Test
depend on the type of roller being used and its position sections should be constructed to determine the most
in the compaction process. For static steel wheel and efficient and most effective combination of compaction
pneumatic tire rollers in the breakdown position, the equipment and roller patterns to use for each combina-
maximum speed should not exceed 2 1/2 miles/hr. For tion of job variables.
a vibratory roller in the same position, the maximum • Two similar rollers run side by side ( in echelon)
speed should not exceed 3 1/2 miles/hr. will typically produce a greater level of density in the
• A vibratory roller should be operated at the maxi- mix, with the same number of roller passes, than will the
mum possible vibratory frequency in order to increase same two rollers operated end to end as a breakdown
the number of impacts per foot. At least 8 to 10 and an intermediate roller.
impacts/ft are needed to obtain adequate density and If the rollers cannot keep up with the speed of
layer smoothness. the paver, more rollers should be used or the paver
• The nominal amplitude setting on the vibratory should be slowed down.

Page 3-88
AC 150/5370-14
10/15/91 Appendix 1

SECTION SEVEN
EQUIPMENT AND MAT PROBLEMS

INTRODUCTION causes the screed to rise and fall as the force pushing
Equipment and mat problems can be defined as against it changes. Too much mix (at the top of the
defects that occur in the asphalt mixture during or soon augers) and then too little mix (at the bottom of the
after the laydown and compaction operations. These augers) being carried in the auger chamber in front of
problems can be divided into two primary categories: (a) the screed causes the wavy surface as the screed reacts
equipment-related problems and (b) mixture-related to the variable forces on it.
problems. Several different types of mat deficiencies are Another cause of short waves can be a screed that is
discussed, with emphasis on the description of the in poor mechanical condition; one that has excessive
problem, the cause of the problem (equipment- or mix- play in the screed-control connections. Short waves can
related) , the solution, and the effect on pavement also be formed in the mat by improper mounting or
performance. sensitivity of the automatic grade control on the paver
Figure 3-101 summarizes the various kinds of prob- or by use of an inadequate grade reference device. The
lems that can occur in an asphalt concrete layer during problem might also be related to a mobile reference
construction. Problems in other types of mixes are not (floating beam) that is bouncing or to the truck driver
listed, but many problems are common to all mixes. holding the brakes while the truck is being pushed by
Listed in the first column is a description of various mat the paver .
defects. Marked in the remaining columns are several Short waves can also be a function of the mix design,
possible causes for each particular mat problem. The particularly in regard to a mix that varies in stiffness
check marks indicate equipment-related causes, and the caused by changes in mix temperature or mix composi-
X marks indicate mix-related causes. Mix-related causes tion. As the stiffness of the mix varies, the forces of the
should generally be corrected by changes in the mix mix pushing on the screed also vary, causing the screed
design. Because of the interaction of various equip- to rise and fall and place a mat with short waves.
ment-related and mix-related causes, no attempt has Finally, if the mix design is improper in aggregate
been made to prioritize the causal items. gradation, asphalt content, mix temperature, and/or
moisture content, the rollers may shove and displace the
SURFACE WAVES mix during the compaction process . Normally, however,
Description the short waves are placed in the mat by the paver
An asphalt surface can have two types of waves: either because of its operation or because of changes in
short waves and long waves. Short waves are generally mix stiffness rather than by the compaction equipment.
1 to 3 ft apart, with 1 1/2 to 2 ft being the most common Long waves are caused by some of the same variables
distance. Long waves are considerably further apart and that cause short waves. A fluctuation in the amount of
may correspond to the distance between truckloads of material in front of the screed and mix stiffness variation
mix. Long waves may also be associated with the causes the screed to react to the change in the pressure
reversal points ofthe compaction equipment, particularly on it. If the distance between the wave peaks, however,
on thick-lift construction. corresponds to the length of pavement between truck-
An additional type of defect in the pavement surface loads of mix, the waves may have been caused by incor-
is a roughness or washboard effect caused by improper rectly set hopper flow gates on the paver or by the paver
operation of the vibratory roller . The distance between hopper and slat conveyor being emptied between loads
this type of wave is generally very small, typically less of mix. Poor mechanical condition and improper
than 3 or 4 in. operation of the screed (continually changing the
manual thickness-control cranks, for example) as well as
Cause incorrectly mounted automatic grade controls can cause
A major cause of short waves is a fluctuating head of a long-wave type of surface problem. If a stringline is
material in front of the paver screed . This variation in being used as a grade reference, a sag in that line
the amount of mix being carried back to the augers by between support posts can be a cause of long waves.
the slat conveyors and deposited in front of the screed Delivery of the mix to the paver can also be a factor in

Page 3-89
AC 150/5370-14
Appendix 1
10/15/91

CAUSES
e
ur
r at re

X X X
e u XXXX
on ld x mp at

X
X
X
X

XX
a ti Co Mi Te per XXX

X
X
X
ri x mre

XXX
XXX

XXX
Va of Mi Tsetu n
i iox
M o
gian tMi
e
er x gr

X
X

XX
XX
XX

XX
t
r op Mi igSne hale

X
p e r x s p t
Imop Mi Degn (Asega )
pr x g si gr

XX
Ingm Mkiin De ler (Ag )
t t

X
r g ol

X
X
X
s i a
P in R ot Ho Mears
n
r
ve rn r o s ll on

XX

X
Re or Tu opeTo Fiang of Roation XXXX
r l r
e ti

Χ
r l

X
p
Im ope Ro Op ara

X X
r e p

X
XX
p s eg
Im kBa Pirn es
r us c oldng rak er
Tcks H pi B ish
er us m

X
n
op Tkrne Bu Fi
r c r ax gg izep

Χ
X
X

X
m p a t hi o r
e
I M T f p M . At . Sla
ro n r
mp d JoieenOve es
[
n g I 1 1
t i g rio cetw dt
Si
t n
Lo de Pe renBe oua
e g d eLq ce 1 1
l r a ef in Ina ren
e ro G d R c 1
r ad ont l an g oun vitny efe
G e C ro W in B ti o R y
ad nt t si thl
Gr Co e
H un rol(Sen ted Too rHeicg ) [
1
ad nt s un r
co
Gr Co atnosrMo ingIn ly
n o ctow

that cause listed


bir o n e d

moreone
e ed eVnis Rtuall ToorrSe l

is
r t g s nc
Sc Exeed inIns

by d than
r a rt ct ock I o ort 1
Sc St rre Bl ing To Sh edy 1
nc
o ll d rectl
er rew rn I t
s Nunte of Srcre ly

cause
c k u co t
Ki Sc Wo Ou eror Moes In rrec

important each
d

em
g e t t cno
in Feper d Gaty Se weIen

probl
s

reene
nn p ar mp et ff oad

.-( arber
the
R u o
H bo E B keo L

aroblem
ld

.
ri o w
Mo on St To Leod

be
ptimes
ld cre

can

G
B
)
o
ed Ces S

assure solving
A

t
re lat ot ighd
d Secs

therefore
eliminated
e nP N T e
r e a t r t r rp s
Sc Peld Wnog Oul or Wa de n 1 1 1
ve rneg idi nicna ift ylintio

guideting
i
‫ކ ކ‬

c
i d c
[
ss

,iist
cSt e R a o L C ne
‫އ‬

1 1

to
ce ayre re echess n
Ex Plcor in Sc M kn Coo ws

troubleshoo
tr NOTE
:Many
v e r
h i c
o n c re
O T C n ! S ed
o tle ad ow

problem
re
To Lit h Le d Cr wn in Sc ed
o c a r o r e
To Mu Leshe Cr ed in Sc ed
Item

n i e o d st
Fidering Sepws ToloaFa
,
investigated

1
Correction

e a t r e r l
Fetu Sc d Ov ria
Surface Short Waves R)( ipples

l uc e a f ate
pavor

F H o M
Outside

.be
Streaks

Transverse)(Checking

.
CenterStreak

Nonuniform
Mat

Responding

to the
indicate related
Long s

Poor paction
Width
Wave

tion
Mat
Transverse

problerns
Full

Under
Roller
Fat ts in
Longitudinal
Not

other
to
Poor Joint

Cracking

Compac

Checks
to

causes
Joint
Precom
PROBLEM

Spo

Mix
Shadows

Find above

Mat
Tearing

Auger
Surface

Screed Marks
-
-

Shoving

problem.
Texture
-

indicate
of Mat
-

Roller Marks
Mat

Bleeding
of

101
X's
Tearing
Tearing

or
Screed

Figure
of

.
Wavy
Wavy

Poor

Poor
Mat

Mat

.2
1.

Page 3-90
AC 150/5370-14
10/15/91 Appendix 1

long-wave roughness, particularly if the haul truck problems can be detected by shutting off the grade
bumps into the paver or if the truck driver holds the controls and determining whether or not the long or
brakes while the truck is being pushed by the paver. short waves continue to be formed . If the grade con-
One final factor can be the condition of the underlying trols are at fault, the operation and maintenance manual
surface; the long waves may be a reflection of the waves supplied with the controls should be consulted to
in that base material. determine the proper corrective action to take. Sags in
Long waves can also be found at the points where a stringline reference can be found by sighting down the
the compaction equipment reverses direction . This line as the grade sensor wand passes along the string.
problem will be most prevalent when the asphalt layer Short or long waves caused by the mechanical condition
being placed is greater than about 4 in . thick. The or operation of the paver screed can usually be detected
problem may be enhanced when the maximum -size by careful observation of the paver during mix laydown.
coarse aggregate used in the mix is relatively small The long waves formed by incorrect haul truck operation
compared with the lift thickness. The waves are caused and/or incorrect compaction equipment operation can
by the bow wave that forms in front of the roller. also be detected easily by spending a few minutes
In terms of mix design, long waves can be caused by watching each of these processes.
truckload-to-truckload segregation of the mix and by If washboarding is caused by the incorrect operation
changes in mix temperature. Both of these deficiencies of the vibratory roller, a change should be made in the
cause the forces on the screed to vary, causing, in turn , vibratory amplitude setting, the vibratory frequency,
a wavy surface. Compaction equipment can also create and/or the speed of the roller. This problem is discussed
a wavy mat if the roller operator turns or reverses the in detail in the section on compaction techniques.
machine too abruptly.
Roughness or washboarding is normally caused by Performance
improper operation of the vibratory roller. This type of Long-term pavement performance is affected by
equipment should be operated at as high a frequency as surface waves, both short and long, in two primary ways.
possible and at an amplitude related to the thickness of First, the waves reduce the smoothness of the pavement,
the layer being compacted ; usually a greater amplitude which lowers the pavement condition rating or present
setting for a thicker layer of mix and a lower amplitude serviceability index of the roadway. Structural perfor-
setting for thinner lifts of material. Further, the wash- mance of the pavement may be changed , however, only
board effect can be worse if the roller is operated at a if the waves are severe enough to increase the dynamic
high speed, particularly if the frequency setting is less or impact loading of the pavement under heavy truck
than 2400 vibrations/min. traffic. Second, short waves and the factors that cause
the short waves can affect pavement density levels . A
Solution tender mix is generally more difficult to compact proper-
Short waves can be cured only by preventing their ly than is a stable mix. This may result in a decrease in
formation. The most important factor for short waves density and a corresponding increase in air void content .
is to keep the amount of mix (head of material) in front Washboarding is basically roughness built into the
of the screed as consistent as possible . In addition, the pavement surface during the compaction operation. As
stiffness of the mix that is related to both its tempera- it affects the degree of density obtained during the
ture and its composition should be maintained as compaction process, this type of defect can reduce the
constant as feasible. The amount of mix is controlled by long-term durability of the pavement layer. In addition,
the proper setting of the hopper flow gates and by it contributes to a rough ride for the vehicles using the
keeping the slat conveyors and augers operating as much pavement.
of the time as possible (close to 100 percent) while the
machine is moving forward . Mix stiffness is controlled TEARING
at the asphalt plant by keeping the mix temperature, Description
aggregate gradation, and fluids content (asphalt content There are three types of mat tearing or pulling of the
plus moisture content) within normal specification limits. asphalt mix under the screed of the paver. Each of the
Any factors that cause either the volume or the stiffness types is described by the location of the tear marks in
of the mix at the screed to change can cause short waves the mat: (a) in the center of the lane, (b) on the outside
in the asphalt concrete mat. edges of the lane, and (c) full width. Tearing of the mat
Surface waves caused by automatic grade-control is usually caused by improper paver condition or opera-

