No. : 022 / PT.

CUNG/ I /2024 Lumajang, 22 Januari 2024


Lamp : 1 One File
Subject : Price Offer Letter

Dear,
Mr. Daniel Franklin
Director PT. Lombok Torok Development
Sanur – Bali.

Up. Mr. Rovin

Yours faithfully,
We hereby submit a price offer letter for the construction of Villa Samara Resort in Lombok, with
BQ details attached

The details of the costs that we provide are as follows:

 Total work amounting to : Rp. 28,307,670,608,-


 Rounding : Rp. 28,307,670,000,-

It says : Twenty-eight billion, three hundred and seven million, six hundred and
Seven Ten Thousand Tupiah.

With the following offer conditions:

1. Offer price includes PPN and PPH


2. Prices are in accordance with the proposed BQ Negotiation Results
3. Nature of Unit Price Contracts
4. Validity period is 2 (two) weeks from the date the Offer Letter is submitted

Payment method :

 Down payment/advance 30% (thirty percent)


 The next payment term is according to progress, accompanied by a progress report in
the field with details of the stages included in the work order (SPK).
 Payment 1 (one) calendar week after the receipt/invoice is submitted.

Thus we convey this Price Offer Letter for your attention and cooperation. Thank you

Best regards,
PT. Cipta Usaha Nusa Gede

DEDEN MUKAROM
President Director
Offer attachment :

HARGA HARGA
NO KETERANGAN PPN 11 %
SEBELUM PPN STELAH PPN

1 Architecture Work 01 10,451,235,071 1,149,635,858 11,600,870,929

2 MEP Work 01 928,100,396 102,091,044 1,030,191,440

3 Architecture Work 02 4,568,656,061 502,552,167 5,071,208,228

4 Structure 7,703,169,277 847,348,620 8,550,517,897

5 MEP Work 02 1,851,245,148 203,636,966 2,054,882,114

TOTAL 25,502,405,953 2,805,264,655 28,307,670,608