Professional Documents
Culture Documents
Authorization No.:
Certificate No.:
INTERNATIONAL LOADLINE SURVEY CHECKLIST
Date Survey
Assignment No: Port of Survey: Date Survey Completed:
Commenced:
Note: Complete relevant sections as applicable for the surveys carried out. Check boxes under ‘Y’
to indicate YES, ‘N‘ to indicate NO and “N/A“ to indicate NOT APPLICABLE.
1/3
F-LLS-02c
A PERIODICAL LOADLINE INSPECTION (continued) Y N N/A
Arrangements for protection of crew and access to crew’s quarters such as gang-
13 ways or under deck passageways, lifelines, walkways, bulwark and/or guard rails
examined and found in satisfactory condition.
For ships with special arrangements such as timber carriers (uprights, sockets,
lashings, guard rails and lifelines), tankers (safe access to tanker bows etc), Ro-Ro
14
vessels (bow, stern, side doors etc) and other special type ships, the condition of
the special arrangements is satisfactory as far as could be seen.
The freeboard marks have been verified and found in accordance with the
15
freeboards assigned in the International Loadline Certificate.
Stability booklet approved by on . (All ships)
Loading manual approved by on .
(Cargo ship more than 100 meters in length)
16
Loading instrument approved by on .
(Bulk carriers more than 150 meters in length)
Loading/stability information are in language(s) understood by the ship’s officers.
For ships assigned timber loadlines, the approved timber deck cargo loading and
17
lashing plan is on board, approved by on .
2/3
F-LLS-02c
C FIRST SURVEY BY CONARINA (continued) Y N N/A
Was any service restriction (trading area limits etc) imposed by the previous
society/organization?
6 (If YES, the same service restrictions should be included/ endorsed in the Interim
certificate)
Has vessel been modified since the last Loadline Certificate was issued?
7 (full details to be forwarded to CONARINA Technical Head Office and certificate
to be issued only after confirmation from CONARINA Technical Head Office)
Has new Record of Conditions of Assignment of Loadlines been prepared, a copy
left on board and a copy forwarded to CONARINA Technical Head Office?
8
(required only if a previous record is not available or if the previous record does
not contain the necessary information as contained in IS form LL-1)
D MODIFICATIONS / ALTERATIONS
Details:
E DEFICIENCIES / REMARKS
Details:
A Periodical Load Line Survey has been carried out in accordance with the Article 14 (b) of
the Convention and as described above;
(a)
A Periodical Load Line Inspection has been carried out in accordance with the Article 14(c)
of the Convention and as described above.
(b) Minor deficiencies, if any, has been described in section E
An INTERIM/CONDITIONAL Load Line Certificate No.
(c) has been issued on and valid until ;
A full term Certificate may be issued by CONARINA Technical Head Office;
A full term International loadline Certificate should not be issued by CONARINA Technical
(d)
Head Office
until the deficiencies noted at E above have been rectified.
The full term International loadline Certificate No. has been endorsed for the
(e) periodical loadline inspection on at .
Signature of Surveyor
Name of Surveyor
Port
Date
3/3