Page 3-91
AC 150/5370-14
Appendix 1 10/15/91

tion, by a cold mix temperature, or by a compacted mat thickness that is less than twice the depth of the maxi-
thickness that is less than twice the maximum size of the mum aggregate, can be cured by preheating the screed
aggregate used in the mix. properly before paving commences, increasing the mix
temperature, replacing the warped or worn-out screed
Cause plates, or increasing the lift thickness, respectively.
The screed on the paver should be adjusted to
provide the correct degree of crown . The appearance of Performance
streaks behind the screed is primarily caused by an Tearing of the mat affects the long-term pavement
improper relationship between the crown at the leading performance by causing changes in mixture density in
(front) and trailing (back) edge of the screed. A tearing areas where the tearing has occurred . Torn areas may
or open texture of the mat several feet wide in the appear segregated and are usually deficient in mix
center of the mat may be caused by a lack of lead crown quantity. Depending on the severity of the tearing,
in the paver screed . Conversely, a tearing or open pavement performance will be reduced in relation to the
texture along both outside edges of the asphalt mixture degree to which the tearing reduces the density and
is normally caused by an excess of lead crown in the increases the air void content of the mat. In addition,
screed. For most mixes, the lead crown of the screed the torn areas will be more susceptible to raveling and
should be set slightly greater than the tail crown . The also to the effects of moisture (stripping) in those areas.
proper relationship between lead and tail crown results
in a uniform texture of the mat across its full width. NONUNIFORM TEXTURE
Center streaks, 6 to 8 in. wide, can be caused by a Description
lack of asphalt material being tucked under the auger Nonuniform mat texture (Figure 3-102) can be
gearbox area at the center of the auger chamber . This described as differences in the appearance of the mix,
could be the result of improper flow gate settings: not both transversely and longitudinally, as the mix is placed
enough mix being fed back to the screed . It is more and compacted. Normally, minor differences in surface
likely to be caused by missing, worn, or improperly set texture will be apparent because of differences in the
reverse augers or paddles on the augers that are used to alignment of the larger coarse aggregate particles as the
force mix underneath the gearbox. Edge streaks can be mix passes out from beneath the paver screed . ' Addi-
formed by improper flow gate settings or by incorrect tionally, a mix with a higher fine aggregate (sand)
installation of the screed extensions . content will have a more uniform surface texture than a
Full-width tearing of the mat can be attributed to a mix containing a larger percentage of coarse aggregate.
number of different factors. Tearing can occur because
of warped or worn-out screed plates . If the forward Cause
speed of the paver is too great for a particular mix, Many factors concerning the operation of the asphalt
tearing can occur. The use of a mixture with aggregate paver affect the uniformity of the surface texture of the
that is large compared with the mat thickness being mix. A variable amount of mix against the screed,
paved can be responsible for tearing of the mat . Cold caused by overloaded augers or running the hopper
mix temperatures, particularly when combined with a empty between truckloads, can cause variations in the
cold paver screed , can significantly affect the amount of amount of mix tucked under the screed and thus produc-
tearing that will occur. In addition , if the thickness of es a nonuniform texture. Improper screed maintenance,
the layer being placed is less than twice the size of the including worn or loose screed plates, screed extensions
maximum aggregate used in the mix, full-width tearing incorrectly installed , or low screed vibratory frequency,
can occur. may alter the mat texture significantly and cause non-
uniformity. A low mix temperature, caused either by
Solution plant problems or by the paver sitting too long between
Constant center or outside edge mat tearing usually truckloads of mix, can also be a factor in obtaining
can be eliminated by adjusting the relationship between uneven mat texture, especially if the paver screed is also
the lead and tail crown on the paver screed . If this cold .
change does not solve the problem, the setting of the When the compacted layer thickness is less than two
paver flow gates should be modified . Full-width tearing, times the dimension of the largest aggregate particles,
which is normally caused by a cold screed, cold mix tearing of the mat and nonuniform surface texture
temperature, worn screed plates, or a compacted mat result. A good rule of thumb for the relationship

Page 3-92
AC 150/5370-14
10/15/91
Appendix 1

compacted thickness of the mat being placed should be


designed so that it is at least twice the size of the largest
coarse aggregate piece used in the mix. Finally, a mix
that is tender, variable in aggregate gradation or asphalt
content, or easily segregated should be modified to
improve its characteristics before it is delivered to the
paver for laydown .

Performance
Nonuniform surface texture usually goes together
with nonuniform density. Areas in which the coarse
aggregate has been dragged by the paver screed or in
which segregation of the mix has occurred will generally
have a lower density after the application of the same
compactive effort by the rollers. As density decreases
and air void content increases, the durability and service-
ability of the asphalt concrete mat decrease markedly.

SCREED MARKS
Description
Screed marks are transverse indentations in the
asphalt mat . They occur when the paver stops between
truckloads of mix (Figure 3-103) . Depending on the
mixture being placed, some screed marks are barely
Figure 3-102. Nonuniform mat texture (J. Scheroc- noticeable, whereas some can be very deep. Screed
man). marks can also occur in the longitudinal direction when
rigid or hydraulic extensions are used (Figure 3-104) .
between maximum aggregate size used in the mix and
the minimum compacted course thickness is that the Cause
depth of the compacted layer should be at least twice There are several causes of transverse screed marks .
the largest coarse aggregate particle size . Thus a mix One is excessive play in the mechanical connections on
containing a 3/4-in. top-size aggregate should be placed the screed. If this is the problem, the screed marks will
at least 1 1/2 in. thick. be visible each time the paver stops. A second cause of
A soft or yielding base under the course being con- screed marks is when the screed is set up incorrectly and
structed may cause a variable surface texture for the new rides heavily on its rear edge. Another cause is the haul
layer. Obviously, segregation of the mix caused by poor truck bumping into the paver when preparing to dis-
mix design or improper handling of the mix during the charge the mix, and/or the truck driver holding the
mixing, loading, hauling, unloading, or placing opera- brakes on the truck when the paver starts to push the
tions can contribute to a nonuniform surface texture. truck. In this case, the screed marks will appear only
The variability of the texture will also be affected by any when the truck-paver interchange is improper. An
factors that cause nonuniformity in the mix, such as asphalt mix that is very tender will be indented by the
deviations in aggregate gradation, asphalt content, or paver screed, particularly if the screed is heavy, such as
mix temperature . a screed with hydraulic extensions or with several rigid
extensions.
Solution Longitudinal screed marks are caused by improper
The causes of nonuniform surface texture are many, setting of the screed extensions relative to the main
and thus the solutions to the problems are many. Paver screed . When extensions are used , the vertical position
operation, particularly in regard to the need for a con- of the extension and the angle of attack of the extension
stant head of material in front of the screed, should be must be the same as that of the primary paver screed .
monitored closely. The paver and screed should both be If rigid extensions are set at the wrong elevation, a
well maintained and in good operating condition . The longitudinal mark will occur at the point where the

Page 3-93
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-103. Transverse screed marks on one side of an extendable screed (J. Scherocman).

screeds are joined . If hydraulic extensions are used, two segregation.


longitudinal marks may occur--one at the end of the Longitudinal screed marks caused by improper
main screed and/or one at the inside edge of the exten- setting of the elevation of the extensions can be elimi-
sion on each side of the machine. nated by correcting the position of each extension
relative to the main screed . Adjustments to both the
Solution vertical position and the angle of attack of the exten-
If the transverse screed marks are a result of the sions may be needed .
mechanical condition of the paver screed or improper
setup of the screed, the screed should be repaired . If Performance
the screed marks are caused by the truck bumping into Transverse screed marks generally are not detrimen-
the paver, the laydown operation should be altered so tal to the durability of the mat. They may, however,
that the paver picks up the haul truck instead of the affect the ride, creating a bump whenever the marks
truck backing into the paver. In addition, once the cannot be rolled out completely by the compaction
paver establishes contact with the truck, the truck drivers equipment. In many cases, the screed marks affect the
should apply only enough pressure to the brakes to keep overall performance of the mix less than does the
the truck in contact with the paver. slowdown and startup of the paver when the operator
The development of screed marks, particularly if the attempts to keep the paver moving as the empty truck
mix is very tender, can be eliminated by not stopping the pulls away from the paver and the loaded truck backs
paver between truckloads of mix. This can be accom- into the hopper .
plished by using a windrow elevator or material transfer Longitudinal screed marks indicate that the level of
vehicle to deliver mix to the paver hopper. If dump the mix under the extension is different from the level of
trucks are used to haul the mix, however, it generally is mix under the main screed . If the screed marks are
better paving practice to stop the paver between truck- severe, differential compaction may occur across the
loads of material (stopping and restarting the paver as "joint," with the compaction equipment initially riding on
quickly as practical) instead of allowing the opportunity the higher mat. If not able to be completely rolled out,
for the paver operator to run the paver hopper dry, the longitudinal screed marks can leave a ridge in the
reduce the head of mix in front of the paver screed, and mix.
increase the opportunity for truckload-to-truckload

Page 3-94
AC 150/5370-14
10/15/91
Appendix 1

screea lift cylinders or loose connections on the thick-


ness-control cranks will cause the screed to be unrespon-
sive. If automatic grade controls are used, an incorrect
sensor location will cause the screed to be unable to
react to input signals from the grade sensors. If the
maximum aggregate size used in the mix is too great
compared with the depth of mix being placed , the screed
will ride on or drag the largest aggregate pieces. The
screed, therefore, cannot change angle and is thus
unresponsive to changes in the thickness-control settings.
Variations in mix temperature also cause the screed to
be unresponsive to angle-of- attack changes, because the
mix stiffness variations themselves are causing the screed
to continually seek new equilibrium levels for the forces
acting on it.

Solution
The paver and screed must be in good operating
condition. The sensor for the automatic grade controls
must not be located at either the tow point or behind
the pivot point of the screed; the sensor should be
placed in the area between one-third and two-thirds of
the length of the leveling arm. If the mix texture is
uniform (indicating a proper relationship between course
thickness and maximum aggregate size) , the screed will
be able to respond to changes in the settings on the
thickness controls.

Figure 3-104. Longitudinal screed marks between


Performance
main and extendable screed (J. Scherocman).
An unresponsive screed causes a rough asphalt mat .
The screed is unable to react to manual changes in the
SCREED RESPONSIVENESS thickness settings and also loses its ability to self-level an
Description existing pavement surface by being unable to reduce the
As the thickness-control cranks on the screed are amount of mix placed over the high points in that
changed, the angle of attack of the screed is increased or surface and increase the volume of material placed in
decreased . As the paver moves forward to place the the low areas. Thus, the rideability of the course being
mix, the screed moves up to or down to the new equilib- placed can be affected significantly by the unresponsive-
rium point for the new mat thickness. When the screed ness of the paver screed .
fails to respond to changes in the thickness-control
cranks, the operator is unable to alter the depth of the SURFACE SHADOWS
layer being placed . The paver also loses its inherent Description
ability, through the principle of the floating screed , to Surface shadows are dark areas (Figure 3-105) that
provide the self- leveling action needed to place a smooth appear in the surface of an asphalt concrete mix. In
asphalt mat. most cases, the surface shadows cannot be seen until
sometime after the asphalt concrete mix has been used
Cause by traffic and some of the asphalt cement film has been
An extremely fast paver speed (more than 80 ft/min worn off the exposed aggregate particles by the vehicle
for thin lifts or more than 50 ft/min for layers more than tires. Auger shadows are seen most easily under certain
2 1/2 in. in depth) may cause a lack of responsiveness of sunlight conditions--when the sun is low on the horizon
the screed. The mechanical condition of the screed and the pavement is viewed when looking into the sun.
affects the screed reaction . The screed riding on the In severe cases, however, they may be visible immediate-

Page 3-95
AC 150/5370-14
Appendix 1 10/15/91

surface texture associated with the loca-


tion of the surface shadows . They can
only be seen from an angle; when viewed
from directly overhead, the shadows
usually cannot be seen. The intensity of
the shadows is often increased when a
tender mix is being laid.

Solution
The asphalt concrete mixture carried
in the auger chamber should be main-
tained at a level near the center of the
auger shaft. This means that the flow
gates should be set so that the augers
Figure 3-105. Surface shadows (J. Scherocman) .
operate as close to 100 percent of the
time as possible and the stopping and
starting of the augers is minimized. In no case should
ly behind the screed during the laydown operation . the top of the augers be completely covered with mix.
Even in this latter case, the shadows will "disappear" Further, the location of the screed should be set as far
when the mix is being compacted by the rollers. The forward as possible so that the amount of material in the
auger shadows may be completely across the lane width auger chamber is reduced and the head of material in
being placed or they may be only partway across the front of the screed is kept to a minimum.
width.
Performance
Cause
Surface shadows are not necessarily detrimental to
Surface shadows are caused primarily by overloading the mix except as they may affect rideability in a minor
the augers on the paver. If the head of material in the way. The difference in density of the mix in areas where
auger chamber is so great as to "bury" the augers, the the shadows are present and between the shadows is
screed will react to the variable forces acting on it. The generally not enough to be determined accurately. The
spacing between the shadows will normally correspond main concern with surface shadows is the visual appear-
to the starting of the augers when those augers are ance of the mix to the vehicle driver.
operated in a stop-start manner. Whenever the amount
of mix in front of the screed is at or above the top of PRECOMPACTION LEVELS
the auger, the shadows will be formed and ultimately be Description
seen in the asphalt concrete mix. A modern asphalt paver normally is equipped with a
On most pavers it is possible to adjust the distance vibratory screed . This type of screed allows the mix to
between the screed and the tractor unit. This is accom-
be compacted partially as it passes beneath the screed.
plished by unbolting a connection on the leveling or tow Depending on such variables as forward paver speed,
arm of the paver and moving the tractor forward (or layer thickness, mix temperature, and ambient environ-
backward) with the screed sitting stationary on the mix. mental conditions, the density of the asphalt concrete
Depending on the make and model of the paver, there mixture measured behind the paver screed before roller
is typically a 4-in. length of slide for the screed connec- compaction is usually in the range of 70 percent to 80
tion. The severity of the surface shadows may be percent of the theoretical maximum density (a voidless
increased with the screed in the back position--when mix) .
more mix is being carried in the auger chamber and the Some pavers are equipped with combination screeds:
augers are being overloaded . screeds that have both tamper bars and vibratory mecha-
The dark areas, or shadows, are thought to be the nisms. At slow paver speeds, the degree of compaction
result of a slight increase in mix density caused by the achieved in the mix by the combination screed is typical-
startup of the augers and the forcing of additional mix ly greater than that obtained by the vibratory screed
under the screed at the time the augers begin turning alone. At paver speeds greater than 25 ft/min, however,
again after being stopped . There is no difference in the increased effectiveness of the tamper bar compactive

Page 3-96
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-106. Excessive raking of transverse joint (J. Scherocman) .

effort is lost and the degree of compaction obtained by the number of roller passes needed to meet the density
the combination screed is similar to that achieved with and air void content criteria if the amount of precom-
a normal vibratory screed . paction obtained by the screed is higher. In addition,
increased precompaction density can reduce the amount
Cause of differential compaction that will occur in low spots
The amount ofprecompaction obtained by the paver and rutted areas.
screed decreases as the paver speed increases. It
increases somewhat as the frequency of the screed JOINT PROBLEMS
vibration increases. Precompaction will decrease signifi- Description
cantly, however, if the paver screed is riding on the Poor transverse joints (Figure 3-106) are associated
screed lift cylinders, thereby limiting the available either with a bump at the joint, a dip in the pavement
compactive effort . The level of precompaction obtained surface several feet beyond the joint, or both. Poor
will be further limited if the mat is too thin for the longitudinal joints (Figure 3-107) between passes of the
maximum aggregate size used in the mix, if the mix paver are usually characterized by a difference in eleva-
being placed is too cold, or if the base on which the new tion between the two lanes, by a raveling of the asphalt
layer is being laid is soft and yielding. at the joint, or both. The area adjacent to the longitudi-
nal joint is usually depressed below the level of the
Solution surrounding pavement surface .
Decreasing the paver speed and increasing the
frequency of vibration of the paver screed should in- Cause and Solution
crease, within limits, the level of precompaction achieved As discussed in Section 5 on joint construction, the
during the laydown operation . It is also possible on key to a good transverse joint is to start the paver with
some pavers to increase the amplitude of the vibration the screed sitting on blocks on the cold side of the joint.
in order to increase the impact force of the screed on The thickness of the blocks is related to the depth of the
the mix. Proper maintenance of the screed also helps course being laid. The second factor is to do only the
obtain a uniform compactive effort from the screed . amount of raking necessary to form the joint properly.
Finally, the joint should be compacted by rolling it in a
Performance transverse direction, if possible . The key to a good
As long as the required density level is obtained longitudinal joint is the amount of overlap of the new
using conventional rollers behind the paver, the absolute mat over the adjacent cold material. If the overlap is
level of precompaction accomplished by the screed will not greater than 1 to 1 1/2 in., minimal raking is neces-
not affect the long-term performance of the asphalt sary, and the compaction equipment will be able to
concrete layer. It may be possible, however, to reduce densify the mix at the joint properly.

Page 3-97
AC 150/5370-14
Appendix 1 10/15/91

used for breakdown rolling. If a pneumatic tire roller is


followed by any type of static steel wheel roller when the
mat temperature is too high, however, that steel wheel
roller may introduce the check marks into the mix if the
mix is tender. Checking is not normally caused by "over-
rolling" of the mix by the compaction equipment . The
checks typically do not extend completely through the
course but normally are only 1/2 to 3/8 in . in depth.

Cause
Checking can be caused by two primary factors: (a)
excessive deflection of the pavement structure under the
compaction equipment and (b) a deficiency in the
asphalt concrete mix design. In the former case, the
pavement on which the new asphalt concrete layer is
being placed is weak. The weight of the rollers causes
the pavement layers to bend excessively, placing the new
mix in tension at the surface. The check marks are then
formed when the surface of the new mixture is pulled
Figure 3-107. Excessive raking of longitudinal joint (J. apart as the pavement deflects during the rolling opera-
Scherocman). tion.
A more prevalent cause of checking is a deficiency in
Performance the asphalt concrete mixture: (a) an excess of fluids in
A poor transverse joint will not affect pavement the mix: too much asphalt cement or too much moisture
performance to any significant degree if proper density in the mix, or both; (b) a nonuniform sand gradation:
levels are obtained by the compaction equipment . A too much middle-size sand [ No. 16 and No. 30 ( 1.18 mm
poor ride will usually be the only negative result . An and 600 μm) sieve size material] and too little fine size
improperly constructed longitudinal joint, however, can sand [ No. 50 and No. 100 (300 μm and 150 μm) sieve
seriously decrease the serviceability of the pavement size material] ; and (c) a lack of room in the aggregate
structure. A poorly placed and compacted joint will gradation for the asphalt cement (low voids in mineral
ravel and cause one side of the joint to be lower than aggregate--VMA) . The excess of fluids makes the mix
the other side. If the density level is too low, it is tender and allows it to be displaced easily by the com-
possible for the whole pavement layer thickness at the paction equipment. The hump in the fine aggregate
longitudinal joint to wear away under the action of gradation curve also causes the mix to be tender. Mixes
traffic. A poor joint will also be porous, allowing water that are low in voids in mineral aggregate content will
to enter the underlying pavement courses. generally be tender and move easily under the force of
a vibratory or static steel wheel roller. Further, the
CHECKING various characteristics of the aggregate such as surface
Description texture, crushed content, and amount of dust coating can
Checking can be defined as short transverse cracks, play a role in the amount of checking that occurs.
usually 1 to 4 in. in length and 1 to 3 in. apart, which The mix tends to be shoved by the roller instead of
occur in the asphalt concrete mat (Figure 3-108) . These being tucked under the drums or tires of the compaction
surface cracks, or checks, are not visible when the paver equipment. The potential for checking is characterized
places the material. The cracks may occur after the by a bow wave that occurs in front of the drums on a
second or third pass of the compaction equipment over steel wheel roller. The mix deficiency is compounded,
the mix or after several passes of the roller when the and the amount of checking that occurs is increased,
mix is approaching the design density level, particularly when the mix temperature is too high for the particular
when a static steel wheel roller is employed for the asphalt cement grade being used in the mix. As the mix
breakdown rolling. Rarely does the checking appear temperature increases, the viscosity of the asphalt
after only one pass of the breakdown roller. Checking cement decreases, causing the mixture to be more
typically does not occur when a pneumatic tire roller is tender. An additional factor that can affect the degree

Page 3-98
AC 150/5370-14
10/15/91
Appendix 1

Figure 3-108. Checking of the mix (J. Scherocman) .

of checking that occurs is the temperature susceptibility ing the asphalt content or reducing the moisture content
of the asphalt cement itself. by drying the aggregates properly. In addition, the
Occasionally, checking can be caused by temperature temperature of the mix at the plant can be reduced, but
differentials within a layer of asphalt concrete mix (heat this might increase the amount of moisture left in the
checking) . On a cool day and under windy conditions, mix. Other changes, however, might be time-consuming
it is possible for the mix that is in contact with the and expensive, such as altering the fine aggregate grada-
existing pavement surface to decrease in temperature tion to remove the hump from that portion of the
quickly. In addition, the top surface of the mix will also grading curve or changing the gradation of the aggregate
cool quickly. The temperature of the mix in the middle to increase the amount of VMA in the mix. Care
of the layer, however, is still high. This temperature should be taken, however, in making arbitrary adjust-
differential can sometimes cause the mix to check under ments to the mix design without determining how the
the compactive effort of the rollers. mix design changes affect the long-term mechanical
There are also a number of secondary causes of properties and performance of that mixture.
checking. Included are a mix whose temperature is too In the short term, if checking develops under the
high; the mix overheated in the plant. In addition, compaction equipment, changes in both the rolling zone
improper rolling techniques can cause checking: rolling and in the type of rollers used to densify the mix can be
too fast, stopping too quickly, making sharp turns on the made to reduce the amount of checking obtained . If the
hot mat, or making an excessive number of passes with mix is tender because of excess fluids, a problem with
the finish roller or finish rolling with the mat still at an the fine aggregate gradation, or lack of VMA, it may be
elevated temperature . Finally, checking may be en- possible to densify the mix at an elevated temperature
hanced by a poor bond between the new mat and the without causing the checking. By delaying compaction,
underlying surface because of a dirty surface or the lack the mix has a chance to cool and the viscosity of the
of a tack coat. asphalt cement increases. This, in turn, stiffens the mix
and decreases its displacement by the rollers. The delay
Solution in rolling, however, may reduce the opportunity, for
Because checking is generally a mix-design-related some mixtures, to obtain the required level of density in
problem , the proper long-term solution is to change the the mix. Thus the problem concerns how to obtain the
mix properties. Quick mix changes might include reduc- proper compaction in the mix while the mix is moving

Page 3-99
AC 150/5370-14
Appendix 1 10/15/91

under the compaction equipment. With a tender mix, it commences.


may not be possible to accomplish both objectives (no None of the solutions to the checking problem will
checking and adequate density) at the same time. always work. Each mix will have its own compaction
Depending on the cause of the mix tenderness, some characteristics . For some very tender mixes, checking
mixes can be adequately compacted at lower than may occur at a wide range of temperatures, even as low
normal mix temperatures. In some cases, because of the as 150°F. For other mixes, checking may occur only at
properties of the aggregate and the asphalt cement in more elevated temperatures. In general, mixes that lack
the mix, the effective compaction temperature range internal stability will check under the steel wheel rollers
may shift downward by as much as 50°F and adequate and should not be used--the mix should be redesigned.
density can be obtained even at relatively low compac-
tion temperatures. This means that the rolling zone (the Performance
distance between the paver and the breakdown roller) is Although the cracks or checks extend only a short
increased and the mix is permitted to cool more before distance down from the surface, they are detrimental to
the initial compactive effort is applied . The feasibility of long-term performance, because the tender mix charac-
this solution to the checking problem is determined by teristics affect the level of density obtained . If the
two factors: whether checking is eliminated or signifi- rollers are kept back from the paver to attempt to
cantly reduced during the delayed rolling procedure and decrease the amount of checking that occurs, and if the
whether an adequate level of density is obtained . A level of density obtained by the compaction equipment
roller combination test strip should be constructed to is thus reduced, checking can decrease the ultimate
determine the proper rolling zone to be used. The pavement life significantly, because the air void content
density level obtained should be checked with both a of the asphalt concrete mat is increased . A mix that
nuclear density gauge and with cores cut from the contains check marks is one that has significant potential
roadway. If the density level achieved is proper and if to have reduced pavement life under traffic.
the amount of checking obtained is significantly reduced ,
the delayed rolling procedure can be used to overcome SHOVING
the problem. Description
Another solution is to change the roller type and Shoving of an asphalt concrete layer is the displace-
pattern being used to compact the mix. If a static steel ment of the mixture in a longitudinal direction . It can
wheel roller is being used in the breakdown position, it take place during the compaction operation or can occur
should be removed and either a pneumatic tire roller or later under traffic. In most cases, shoving is accompa-
a vibratory roller used as the initial compaction machine. nied by a large bow wave in front of the breakdown
On some very tender mixes, even when a pneumatic tire roller, particularly if that roller is a static steel wheel
roller or a vibratory roller is used in the breakdown machine. Shoving may also occur in conjunction with
position, checking may still occur if a steel wheel roller mix checking if the mix is tender enough because of the
is used as the intermediate roller. Some benefit, in aggregate gradation or excess fluids (asphalt cement
terms of "healing" the cracks, may also be obtained by and/or moisture) content deficiencies. Finally, mat or
using the pneumatic tire roller in the intermediate or in mix shoving can happen at the reversal point of the
the finish rolling position . In general, however, it is rollers, especially at the location closest to the paver .
often more effective and efficient to use the pneumatic
tire roller in the breakdown position because checking Cause
rarely occurs under this piece of compaction equipment. Shoving is caused primarily by an unstable or tender
The level of density obtained with the change in roller mix. This instability can be caused by the same variables
type and pattern must be checked through the use of a that cause checking: an excess of fluids (asphalt cement
roller compaction test strip together with nuclear density and/or moisture) in the mix, a hump in the fine aggre-
gauge readings and core density determinations . gate grading curve, the properties of the aggregates and
If the mix delivered to the paver is too hot, the mix the asphalt cement, or excessive mat temperature during
should be allowed to cool to normal laydown tempera- rolling. A mix that has a high Marshall stability can still
ture before the compaction process is started . Improper be a mix that will distort longitudinally under the
rolling techniques should be corrected . The surface of compaction equipment and later under traffic. Shoving
the underlying pavement surface should be clean and can be very prevalent when a sand mix is placed in a
properly tack coated before placement of the new mix thick layer (more than 1 1/2 in . ) at a high temperature

Page 3-100
AC 150/5370-14
10/15/91
Appendix 1

(more than 280°F) . Further, thicker lifts in proportion Tender mixes should be placed at lower laydown tem-
to the maximum-size aggregate used in the mix will tend peratures, consistent, however, with the ability to obtain
to shove more than thinner lifts with the same aggregate sufficient density under the rollers. Sand mixes, because
grading. of their inherent tender nature, should be placed in
Improper roller operation, particularly sudden several thin layers instead of one thick layer when used
reversal of the roller, can also be a contributing factor as base or binder courses.
to the shoving of the mix during construction. If a The compaction equipment should be operated
vibratory roller is run at too great a speed and the properly so as to reduce the opportunity to displace the
impact spacing is too great, the mat may develop a mix during the rolling operation. Further, if the under-
washboard effect where the peak-to-peak distance is the lying pavement surface is dirty, it should be cleaned and
impact spacing. Washboarding or shoving is more likely a proper tack coat applied.
to occur at normal frequencies but at high speeds where
the impact force is greater. If a pneumatic tire roller Performance
with high tire pressure is used for breakdown compac- Mats that tend to shove under the compaction equip-
tion, a tender mix may shove laterally under the tires. ment are basically unstable. These mixtures, under
Shoving can occur under any roller if the roller is traffic, usually will continue to distort, both longitudinal-
operated improperly. ly and laterally. Shoving of the asphalt concrete mixture
Another possible cause of shoving is an excess of during construction is a strong indication that the pave-
tack coat material that may be pulled into the mix. In ment will not perform properly under traffic.
a similar manner, excess asphalt from a bleeding under-
lying surface or from joint filler material can be pulled BLEEDING AND FAT SPOTS
into the mix and increase its fluidity and tenderness. Description
Shoving may also occur when the underlying surface is Fat spots in an asphalt mixture (Figure 3-109) are
dusty or dirty--a slippage-type failure . isolated areas where asphalt cement has come to the
surface of the mix during the laydown and compaction
Solution operation. These spots can occur very erratically and
The cure for a mix that shoves under the compaction irregularly, or they may be numerous and in a fairly
equipment is to increase the internal stability of the regular pattern. Bleeding of an asphalt mixture (Figure
mixture . This can be accomplished by reducing the 3-110) occurs when the asphalt cement flows to the top
fluids content (either asphalt content or moisture of the mix surface under the action of traffic. Bleeding
content or both) of the mix, but only after determining is often seen as two flushed longitudinal streaks in the
the effect of a change in asphalt cement content on the wheelpaths of the roadway.
mechanical properties of the mix. It can also be done by
increasing the internal friction among the aggregate Cause
particles by changing the aggregate gradation or increas- Fat spots are caused primarily by excessive moisture
ing the amount of angular (crushed) particles in the mix. in the mix. The problem is more prevalent with mix-

Figure 3-109. "Fat" spots in mix (J. Scherocman).

Page 3-101
AC 150/5370-14
Appendix 1 10/15/91

Figure 3-110. Bleeding (and rutting) in the mix (J. Scherocman) .

tures that contain high percentages of fine aggregate binder material, bleeding can occur as the mix is dens-
(oversanded mixes) and on mixtures that contain aggre- ified by traffic, both shortly after construction and at
gates that have a high porosity. If all the moisture in later time periods. The traffic compaction process will
the coarse and fine aggregate is not removed during the decrease the air void content of the mix and may, in
drying and mixing operation at the asphalt plant, the turn, squeeze some of the asphalt cement out of the mix.
moisture will pull asphalt cement to the surface of the The "extra" asphalt will appear as a longitudinal streak
mix behind the paver as the moisture escapes from the or fat spot throughout the length of each wheelpath.
mix and evaporates. Fat spots occur more frequently One additional possible cause of bleeding is the
when the aggregate stockpiles are wet or when the condition of the pavement layer on which the new mix
moisture content varies in different parts of those stock- is placed. If the underlying layer has excess asphalt on
piles. Fat spots can also be associated with segregated its surface or excess crack seal material in the cracks and
areas in the mix. If the mix deposited on the roadway joints, some of this material can be drawn up through a
by the paver is segregated , areas where excess asphalt thin new mix layer. Further, if too much tack coat is
cement is present in the mix can result in free binder applied to the original pavement layer, the excess
material on the top of the layer being placed . material can be pulled up through a thin overlay and
The cause of bleeding can normally be divided into contribute to the bleeding problem.
two categories. The first cause is related to an excess of
fluids in the asphalt mixture, either asphalt cement or Solution
moisture or both. Under traffic, the extra moisture and A wide fluctuation in the asphalt mix temperature is
asphalt cement will be pulled to the surface by passage an indication that the moisture content of that mix may
of the vehicle tires. This bleeding phenomenon usually also be variable . This latter phenomenon can contribute
occurs on new mix and during hot weather when the to both the generation of fat spots in the mix during
viscosity of the asphalt cement is at its lowest level. construction and bleeding of the mix later under traffic.
Typically the bleeding will occur shortly after traffic is It is important, therefore, that the aggregate used in the
allowed to travel over the fresh mix, while there is still mix be dry and that the moisture content of the mix,
some moisture in the mix and while the viscosity of the upon discharge from the asphalt plant, be as low as
asphalt cement binder is still relatively low. possible but not more than 0.5 percent. Extra care in
Bleeding can also be associated with a lack of ade- drying needs to be exercised when producing mixtures
quate room in the mix for the asphalt cement. If the that incorporate highly absorptive aggregate. Bleeding
voids in mineral aggregate content and the air void problems caused by excess asphalt cement in the mix can
content of the mix do not provide enough room for the most easily be solved by reducing the asphalt content of

Page 3-102
AC 150/5370-14
10/15/91
Appendix 1

mix consistent with other mixture properties such as air the longitudinal indentations that remain in the surface
voids, voids in the mineral aggregate , and stability. of the mix after the final rolling has been completed
Bleeding problems that occur in conjunction with pave- (Figure 3-111 ).
ment rutting may only be solved , however, by a complete Roller marks also exist in the asphalt surface when
redesign of the asphalt mixture with emphasis on the air any roller is parked on the hot mat for a period of time
void content and the voids in mineral aggregate criteria. or when a vibratory roller is vibrated in place. Particu-
larly when used in the breakdown position, pneumatic
Performance tire rollers can leave visible longitudinal marks that can
Fat spots in the mix, if there are only a few of them, still be seen after the finish rolling has been completed .
should not affect the ultimate durability of the mixture Vibratory washboard marks may be visible if that roller
to a significant degree. A great number of fat spots or is operated at an improper vibratory amplitude or
bleeding in the wheelpaths does affect pavement perfor- frequency setting.
mance because of variable asphalt and air void contents
in different parts of the mix. In addition, other mix Cause
problems, such as shoving, rutting, and loss of skid Roller marks can be an indication that the proper
resistance, can occur in a mix that contains many fat number of roller passes have not been made on the mix.
areas or bleeding in the wheelpaths . The design of the If the compaction process is halted before the required
asphalt mixture, the operation of the asphalt plant (more amount of rolling is completed or if the mix cools before
complete removal of the moisture), or both should be the compaction process is completed , the longitudinal
checked to assure adequate pavement performance marks or creases made by the rolling process will still
under vehicular loading. remain in the mix.
Roller marks left in an asphalt layer also can be an
ROLLER MARKS indication of a tender mix. The roller operator will
Description normally be unable to remove all the marks left by the
During the compaction process by the breakdown compaction equipment if the mix is tender or unstable.
and intermediate rollers, whether static steel wheel, A tender mix normally will not support the weight of the
vibratory, or pneumatic tire, longitudinal creases are left roller until the mix has cooled sufficiently for the asphalt
in the surface of the mix. Once the mix has cooled to a cement viscosity to increase enough to stiffen the mix.
temperature range of 160°F to 140°F, these marks are By the time the mix has decreased in temperature to this
typically removed by the finish roller. Roller marks are point, however, the required level of density can no

Figure 3-111 . Roller marks (J. Scherocman) .

*Page 3-103
AC 150/5370-14
Appendix 1 10/15/91

longer be achieved because the mix has lost its workabil- (140°F or more) , several passes with the pneumatic tire
ity. For this reason, the roller marks or indentations left roller can be made to "iron out" the surface of the
during the breakdown and intermediate roller passes pavement. Roughness or washboarding caused by
usually cannot be removed during the finish rolling incorrect operation of a vibratory roller should be
process. All of the asphalt cement, aggregate, and mix eliminated by applying proper operating techniques with
properties that contribute to the cause of a tender mix this piece of compaction equipment; this type of defect
also contribute to the inability of the finish roller to is virtually impossible to correct once it has been
eliminate the roller marks. introduced into the pavement surface during the com-
paction process .
Solution
If the cause of the roller marks is inadequate com- Performance
paction, additional roller passes should be made with the Roller marks are an indication that the proper level
breakdown, intermediate, and/or finish rollers to proper- of compaction has not been achieved . In terms of
ly densify the mix. The cures for inadequate compaction ultimate pavement durability, the air void content or
related to mix design deficiencies are all concerned with density of the mix is the single most important charac-
improvements in the design of the mix components and teristic that governs the performance of the asphalt
with the production of the mix at the asphalt plant. mixture under traffic. If the air void content of a dense-
Asphalt cement quality and content, aggregate proper- graded mix is high, or too low, the pavement structure
ties and characteristics, and mix temperatures all play a will generally not perform well under vehicular loading.
significant role in the workability and stability of the
asphalt material under the compaction equipment. SEGREGATION
Roller marks normally cannot be removed from a tender Description
mix until the mix temperature has decreased to a Segregation is the separation of the coarse and fine
relatively low level; usually less than 160°F. aggregate particles in an asphalt mix. The segregation
Sometimes it is possible, depending on environmental of the mix can occur at several locations during the mix
conditions and the properties of the mix, to remove the production, hauling, and placing operation . Segregation
roller marks left in the mix through the use of a pneu- can occur as the mix is delivered from the asphalt plant
matic tire roller. If the surface of the mix is hot enough to a surge silo. It can take place as the mix is deposited
into the haul truck from the silo. It can also occur when
the mix is discharged from the truck to the paver
hopper.
Segregation that is evident behind the paver screed
can generally take one of three forms: It can consist of
areas of coarse aggregate (rock pockets) that occur
randomly across the length and width of the layer
(Figure 3-112), it can occur as a longitudinal area along
one side of the paver width (Figure 3-113) , or it can be
seen transversely across the lane " at the end of a truck-
load" of mix. Segregation was discussed at length in
Section 1 of Part 3.

Cause
The cause of segregation behind the paver is directly
related to the type of segregation that is present. Rock
pockets are generally caused by improper handling of
the aggregates in the stockpiles and cold- feed bins at the
asphalt plant. They seldom occur when a batch plant is
used to produce the mix (without a silo) , because the
screens and the hot bins in the plant recombine any
Figure 3-112. Transverse (truckload-to-truckload) segregated material before it is fed into the pugmill.
segreg ation (J. Scher ocman) . Further, the pugmill blends all the aggregates together

Page 3-104
AC 150/5370-14
10/15/91
Appendix 1

and eliminates any segregation that might have occurred


previously. If a silo is employed on the batch plant,
however, the mix may segregate for all the same reasons
as a mix produced in a drum mix plant and passed
through a surge or storage silo.
Rock pockets and random segregation can occasion-
ally be found on the roadway when the mix is manufac-
tured in a drum mix plant. If the loader operator places
a bucketful of segregated aggregate in a cold-feed bin,
that material can pass through the drum, surge silo, haul
truck, and paver without being completely mixed in with
the other aggregates. This is because the drum mix
plant operates on a continuous-flow basis instead of on
a batch basis. If the aggregate in the cold-feed bins is
segregated , that material will show up on the roadway in
a random pattern both transversely and longitudinally.
Some mixes are more prone to segregate than others.
Asphalt mixes that have large top-size coarse aggregates
(1 in. or greater), low asphalt cement contents, and are
gap graded will tend to segregate more readily when
handled than will a dense-graded mix containing opti-
mum asphalt content and a smaller top-size coarse
aggregate.
Segregation that occurs on one side of the paver
(side-to-side segregation) when a batch plant without a
Figure 3-113. Longitudinal (side-to- side) segregation
silo is used to produce the mix is normally caused by
(J. Scherocman) .
improper loading of the haul truck from the pugmill . If
the mix is not loaded in the center of the width of the
truck bed, the coarse aggregate particles in the mix can tial causes. The most prevalent cause is improper
roll to one side of the truck and accumulate along that loading of the haul truck from the silo. If mix is placed
side. When the mix is delivered to the paver hopper, in the truck bed in one drop from the silo, the coarse
the segregated mix will be placed on the roadway along aggregate particles in the mix have a tendency to run to
the same side and the segregation will appear as a both the front of the bed and to the back tailgate . The
longitudinal streak on one side of the paver only. rolling of the coarse aggregate is aggravated by the plant
Segregation that occurs on one side of the paver operator continuously opening and closing the silo gates
when a batch plant with a silo or a drum mix plant is near the end of the truck- loading procedure to assure
used to produce the mix is typically caused by improper that the full weight of mix is placed on the truck .
loading of the mix into the surge silo. As the mix is It has been stated that truckload- to-truckload segre-
deposited into the silo from the conveying device (slat gation can also be caused by improper discharge of the
conveyor, belt conveyor, or bucket elevator) , the mix is mix into the silo. Mix that is dribbled into the silo from
thrown to one side of the silo and the coarse aggregate the conveying device is said to be susceptible to segrega-
particles are separated from the finer materials. When tion inside the silo. Even if this occurs, the mix that is
the silo is emptied, the coarse aggregate is deposited on segregated in the silo would appear only as random rock
only one side of the truck. This segregated material pockets in the layer behind the paver instead of in a
then passes through the paver and is seen on one side of systematic manner between truckloads of mix delivered
the mix after laydown. Further, similar to the batch to the paver. Thus, it is doubtful that any segregation of
plant operation, if the truck is not loaded in the center the mix that occurs during the continuous process of
of its width under the silo, rolling of the coarse aggre- loading the silo would appear on the roadway in a
gate particles can occur and longitudinal segregation will discontinuous pattern --only at the beginning and/or the
appear on one side of the new mat. end of a truckload of mix.
Truckload- to-truckload segregation has many poten-

Page 3-105
AC 150/5370-14
Appendix 1 10/15/91

Solution process. Each time the silo gates are opened and a little
The solution to each type of segregation is related to bit of mix is dribbled into the truck, the coarse aggregate
its cause. For random rock pockets that appear inter- particles will have a definite tendency to separate from
mittently in the mat, the method of stockpiling the the finer material. This can only be eliminated by
coarse aggregates at the asphalt plant and the charging preventing its occurrence in the first place.
of those materials into the cold-feed bins by the front- If segregation does take place during the loading of
end loader should be checked to assure proper aggre- the truck and there is an accumulation of coarse aggre-
gate-handling techniques are used . Further, all points in gate particles both at the tailgate of the truck and at the
the mix-production system where coarse aggregate front of the bed, the amount of segregation that appears
particles might accumulate should be inspected to on the roadway can be reduced by proper unloading of
determine if the flow of the coarse and fine aggregate the haul truck at the paver. First, the truck bed should
pieces is uneven. A batcher should be used at the top be raised a short distance, before the tailgate of the
of the silo to direct the mix into the center of that piece truck is opened, so that the mix can slide against the
of equipment. tailgate. This procedure surrounds any coarse particles
For longitudinal (side-to-side) segregation, the that have rolled to the tailgate area in nonsegregated
loading of the haul truck from the batch plant pugmill mix. Instead of only the coarse aggregates being deposit-
or from the silo at either the batch or drum mix plant ed first into the paver hopper, a mass of mix is dis-
should be monitored to assure that the mix is being charged once the truck tailgate is opened , flooding the
delivered into the center of the width of the vehicle. hopper with mix.
When a drum mix plant is employed to manufacture the The operation of the paver can also enhance or
mix and the segregation always appears on one side of reduce the amount of segregation that appears behind
the paver, several trucks should be loaded at the silo the screed. If the paver hopper is emptied of mix, if the
while facing in the opposite direction to their normal slat conveyors are visible, and if the wings of the hopper
loading procedure. When this mix is passed through the are dumped after each truckload of mix, any coarse
paver, the longitudinal segregation should change aggregate particles that have collected at the tailgate of
sides--go from one side of the paver lane to the other the new truckload of mix will be deposited into the
side. If the transverse position of the longitudinal bottom of the hopper and then carried directly back to
segregation does change (and it should), the solution to the empty auger chamber in front of the screed . This
the side-to-side segregation problem must take place at segregated material will appear behind the screed as
the top of the silo. The mix deposited into the silo from soon as the paver moves forward . This transverse
the conveying device must be placed into the center of segregation, therefore, does not really occur at the end
the silo instead of to one side. The flow of mix entering of the truckload but rather occurs at the beginning of
the silo must be redirected into the middle of the silo so the next truckload of mix.
that the coarse aggregate particles in the mix are not Segregation can be reduced by keeping the hopper
thrown to only one side of the silo . This cure will full of mix between truckloads. The mass of mix that
require some changes in the configuration of the equip- floods the hopper from the haul truck will be blended
ment at the top of the silo. with the mix already in the paver hopper. Any segregat-
Most truckload-to-truckload segregation can be ed material will be further "lost" in the amount of mix
reduced significantly by using multiple drops of mix to that is pulled back to the augers by the slat conveyors
load the haul trucks. If a tandem-axle truck is being and carried under the paver screed . The amount of
loaded, at least three different drops of mix should be truckload-to -truckload segregation can be decreased
made: into the front of the truck, into the back of the significantly, but not always eliminated completely, by
truck, and into the center of the truck bed . If a larger good paver operating techniques. The problem of
truck is used, additional drops of mix should be made. truckload-to-truckload segregation should be solved
One of the main solutions to the truckload- to -truckload during the truck-loading procedure.
segregation problem is to minimize the distance that the
coarse aggregate particles can roll . This is accomplished Performance
by employing multiple drops of mix into the truck Segregation can affect pavement durability directly by
instead of a single loading of mix into the bed. increasing the air void content of the mix in the segre-
The plant operator should be prohibited from gated areas and increasing the potential for moisture
"topping off" the load of mix at the end of the loading damage. Further, the segregated locations are suscepti-

Page 3-106
AC 150/5370-14
10/15/91
Appendix 1

ble to raveling and, if bad enough, to total disintegration distresses that occur at the time of the asphalt mix
under traffic. Segregation, in the form of rock pockets, production, laydown, and compaction. There are a
longitudinal side-to -side segregation, or transverse number of other deficiencies that can occur on an
truckload-to-truckload segregation , is detrimental to the asphalt pavement structure with time and traffic loading
long-term performance of the asphalt mixture. once construction has been completed . Some of those
distresses include fatigue cracking, rutting, shoving,
OTHER PAVEMENT PROBLEMS raveling, and disintegration. A discussion of these
The discussion above is concerned only with those distresses is beyond the scope of this handbook.

Page 3-107
AC 150/5370-14
Appendix 1 10/15/91

BIBLIOGRAPHY

Abd El Halim, A.O. , W. Phang, and M.E. Gindy, "Ex- ASTM STP 829 (December 1982) pp. 131-144 .
tending the Service Life of Asphalt Pavements "Bituminous Mix Design and Field Control," Technical
through the Prevention of Construction Cracks," in AdvisoryT5040.24, Federal Highway Administration,
Transportation Research Record 1178: Flexible Pave- Washington, D.C. (August 1985) 23 pp.
ment Construction, Transportation Research Board, Bjorklund, N.A. , "Pavement Deformation and Resistence
National Research Council, Washington, D.C. (1988) to Fatigue of Resurfaced Pavements. A Laboratory
Pp. 1-8. Investigation Performed on Beams Taken Across the
Acott, M. and R. Dunmire, "Hot Mix Asphalt Construc- Wheelpath and Resurfaced in the Laboratory," Pro-
tion-Field Diagnosis and Trouble-shooting Guide," ceedings, Association of Asphalt Paving Technolo-
Proceedings, Association of Asphalt Paving Technolo- gists, Vol. 54 ( 1985 ) pp. 551-568 .
gists, Vol. 56 ( 1987) pp. 330-360. Brock, J.D. , "Pavement Smoothness," Technical Bulletin
Afferton, K.C. , "Achieving and Verifying Specified Com- No. T- 112 , Astec Industries Inc. ( 1984) 17 pp .
paction," presented at the Asphalt Compaction Con- Brock, J.D. , " Segregation of Asphalt Mixtures," Proceed-
ference, Albany, N.Y. (December 1979) 28 pp. ings, Association of Asphalt Paving Technologists,
Alexander, M.L., "Cost/Benefit Evaluation ofEnd- Result Vol. 55 ( 1986) pp. 269-277.
Asphalt Concrete Compaction Specifications," Brock, J.D. and L. Wagner, "Trucking, Our Out of
Report No. FHWA/CA/TL- 88/03, California Depart- Control Cost," Bulletin No. T- 118, Astec Industries,
ment of Transportation (June 1988) 56 pp. Inc. ( 1988) 29 pp.
Alexander, M.L. and R.N. Doty, " California Study of Brown, E.R. , " Experiences of Corps of Engineers in
Asphalt Concrete Density Measurement-Nuclear Compaction of Hot Asphalt Mixtures," ASTM STP
Versus Core Density," ASTM STP 829 (December 829 (1984) pp. 67-79.
1982) pp. 80-92 . Brown, E.R. , " Experiences of Corps of Engineers in
Alexander, M.L. and R.N. Doty, "California Study of Compaction of Hot Asphalt Mixtures," ASTM STP
Asphalt Concrete Density Measurement--Nuclear 829 (December 1982) pp. 67-79.
Versus Core Density," ASTM STP 829 ( 1984) pp . 80- Brown, E.R. and J.E. Shoenberger, " Experiences of
92. Corps of Engineers in Compaction of Hot Asphalt
Asphalt Overlays for Highway and Street Rehabilitation, Mixtures," Proceedings, 20th Paving and Transporta-
Manual Series No. 17 (MS- 17) Asphalt Institute tion Conference, University of New Mexico (Decem-
(1983) 164 pp . ber 1983) pp . 96-108 .
Asphalt Paving Manual, Manual Series No. 8 (MS-8) Bulger, S.A. , P. Korgemagi, and D.F. Lynch, "An Evalu-
Asphalt Institute ( 1978) 148 pp . ation of a Triple-Jointed Screed Paver as a Solution
Basha, M.A. , "Bituminous Paving Operations," Utah to Pavement Rutting," Ontario Ministry of Transpor-
Department of Transportation (April 1979) 114 pp . tation (January 1987) 21+ pp .
Bell, C.A. , R.G. Hicks, and J.E. Wilson, "Effect of Bulger, S.A. , P. Korgemage, and D.F. Lynch, "An
Percent Compaction on Asphalt Mixture Life," in Evaluation of a Rubber-Coated Steel Drum Vibrato-
ASTM STP 829: Placement and Compaction of As- ry Roller," Ontario Ministry of Transportation
phalt Mixtures ( 1984) pp. 107-130 . (January 1987) 20+ pp.
Bissada, A.F. , " Compactibility of Asphalt Paving Mix- Burnett, W.C. , J.J. Thomas, and W.C. Dixon, "Density
tures and Relation to Permanent Deformation," in Studies of Asphalt Concrete," Research Report No.
Transportation Research Record 911: Asphalt Materi- 65-6 (Interim Report) , New York State Department
als, Mixtures, Construction, Moisture Effects, and of Public Works (June 1965) .
Sulfur, Transportation Research Board, National Burnett, W.C. , J.J. Thomas, and W.C. Dixon, " Density
Research Council, Washington, D.C. ( 1983) pp. 1-10 . Studies of Asphalt Concrete," Physical Research
Bissasa, A.F. , " Resistance to Compaction of Asphalt Report RR 65-6, New York State Department of
Paving Mixtures and Its Relationship to Stiffness," Public Works (June 1965) 26 pp .

Page 3-108
AC 150/5370-14
10/15/91
Appendix 1

Cechetini, J.A., "Vibratory Compaction of Asphalt Con- Pavements," Research Report 90-2F, Texas A&M
crete Pavements," Proceedings, Association of Asphalt University (July 1969) 147 pp .
Paving Technologists, Vol. 43 ( 1974) pp. 384-408 . Estimating Net Average Speeds for Pavers and Rollers,
Chu , T.Y., " A Study for Improving the Durability of Dynapac Mfg. Inc. (September 1978) 56 pp .
Plant-Mix Asphalt Surfaces in South Carolina," Factors Affecting Compaction, Educational Series No. 9
Research Project 525, University of South Carolina (ES-9) Asphalt Institute ( 1980) 12 pp .
College of Engineering (February 1979) 132 pp. Fee, F. , " Evaluation of the In -Place Density of Bitumi-
Compacting Asphalt with a Dynapac Vibratory Tandem nous Paving Air Void Method vs % Compaction ,"
Roller, Dynapac Mfg. Inc. ( October 1978) 40 pp . Proceedings, Federal Aviation Administration Airport
Compaction Handbook, Hyster Co. (May 1978) 127 pp . Conference (March 1983) 5+ pp.
Corlew, J.S. and P.F. Dickson, " Cold-Weather Paving of Finn, F.N. and J.A. Epps, "Compaction of Hot Asphalt
Thin Lifts of Hot-Mixed Asphalt on Preheated As- Concrete," Research Report 214-21 , Texas A&M
phalt Base," in Highway Research Record No. 385: University (August 1980) 35 pp .
Bituminous Construction and Quality Control: 5 Fisher, D.R. , "A General Overview of Asphalt Roadway
Reports, Highway Research Board, National Research Construction," Ingersoll-Rand Construction Co.
Council, Washington, D.C. ( 1972) pp. 1-6 . (1983) 42 pp.
Cosbey, H., "Asphalt Compaction by Vibratory Roller," "Flexible Pavement Density: Three Studies," Research
Proceedings, Association of Asphalt Paving Technolo- Report 6, New York State Department of Transpor-
gists, Vol. 46 ( 1977) pp. 279-293. tation (July 1972) 50 pp.
Cowden, R.H., "Update: A study of Modern Vibratory Foster, C.R., "The Effect of Distance of Haul and
Asphalt Compaction and Its Benefits," Proceedings, Traffic Restrictions on the Cost of Asphalt Pave-
Canadian Technical Asphalt Association , Vol . XXIII ment," Information Series 79, National Asphalt
(November 1978) pp. 232-252. Pavement Association (June 1981) 6 pp.
Crawford, C., " Tender Mixes," QIP 108, National As- Foster, C.R. , " The Effect of Paver Speed on Roller
phalt Pavement Association (March 1986) 9 pp . Requirements," in Highway Research Record No. 316:
Daines, M.E. , " Cooling of Bituminous Layers and Time Construction and Construction Equipment: 9 Reports,
Available for Their Compaction," Research Report Highway Research Board, National Research Coun-
4, Transport and Road Research Laboratory ( 1985) cil, Washington, D.C. ( 1970) pp . 76-81 .
11 pp . Foster, C.R. , "The Effect of Weight of Steel Tired
Dellert , R.B. , " Vibrat Rollers on the Unit Weight of Compacted Asphalt
ory Compaction of Thin Lift
Asphalt Resurfacing," Proceedings, Association of Paving Mixtures," Information Series 90, National
Asphalt Paving Technologists, Vol. 46 ( 1977) pp . Asphalt Pavement Association (November 1983) 46
287-293. pp.
Design ofHot Asphalt Mixtures, Educational Series No. Foster, C.R., " Pavement Smoothness," Information
3 (ES-3) Asphalt Institute ( 1986) 8 pp. Series 53 , National Asphalt Pavement Association
Dickson, P.F. and J.S. Corlew, " Cooling of Hot- Mix (undated) 7 pp .
Asphalt Laid on Frozen Subgrade," Proceedings, Foster, C.R. , " A Study of Cessation Requirements for
Association of Asphalt Paving Technologists, Vol. 41 Constructing Hot-Mix Asphalt Pavements," in High-
(1972) pp . 49-65 . way Research Record No. 316: Construction and
Epps, J.A. and F.N. Finn, " Asphalt Concrete: Methods Construction Equipment: 9 Reports, Highway Re-
for Specifying In-Place Density," presented to the search Board, National Research Council, Washing-
Texas Hot Mix Asphalt Pavement Association ton, D.C. ( 1970) pp . 70-75 .
Annual Meeting (October 1982) pp. 59-89 . Franswick, W.A. and S.B. Hudson, " Quality Control for
Epps, J.A. , B.M. Gallaway, and W.W. Scott, " Long-Term Hot Mix Plant and Paving Operations," QIP-97,
Compaction of Asphalt Concrete Pavements," in National Asphalt Pavement Association (undated)
Highway Research Record No. 313: Bituminous Materi- 131+ pp.
als, Mixes, and Compaction: 7 Reports, Highway Geller, M. , " Compaction Equipment for Asphalt Mix-
Research Board , National Research Council, Wash- tures," in ASTM STP 829: Placement and Compaction
ington, D.C. ( 1970) pp . 79-91 . ofAsphalt Mixtures (1984) pp. 28-47.
Epps, J.A., B.M. Gallaway, W.J. Harper, W.W. Scott, Geller, M. , " Compaction Equipment for Asphalt Mix-
and J.W. Seay, " Compaction of Asphalt Concrete tures," Dynapac Research Bulletin No. 8030 (January

Page 3-109
AC 150/5370-14
Appendix 1 10/15/91

1983) . Kennedy, T.W. , F.L. Roberts, and R.B. McGennis,


Geller, M. , "Summarizing the Development of Vibratory "Effects of Compaction Temperatures and Effect on
Roller Application for Compacting Bituminous Mixes the Engineering Properties of Asphalt Concrete
in the USA," Proceedings, Association of Asphalt Mixtures," in ASTM STP 829: Placement and Com-
Paving Technologists, Vol . 46 ( 1977) pp. 272-279 . paction ofAsphalt Mixtures ( 1984) pp . 48-66.
Gessler, M. , " Compaction of Tender Asphalt Mixes," Kennedy, T.W. , F.L. Roberts, R.B. McGennis, and J.N.
Dynapac Research Bulletin No. 8027 (November Anagnos, "Compaction of Asphalt Mixtures and the
1981 ) 8 pp. Use of Vibratory Rollers," Research Report 317-1,
Gibboney, W.B. , "Development of a Bituminous Con- Center for Transportation Research (March 1984) 44
crete Compaction Specification," Ohio Department pp .
of Highways (April 1972) 32 pp . Kilpatrick, M.J. and R.G. McQuate, " Bituminous Pave-
Graham, M.D. , W.C. Burnett, J.J. Thomas, and W.C. ment Construction," Federal Highway Administra-
Dixon, "Pavement Density-What Influences It," Pro- tion, Washington, D.C. (June 1967) 42 pp.
ceedings, Association of Asphalt Paving Technolo- Kopac, P.A., " Current Practices in Acceptance of Bitu-
gists, Vol. 34 (1965) pp. 286-308. minous Concrete Compaction ," in Transportation Re-
Handbook of Bituminous Compactionology, American search Record 986: Construction: Quality Control and
Hoist & Derrick Co. (1977) 49 pp . Specifications, Transportation Research Board , Na-
Henrick, H.W. , "Modern Asphalt Compaction in West- tional Research Council, Washington , D.C. (1984)
ern Europe," Proceedings, Canadian Technical As- pp. 43-46.
phalt Association (November 1983) pp . 339-375 . Korgemagi, P. and D.F. Lynch, "Attacking the Problem
Hot-Mix Bituminous Paving Manual, Federal Highway of Segregated Hot Mix Pavements," Proceedings,
Administration, Washington, D.C. (December 1984) Canadian Technical Asphalt Association, Vol.
121 pp . XXXIII (November 1988) pp . 76-85.
Hughes, C.S. , "A Density Specification with Pay Fac- Layson, C.S., V.L. Schrimper, and R.B. McGennis,
tors," Proceedings, Association of Asphalt Paving "High Energy Screeds On Asphalt Pavers," presented
Technologists, Vol. 52 ( 1983) pp . 357-362. to Transportation Research Board Committee
Hughes, C.S. , "Incentive and Disincentive Specification A2F02, Flexible Pavement Construction (January
for Asphalt Concrete Density," in Transportation 1986) 9 pp.
Research Record 986: Construction: Quality Control Liljedahl, B., "Aids in Compacting Hot Mix Asphalt
and Specifications, Transportation Research Board, Layers," European Asphalt Pavement Association
National Research Council, Washington , D.C. ( 1984) (March 1988) 6 pp.
pp. 38-42. Linden, F. and J. VanDerHeide , " Some Aspects of the
Hughes, C.S. , NCHRP Synthesis ofHighway Practice 152: Compaction of Asphalt Mixes and Its Influence on
Compaction of Asphalt Pavement, Transportation Mix Properties," Proceedings, Association of Asphalt
Research Board, National Research Council, Wash- Paving Technologists, Vol. 55 ( 1986) pp . 607-614.
ington, D.C. ( October 1989) 42 pp. Lister, N.W. , " Dense Graded Macadams: Improving
Hughes, C.S. , "Symposium-- Effect of New Equipment on Compaction and Performance," Asphalt Technology,
Asphalt Pavement Construction: Virginia Practice ," No. 30 (December 1980) pp 44-56.
Proceedings, Association of Asphalt Paving Technolo- Lister, N.W. and W.D. Powell, "The Compaction of
gists, Vol. 39 ( 1970) pp . 661-670. Bituminous Base and Base-Course Materials and its
Kandhal , P.S. , " Specification for Compaction of Asphalt Relation to Pavement Performance," Proceedings,
Pavements," Proceedings, Association of Asphalt Association of Asphalt Paving Technologists , Vol. 44
Paving Technologists, Vol . 52 ( 1983) pp. 362-369 . (1975) pp. 75-107 .
Kandhal, P.S. and W.C. Koehler, "Pennsylvania's Experi- Lohshene, E.S. , R.C.G. Haas, E. Meyer, and A. Chest-
ence in the Compaction of Asphalt Pavements," in ham, "Management of Construction Proceedures for
ASTM STP 829: Placement and Compaction of As- Asphalt Compaction," Proceedings, Canadian Techni-
phalt Mixtures (1984) pp. 93-106. cal Asphalt Association, Vol. XXIII (November
Kennedy, T.W., R.B. McGennis, and R.J. Holmgreen, 1978) pp. 126-157.
"Asphalt Mixture Segregation: Diagnostics and Marker, V. , "Factors Affecting Compaction," IG- 3, The
Remedies," Proceedings, Association of Asphalt Asphalt Institute (November 1979) 27 pp.
Paving Technologists, Vol. 56 ( 1987) pp. 304-329. Marker, V. , "Symposium-- Effect of New Equipment on

Page 3-110
AC 150/5370-14
10/15/91
Appendix 1

Asphalt Pavement Construction: Thick Lift Compac- Leaflet No. 10 (CL- 10) Asphalt Institute ( 1974).
tion for Asphalt Concrete Bases," Proceedings, Palmer, R.K. and J.J. Thomas, "Density Studies of
Association of Asphalt Paving Technologists, Vol. 39 Asphalt Concrete," Research Report 68-2, New York
(1970) pp. 658-660 . State Department of Transportation (June 1968) 40
Marker, V. , "Symposium--Technology of Thick Lift pp.
Construction: Construction Methods," Proceedings, Pavement Rehabilitation--Preparation forAsphalt Overlays,
Association of Asphalt Paving Technologists, Vol. 41 Construction Leaflet No. 5 (CL-5) Asphalt Institute
(1972) pp. 354-364. (1974) .
Martenson, E.D. , "Innovations in Variable -Width As- "Paver Operations for Quality," Information Series 59 ,
phalt Paving," Technical Notes T502 , Barber- Greene National Asphalt Pavement Association (October
Co. (undated) 9 pp. 1976) 6 pp.
McGennis, R.B. and T.W. Kennedy, "Segregation of Paving Manual, Blaw-Knox Construction Equipment,
Asphalt Mixtures: Causes, Identification, and Cures," Inc., undated, 43 pp.
Proceedings, Canadian Technical Asphalt Association "Placing and Compacting Thick Lifts of Hot Mix Asphalt
(1986) pp. 46-70. Pavements," Information Series 21 , National Asphalt
McKillen, E.R. , "Vibratory Compaction of Asphalt is Pavement Association (March 1986) 13 pp .
Not Always Easy," Proceedings, Canadian Technical Powell, W.D. , " Methods of Improving Compaction of
Asphalt Association, Vol. XXI (November 1976) pp . Dense Coated Macadam," Asphalt Technology, No. 24
249-268. (May 1978).
McQueen, R.D. , "Investigation of the Inter- Relationship Powell, W.D. and D. Leech, "Standards for Compaction
Between Base Pavement Stiffness and Asphalt of Dense Roadbase Macadam," Supplementary
Overlay Compaction," DOT/FAA/ES-88-1 , Federal Report 717, Transport and Road Research Laborato-
Aviation Administration, Washington , D.C. (March ry ( 1982) 12 pp .
1988) 49 pp. Powell , W.D. , N.W. Lister, and D. Leech, " Improved
Minor, C.E., "Are Hot-Mix Tarps Effective?" Informa- Compaction of Dense Graded Bituminous Mac-
tion Series 77, National Asphalt Pavement Associa- adams," Proceedings, Association of Asphalt Paving
tion (March 1981 ) 8 pp. Technologists, Vol. 50 ( 1981 ) pp . 394-411 .
Mix Design Methods for Asphalt Concrete and Other Hot- "Precision Experiment: Percentage Refusal Density Test,
Mix Types, Manual Series No. 2 (MS-2) Asphalt The Panel's Report," Contractor Report 1 , Transport
Institute ( 1988 ) 112 pp. and Road Research Laboratory ( 1985) 14+ pp.
Monoscalco, E.F. , M. Feaster, and J.R. Stephenson, Price, D.A. , "Nighttime Paving," Report No. CDH- DTP-
"Transportation, Laydown and Compaction," Proceed- R-86-6, Colorado Department of Highways (April
ings, National Asphalt Pavement Association Annual 1989) 12 pp.
Meeting (January 1985) pp . 211-240 . Price, D.A. , "Nighttime Paving," Report No.
Nittinger, R.J., "Thick-Lift Flexible Pavement Wearing CDOH-DTP- R-85-2 , Colorado Department of High-
Courses," Research Report 41, New York State ways (February 1985) 20 pp.
Department of Transportation (February 1977) 21 Principles ofConstruction ofHot-Mix Asphalt Pavements,
pp. Manual Series No. 22 (MS-22) Asphalt Institute
Nittinger, R.J., "Vibratory Compaction of Asphalt Con- ( 1983) 300 pp.
crete," in Transportation Research Record 659: Bitumi- Procedures for Rolling a Test Strip with a Dynapac Vibra-
nous Concrete Materials, Mixtures, and Additives, tory Roller, Dynapac Mfg. Inc. (October 1978) 32 pp.
Transportation Research Board, National Research Puangchit, P. , R.G. Hicks, J.E. Wilson, and C.A. Bell,
Council, Washington, D.C. ( 1977) pp. 46-53. "Development of Rational Pay Adjustment Factors
Noel, R.B. , "Compacting Heavy Duty Highway Pave- for Asphalt Concrete," in Transportation Research
ments," Proceedings, Association of Asphalt Paving Record 911 : Asphalt Materials, Mixtures, Construction,
Technologists, Vol . 46 ( 1977) pp . 309-326. Moisture Effects, and Sulfur, Transportation Research
Nunn, M.E. and D. Leech, "Substitution of Bituminous Board, National Research Council, Washington, D.C.
Roadbase of Granular Sub-Base," Research Report (1983) pp. 70-79.
58, Transport and Road Research Laboratory ( 1986) "Quality Control for Hot Mix Asphalt Manufacturing
11 pp. Facilities and Paving Operations," QIP-97, National
Open-Graded Asphalt Friction Courses, Constru Asphalt Pavement Association (September 1987) 57
ction

Page 3-111
AC 150/5370-14
Appendix 1 10/15/91

pp . Research Board, National Research Council, Wash-


Roberts, F.L., "Importance of Compaction of Asphalt ington, D.C. ( 1988) pp . 38-46 .
Mixtures," presented at the State-of-the-Art Confer- Superintendent's Manual on Compaction of Hot Mix
ence on Improved Asphalt Pavement Performance Pavement, Training Aid Series 12, National Asphalt
Through Effective Compaction, Arlington, Tex. Pavement Association (January 1985) 32 pp.
(January 1980) 21 pp . Systems Analysis of Storage, Hauling, and Discharge of
"Roller Operations for Quality," Information Series 58, Hot Asphalt Paving Mixtures, QIP-94, National
National Asphalt Pavement Association (March Asphalt Pavement Association ( 1972) 154 pp.
1980) 4 pp. A Systems Analysis of the Production and Laydown of
Rolling and Compaction ofAsphalt Pavement Instruction Hot-Mix Asphalt Pavement, Texas A& M University
Manual, VA-21 , The Asphalt Institute, TAS-3, (undated) 149 pp.
National Asphalt Pavement Association (undated) 32 Technology andthe Asphalt Paver, Blaw-Knox Construc-
pp. tion Equipment Co. (1983) 11 pp.
Santoro, R.R. , K.C. Afferton , and J.A. Walz, J.A. , "Stan- Tegeler, P.A. and B.J. Dempsey, " A Method of Predict-
hope Study of Compaction Methods for Bituminous ing Compaction Time for Hot-Mix Bituminous
Stabilized Base," in Highway Research Record No. Concrete," Proceedings, Association of Asphalt Paving
385: Bituminous Construction and Quality Control: 5 Technologists, Vol . 42 ( 1973) pp . 499-520 .
Reports, Highway Research Board , National Research Tender Mixes, Information Series No. 168 ( IS- 168)
Council, Washington, D.C. ( 1972) pp. 7-18 . Asphalt Institute ( 1978) 8 pp .
Scherocman, J.A. and E.D. Martenson, " Placement of Tunnicliff, D.G. , " Symposium on Vibratory Compaction
Asphalt Concrete Mixtures," ASTM STP 829 ( De- of Asphalt Pavement: Introduction," Proceedings,
cember 1982) pp. 3-27. Association of Asphalt Paving Technologists, Vol. 46
Schoonover, R.D. , " Standard Costs for Asphalt Paving, (1977) pp. 260-264.
Applications for Contract Bidding and Performance "Vibratory Compaction of Asphalt Paving Mixtures,"
Management," Management Series 2, National As- Educational Series No. 2 (ES-2) , Asphalt Institute
phalt Pavement Association (undated) 14 pp. (June 1978) 12 pp .
Seaman, D.J. , "Dynamic Testing: Density on the Run," Vyce, J.M., L. Hartvigas, and J.W. Reilly, " Thick- Lift
in Transportation Research Record 1178: Flexible Pave- Flexible Paving," Research Report 9, New York State
ment Construction, Transportation Research Board, Department of Transportation (March 1972) 19 pp .
National Research Council, Washington , D.C. ( 1988) Waller, H.F. , " Compaction of Hot Asphalt Mixes,"
pp. 16-82. resented to the First Annual South Carolina State
Service Training Manual, Blaw-Knox Construction Equip- Highway Conference (March 1983 ) pp . 3-1-3-21 .
ment, Inc. , undated , 32 pages. Wester, K. , "Symposium--Asphalt Paving for the Seven-
Shah, N.D. and P.F. Dickson, "Design Consideration for ties: Compaction," Proceedings, Association of As-
a Direct-Fired Propane Heater to Preheat the Base phalt Paving Technologists, Vol. 40 ( 1971) pp. 279-
for Cold-Weather Paving," in Transportation Research 293.
Record 549: Bituminous Mixtures, Aggregates, and White, S., G. Heiman, R. Besantm, and A. Bergen,
Pavements, Transportation Research Board , National "Saskatchewan Pavement Cooling Charts: Develop-
Research Council, Washington, D.C. ( 1975) pp. 55- ment of a Tool to Control Paving Operations in
62. Marginal Weather," Proceedings, Canadian Technical
Smith, R.A. and J. Epps, "Environmental Conditions for Asphalt Association , Vol . XXXIII (November 1988)
Placing Asphalt Concrete ," Research Report 214-11 , pp. 120-153.
Texas A& M University (December 1975) 48 pp. Williamson, A.O. , " Compaction and Compaction Tech-
State of the Art: Vibratory Compaction of Asphalt Pave- niques," Bros, Inc. (undated) 16+
ments, Transportation Research Circular No. 242, Wilson, J.E. and R.G. Hicks, " Evaluation of Construc-
Transportation Research Board , National Research tion and Short -Term Performance Problems for
Council, Washington, D.C. (April 1982) 7 pp . Asphalt Pavements in Oregon," Proceedings, Associa-
Stroup-Gardiner, M. and D. Newcomb, " Statistical tion of Asphalt Paving Technologists, Vol. 48 ( 1979)
Evaluation of Nuclear Density Gauges under Field pp. 1-28.
Conditions," in Transportation Research Record 1178: Winslow, M.S. , " Adjustment for Asphalt Pavers," Louisi-
Flexible Pavement Construction, Transportation ana Department of Highways Research and Develop-

Page 3-112
AC 150/5370-14
10/15/91
Appendix 1

ment Section (undated) 23 pp. Worthan, G.R. and L.F. Erickson, "Determination ofthe
Wolters, R.O. , "Modern Concepts For Density Control, Effect of Environmental Temperatures on Compac-
Phase I: Bituminous Wearing Courses," Investigation tion of Asphaltic Pavements," Research Project No.
No. 191 , Minnesota Department of Highways ( 1973) 54, Idaho Department of Highways (July 1970) 88
51 pp . pp.

Page 3-113 ✩U.S. GOVERNMENT PRINTING OFFICE:1991-312-687/55565


3 0000 044 579 260

ISBN 0-16-036002-1
90000

9 780160 360022

You might also like